Professional Documents
Culture Documents
88+638
OF NAGDA-DHAR-GUJRI ROAD SECTION OF SH-31 TO TWO LANE
FROM KM. 68+800 TO KM.138+300”
2017-2018
MAJOR PROJECT REPORT
(PHASE – 1)
Major Project Report Phase – I report Submitted to
Rajiv Gandhi Proudyogiki Vishwavidyalaya, Bhopal (M.P.) towards the
partial fulfillment of
The degree of Bachelor of engineering (Civil)
Date : _______________
RECOMMENDATIONS
We are pleased to recommend that the project work of B.E. final year students
Major Project Phase-1 entitled “STUDY, DESIGN AND ANALYSIS OF GRADE
SEPARATOR AT CH. 88+638 OF NAGDA-DHAR-GUJRI ROAD SECTION OF SH-31
TO TWO LANE FROM KM. 68+800 TO KM.138+300” Submitted to Rajiv Gandhi
Proudyogiki Vishwavidyalaya, Bhopal during the year 2017 completed under the
supervision for acceptance as partial fulfillment for the requirement for the award of degree
of Bachelor of Engineering (Civil).
We found us beholden to put on record the generous help rendered by all concerned with
the successful completion of this work.
It is our proud privilege to express our gratitude and vulnerable regards to our esteemed
guide Dr. R.K. Khare Sir, Professor CE-AMD, SGSITS, Indore for extending their
valuable time, guidance, expertise, criticism and encouragement for the completion of the
project. They have taken personal efforts and inspired us to carry out the project
successfully so as to obtain fruitfulness which would be beneficial to all the concerned and
hence to the society. Without their guidance and suggestions, an urge to bring out the best
would not have been possible.
We are also thankful to Dr. D.J. Killedar Sir, Professor and Head CE-AMD, SGSITS,
Indore for his valuable cooperation and timely support in completing this project work.
We are extremely thankful to Prof. R.K. Saxena Sir, Director, SGSITS, Indore, for
providing the necessary facilities and financial assistance.
We are very thankful to Prof. M.K. Laghate Sir, Professor CE-AMD, SGSITS, Indore for
their kind cooperation.
Thank You
Projectees:
Adhirath patel Anshul mishra
Bhawna dogne Sakshi Kirar
Mohd. Fuzail khan Radheshyam gurjar
Tushar maravi Antarsingh singhar
Mausam meshram
This report is an important initiative intended to present Study, Design and Analysis of
Grade Separator.
The intent of this report is to summarize the preliminary analysis and design results
associated with GRADE SEPARATOR AT CH. 88+638 OF NAGDA-DHAR-GUJRI
ROAD SECTION OF SH-31 TO TWO LANE from km 68+800 to km 138+300. This
project was authorized by Madhya Pradesh Road Development Corporation and undertaken
by Path India Ltd, Mhow, Madhya Pradesh. An attempt is made to study the process of
design of grade separator in accordance with IRC standard code of practice, specifying the
various loading possibilities and incorporating various design parameters.
Alternative slab designs including solid slab and I beam girder for the bridge have been
represented. It is suggested that the final design should further depend upon information
related to the project including detailed geotechnical investigation, hydrological analysis,
and assessment of traffic, constructability, maintenance, schedule and cost factors.
The findings, design and recommendations have been appropriately presented for assistance
subjected to verification and modification for final design.
Table Of Content
DECLARATION i.
RECOMMENDATION ii.
CERTIFICATE iii.
ACKNOWLEDGMENT iv.
ABSTRACT v.
1. INTRODUCTION 1-2
1.1.2. Advantages.
1.1.3. Disadvantages.
2.2. Components.
2.3. Classification.
3.1. Objective.
5.3. Slab
5.4. girder
INTRODUCTION
Due to traffic congestion, development of Nagda-Dhar-Gujri Road section of SH-31 to two lane from km 68 + 800
to km 138 + 300, a grade separator at Ch. 88+638 has been provided.
1.1 Grade separator is a form of interaction in which one or more conflicting movements or intersecting
ground transport facility such as road, rail, pedestrian way or cycle path are segregated in space. Flyover,
railway over bridges, under bridges, subways and underpasses both for vehicular pedestrian traffics are all
grade separators and will be reckoned as such.
Fully separated
These junctions connect two freeways:
Stack interchange (two-level, three-level, or four-level stack, depending on how many levels cross at
the central point)
Cloverleaf interchange
Partially separated
These junctions connect two roads, but only one is fully grade-separated, i.e. traffic on one road does not
have to stop at yield lines or signals on one road, but may have to do so when switching to the other:
Diamond interchange
Partial cloverleaf interchange
Single-point urban interchange
Roundabout interchange
Compact grade-separation, whereby the two roads are linked by a compact "connector road", with
major-minor priority junctions at each of its ends; usually a variant of the cloverleaf type interchange, but
only involving two quadrants rather than four.
Other variants
These junctions connect three or more roads:
Trumpet interchange
Directional-T interchange
1.1.2. Advantages
Roads with grade separation generally allow traffic to move freely, with fewer interruptions, and
at higher overall speeds; this is why speed limits are typically higher for grade-separated roads. In
addition, less trouble between traffic movements reduces the risk of accidents.
1.1.3. Disadvantages
Grade-separated road junctions are typically space-intensive, complicated, and costly, due to the
need for large physical structures such as tunnels, ramps, and bridges. Their height can be
obtrusive, and this, combined with the large traffic volumes that grade-separated roads attract, tend
to make them unpopular to nearby landowners and residents. For these reasons, proposals for new
grade-separated roads can receive significant public opposition.
Rail-over-rail grade separations take up less space than road grade separations: because shoulders
are not needed, there are generally fewer branches and side road connections to accommodate
(because a partial grade separation will accomplish more improvement than for a road), and
because at-grade railway connections often take up significant space on their own. However, they
require significant engineering effort, and are very expensive and time-consuming to construct.
Grade-separated pedestrian and cycling routes often require modest space since they do not
typically intersect with the facility (such as a highway) that they cross.
Grade-separation can create accessibility problems for people with disabilities due to the vertical
gradient required to pass or to reach rail platforms.
