Professional Documents
Culture Documents
This chapter describes specific Best Management Practices • Project design considerations : The project should be
(BMPs) for common construction activities that result in designed to integrate into existing land contours as far
erosion of construction sites and the generation of as practicable. Significant regrading of a site will
sediment , which impacts waterways and off-site property. require more costly erosion and sediment control
measures and may necessitate the installation of
Recommended erosion and sediment control measures for additional on-site drainage facilities.
construction sites are drawn from Camp Dresser & Mckee • Incorporate existing natural areas : Inventory and
et al., (1993). These measures are summarised in evaluate the existing site terrain and vegetation.
Table 39.1 in relation to BMP objectives. Disturbance of highly erosive natural areas (e.g. steep,
unstable slope areas, watercourses) should be
The following information is provided on each BMP: minimised, while protecting other areas may enhance
• a description of the BMP site aesthetics. These areas should not be disturbed
by construction activities or driven on by heavy
• suitable applications
construction equipment (refer Section 39.2.2).
• installation/application criteria
• Avoid rainy periods : Schedule major grading
• maintenance requirements (where applicable) operations during dry months. Allow enough time
• relative cost (where applicable) before rainfall begins to stabilise the soil with
• limitations vegetation or physical means (refer Sections 39.3 and
39.4) or to install temporary sediment trapping
Standard drawings for the BMP practices described are devices (refer Section 39.7).
provided in Appendix 39.B. These are suitable for inclusion • Practice erosion and sediment control all year round :
in Erosion and Sediment Control Plans (ESCPs) described in Erosion may be caused during dry seasons by ‘freak’
Chapter 41. They may be used to supplement and provide rainfall, wind, and vehicle tracking. Therefore, keep
details for erosion and sediment control BMPs shown on the site stabilised all year round, and retain wet
the project drawings. season sediment trapping devices.
• Minimise the extent of soil exposed at one time :
Schedule project activities to disturb only small
39.2 SITE PLANNING CONSIDERATIONS portions of the site at any one time. Complete
grading as soon as possible. Immediately stabilise the
39.2.1 Scheduling disturbed portion before grading the next portion.
Practice staged seeding, i.e. re-vegetate cut and fill
slopes as the work progresses.
• Trenching : Close and stabilise open trenches as soon
as possible. Sequence trenching operations so that
most open portions of the trench are closed before
new trenching is begun.
BMP OBJECTIVES
Good House-
Slopes and
BMP CATEGORY
Perimeter
Disturbed
Disturbed
Channels
Standard
Numbers
Minimise
Drawing
Stabilise
Practice
keeping
Internal
Contain
Erosion
Control
Control
Protect
Waste
Area
Area
Site
Site Planning Considerations
Scheduling -
Vegetative Stabilisation
Mulching -
Physical Stabilisation
Dust Control -
Diversion of Runoff
Sediment Trapping/Filtering
Carefully planned preservation of existing vegetation There is little cost associated with preserving existing
minimises the potential of removing or injuring existing vegetation if properly planned during the project design.
trees, shrubs, and/or grasses that serve as erosion Aesthetic benefits may also enhance property values.
controls.
(f) Limitations
Corridors of vegetation act as buffer zones to separate
disturbed land from an adjacent watercourse, protected • Requires forward planning by the owner/developer,
forest, or other sensitive areas. Leaving a clearly marked contractor, and design staff.
buffer zone around these unique areas will help to • For sites with diverse topography, it may be difficult
preserve them as well as take advantage of their natural and expensive to save existing trees while grading the
erosion prevention and trapping characteristics. site satisfactorily for the planned development.
• Areas within the site where no construction activity 39.3 VEGETATIVE STABILISA TION
occurs, or occurs at a later date.
39.3.1 Seeding and Planting
• Sensitive areas where natural vegetation exists and
should be preserved, such as steep slopes,
watercourses, and building sites in wooded areas.
