You are on page 1of 20

Week 6: Maintenance and Rehabilitation

What is Maintenance?

- Highway maintenance- Defined By AASHTO as “Maintenance is the preservation and keeping each type
of roadway, roadside, structures and facilities as nearby as possible to its original condition as constructed
or as subsequently improved the operation of highway facilities and services to provide satisfactory and
safe transportation. [4]

A day-to-day work that the goal is to preserve the infrastructure facilities to prolong the Lifespan of the
infrastructure. Improve thru.

a.) Routine Maintenance


b.) Preventive Maintenance
c.) Long Term Performance based on Maintenance

Routine Maintenance:

refers to maintenance activity regularly performed throughout the year and includes carriageway and
roadside maintenance.

For Routine Maintenance Activities:

Pothole patching

Sealing of cracks on pavement


Manual cleaning and clearing of drainage and
culvert (inlet and outlet)

Roadside and feature maintenance; vegetation


control, road signs, guardrail cleaning,and
repainting; maintenance of other roadside
features and road markings maintenance

Bridge maintenance, cleaning of bridge decks,


shelves framework and drainage, spot repainting
and clearing of waterway flows.

Preventive Maintenance
-refers to works more extensive than routine maintenance and helps prevent:

Preventive Maintenance

(a) undue roadway deterioration


(b) increased routine maintenance requirement
(c) vehicular accidents.

For Preventive Maintenance Activities:


Asphalt overlay

Concrete -Relocking

Long Term Performance based on Maintenance


Increase the efficiency and effectiveness of road maintenance operations.

A multiyear contract consists of two components:

a) Road and Bridge Performance Based Maintenance,


b) Preventive Maintenance.

Objective of Highway Maintenance

In order to keep up with the demand


Maintenance has its own role; in
for traffic, highway projects and
particular, paving rehabilitation after
activities are calculated by the
the construction has been completed
amount of spending for the building
is given priority to central, rural and
of new infrastructure and the
urban facilities.
rehabilitation of existing structures.

It requires grading and paving to


correct steep grades or sharp curves,
Maintenance was based on
re-surfacing and mulching, planting,
initiatives for change.
flood and erosion management for
short alignment adjustments
Maintenance Management System:

• Planning- it provides direct relationship between programmed work and budgeted costs
and bases for meaningful comparison of planned work with actual performance
• Scheduling- timely execution of maintenance activities it composed of the following
activities:
1. Identification of maintenance needs
2. preparation of quincenal schedule
3. Work assignment.
• Directing- actions necessary to produce acceptable work.
• Reporting- acts as the source of information and data upon which control of all
components system depends.
• Control- Ensuring the maintenance work done as nearly as possible to plans and
standards and that it is carried out with the financial constraints.
A. Relationship Between Design, Construction and Maintenance [1]

Poor very
insufficient poor mixture
preparation expensive
slab thickness ratio
of the base road repair

material expensive
Poor drainage
corrosion or clean-up
design
deposition operations.

expensive
sharp ditches steep slopes manual labor
maintenance.

Poor high
bad design construction maintenance
methods costs.
Types of defects of roads and bridges and possible causes

Asphalt Pavement:

Surface Texture Deficiency


Description Possible Cause
Delamination- Loss of a Possible causes °
discrete and large area of Inadequate cleaning or
the wearing course layer. inadequate tack coat
Usually there is a clear before placement of
delineation of the upper layers ° Seepage
wearing course and the of water through
layer below (synonym - cracks to break bond
peeling) between surface and
lower layers °
Insufficient thickness
or stability of wearing
course ° Full damage
of surface layer °
Patching over failed
pavement
Polishing- Smooth and Inadequate resistance
rounding of the upper to polishing of surface
surface of the roadstone, aggregates,
usually occurs in the particularly in areas of
wheel tracks. Identified heavy traffic
partly by relative movements or where
appearance and feel of high stresses are
trafficked and nontraffic developed between
areas. Polished areas will surface and tyres
feel relatively smooth
and will sometimes be
noticeably shiny. The
quality of polishing
cannot be quantified by
observation
Ravelling- Progressive ° Separation of
disintegration of the bituminous film from
pavement surface by loss aggregates (stripping)
of both binder and due to water action,
aggregates chemicals (including
hydrocarbon oils) or
mechanical forces °
Disintegration of
aggregates ° Poor
construction
(segregation, faulty
mix design,
overheating of mix,
bad compaction,
inadequate coating of
aggregates or
aggregates Badly
embedded)
Flushing- Immersion, Excessive binder
partially or completely, of content of wearing
the aggregate into the course and associated
bituminous binder low voids °
resulting in a black and Penetration of
brilliant aspect (synonym aggregate into base
- bleeding) (low strength base)

Stripping- The loss of Poor aggregate


bond between surface chemistry •
aggregates and asphalt Water in the HMA
binder that typically causing moisture
begins at the bottom of damage • Overlays
the HMA layer and over an existing open-
progresses upward. graded surface course.
When stripping begins at Based on experience,
the surface and these overlays will
progresses downward it tend to strip
is usually called raveling
Deformation
Depression- Localized Loss of sub-base
area with elevations support ° Settlement
lower than the of service trenches °
surrounding area Consolidation of
isolated areas of soft
or poorly compacted
subgrade or
embankment
materials ° Vehicle
damage

Corrugations- Transverse Low in service stability


undulations, closely and of bituminous mix °
regularly spaced Low air voids ° Road
(synonym - ripples) locations under high
tangential traffic
stresses (steep
gradients with
considerable heavy
traffic – braking
zones).
Rutting- Longitudinal Inadequate strength
deformation in a wheel in surfacing or base °
path (synonym - Poor bond between
channeling) pavement layers °
Stop and start of
vehicles at
intersections °
Pressure exerted by a
cement concrete
pavement at
transition point with
bituminous pavement
° Low void content in
surfacing or other
layers
Cracks
Alligator cracks-it Possible causes °
resembles the alligator’s Saturated base or
skin or chicken wire. a subgrade ° Rupture of
crack that is caused by surface course due to
excessive deflection of traffic load, fatigue,
surface over unstable ageing and brittleness
subgrade of the binder °
Inadequate pavement
thickness ° Developing
from a surface
showing block
cracking
Shrinkage Crack- a large Hardening and
series of cracks,usually shrinkage of
with sharp corners or bituminous mixture °
angles. It caused by Fatigue cracking in
change in volume of fine embrittled bituminous
aggregates that have a wearing course
high content of low
penetration asphalt

Corrective measure- fill it with asphalt emulsion


slurry followed by putting slurry seal over the
entire surface.
Slippage crack-Caused by Inadequate bond of Corrective measure-
braking or turning of the wearing course with Remove the affected
wheels due to lack of underlying layer or surface layer from
good band between the insufficient thickness around the crack to
surface layer and the of wearing course. the point where you
course beneath Inadequate bond may find a good bond
be due to dust, dirt, between the layers.
oil or the absence of a Then patch the area
tack coat ° Slippage of with plant-mixed
wearing course at asphalt.
road locations with
high shearing stresses

Concrete Pavement:

Surface Texture Deficiency


Faulting- A
difference in the
levels of abutting
concrete slabs at a
transverse joint.