BASICS OF BRIDGE:
2.1. Definition And Introduction
A bridge is a structure built to span physical obstacles without closing the way underneath such as
a body of water, valley, or road, for the purpose of providing passage over the obstacle. There
Designs of bridges vary depending on the function of the bridge, the nature of the terrain where the
bridge is constructed and anchored, the material used to make it, and the funds available to build it
2.2. Components of a bridge:
The bridge comprises of the following parts:
1. Superstructure or decking
This includes slab, girder, truss, etc. This bears the load passing over it and transmits the forces caused by
the same to the substructure.
2. Bearings
The bearings transmit the load received from the decking on to the substructure and are provided for
distribution of the load evenly over the substructure material which may not have sufficient bearing
strength to bear the superstructure load directly.
3. Substructure
This comprises piers and abutments, wing walls or returns and their foundation.
4. Piers and abutments
These are vertical structures supporting deck/bearing provided for transmitting the load down to the
bed/earth through foundation.
5. Wing walls and Returns
These are provided as extension of the abutments to retain the earth of approach bank which otherwise
has natural angle of repose.
6. Foundation
This is provided to transmit the load from the piers or abutments and wings or returns to and evenly
distribute the load on to the strata. This is to be provided sufficiently deep so that it is not affected by the
scour caused by the flow in the river and does not get undermined. While the above mentioned are
structurally operational parts, for safety hand rails or parapets, guard rails or curbs are provided over the
decking in order to prevent vehicle or user from falling into the stream or for the separation of the traffic
streams.
2.3. Classification
Bridges may be classified on various basis as follows:
1. Type of bridge based on Super Structure
Arch Bridge
Arch bridge is curve shaped bridge, in which horizontal thrust is developed and is restrained by the
abutments at each end of the bridge. There are many types of arch bridges . In some cases, the arch may be
under the deck slab also.
Girder Bridge
In case of Girder Bridge, the deck slab is supported by means of girders. The girder may be of rolled steel
girder or plate girder or box girder. Load coming from the deck are taken by girder and transferred them to
the piers and abutments.
Truss Bridge
Truss is member consisting connected elements to form triangular units. In case of truss bridge the super
structure is provided with trusses. Generally, trusses are made of steel. There are several types of trusses are
available.
Suspension Bridge
In case of Suspension bridge, deck slab is suspended with the help of cables and suspenders. These will
give good appearance. For long span bridges, this type of suspension is suitable.
Timber Bridge
Bridges constructed using timber are called timber bridges. These are generally constructed for short spans
or as temporary bridges. They are not useful for heavy loads.
Masonry Bridge
Masonry Bridge constructed by using bricks or stones. These are generally constructed for short spans and
in low depth canals.
Steel Bridge
Steel bridges are constructed using steel bars or trusses or steel cables. These are more durable and bear
heavy loads.
R.C.C Bridge
R.C.C bridges are constructed using reinforced cement concrete. These are more stable and durable. They
can bear heavy loads and are widely using nowadays.
Culvert Bridge
When the bridge span length is below 6meters then it is called as Culvert Bridge.
Major Bridge
For major bridge, the span is generally about 30 to 120 meters.
Over Bridge
To pass over another route (railway or highway), a bridge is constructed to allow traffic. This is called
over bridge or fly over bridge.
Under Bridge
If over bridge is not possible, an underground type bridge is constructed to pass another route. This is called
under bridge.
Foot Bridge
Foot Bridge is generally constructed for humans to cross the roads or rail route or any canal by foot.
Vehicles are not allowed in this bridge.
Highway Bridge
High way or road Way Bridge is used for road transportation. These are constructed over rivers or another
routes to allow road way traffic. Girder type bridges are used as highway bridges over rivers or canals.
Railway Bridge
Rail bridges are constructed for rail transportation. Truss type bridges are preferred for railways but
however RCC bridges are also used.
Aqueduct Bridge
Aqueduct bridges are nothing but water carrying bridges which are constructed to transport water from
source to system.
Road cum Railway Bridge
This type of bridge is useful for both road way and railway transport. It may be of one floor or two floors. If
one floor is there then, rail and road way are arranged side by side. Otherwise roadway on top deck and
railway in bottom deck is preferred.
Simple Bridge
Simple bridge is like simply supported beam type which consist two supports at its ends. For shorter spans,
simple bridges are suitable.
Continuous Bridge
If the bridge span is very long, then we have to build more supports in between end supports. This type of
bridge is termed as continuous bridge.
Cantilever Bridge
Cantilever type of bridge have only supported at one end and another end is free to space. Generally, two
cantilever portions are joined to make way to the vehicles or humans.
Temporary Bridge
During construction of dams or bridges or during floods, temporary bridges are constructed at low cost for
temporary usage. These bridges are maintained at low cost. After construction of original structure
temporary bridges are dismantled. Generally timber is used to construct temporary bridges.
Permanent Bridge
These bridges are constructed for long term use and maintained at high level. Steel or R.C.C bridges are
come under this category.
Deck Bridge
In case of Deck Bridge, super structure or floor of bridge is positioned in between the high flood level and
formation level.
Through Bridge
In case of through bridge, Super structure of bridge is completely above the formation level.
Semi-Through Bridge
If the super structure of bridge is partly above and partly below the formation level, then it is called as
semi-through bridge.
two short concealed spans, one at each side of the opening, each provided with a cantilever
extending into opening and supporting a short span.
The simply supported structure with deck or through girder is statically determinate and is simplest to
design, but its cost is the highest. When unyielding foundation is attainable, the right angle rigid frame
and right angle frames with or without counterweights provide the most economical solution. Girders with
cantilevers with simply supported girders with concealed cantilevers, with or without counterweights and
two short concealed spans, one at each side of the opening, each provided with a cantilever extending into
opening and supporting a short span should be considered for long spans where small depth of girders is
decided.
For a bridge with several span, the following arrangements should be considered:
a number of simply supported girder spans
a combination of girders provided with cantilevers and short spans supported by these cantilevers
multi span rigid frames in which the girders forming the superstructure are rigidly connected with
elastic vertical supports.