• Areas where Local, State, and Federal government
requires preservation, such as: vernal pools, wetlands,
marshes, and certain native trees, etc.
(c) Installation/Application Criteria compaction and cracking of soil, and aids the growth of
seedings and plantings by holding the seeds, fertilisers,
Type of vegetation, site, and seedbed preparation, planting and topsoil in place until growth occurs.
time, fertiliser, and water requirements should be
considered for each application. Mulching can be used either to temporarily or permanently
stabilise cleared or freshly seeded areas. Types of mulches
(i) Grasses include organic materials, straw, wood chips, bark or other
wood fibres, decomposed granite, and gravel. A variety of
• Select grasses that are tolerant of short -term mats of organic or inorganic materials and chemical
temperature extremes and waterlogged soil stabilisation may be used with mulches.
conditions.
• Soil must be fertilised and mechanically stabilised. (b) Suitable Applications
(d) Maintenance Requirements Organic mulch materials such as straw, wood chips, bark,
and wood fibre, are most effective where re -vegetation will
• Shrubs and trees must be adequately watered, be provided by reseeding. The choice of mulch should be
fertilised, and pruned if needed. based on the size of the area, site slopes, surface
• Grasses may need to be watered and mowed. conditions (such as hardness and moisture), weed growth,
and availability of mulch mat erials.
(e) Limitations
• May be used with netting to supplement soil
• Permanent and temporary vegetation may not be stabilisation.
appropriate in dry periods without irrigation. • Apply to planting areas where slopes are 2(H):1(V) or
• Fertiliser requirements may have the potential to greater.
create stormwater pollution if improperly applied. • Binders may be required for steep areas, or if wind
and runoff is a problem.
• Type of mulch, binders, and application rates should
39.3.2 Mulching
be recommended by manufacturer/contractor.
(e) Limitations
(f) Limitations
• Steep slopes.
Dust control measures are used to stabilise soil from wind
erosion, and reduce dust generated by construction
(c) Installation/Application Criteria
activities.
Site Condition
Wet Gravel or Temporary Gravel Haul Minimise
Permanent Suppression Chemical Construction
Mulching Asphalt Truck Extent of
Vegetation (Watering) Suppression Surfacing Entrance/Equipment Covers Area
Wash Down Disturbed
Disturbed areas
subject to traffic
Material stockpile
stabilisation
Demolition
Clearing/Excavation
Truck traffic on
unpaved roads
Mud/dirt carry-out
1
Salts Organic, Non-Petroleum Based Petroleum Based Products
Products
2
Chemical Types • Calcium Chloride • Calcium Lignosulfonate • Bunker oil
• Magnesium Chloride • Sodium Lignosulfonate • Asphalt Primer
• Natural Brines • Ammonium Lignosulfonate • Emulsified Asphalt
Limitations Can lose effectiveness in dry Not affected by dry weather and Generally effective regardless of
periods with low humidity. low humidity. Leached from climatic conditions. May pothole
Leaches from road in heavy rain. road in heavy rain if not in wet weather.
sufficiently cured.
Not recommended for gravel Best performance on gravel Best Performance on gravel
road surfaces with low fines. roads with high surface fines roads with 5-10% fines.
Recommended 10-20% fines. (10-30%) and dense compact
surface with loose gravel.
Comments May become slippery when wet Ineffective on gravel surfaces Creates a hardened crust.
on gravel surfaces with high low in fines. May become
fines. slippery when wet on gravel
surfaces with high fines content.
1
Motor oils and oil treatments are not recommended due to adverse effect on plant life and groundwater
2
Not recommended due to adverse effects on plant life
Most dust control measures require frequent, often daily, Temporary waterway crossings should be installed at all
attention. designated crossings of perennial and intermittent
waterways on the construction site, as well as for dry
(e) Relative Cost channels which may be significantly eroded by construction
traffic.
Installation costs for water/chemical dust suppression are
low, but annual costs may be quite high since these (c) Installation/Application Criteria
measures are effective for only a few hours to a few days.
