Professional Documents
Culture Documents
Road Marking Cold Plastic
Road Marking Cold Plastic
Contents
1. Purpose
2. Scope of Work
3. Definitions
4. References
7. HSSE
8. Prior Activities
9. Procedure
10.Responsibilities
2- Scope of Work
a. This procedure is applicable to the following works associated with
the project.
b. This method statement outlines the procedures to be followed
in construction of Road Marking and Signs.
3- Definitions
CM Construction Manager
CS Chief Surveyor
4- References
Contract – General &Special Conditions – BOQ – Approved Drawings –
Specifications - Shop drawings (Respectively).
Temporary signs
Safety Barriers
Traffic Cones
Grade Stakes
The major equipment used for this construction works includes, but are not
limits to the followings;
Pavement Marking Equipment
Process Monitoring Equipment
1. Portable environmental measuring devices for
temperature & humidity
2. Paint application rate computers
3. Electronic scales / bead bucket and stop watch for
glass bead application rate
4. Applicator speedometers, calibrated over range
of applicator speeds
5. Paint pressure and / or hydraulic/air pressure gauges
6. Wet film gauges
7. Bead application comparison plates.
7- HSSE
a. Approved safety plan procedures shall be strictly followed.
b. Where possible hazards may arise from filling activities, the necessary
safety measures will be taken to prevent accident or injury at all
times. This may include barriers, warning tape/ net, signage,
watchman, and proper lighting.
c. Where work upon existing services may be required, the necessary
work permits and safety equipment should be obtained prior to the
activity commencement.
d. HSSE officer will enforce that Personal Protective Equipment (such as
Respiratory mask, Safety Shoes, Face mask, Hard hats,,, etc.) be worn
by site personnel at all times during construction activities .
e. Prior to the commencement of any activities, the workforce will receive an
induction talk on the project site safety requirements. This induction talk
will include both activity safety issues, as well as general safety
requirements.
f. Safety engineer will ensure that Personal Protective Equipment is worn
by site personnel at all times during construction activities.
g. Plant and Equipment will be provided with back-up alarms, lights, and
all other applicable safety devices.
h. Proper access to the work area shall be maintained throughout the
working period.
9- Procedure
A. Road Marking
1. Surfaces to be painted shall be prepared by removing
effervescence, chalk, dust, dirt, grease, oil and release agent
and roughening the surface with fine emery paper to remove
glaze.
2. The Surveyor will locate and mark all main Outlines, Spots and
Coordinates for every type of marking and signs. These
outlines will be clearly marked using chalk lines and tapes.
3. Carefully mix and prepare paint materials in accordance
with manufacture direction.
4. Use suitable thinner approved by Paint manufacture and
only within recommended limits.
5. Using Roller Brush, a single coating of white color road
marking paint is applied on to the yellow rubber surface
evenly.
6. While painting adjacent areas and installations shall be
protected by using of masking tape or other approved
precautionary measures.
7. When the white color paint is dried, a coat of Yellow Color road
marking paint is applied evenly on the top of the white
surfaces.
8. When the single coat of Yellow Paint is dried, another final coat
is applied of Yellow Road Marking and let to dry.
9. Apply paint to an even and fine texture, leave no evidence
of rolling such as laps, irregularity in texture, skid marks.
TAHER AMMAR totytaher@yahoo.com Page 5
METHOD STATEMENT
10. Apply additional coat where under coats, stain or other
condition show in final coat.
10- Responsibilities
10.1 The CM will coordinate with PE / SE and ensure that the necessary
resources to implement the approved method statement and ITP
have been allocated to the task.
10.2 The PE / SE will ensure that the site preparation activities are
conducted according to the approved method statement and all in-situ
tests according to the ITP are implemented.
MARKERS