The number of simply supported girder spans and a combination of girders provided with cantilevers and
short spans supported by these cantilevers are statically determinate arrangements. Continuous girder
supported by independent piers and multi span rigid frames in which the girders forming the
superstructure are rigidly connected with elastic vertical supports are statically determinate.
The cost of the structure is highest for simply supported girder spans and lowest for rigid frames in which
the girders forming the superstructure are rigidly connected with elastic vertical supports.
The number of simply supported girder spans and a combination of girders provided with cantilevers and
short spans supported by these cantilevers should be used only where reasonably unyielding foundation is
not easily obtainable.
Of these two types, the design of number of simply supported girder spans is simpler but costlier than a
combination of girders provided with cantilevers and short spans supported by these cantilevers.
Where heavy piers are required, as in river crossings, or where the structure is to be supported on already
existing piers, continuous girders supported by independent piers is recommended.
A rigid connection between heavy piers and more flexible superstructure should never be attempted. The
rigid frames with multi span rigid frames in which the girders forming the superstructure are rigidly
connected with elastic vertical supports is preferable with where vertical supports of the bridge are elastic.
The loads, forces and stresses to be considered in designing Road bridges and culverts include:
Dead load, live load, snow load, impact due to vehicles, impact due to floating bodies or vessels, vehicle
collision load, buoyancy, wind load, water current, longitude forces, centrifugal forces, Earth pressure,
temperature effects, deformation effects, secondary effects, erection effects, seismic force, wave pressure
and grade effect.
GEOTECHNICAL INVESTIGATIONS FOR A STRUCTURE
3.1. OBJECTIVE: -
Geo Engineering Services, Dahod have carried out the Geotechnical Investigation, which
covers field sampling and tests, necessary tests and finally analysing the subsoil
characteristics and behaviour of the proposed site.
The objective of the geotechnical investigation was to explore the sub soil profile up to
predetermined depth and work out the design capacity of the soil beneath at a required
foundation depth for the proposed type of foundation.
A complete geotechnical investigation work was undertaken to obtain the required subsurface information
to study and define the nature and behaviour of soil, under the application of loads of proposed structures.
Such information was obtained through following steps:
By making boreholes and collecting disturbed and undisturbed soil samples.
Performing required in situ tests (SPT Test).
Conducting laboratory tests to classify it and to determine the engineering of soil.
An analysis was made to derive the allowable bearing capacity, taking into considerations the anticipated
settlements and the present soil conditions with future possibilities. Based on such analysis of the soil
properties, the conclusions are made regarding the precautions and protective measures to be taken, if
found necessary.
This report has been prepared after a careful study of the field testing and laboratory test results. The type
and depth of foundation are suggested.
(for example, ground disturbance, vegetation removal, water discharge, noise etc).
On-ground survey details.
Notes on any exposed geology, for example the presence of boulders, bedrock exposure, swamps
etc.
The physical relationship of the proposed construction to the immediate natural surroundings and
any existing developments.
Previous site investigation reports, borehole logs, penetrometer results and construction experience
e.g. piling records.
Hydrological data.
Aerial photographs
The collection and collation of the above information, where possible, could be undertaken during the
field reconnaissance survey stage. However, further work to fully explore the extent of information
available may be required.
During the desk study stage, an overview of complexity and risks associated with each geotechnical
design should be clearly identified.
Atterberg’s Limit
Specific Gravity
2.2 SAMPLING: During the advancement of the boring disturbed and undisturbed samples are collected at
every 1.5m interval or at the change of strata whichever occurs earlier. Along with the samplings, field
standard penetration tests is conducted to correlate thee strata denseness & stiffness.
3.1 DESIGN: Calculation for the Safe Bearing Capacity (SBC) and Safe Bearing Pressure (SBP) are
carried out considering shear parameters and consolidation characteristics of the sub strata values of SBC
& SBP are mentioned below.
4.0 SUMMARY OF ANALYSIS: Based on the field and laboratory test data allowable bearing capacity is
derived for open Footing. The bearing capacity is derived based on the minimum achieved value from
shear failure and settlement analysis.
TABLE OF SAFE BEARING CAPACITY
Type Size in m Depth in m Safe Bearing
Capacity, T/m2
R.C.C. Raft 5.0 m wide 2.5 m Below 19.96
Footing 7.5 m wide EGL 23.22
10.0 m wide 26.62
5.0 RECOMMENDATIONS:
5.1 The net safe bearing capacity of soil at a depth of 2.5m shall be considered as 19.5T/m2.
5.2 The Sub Soil can be used for backfilling but with proper compaction.
5.3 The excavation of foundation of foundation pit shall be carried out with a side slope of about 15°with
vertical.
GENERAL NOTE
1. Factor of Safety considered is 2.5.
2. Ground water was not during the exploration work.
3. The foundation shall in no mean rest on Filled up Soil or Black Cotton Soil.
4. If in the course of excavation, if sub soil strata differ from the bore log strata the same shall be reported
for necessary steps.
5. For Intermediate footing size the value of SBC shall be interpolated. No Extrapolation is allowed.
DESIGN OF VARIOUS COMPONENTS OF GRADE
SEPARATOR
Load calculations:
A B C D
IRC 6-2014
IF = 0.5
(ii) For class 70R loading;
IF = 0.25
= 96.61KN/m
Dispersion width along span. (longitudinal) = 0.5 + 2(0.21+0.065)
= 1.05m
Dispersion width in cantilever portion = (1.05/2) + 0.175
= 0.70m
Load in cantilever portion (i) for 1.05m = 96.61KN/m
Effective width (transverse) A/c to IRC-112 = beff = 1.2X+bw = 1.2(0.6) + 0.3= 1.10m
= 1.05m
A 1.8 B C D
0.45 0.8 0.95 0.35 1.45
SIDL 15.2 3.20 6.0 11.3 2.4 4.4 11.3 2.4 4.4
CB
OK OK
CALCULATION OF DEFLECTION
SPAN CANTILEVER
span(mm) 3000 1500
permissible limit 3.8 5
cl.12.4.1(2) 0f IRC:112-2011
short term elastic deflection from STAAD 0.99 2.87
OK OK
5.6. DESIGN OF LONGITUDINAL GIRDER
O.K.