Requires knowledge of stream flows and soil strength and
(f) Limitations should be designed under the direction of a suitably
qualified engineer with knowledge of both hydraulics and
• Watering prevents dust for only a short period and construction loading requirements for structures.
should be applied daily (or more often) to be effective.
• Over-watering may cause erosion. (d) Maintenance Requirements
• Oil should not be used for dust control because the oil
• Inspect weekly and after each significant rainfall,
may migrate into waterways and/or seep into the soil.
including assessment of foundations.
• Certain chemically -treated subgrades may make soil
• Periodically remove silt from crossings.
water repellant, increasing runoff.
• Replace lost aggregate from inlets and outlets of
culverts.
39.4.3 Temporary Waterway Crossing
(e) Limitations
(a) Description
39.4.4 Construction Road Stabilisation
transported off-site on the wheels of construction vehicles. Management of construction traffic is subject to air quality
Dirt roads can become so unstable during wet weather control measures. Contact the Local Authority for specific
that they are virtually unusable. requirements.
• Repair any eroded areas immediately. • Provide ample turning radii as part of the entrance.
• Gravel construction roads are moderately expensive, • Inspect monthly and after each rainfall.
but cost is often balanced by reductions in • Replace gravel material when surface voids are visible.
construction delays. • Remove all sediment deposited on paved roadways
• No additional costs for dust control on construction within 24 hours.
roads should be required above that needed to meet • Remove gravel and filter fabric at completion of
local air quality requirements. construction.
• The roadway must be removed or paved when • Requires periodic top dressing with additional stones.
construction is complete.
• Should be used in conjunction with street sweeping on
• Certain chemical stabilisation methods may cause adjacent public right-of-way.
stormwater or soil pollution and should not be used
(refer Section 39.4.2).
39.5.1 Earth Bank • Inspect periodically and after every significant rainfall.
• Repair as necessary
(e) Limitations
An earth bank does not in itself control erosion or remove Regrading the site to remove the bank may add additional
sediment from runoff, it prevents erosion by directing cost.
runoff to an erosion control device such as a sediment trap
or basin or directing runoff away from and erodible area.
Temporary earth banks should not adversely impact 39.5.2 Diversion Channel
adjacent properties and must conform to any local
floodplain management regulations. They should not be
used in areas with slopes greater than 10%.
• Maximum drainage area per slope drain is 2 hectares. • Inspect after each significant rainfall for erosion
For larger areas, use a paved chute, rock lined and/or disruption of the rock, and repair immediately.
channel, or additional pipes. • Grouted or wire-tied rock riprap can minimise
• Clogged slope drains will force water around the pipe maintenance requirements.
and cause slope erosion.
• Dissipation of high flow velocities at the pipe outlet is (e) Limitations
required to avoid downstream erosion.
• Large storms often wash away rock outlet protection
• Failure can result in flooding and severe erosion.
and leave the area susceptible to erosion.
• Sediment captured by the rock outlet protection may
be difficult to remove without removing the rock.
39.6 FLOW VELOCITY REDUCTION
• Outlet protection may negatively impact the channel
habitat.
39.6.1 Drainage Outlet Protection
(a) Description
(b) Suitable Applications A check dam is a small temporary dam constructed across
a diversion channel or swale. Check dams reduce the
• Wherever discharge velocities and energies at the velocity of concentrated stormwater flows, thereby
outlets of culverts, conduits, or channels are sufficient reducing erosion of the diversion channel or swale and
to erode the next downstream reach. promoting sedimentation behind the dam. If properly
• Rock outlet protection is best suited for temporary use anchored, brush or rock filter berms (refer Section 39.7.3)
during construction because it is usually less expensive may be used for check dams.
and easier to install than concrete aprons or energy
dissipators. (b) Suitable Applications
• A sediment trap below the drainage outlet is
recommended if runoff is sediment -laden. • Primarily used in small channels in steep terrain where
velocities exceed 0.6 m/s.
