Professional Documents
Culture Documents
CH 5 2
CH 5 2
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
5/14/2019 Months
By: Gebrewold T.(M.Sc.)
Example
o
represented by a circle ‘ ’ in a network which
is also known as a node or connector.
( E S ) ij Ei
b) Earliest finish time of activity (i, j) is the earliest starting time
plus the activity time. i.e.,
( E f ) ij ( E S ) ij Dij
or
( E f ) ij Ei Dij
The computed ‘E’ values are put over the respective circles
representing each event.
EL
Remember that all E’s have been computed by forward pass
computations.
Step 2. Latest finish time of activity (i, j) is equal to the latest event
time of event j. i.e.,
( L f ) ij L
( LS ) ij ( L f ) ij Dij
or
( LS )ij L j Dij
Step 4. Latest event time for event I is the minimum of the latest
start time of all activities originating from the event, i.e.,
Li min. j [(LS )ijfor all immediate successors of (i, j)] min. j[(Lf )ij - Dij] min. j[ L j Dij ]
Slack (i) Li Ei
the events with zero slack times are called critical
events. In other words, the event i is said to be critical
if
Ei Li
5/14/2019 By: Gebrewold T.(M.Sc.)
ii) Critical activity: Since the difference
between the latest start time and earliest
start time of an activity is usually called as
total float, the activities with zero total
float are known as critical activities.
In other words an activity is said to be
critical if a delay in its start will cause a
further delay in the completion date of the
entire project.
Most likely time t l the duration that would occur most often if
the activity was repeated many times under
the same conditions.
(t o 4t l t p )
te
6