Design Shear stress, Tc 0.61
Unbalanced Shear force Vus 1730.33
Asv provided(sq mm) 402.13
Spacing(mm) 150
PRE-STRESSING TECHNIQUE
PRE-STRESSING
Pre stressing of a member means introduction of permanent stresses in a member, before the
application of design loads, of a calculated magnitude and desired distribution such that these
stresses neutralize or balance the stresses due to external loading up to a desired level. It is a method
in which stress distribution in a member can counteract the effect of external loading to a desire
degree.
Economically viable and easily constructed, these two are the most important criterions in the
construction of modern structures and this is achieved by the use of high strength materials and the
adaptation of advance designing methods. This results in reduction of cross-sectional dimensions
and consequent weight savings. Such developments are particularly important in the field of
reinforced concrete where the dead load represents a substantial part of total load. Significant
savings can be achieved by using high-strength concrete and steel in conjunction with prevailing
design methods in India which permits an accurate appraisal of member strength however , there
are limitations on this development mainly due to interrelated problems of cracking and deflections.
Reinforced concrete is weak in tension but strong in compression. In order to maximize utilization
of its material properties, an internally or externally compressive force P is induced on the structural
element through the use of stressed high-strength pre-stressing wires or tendons prior to loading. As
a result, the concrete section is generally stressed only in compression under Service and sometimes
overloads conditions. Such a system of construction is termed as prestressed concrete.
The pre-stressing force that satisfies the particular conditions of geometry and loading of a given
element is determined from the principles of mechanics and stress--strain relationship. Sometimes
simplification is necessary, as when a pre-stressed beam is assumed to be homogeneous and elastic.
ADVANTAGES OF PRE-STRESSING
Pre-stressing applies a pre-compression to the member which eliminates unwanted tensile
stresses.
Deflection and crack control achieved through pre-stressing permit the engineer to make use of
economical high strength steels in the form of strands, wires or bars in conjunction with concrete of
much higher strengths.
Stress resulting in pre-stressing effects in overall improvement in performance of structural
concrete.
Spans can be extended far beyond the limiting range for ordinary reinforced concrete leading to not
only much longer spans than previously thought but also permitting innovative new structural forms
to be employed.
Pre-stressing of concrete reduces the self-weight of the structure and due to which longer span
EFFECTS OF PRE-STRESSING
Concrete is weak in tension and with the help of pre-stressing this weakness can be overcome.
As a mean for introducing equivalent load on the concrete member so that the effect of the applied
loads are counteracted to the desired degree.
A special variation of reinforced concrete in which pre-strained high strength steel is used usually
in conjunction with high strength concrete.
METHODS OF PRE-STRESSING
There are two methods of pre-stressing:
Pre-tensioning
Post-tensioning
PRE-TENSIONING
Pre-tensioning is used in factories for the manufacturing of pre-cast structural units and usually not
used for large span girders. The term pre-tensioned means that the tendons are tensioned to their
full load before the concrete is placed. They are held under tension by anchors beyond the ends of
the prestressed concrete member. After the concrete has been placed and allowed to cure to
sufficient strength, the load in the tendons is transferred from the external anchors into the newly
poured member, thus pre-stressing it. In the United States the standard tendons for pre-tensioned
work are seven-wire uncoated stress-relieved pre-stressed concrete strands.
POST-TENSIONING
Post-tensioning is used on large scale for the production of large span bridge girders in the factories
as well as in the field. The term post-tensioned means that the tendons are tensioned after the
concrete has been placed and allowed to cure. Frequently the tendon is placed inside a flexible
metal hose, the entire assembly is placed in the form, and concrete is poured around After the
concrete has cured, the tendon is tensioned and held under load by anchor fittings at its ends. Bond
between the tendon and the concrete member is achieved by pumping the metal hose full grout.
BASIC OPERATION OF POST-TENSIONING
Post-tensioning is defined as "A method of pre-stressing reinforced concrete in
The tendon assembly is placed in the form and tied in place in the same manner as the reinforcing
bars.
Concrete is poured and allowed to cure to the strength specified for tensioning.
Hydraulic jacks elongate tendons, and the anchor fitting is adjusted to hold the load in the tendons.
The space around the tendon is pumped full of cement grout under pressure.
In some cases a hole is cored in the concrete and the tendon is threaded through the hole just before
it is to be tensioned. Holes can be covered by casting in a rubber tube of the desired shape and then
withdrawing it after the concrete has set. Holes can also be covered by casting in a flexible metal
hose. The hose becomes a permanent part of the structure. Since the hose is not stiff enough to
maintain its position while the concrete is placed, one or more steel bars are placed inside the hose
and are withdrawn after the concrete has set. In large hollow structures such as hollow-box bridges,
the tendons are threaded through the hollow spaces and tensioned against anchor plates cast in the
end block of the structure. Galvanized strands are used in these structures, and grouting is not
required.
The jacking pre-stress force Pj is applied; then, at transfer, the force is transmitted from the pre-
stressing strands to the concrete.
The full self-weight WD acts on the member together with the initial pre-stressing force, provided
that the member is simply supported, that is, there is no intermediate support.
The full superimposed dead load WSD including topping for composite section is applied to the
member.
Most of the short-term losses in the pre-stressing force occur initially, leading to a reduced pre-
stressing force Pj to Pi.
The member is subjected to full service load, with long-term losses due to creep, shrinkage, and
steel strand relaxation taking place leading to a net pre-stressing force Pe. Overloading of the
member occurs under c
PRE-STRESSING STEEL
For prestressing, high strength steel is used because the ordinary steels, such as grade 300 steel, are
ineffective in providing effective prestressing. The prestressing steel may be in the form of smaller
diameter wires, relatively larger diameter alloy steel bars or in the form of strands.
Strand
The term strand is used for a group of wires helically wounded. Usually a 7-wire strand is used for the
prestressing purposes as shown in Fig. 3.1
Tendon
The term tendon is used for one group of reinforcement consisting of a single wire, a strand or a group of
strands used together.