• Permanent rock riprap protection should be designed
and sized by an engineer as part of the culvert, • Used to prevent erosion by reducing the velocity of
conduit, or channel design. channel flow in small intermittent channels and
temporary swales.
(c) Installation/Application Criteria • May also promote sedimentation behind the dam, but
should not be considered to be a primary sediment
Rock outlet protection is effective when the rock is sized trapping device because subsequent storms will scour
and placed properly. When this is accomplished, rock and resuspend much of the trapped sediment.
outlets do much to limit erosion at pipe outlets. Rock size
should be increased for high velocity flows. The best (c) Installation/Application Criteria
results are obtained when sound, durable, angular rock is
used. • Check dams should be of sufficient height and spacing
to allow small pools to form between each one.
• Remove accumulated sediment whenever it reaches • Use the Rational Method to estimate flows draining to
one-third of the height of the dam, or one-half of the a sediment fence (refer Section 14.5).
sump depth if a sump is provided. • Turn the ends of the fence uphill at not more than
30 m intervals to limit the amount of concentrated
(e) Limitations runoff at any one point along the fence and to prevent
runoff from flowing around the fence.
• Use only in small open channels, which drain an area • Install along a level contour, so water does not pond
of 4 hectares or less. more than 600 mm deep at any point along the
• Not to be used in streams, or in lined or vegetated sediment fence.
channels. • Provide an area behind the fence for runoff to pond
and sediment to settle (approximately 280 m2 per
hectare draining to the sediment fence).
39.7 SEDIMENT TRAPPING/FILTERING • The maximum ground slope perpendicular to the
fence should be 1(H):1(V)
39.7.1 Sediment Fence • Leave an undisturbed or stabilised area immediately
downslope of the fence.
• Select filter fabric which retains 85% of the soil, by
weight, based on sieve analysis, but is not finer than
an equivalent opening size of 70.
• Sediment fences should remain in place until the
disturbed area is permanently stabilised.
• intercepting and detaining small amounts of sediment • Do not use where 85% of the soil, by weight, passes
from disturbed areas during construction operations in through a No. 200 sieve as the filter fabric will clog.
order to promote sedimentation behind the fence
• Do not place the fence on a slope, or across any
• decreasing the velocity of low flow s (up to 15 l/s) in contour line.
swales and small diversion channels.
• Do not use in streams, channels, or anywhere the flow
is concentrated.
Sediment fences are generally effective in locations where
the flow is concentrated and are only applicable for sheet • Do not use in locations where ponded water may
or overland flows. cause flooding.
(f) Limitations
Stacking sand bags along a level contour creates a barrier, 39.7.3 Brush or Rock Filter
which detains sediment -laden water by ponding upstream
of the barrier water, thereby promoting sedimentation.
Sand bags provide a semi-permeable barrier in potentially
wet areas and are more permanent than sediment fences.
They also allow for easy on-site relocation to meet
changing needs during construction.
• Inspect after each rainfall. • Leave area behind berm where runoff can pond and
sediment can settle.
• Reshape or replace damaged sand bags immediately.
• Remove sediment when it reaches 150 mm in depth.
• Inspect monthly and after each rainfall. • Five types of inlet protection are presented below,
• If berm is damaged, reshape and replace lost or however, other effective methods and proprietary
dislodged rock. devices are available:
• Remove sediments when depth reaches the lesser of ° Filter Fabric Fence : Appropriate for catchment
one-third the berm height or 300 mm. areas less than 0.4 hectares with a slope of less
than 5%.
(e) Relative Cost ° Block and Gravel Filter : Appropriate for flows
greater than 15 l/s.
• Brush filter : Low to moderate cost if debris from on- ° Gravel and Wire Mesh Filter : Used on kerb or
site clearing and grubbing is used. drop inlets where construction equipment may
• Rock filter : Expensive, since use of off-site materials, drive over the inlet.
hand construction, and demolition/removal are usually ° Sand Bag Barrier : Used to create a small
required. sediment trap upstream of inlets on sloped, paved
streets.
