You are on page 1of 2

Scope of Work

Project Definition

1.1 Client and Project Information


Name of Client/Organization Name of Project
PAMPANGA 1ST DISTRICT ENGINEERING
OFFICE CONSTRUCTION OF RCDG BRIDGE

Name of Contact Person Project Location Project No.


MALIWALU, BACOLOR,
LOURDES MAE ARCEO 88HP9999
PAMPANGA
Contact’s Mailing Address City Province
arceo.lm@dpwh.com BACOLOR PAMPANGA
City Province Postal Code E-mail Address of Contact Person
BACOLOR PAMPANGA 2001 arceo.lm@gmail.com
Telephone Number Ext. Fax Number
777 666-555 111 222 33-4444
1.2 General Objective
THE OBJECTIVE OF THIS PROJECT IS TO CONSTRUCT A REINFORCED CONCRETE
DECK GIRDER BRIDGE AT MALIWALU, BACOLOR, PAMPANGA NEAR AT THE EXISTING
OLD STEEL BRIDGE FOR THE ACCESSIBILITY OF THE RESIDENCE IN BARANGAY
MALIWALU, BACOLOR, PAMPANGA.
1.3 Description of Project:
PROPOSAL OF RCDG BRIDGE AT MALIWALU, BACOLOR, PAMPANGA

1.4 Pre-design work completed to date (or) required:


SEPTEMBER 20, 2020 (150 CALENDAR DAYS)

1.5 Timeline of Project:


Start Design Work: Start Construction: Planned Occupancy Date:
MARCH 20, 2020 APRIL 20, 2020 SEPTEMBER 20, 2020
1.6 CONSTRUCTION COST ESTIMATE
A total Contract price of ELEVEN MILLION ONE HUNDRED FORTY SIX THOUSAND
THREE HUNDRED NINETY FIVE PESOS & 84/100 (11,146,395.84) Philippine pesos

1.7 Approval Requirements:


APPROVAL OF DEPARTMENT OF PUBLIC WOKRS AND HIGHWAYS REGION III

CONSTRUCTION SCHEDULE
The following schedule identifies the estimated design and construction phases for this
project and the estimated durations.

PROJECT PHASE ESTIMATED DURATION (CALENDAR DAYS)


1. Site Access Approvals & Schedule Design Kick-off Meeting 14

2. Schematic Design Phase 25% (Minimum) 28


• Project Team & DPMC Plan/Code Unit Review & Comment 14

3. Design Development Phase 50% (Minimum) 60


• Project Team & DPMC Plan/Code Unit Review & Comment 14

4. Final Design Phase 100% 42


• Project Team & DPMC Plan/Code Unit Review & Approval 14

5. Permit Application Phase 7


• Issue Plan Release

6. Bid Phase 42

7. Award Phase 28

8. Construction Phase 150