The external bending moment in a beam is resisted by a couple formed by internal tensile force in
steel and compressive force in concrete.
In ordinary reinforced concrete beam, the increase in the lever arm by the increase of loading is
lesser and the resistive moment basically increases by increase in steel tensile force and compression
in concrete.
The situation is reversed in case of prestressed concrete beam where the forces in the steel and
concrete remain nearly constant and the resisting moment increases by the increase in the lever arm.
After the development of tensile stresses in concrete due to increase of load on prestressed beam,
its behavior is almost similar to ordinary reinforced concrete.
TENDON PROFILE
Positive moment requires prestressing force below the section centroid; negative moment requires
it above the centroid and required eccentricity of prestressing increases with the increase of applied
bending moment.
Curved tendon profiles approximately following the shape of bending moment diagram are better
and easy to be placed in case of post tensioning. However, in case of pretensioning especially for
large prestressing loads having a number of members to be cast together, straight tendons are easy
to be placed. The tendon profile may be Straight, Parabolic, Draped or Harped as shown in Fig.
3.2.
At this stage the initial pre-stress force acting at an eccentricity ‘e’ produces a uniform compression
due to Pi and the moment Pi x e produces tension at the top and compression at the bottom as shown
in Fig. 3.3. The net result may be smaller tension at the top and larger compression at the bottom.
Fc ft
Pi Pi
f
fc fc c
The self weight causes tension at bottom and compression at the top and the net result may be
smaller compression at the top and larger compression at the bottom as shown in Fig. 3.4.
Wo Fc ft fc
Pi Pi
fc fc ft
fc
Wo Fc ft fc
Pe Pe
fc fc ft
fc
WD+l fc ft fc
Pe Pe
e fc fc ft
Fc fc
Ft ft
f1 = Stress at top = Pe/Ac+ Pe *e*c/I + Mg*c/I- M(d+l)*c/I
f2 = Stress at Bottom = Pe/Ac+ Pe *e*c/I – Mg*c/I+ M(d+l)*c/I
LOSS OF PRESTRESS
Jacking Force (Pj)
It is the largest force that will act on the steel tendon to pull it to required stress level. The jacking operation
may be thought of a performance test of the tendon.
Initial Prestress Force (Pi)
It is the force in the steel tendon after transfer and is equal to jacking force reduced due to instantaneous
shortening of the concrete.
Effective Prestress Force (Pe)
It is the ratio of effective prestress to the initial prestress. Usually a conservative value of R = 0.85
may be used in place of detailed actual calculations.
It is a well-established fact that the initial pre-stressing force applied to the concrete elements
experiences a progressive process of reduction over a span of approximately 5 years.
Consequently, it is important to determine the level of pre-stressing force at each loading stage,
from the stage of transfer of pre-stressing force to the concrete, to the various stages of prestressing
available at service load, up to the ultimate. Essentially the reduction in the prestressing force can
be grouped into two categories:
i) Instantaneous Losses
ii) Time Dependent Losses
INSTANTANEOUS LOSSES
These losses take place immediately after the application of jacking force. These losses
include the following:
i. Losses due to friction
ii. Losses due to anchorage set
iii. Losses due to elastic shortening
where,
fp = stress at jacking end
l = span of girder
K = wobble coefficient
μ = curvature coefficient
α = total angular change of tendon profile in radians from jacking end to any point x.
In post tension construction, when the jacking force is released, the steel tension is transferred to
the concrete by special anchorages. Invariably, there is a small amount of slip at the anchorages
upon transfer, as the wedges seat themselves into the tendons, or as the anchorage hardware
deforms. The usual value of anchorage set may be 10 mm with a minimum value of 1.3 mm. These
losses can be determined using the equation (3.2).
Where,
Δl = amount of slip
l = tendon length
When the prestress force is transferred to a member, there will be elastic shortening of concrete as
it is compressed. For the post-tensioned members, if all the steel is tensioned at once, there will be
no loss due to elastic shortening.
However, for the practical purposes where multiple tendons are used , with tendons tensioned in
sequence, there will be losses. These losses can be satisfactorily determined by employing equation
(3.3).
= 0.5 x np fcs
Where,
np = Ep/Ec
fcs = compressive stress at the level of steel centroid when eccentric prestress
These are the losses due to creep and shrinkage of concrete and relaxation of prestressing
steel.
These losses occur after the concrete has gained its specified cylindrical compressive stress
(fc′).
These losses occur due to the application of a sustained compression load on the concrete
causing it to first deform elastically and then continue to strain over an extended period of
time.
Where,
np =Ep/Es
fcs = compressive stress at the level of steel centroid when eccentric prestress plus
self weight are acting.
Drying shrinkage of concrete permits a reduction of strain in the prestressing steel equal to
the shrinkage strain of the concrete.
The resulting steel stress loss is an important component of the total prestress loss for all
types of prestressed concrete members. The ultimate concrete strains resulting from drying
shrinkage may fall in the range from about 500 x 10-6 to 1000 x 10-6.
The value ultimate shrinkage strain for moist cured concrete can be taken equal to 800 x 10-
6 in the absence of specific data, and for steam-cured a value of 730 x 10-6 can be used.
εsh = amount of shrinkage strain occurring during the period under consideration
The amount of relaxation depends on the intensity of prestressing steel stress as well as time.
Log tn {(fp/fpy)-0.55}
DESIGN OF GIRDER
Design of prestress concrete girder means the determination of dimensions of the cross section and
location of the prestress force such that the stresses before and after the application of service loads
remain within the ACI specified stress limits.
The materials behave elastically for such loads and hence straight line relationship between stresses
and strains may be considered.
DESIGN CALCULATIONS:
DESIGN OF GIRDER
As the design forces for Exterior Girder are more critical therefore, the design will be carried out for
exterior girder and same will be provided as interior girder.
DESIGN FOR FLEXURE
DESIGN DATA
Span of girder = L = 30 m
MD = 5885 KN-m
ML = 1780 KN-m
fc′ = 40 MPa
fci′ = 40 MPa
fpu = 1860 MPa
fpy = 1676 MPa
R = 0.85 (Assuming 15 % time dependent losses)
Approximate Depth of Girder
h ≈ 0.075 x L
= 0.075 x 30000
h = 2300 mm
Approximate Self Weight of Girder
wg = 0.006 h2 to 0.007 h2 (N/m)
= 0.007 X 2600^2/ 1000.