(f) Limitations
° Excavated Drop Inlet Sediment Trap : An
excavated area around the inlet to trap sediment
• Rock berms may be difficult to remove.
(refer Section 39.7.5).
• Removal problems limit their usefulness in landscaped
• Use only for drainage areas smaller than 0.4 hectares
areas.
unless a sediment trap first intercepts the runoff.
• Not appropriate for drainage areas greater than
• Grates and spaces around all inlets should be sealed
2 hectares.
to prevent seepage of sediment -laden water.
• Runoff will pond upstream of the filter, possibly
• Provide an area or sediment sump around the inlet for
causing flooding if there is insufficient storage space.
water to pond without flooding surrounding structures
and property.
39.7.4 Drainage Inlet Protection • Excavate sediment sumps (where needed) to a depth
of 0.3 to 0.6 m with 2(H):1(V) side slopes around the
inlet.
• At the outlet of all disturbed catchment areas greater The effective design and operation of sediment basins
than 2 hectares. depends primarily on the nature of the soil materials likely
• At the outlet of smaller disturbed catchment areas, as to be eroded and washed into the basin.
necessary.
The design approach allows for differences in the settling
• Where permanent detention basins or water quality
behaviour of different size particles in water. Clearly,
control struct ures will be located.
coarse-grained sediment will settle quicker than fine-
• Should be used in association with earth banks, grained sediment, and some types of clay particles never
diversion channels pipes, and other measures used to settle at all unaided.
divert disturbed areas into the basin and divert
undisturbed areas around the basin. Table 39.4 lists the three different soil types discussed in
this section, and the design considerations which apply to
(c) Installation/Application Criteria sediment basin design and operation for each soil type.
This approach is based in part on recommendations from
• Sediment basins must be installed entirely within the the NSW Department of Housing (1998).
limits of the site.
• Construct before clearing and grading work begins.
• Basins must not be located in a stream. Table 39.4 Sediment Basin Types and Design
Considerations
• All basins should be located where failure of the
embankment would not result in loss of life, damage
to homes or buildings, or interruption of use or service Soil Basin Design
of public roads or utilities. Soil Description
Type Type Considerations
• Local ordinances regarding health and safety must be
Coarse-grained C Dry Settling velocity,
adhered to.
sand, sandy sediment storage
• Large basins may be subject to State and/or Federal loam: less than
dam safety requirements. Refer to Section 35.5 for 33% <0.02mm
dam design considerations.
• Sediment traps are attractive to children and can be Fine-grained F Wet Storm
very dangerous. Adequate safety precautions must be loam, clay: more impoundment,
provided by restricting access to the site or access to than 33% < sediment storage
the basin with suitable fencing. 0.02mm
• For dry basins, securely anchor and install an anti- Dispersible fine- D Wet Storm
seep collar on the outlet pipe/riser. grained clays as impoundment,
• A stable emergency spillway must be installed to per type F, more sediment storage,
safely convey flows up to and including 10 year ARI. than 10% of assisted flocculation
The flood volume for this flow must be large enough dispersible
to contain the flow without causing upstream damage material
and/or overtopping of the embankment.
• The basin should be sized in accordance with the The design capacity of a sediment basin is the sum of two
criteria given in Section (d). components:
• The basin length to settling depth ratio should be less
• a settling zone at least 0.6 m deep to contain runoff
than 200:1.
and allow suspended sediment to settle, and
• The basin length to width ratio should be greater than
• a sediment storage zone at least 0.3 m deep to store
2:1. If not , baffles should be provided to prevent
settled sediment until the basin is cleaned out. In
short-circuiting.
some cases, basins may be sized to trap sediment for
• Side slopes should not be steeper than 2(H):1(V) to the life of the construction activity
prevent sloughing.