Rocking- Vertical ° Lack of support from sub-


movement at joint base ° Lack of or ineffective
(or crack) when load transfer dowel or tie
vehicles pass over - bars at joint
Plate 15,
sometimes the
vertical movement
cause water of
slurry to be ejected
up through the
joints or cracks
leading to loss of
support which may
be referred to as
pumping
Sagging- a ° Weakness of subgrade °
downward curve or Excessive weight or pressure
bulge in a structure
or concrete slab
Depression- Loss of sub-base support °
Localised area with Settlement of service
elevations lower trenches ° Consolidation of
than the isolated areas of soft or
surrounding area poorly compacted subgrade
or embankment materials °
Vehicle damage

Scaling- is the • poor quality of


disintegration or concrete
loose of concrete • Improper finishing
from the surface of technique
the pavement

Spalling- Break Infiltration of stones, silt or


down or other fine material into the
disintegration of joint groove/crack ° Weak
slab surface at concrete lacking in durability
edges, joints, or compaction ° Mechanical
corners or cracks damage caused by removal
of formwork etc. ° Dowel
restraint ° Corrosion of
dowels
Cracks
Block Crack- Insufficient slab thickness °
Interconnected Settlement of sub-base or
cracks forming a subgrade ° Advanced stage in
series of blocks pavement life cycle
approximately
rectangular in
shape, commonly
distributed over
the full pavement
Longitudinal crack- Poor longitudinal joint
crack running construction
longitudinally along Differential movement in the
the pavement. Can case of pavement widening
occur singly or as a
series of almost
parallel cracks.
Some limited
branching may
occur.
Transverse crack - Shrinkage of slab during
Crack or break curing, associated with
running contraction joints being sawn
transversely across too late or excessive slab
the pavement/slab length ° Dowel bar restraint
at joints ° Sub-base restraint
(lack of separation layer or
excessive irregularity

Corner crack: Crack Lack of load transfer joints °


linking a transverse Dowel bar restraint near
joint to the slab edge of slab ° Ingress of
edge or a solids into joint at edge of
longitudinal joint. slab ° Acute angles in non-
rectangular slabs ° Loss of
sub-base support

Routine Maintenance Activity:

Reference (DPWH)

BITUMINOUS PAVEMENTS

➢ PREMIX PATCHING BITUMINOUS PAVEMENTS (Related Activity Standard No. 111)

Purpose: To eliminate hazardous conditions and to provide smooth, well-drained surfaces.

Procedure:

1. Remove standing water and temporary


patching material from defect or area to
be leveled.

2. Shape defects so that: (a) depth provides


for sufficient strength; (b) sides are
vertical; (c) corners are square or slightly
rounded; (d) sides have no abrupt
changes in line; and (e) hole is cut back
into sound pavement. Add base material
if needed.

3. Clean and tack defects or area to be


leveled
4. Place premix in layers and compact each
layer. Mix should be placed only within
limits of hole and area to be leveled.
Manual Compaction
5. Final layer should be flushed with
surrounding surface.

Machine Compaction

6. Dig channels through shoulders, if


needed, to allow water to drain.

7. Check cross section, profile and drainage. Rework if needed.

Checkpoint

• Materials to be used should be dense graded asphalt mixture with maximum grain size equal to or
less than 19 mm.
• Wet part should be heated to be dried with burner
• Laying of asphalt mixture should be approx.1 cm. higher than the adjacent surroundings to give
allowance for settlement during compaction.
• When depth of pothole is more than 7 cm, compact mixture in two layers.

➢ PENETRATION PATCHING BITUMINOUS PAVEMENTS

Purpose - To provide smooth, well-drained surfaces. This activity is not suitable for repairing hazardous
conditions, since lack of mobility prevents quick response.

Procedure:

1. Remove standing water and temporary When traces of water is observed, sealing of
patching material from defect or area to cracks and joints should be done to prevent
be leveled. water intrusion to the base.
2. Shape defects so that: (a) depth provides
for sufficient strength; (b) sides are
vertical; (c) corners are square or slightly
rounded; (d) sides have no abrupt
changes in line; and (e) hole is cut back
into sound pavement. Add base material
if needed.

3. Clean and tack defects or area to be


leveled
4. Place aggregate in layers and compact
each layer.

Mix macadam aggregates and smaller


sized chippings to minimize void among
aggregates.