= 37.03 kN/m
Mg = 47.32 x 35^2/ 8.
= 4165.875 kN-m
As per is 1343 1980 3 types of prestressed members ;
type -1: in this no tensile stress is allowed in concrete at transfer or under service loads
type -2: in this tensile stress is within cracking stress of concrete at transfer or under service loads
type -3: in this tensile stress is such that crack width is within allowable limit
SELECTION OF SECTION
The pre-stressed concrete girder section is selected based on the on the following:
The modulii of elasticity (at top & bottom) of the section are greater than or equal
200 mm
150 mm
2400 mm
1450 mm
200 mm
300 mm
1000 mm
Sectional Properties
At Transfer Stage
To determine sectional properties, we will ignore the sloping portions to get the
section as shown in Fig. 5.13.
1000 mm
200 mm
1800 mm 400mm
300 mm
1000 mm
Fig. 5.13 Girder Section with Ignored Sloping Portions
Area of Section
Area of the section is calculated by considering the actual girder section.
A = 1000 x 200 + 1000 x 300 + 1450 x 400 + 2 x 1400 x 150 + 2 xv1400x 200
= 1325000 mm = 1.325 m2
Actual Self Weight of Girder
wg = 1.325
= 33.125 kN/m
Mg = 24.8 * 35^2/8
= 3727 kN-m < Mg,assumed (4165) (OK)
The other sectional properties are calculated by considering the simplied section
as shown in Fig. 5.13.
Location of Centroid
y ={ 1000*250*125 + 2000*250*125 + 8000*350*2425 } / { 1000*250 + 2000*250+ 8000*2425}
c1 = y = 1194.26 mm
c2 = 2300 – 1194.26 = 1105.73 mm
Moment of Inertia
I = [ (1000*250^2/12) + 1000*250*1176.36^2] + [ (250*2000^2/12) + 2000*250*46.36^2] +
[ (800*350^2/12) + 800*350*1128.64^2 ]
= 71600000 x 104 mm4
S1 = 8172 * 10^11 / 1296.36 =672653 x 10^3 mm3
S2 =8172 * 10^11 / 1303.64 = 668896 x 10^3 mm3
SELECTION OF TENDONS
Uniform Concrete Centroidal Stress
It is the uniform stress in the concrete section if initial prestress force is applied at the centroid of the
section.
It is determined as:
fcci = fti – (c1/h)* (fti – fci )
= 1.58 – (1296.36/2800) * 1.32 + 16.8 = -11.7 MPa
Initial Prestress Force
It is the prestress force at transfer stage after the instantaneous losses.
Pi = Ac x fcci
= 105550*7.74/1000
= 15502.5 kN
Stress in the Prestressing Steel at Failure
fps is lesser of
i. 0.74 x fpu = 0.74 x 1860 = 1376.4 MPa
ii. 0.82 x fpy = 0.82 x 1676 = 1375 MPa
Therefore,
fps = 1375 MPa
No. of Strands
N = Aps/Ast
= 5921.45/140
= 81
Therefore,
Provide 4 Tendons of 21 Strands Each
1000
210
200 1000
1800 400
300
1000
Area of Section
Area of the section is calculated by considering the actual girder section along
with effective slab portion.
Ac = 1325000 + (1000 x 210) = 1535000 mm2
= 1.535 m2
Actual Self Weight
= 1.535 x 25
= 38.375
wg = 38.375 kN/m
Mg = 30.58*35^2/8
= 4318 kN-m
Location of Centroid
c1 = 1213.46 mm
c2 = 1296.5 mm
Moment of Inertia
I= 101960000 x 10^4 mm4
Check for the Stresses
Pe = R x Pi = 0.85 x 8142 = 6920.7 kN
f1 = Stress at top = Pe/Ac+ Pe *e*c/I + Mg*c/I- M(d+l)*c/I
= -15 < -24 MPa (OK)
f2 = Stress at bottom = Pe/Ac+ Pe *e*c/I – Mg*c/I+ M(d+l)*c/I
TENDON PROFILE
The path of the prestressing tendon along the length of the prestressed member is called
tendon profile and it is decided based on the shape of bending moment diagram.
To find out the ordinates of the parabolic tendons following equation of the parabola
is used.
y = a(x - h) 2 + k
where (h, k) represents the vertex of the parabola and a controls the shape and vertical
direction. The values of the ordinates of the parabolic tendon profile, both in y and z
direction are calculated at various values of x taking the midspan of the girder as origin as
shown in Fig. 5.15. The calculations are shown in table below.
CL of PC girder
1194 Centroid line
347 1
347 2 Cables
500 3
200
x origin
15000mm 12000m 9000mm 6000mm 3000mm
x y z x y z x y z
(mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm)
Effective Depth
It is the distance from extreme compression fibers to the centroid of prestressed
reinforcement.