• Sediment basins may be capable of trapping smaller Where soils of more than one type are present on a site,
sediment particles if sufficient detention time is sediment basins shall be designed to meet the most
provided. However, they are most effective when stringent criterion applicable. Usually, because type F or D
used in conjunction with other BMPs to minimise the soils are more difficult to settle, they will govern the design
amount of sediment mobilised and carried to the if present on any significant portion of the basin
basin. catchment.
(i) General Design Considerations larger design event. In these cases the 6 month ARI event
is recommended.
• For dry basins, the embankment or outlet structure
• The sizing guidelines have been derived using particle
must be designed such that the basin will completely
settling theory for constant flow conditions equal to
empty within 24 hours after a storm event.
the peak rate of flow in the design storm. Peak flow
• Locate sediment basins as close as possible rates shall be estimated using the Rational Method
downstream of disturbed land to trap sediment -laden (refer Chapter 14).
runoff.
• An overall particle removal target of 85% has been
• Locate basins away from normal construction activities adopted.
to minimise disturbance and the need for repairs.
• With fine-grained soils, sediment trapping efficiency is The sizing guidelines were derived assuming particle
reduced and more emphasis is therefore needed on distribution and settling velocities as follows:
erosion control measures.
• Temporary sediment basins should be kept in service
until the works for which they were designed are Settling velocity
Diameter (mm) Percentage
completed and at least 90% of the contributing (m/sec)
catchment has been stabilised.
0.02 30% 0.00029
(ii) Design of Dry Sediment Basins 0.05 55% 0.0019
Dry sediment basins should be used on Type C soils. 0.10 15% 0.007
Type C soils are characterised by a high percentage of
coarse particles. Less than one-third of particles are less
than 0.02 mm in size. With these soils, an acceptable The sizing guidelines for dry sediment basins for normal
discharge water quality can be achieved by providing a situations are given in Table 39.5. The volume of the
short residence time to allow the particles to settle out. settling zone and sediment storage components should
each be half of the total basin volume. However, in areas
For most construction situations, the design storm should of high soil erodibility, the sediment storage volume should
be the 3 month ARI event. If the construction site is be adjusted so as to retain the estimated average 2-month
upstream of an environmentally sensitive area, or if soil loss from the disturbed area of the catchment. This
construction time is likely to exceed 2 years, the Local calculation shall be done using the Modified Universal Soil
Authority may require sizing of the sediment basin for a Loss Equation, as described in FRIM (1999).
Parameter Site Runoff Potential Magnitude of Design Storm Event in mm (see Appendix 13.C)
20 30 40 50 60
(iii) Design of Wet Sediment Basins Sizing guidelines for wet sediment basins for normal
situations are given in Table 39.6. The volume of the
Wet sediment basins should be used on Type F or Type D sediment storage component for wet sediment basins
soils. Recommendations for wet sediment basins are should be 50% of the settling zone volume. However, in
based on the observation that traditional approaches to areas of high soil erodibility, the sediment storage volume
settling fine sediments, particularly dispersible clays, have should be adjusted in a manner similar to that for Type C
been ineffective. The approach adopted is therefore one soils.
of storm containment , fully impounding runoff from a
nominated design event. (e) Maintenance Requirements
The design event is selected using a risk-based approach. The management and operation of sediment basins also
The rainfall and predicted runoff from that design event is depends primarily on the nature of the soil materials likely
then used to size the 'settling' zone of the basin. to be eroded and washed into the basin.
The target water quality should be specified by the Local be dosed with a flocculating agent. Supplies of flocculant
Authority in terms of the Interim National Water Quality shall be kept on or near the site for this purpose. Such
Standards for Malaysia (INWQS). Typically, Class II dosing should occur within 24 hours of a rainfall event.
standards will be required (e.g. TSS < 50 mg/L). If this
quality is not achieved by settling, a flocculating agent (f) Limitations
(e.g. gypsum, enzymes) should be added to the stored
water. • The basin should have shallow side slopes (maximum
4(H):1(V)) or be fenced to prevent drowning.