5. Penetrate final layer with asphalt. Avoid


using too much asphalt.
6. Apply cover sand and compact. Final Bituminous material should be applied uniformly.
layer should be flushed with surrounding The rate of application should be strictly
surface observed.
Use dry and clean coarse sand.

After the spreading of sand, compact


immediately using road roller or plate compactor
to prevent segregation of aggregates.

7. Dig channels through shoulders, if


needed, to allow water to drain.
8. Check cross section, profile and drainage. Rework if needed.

Checkpoint

• Penetration macadam is suitable for regions without asphalt plant.


• Before placing and spreading macadam aggregate, oversized and slender or flat aggregate should be
removed.
• Bituminous material should be spread uniformly so as to penetrate sufficiently and cover aggregate.
• The surface should be provided with seal coat to keep water tightness.
➢ SEALING BITUMINOUS PAVEMENTS

Purpose- To prevent further deterioration caused by entry of water.

Procedure:

1. Remove debris from cracks or clean


raveled surface.

Remove dust and mud in cracks with broom, etc.

2. (a) For individual cracks: fill cracks


completely with asphalt; use
squeegee to force asphalt into cracks
and remove excess. (b) For areas:
apply asphalt, distribute with broom
and remove excess with squeegee.

Seal coat is applied to prevent aging of asphalt


surface and wear resistance. to improve water
proofness and wear resistance.
3. Apply cover sand.
Checkpoint

• Sealing is generally applied to cracks of more than 3 mm in width.


• Loose damaged part around cracks should be removed.
• Fill cracks with bituminous material at a temperature of 180 to 200 degrees centigrade.
• For deep crack, fill it twice with asphalt.
• Sealing for wide area is effective for preventive maintenance if it is carried out regularly prior to rainy
season.
• Aggregate to be used should be clean, hard and durable.

➢ REPLACEMENT OF BITUMINOUS PAVEMENTS

Purpose - To provide smooth, well-drained pavements.

Procedure:
1. Heat asphalt at proper
temperature, if penetration or
hot asphalt is used.

Heat asphalt to proper temperature and


keep it constantly during the activity.

2. Remove damaged pavements.

Disturbed base or subbase should be


levelled and re-compacted prior to laying
bituminous pavement .
3. Add base material if needed.
4. Clean surface to be covered

5. Spray liquid asphalt at specified


rate as tack coat or prime coat.
6. Place pre-mix in layers and
compact each layer, or place
aggregate in layers, compact each
layer, penetrate final layer with
asphalt and apply cover sand.
7. Final layer should be flushed with
surrounding surface

Checkpoint:
• Considering mobility of machine, the width to be replaced should not be less than one
lane of the road.
• When the cause of damage is due to weak base or sub-base, remove and replace the
base or sub-base prior to replacement of bituminous pavement.
• Disturbed base when removing damaged bituminous pavement should be leveled and
compacted prior to laying of bituminous pavement.
• Tack coat or prime coat should be applied uniformly on bottom surface and vertical side
as well.
• Laying of asphalt mixture should be approximately 0.5 to 1.0 cm higher than the
adjacent surroundings to give allowance for settlement.

CONCRETE PAVEMENTS
➢ PATCHING CONCRETE PAVEMENTS
Purpose -To eliminate hazardous condition and to provide smooth, well-drained pavements.

Procedure:
1. Remove standing water from defect or
area to be levelled and remove all broken
pavement.
2. For defects: a.) shape defects, tack, place
pre-mix or penetration patch as in 2-1
and 2- 2. (b) For leveling: clean area, tack,
place pre-mix as in 2-1. (c) For ravelled
areas: clean area, apply asphalt and cover
aggregate as in 2-3.

Before Patching treatment.

Penetration patching is applied to cracked area


Patching with hot pre-mix
3. Dig channels through high shoulders to
allow water to drain to ditch.
4. Check cross section, profile and drainage. Rework, if needed.