de = 2300 – 200 = 2100mm
Vp = Pe sin θ
As there are 4 tendons therefore,
Pe for one tendon = 13177.125 / 4 = 3295 kN
Therefore,
Vc′ = 797 + 996.7 = 1793.75 kN
ф Vc′ = 0.75 x 1793.75 = 1345.312 kN
фVc’/2= 673 kN
As,
Vu (2266 kN) > ф Vc′
Therefore, we have to provide maximum shear reinforcement
Vs =(Vu- фVc’)/ ф
Vs =1227.6 KN
(Vs)max = 1/3√fc′ bv x dv=1/3√ 4 x400 x 1890 = 1593.78 kN
And,
(Vs)max =2/3√fc ′ bv x dv = 3188 kN
As,
fc1/3√fc ′ bv x dv < Vs <2/3√fc ′ bv x dv
Therefore,
Smax = 180 mm
Provide # 12 @ 170 mm c/c Stirrups
Design of Shear Reinforcement for Second Portion
Vu at L/4 = 0.5 x Vu
= 0.5 x 2266
= 1133 kN
Nominal Shear Resistance of Concrete Section
Vn = Vc’ + Vs
Vc ′= Vc + Vp
Here,
Vc = nominal shear resistance of concrete (kN)
Vp = component of prestressing force in the direction of shear force (kN)
Vc =1/6√fc’ bv dv
=1/6√35 x 400 x 1890 / 1000 =797 kN
Vp = 0.5 x Pe sin θ
Vp = 0.5 x .3025 x 3295 = 498.36 kN
Therefore,
Vc′ = 797 + 498.36b= 1295 kN
ф Vc′ = 0.75 x 1295b= 972 kN
фVc’/2= 486 kN
As,
Vu (1133 kN) > ф Vc′
Therefore, we have to provide maximum shear reinforcement
Vs =(Vu– фVc’/ф
Vs = 214.6 kN
(Vs)max =1/3√fc’ bv x dv
=1/3√35 x 400 x 1890 = 1593.787 kN
And,
(Vs)max =2/3√fc’ ′ bv x dv = 3187.5 kN
As,
Vs <1/3√fc’ ′ bv x dv
Therefore,
INSTANTANEOUS LOSSES
These losses take place immediately after the application of jacking force.
These losses include the following:
i. Losses due to friction
ii. Losses due to anchorage set
iii. Losses due to elastic shortening
LOSSES DUE TO FRICTION
The fictional losses in post tension construction can be determined as follow:
Δffr = fp ( Kl + μα )
Here,
fp = stress at jacking end = 0.76 fpu = 0.76 x 1860 = 1413.60 MPa
{ AASHTO permissible steel stress for post tensioning at jacking}
l = span of girder = 30000 mm
K = wobble coefficient = 1.6 x 10-6
{ ACI friction coefficient for grouted tendon in metal sheathing for 7 wire strand }
μ = curvature coefficient = 0.15
α = total angular change of tendon profile in radians from jacking end to
any point x.
= 8y/x(radians)
=8*745/35000
= 0.133 radians
Therefore,
For the post-tensioned beams, if all the steel is tensioned at once there
will be no loss due to elastic shortening. However, for the practical
purposes where multiple tendons are used , with tendons tensioned
in sequence, there will be losses. These losses can be satisfactorily
determined as follow:
Δfel = 50 % of elastic shortening in pre-tensioned beams
= 0.5 x np fcs
Here,
np = Ep/Ec =197000/4700√fc ′ = 6.62
fcs = compressive stress at the level of steel centroid when eccentric prestress force plus self weight are
acting in pretensioned beam.
= -Pi/Ac – Pi*e^2/I + Mg*e/I
Pi = 0.9 x Pj = 0.9 x jacking stress x area of tendons
= 0.9 x 1413.6 x (4 x 21 x140) / 1000
= 14916.15 kN
Therefore,
fcs = 8.60 MPa
Therefore,
Now, the remaining stress in the tendons at midspan after instantaneous losses is:
fpi = 1413.60 – 115.886 = 1297.714 MPa
Therefore,
Pi = fpi x area of tendons
= 1297.714 x (4 x 21 x 140) / 1000
= 15261 kN < Pi used in design (15502. kN)
TIME DEPENDENT LOSSES
These are the losses due to creep and shrinkage of concrete and
relaxation of steel.
Therefore,
fcs = 5.47 MPa
Cu = ultimate creep coefficient = 2.65 corresponding to fc´ = 35 MPa
Therefore,
Δfcp = Cu np fcs= 2.65 x 7.08 x 5.47= 102.63 MPa
DETAILS OF SUPERSTRUCTURE:
Depth of superstructure = 2.31m
Thickness Of wearing coat = 0.065m
Camber in one direction = 2.5%
Expansion joint type = Strip seal
Impact factor = 1.132
DIAGRAM =
Load Calculation:
DEAD LOAD
1) Dead load of superstructure on Cap through girders-
DL of Slab = (.21x30x12x25)/(4X2) = 236.3KN
DL of Girder = 371.1KN
Reaction due to end diaphragm –
On Outer girder = 19.9KN
On Inner Girder = 39.8KN
SIDL1 - Wearing course –
On Outer girder = 71KN
On Inner Girder = 61KN
SIDL2 – Crash barrier.
On Outer girder = 199KN
On Inner Girder = -61KN
DL of Bearing. =30.8KN
LIVE LOAD:
1) Live load maximum moment case –
Position of live load –
BM SUMMARY:
Distance from face of support (in circle square)-
PIER CAP OUTER FACE OUTER BEARING INNER BEARING
4.511 3.948 0.823
4.511 3.948 0.823
LOAD TYPE G1 G2 V ML Mt
t tm tm
DL 68.5 72.4 140.9 330 0
SIDL1 7.1 6.1 13.1 32.8 0
SIDL2 19.9 -6.1 13.8 73.5 0
Total 95.5 72.4
LOAD COMBINATIONS:
BASIC COMBINATION
LOAD PSF V(t) ML(t M(t m) Equiv ML(resultant)