A peg or other mark should be placed in the basin to • Sites with very fine sediment (fine silt and clay) may
indicate the top of the sediment storage zone. A floating require longer detention times for effective sediment
inlet should be used on the pump to ensure that settled removal.
sediment is not picked up during the dewatering process.
• Basins in excess of certain depth and storage volume
criteria must meet State and/or Federal dam safety
Because Type D soils contain a significant level of
criteria.
dispersible materials, sediment basins for these soils must
• Standing water may cause mosquitoes or other pests
to breed.
24-20
Erosion and Sediment Control Measures
Problem: To determine the size of a dry sediment basin and outlet structures required for the Selangor Estate
development shown in model plan ESCP2 in Appendix 41.B2. The catchment area for the development is
6 hectares and the following assumptions are made for the sizing of the basin:
Solution:
107 n L 0.333
From Equation 14.1, t o =
S 0.2
From Equation 14.2(a), t total = t A(L A) + t B(L A +L B) - t B(L A)
From Table 39.5 for a 3 month ARI, the required surface area is 333 m2/ha and the required total volume is
400 m3/ha.
The surface area required for the site = 333 x 6.0 = 1998 m2
(Note: this is the average surface area for the settling zone volume, i.e. at mid-depth)
The total basin volume required for the site = 400 x 6.0 = 2400 m3
From Table 39.5, the required settling zone V 1 = 1200 m3 (half the total volume) and the settling zone depth
y 1 = 0.6 m.
L1 67
ratio = = 2.23 > 2; OK
W1 30
The required sediment storage zone volume is half the total volume, V 2 = 1200 m3
For a side slope Z = 2(H):1(V), the dimensions at the top of the sediment storage zone are,
d1
W2 = W1 – 2 x x Z = 3 0 – 2 x 0.3 x 2 = 28.8 m
2
d1
L2 = L1 – 2 x x Z = 67 – 2 x 0.3 x 2 = 65.8 m
2
The required depth for the sediment storage zone, which must be at least 0.3 m, can be calculated from the
following relationship,
V2 = Z 2y 3
2 −Zy 2
2 (W 2 + L 2 ) + y 2 (W 2 L 2 )
Which gives,
3 2
1200 = 4y 2 − 189.2 y 2 + 1895 y 2
y1
At top water level: W TWL = W 1 + 2 x Z x = 31.2 m say, 31 m
2
y1
L TWL = L 1 – 2 x Z x = 68.2 m say, 68 m
2
y
Base: W B = W 1 - 2 x Z x 1 + y 2 = 26.1 m say, 26 m
2
y
L B = L 1 - 2 x Z x 1 + y 2 = 63.1 m say, 63 m
2
The pipe is to be provided with sufficient small orifice openings to ensure that the basin will completely drain
within 24 hours after filling.
An estimate of the total area of orifice openings required can be obtained by rearranging Equation 19.5 and
using the average surface area and total depth of the basin,
At height increments of 200 mm, starting at the bottom of the pipe, put six rows of 7 x 50 mm orifices evenly
spaced around the pipe.