Checkpoint

• Asphalt materials are widely used instead of cement materials for patching due to its easy
application. Although cement materials used on the existing PCCP is desirable for patching, it is
difficult to cut/taper on the areas to be patched. Likewise, it takes time to be cured before the
road will be opened to traffic. Remove damaged part and expose sound part by chipping off to
clean the surface to be patched.
• Damaged joint and deep cracks should be sealed prior to patching works to prevent water
intrusion into/from the lower layer of road.

➢ CRACK AND JOINT SEALING OF CONCRETE PAVEMENTS (Related Activity Standard No. 122)

Purpose - To prevent entry of water, debris and other incompressible materials into cracks and joints
and allow the free movement (expansion or contraction) of the pavement.

Procedure:

1. Heat asphalt at proper


temperature, if penetration or
hot asphalt is used.

Heat asphalt to proper temperature and


keep it constantly during the activity.
2. Remove incompressible materials
from cracks or joints, including
old filler and blow cracks or joint
clean.

3. Pour asphalt in crack or joint to


within onehalf cm of pavement
surface. For large cracks, fill with
bituminous pre-mix/ aggregate
and asphalt. Do not overfill.
4. Remove any excess asphalt by
squeegeeing.
5. Check to be sure asphalt do not
seep underneath the pavement
and that cracks remained filled.
Apply cover sand.

Checkpoint

• Heat asphalt to adequate temperature (180- 200℃). • Clean or blow thoroughly dust and mud
in cracks and joints.
• Further, remove damaged loose part of surrounding areas.
• Pour asphalt in cracks or joints kept in dry conditions.
• Causes of cracks should be identified and corrected prior to sealing works.

➢ REPLACEMENT OF CONCRETE PAVEMENTS (Related Activity Standard No. 123)

Purpose- To provide smooth, well-drained pavements and prevent progressive deterioration of the
pavement.

1. Remove damaged pavement.


2. Add base material, if needed.
3. Salvage waste material suitable for
backfill. Place remainder in a safe
location for removal

Removal of concrete slab with breaker


4. Shape hole so that sides are vertical,
corners are square and sides have no
abrupt changes in line and hole is cut
back into sound pavement.
5. Mix and place concrete and finish to
match surrounding surface or place hot
mix in layers and compact each layer.

6. Cure concrete. Barricade from traffic for


at least 14 days.

Checkpoint

• Sub-grade or sub-base in poor conditions should be replaced.


• Damaged dowel bars of existing slab should be replaced.
• For contact surface with existing slab, joint should be installed to separate old and new
concrete. In addition, underlay paper is used on the sub-base surface to reduce friction with
concrete slab.

Pavement rehabilitation – is an operation that mainly provides good riding and skid resistance
or enhances the pavement's structural performance.

The FHWA defined rehabilitation as:

“Resurfacing, restoration and rehabilitation work, restoring to the original safe useable
condition without addition to the original capacity”
• A. According to AASHTO, the primary objective of pavement rehabilitations is to
Improve:

Skid resistance
of the road
Construction
the sections
pavement life.
with poor
foundations

The primary
Smoothness of objective of Drainage
the road pavement
rehabilitations Facilities.
surface
is to Improve:

B. The efficiency of the highway system could be rated by:


1. Sufficiency ratings
2. Accident data
3. skid test
4. maintenance report
5. Public comments and suggestion

• Resurfacing – is the extension of the pavement layer to provide additional capacity over the
new roadway or bridge deck surface. The thickness of the added re-surface pavement should
not be less than 20mm.

C Restoration and Rehabilitation

• Restoration and rehabilitation work include: Replacing


faulty
Removing joints.
Spalled
and
joints
replacing
reparations
deteriorate
.
d materials.

Restoration
Major
Improveme and
pavement
nt shoulder Rehabilitation work
Work

Under Reinforcem
drains are ent of the
added Recycling of sub-base
existing
materials to
improve their
integrity in the
structure.

You might also like