The emergency spillway must be designed for a 10 year ARI flood (see Section 39.7.6(c)). The sill level must
be set a minimum 300 mm above the basin top water level. To simplify the calculations, the following
assumptions are made:
• assume riser pipe flow is orifice flow through the top of the pipe only
• riser pipe head is 300 mm, i.e. the height between the top of the pipe and the spillway crest level
Q spillway = Q 10 – Q riser
C .10 I 10 . A
Q 10 =
360
The 10 year ARI rainfall intensity for Kuala Lumpur is derived from Equation 13.3 and Table 13.3, for a 10
minute duration. 10I60 = 83.2 mm/h, 10I30 = 129.2 mm/h, and F = 1.28. Therefore,
10
I 10 =
(64.6 − 1.28 ⋅ (83.2 − 64.6 )) = 245 mm/hr
(10 / 60)
From Equation 14.7, with C = 0.84 (Category (4) in Design Chart 14.3),
From Equation 20.2 for orifice flow and assuming an orifice discharge coefficient of 0.60,
π ( 0 .9 )
2
Q riser = C 0 A0 2 g H 0 = 0 .6 x x 2 x 9 .81 x 0 .3 = 0.93 m3/s
4
Therefore, allowing for the riser pipe flow the required spillway capacity is:
Trial dimensions: B = 5.0 m , H p = 0.5 m and C sp = 1.65 from Design Chart 20.2,
Q spillway = 1.65 x 5.0 x 0.5 1.5 = 2.74 m3/s > 2.50 m3/s; OK
Problem: To determine the size of a wet sediment basin for the development shown in model plan ESCP2 in
Appendix 41.B2 assuming it is located in Ipoh, Perak. The catchment area for the development is 6 hectares
and the following assumptions are made for the sizing of a wet sediment basin:
Solution:
From Appendix 13.C, the 75th percentile 5-day storm event is 36.75 mm.
From Table 39.6, the required settling zone volume is 176 m3/ha and the required total volume is 264 m3/ha
(both interpolated and rounded to nearest whole number).
The settling zone volume required for the site = 176 x 6.0 = 1056 m3
The total basin volume required for the site = 264 x 6.0 = 1584 m3
L1 63
ratio = = 2.25 > 2; OK
W1 28
The required sediment storage zone volume is one-third the total volume or the difference between the total
volume and the settling zone volume, V 2 = 528 m3
For a side slope Z = 2(H):1(V), the dimensions at the top of the sediment storage zone are,
d1
W2 = W1 – 2 x x Z = 2 8 – 2 x 0.3 x 2 = 26.8 m
2
d1
L2 = L1 – 2 x x Z = 6 3 – 2 x 0.3 x 2 = 61.8 m
2
The required depth for the sediment storage zone, which must be at least 0.3 m, can be calculated from the
following relationship,
V2 = Z 2y 3
2 −Zy 2
2 (W 2 + L 2 ) + y 2 (W 2 L 2 )
Which gives,
3
528 = 4y 2 − 177. 2 y 22 + 1656 y 2
y1
At top water level: W TWL = W 1 + 2 x Z x = 29.2 m say, 29 m
2
y1
L TWL = L 1 – 2 x Z x = 64.2 m say, 64 m
2
y
Base: W B = W 1 - 2 x Z x 1 + y 2 = 25.4 m say, 25 m
2
y
L B = L 1 - 2 x Z x 1 + y 2 = 60.4 m say, 60 m
2
107 n L 0.333
From Equation 14.1, t o =
S 0. 2
From Equation 14.2(a), t total = t A(L A) + t B(L A +L B) - t B(L A)
• The emergency spillway must be designed for a 10 year ARI flood when the basin is already full. The sill
is set at the basin top water level.
Q spillway = Q 10
C . 15 I 10 . A
Q 10 =
360
For Ipoh, Perak and t c = 15 minutes, the 10 year ARI rainfall intensity is derived from Equation 13.3 and
Table 13.3. 15I60 = 87.4 mm/h, 15I30 = 137.8 mm/h, and F = 0.80. Therefore,
Trial spillway dimensions: B = 5.0 m , H p = 0.5 m and C sp = 1.65 from Design Chart 20.2.
Therefore,
Q spillway = 1.65 x 5.0 x 0.5 1.5 = 2.74 m3/s > 2.73 m3/s; OK
Physical Stabilisation
Diversion of Runoff
Sediment Trapping/Filtering
_
Vegetated Buffer Area
Physical Stabilisation
Diversion of Runoff
SD
Slope Drain SD I-7
Sediment Trapping/Filtering
ST
Sediment Trap SD I-15
SB
Sediment Basin SD I-16
Barrier Fence _ B B