TYPE m)
DL 1.35 190.3 445.5 0 0 445.5
ABUT 1.35 92.3 187.6 54.6 50.1 237.8
CAP
SIDL1 1.75 23 57.5 0 0 57.5
SIDL2 1.35 18.6 99.2 0 0 99.2
LL1 1.5 73.4 166 0 0 166
LL2 1.5 151.1 349.9 0 0 349.9
W1 0.9 6.1 28.9 0 0 28.9
SEISMIC
COMBINATION
LOAD PSF V(t) ML(t M(t m) Equiv ML(resultant)
TYPE m)
DL 1 140.9 330 0 0 330
ABUT 1 68.4 139 40.5 37.1 176.1
CAP
SIDL1 1 13.1 13.1 0 0 32.8
SIDL2 1 13.8 13.8 0 0 73.5
LL1 0.2 9.8 22.1 0 0 22.1
LL2 0.2 20.1 46.7 0 0 46.7
RARE COMBINATION
LOAD PSF V(t) ML(t M(t m) Equiv ML(resultant)
TYPE m)
DL 1 140.9 330 0 0 330
ABUT 1 68.4 139 40.5 37.1 176.1
CAP
SIDL1 1 13.1 13.1 0 0 32.8
SIDL2 1 13.8 13.8 0 0 73.5
LL1 1 48.9 110.6 0 0 110.6
LL2 1 100.7 233.3 0 0 233.3
W1 0.6 4 19.3 0 0 19.3
FREQUENT
COMBINATION
LOAD PSF V(t) ML(t M(t m) Equiv ML(resultant)
TYPE m)
DL 1 140.9 330 0 0 330
ABUT 1 68.4 139 40.5 37.1 176.1
CAP
SIDL1 1 13.1 13.1 0 0 32.8
SIDL2 1 13.8 13.8 0 0 73.5
LL1 0.75 36.7 83 0 0 83
LL2 0.75 75.5 175 0 0 175
W1 0.5 3.4 16.1 0 0 16.1
QUASI-PERMA
COMBINATION
LOAD PSF V(t) ML(t M(t m) Equiv ML
TYPE m) (resultant)
DL 1 140.9 330 0 0 330
ABUT 1 68.4 139 40.5 37.1 176.1
CAP
SIDL1 1 13.1 13.1 0 0 32.8
SIDL2 1 13.8 73.5 0 0 73.5
LL1 0 0 0 0 0 0
LL2 0 0 0 0 0 0
W1 0 0 0 0 0 0
VERIFICATION OF STRUCTURAL STRENGTH FOR ABUTMENT CAP(ULS):
Material properties and strengths:
1) CONCRETE: (from IRC 112-2011)
Cube strength (28 days) fck = 35N/mm2
Basic combination fcd = 15.63N/mm2
Accidental combination fcd = 19.54N/mm2
Seismic combination fcd = 15.63N/mm
Ec = 32000MPa
2) Steel:
Grade of steel fck = 500N/mm2
Basic combination fy = 435N/mm2
Accidental combination fy = 500N/mm2
Seismic combination fy = 435N/mm2
Es = 2.0E +05MPa
Minimaum strain =0.87fy/Es
Cu= fcd*b*(3/7xulim+2/3*4/7xulim) = 0.8095*fcd*b*xu.
Tu=fyd*Ast
Rlim= Mulim/bd2
Calculation of Reinforcement:
b= 2540mm
D=1500mm
Cc=50mm
MOMENT ON THE SECTION
Basic Seismic
Combination Combination
Actual Moment(KNm) 12048 7104
b 2540 2540
D 1500 1500
c 50 50
d 1422 1422
fcd 15.63 15.63
fyd 435 435
xulimt/d 0.62 0.62
Rlimt 5.8 5.8
Mulim(KNm) 29806 29806
OK OK
Ast Required 21279 12066
Dai of bar (main tension)mm 32 32
Spacing(mm) 160 160
dia of bar (main tension)mm 32 32
Spacing (mm) 160 160
Ast provided (sq mm) 25535 25535
Dia of bar (main compression) (mm) 20 20
Spacing (mm) 160 160
Area of main compression (mm2) 4987 4987
fctm 2.8 2.8
fyk 435 435
Cl. 160501(2) IRC:112-2011
Asmin=0.26fctmbtd/fyk>=0.0013btd 6048 6048
OK OK
Asmax.=.025 Ac(main tension) 95250 95250
cl.16.5.1 IRC: 112-2011 OK OK
Asmax=0.04Ac(tension+compression) 152400 152400
x(mm) 345 345
x/d 0.243 0.243
z(mm) 1278 1278
MR(KNm) 14192 14192
Es = 2.0E +05MPa
CALCULATION OF DEFLECTION AT
TIP OF CAP
Span 4511
Span/300 15
cl.12.4.1
b 2540
D1 750
D2 15003948
I1 8.9E+10
I2 7.1E+11
I 4E+11
E 32000
Distance from face of support to outer 3948
Bearing
Load due to outer bearing 1318600
Deflection due to outer bearing
Pa^2(3x-a)/6EI 2.55
Dist to inner bearing 823
Load due to inner bearing 1192785
Deflection due to inner bearing
Pa^2(3x-a)/6EI 0.1
Deflection due to self weight of cap
DL cap uniform intensity 47.63
Wl^4/8EI 0.19
Total deflection in mm 2.9
OK
ABUTMENT
DIAGRAM-
SALIENT RL’s:
Deck level = 572.049m
Bearing top level = 569.674m
Abutment cap top Level = 569.257m
Abutment bottom Level = 561.462m
Depth of pile cap = 1.8m
GL = 561.962m
Pile cap bottom level = 559.662m
LBL = 561.962m
Expansion Gap = 0.05m
Dia of the abut = 2.1m
Length of pile cap = 5.1m
Width of pile cap = 5.1m
Thickness of wearing coat = 0.065m
Height of deck+girder = 2.31m
Thickness of bearing = 0.1m
Height of pedestal = 0.2m
Total Height from w/c to cap top =2.792m
Span EJ to EJ = 30m
Load Calculation
Taking Moments about founding level
LHS L(long) L(trans) ML Mt
t m m t-m t-m
Dead load 281.9 0 0 0 0
SIDL w/c 26.24 0 0 0 0
SIDL2 27.52 0 0 0 0
LL(max moment)
ClassA 41.52 0 4.2 0 174.4
Class2A 83.05 0 2.45 0 203.47
70R 85.15 0 2.905 0 247.37
Class3A 112.11 0 0.7 0 78.48
70R+classA 114.01 0 0.91 0 103.75
WIND LOAD –
On superstructure.
On Moving load.
On Substrucute.
2) SEISMIC COMBINATION
LOAD CASE FACTORED FORCES/MOMENTS
V ML MT
t t-m t-m
DOWNWARD SEISMIC IN LONGI
DIRECTION
CASE 1 DL+SIDL1+SIDL2 + Seismic 802 1283 2
CASE 2 DL+SIDL1+SIDL2+LL1+ Seismic 889 1098 80
CASE 2 DL+SIDL1+SIDL2+LL2+ Seismic 820 1283 78
CASE 1 DL+SIDL1+SIDL2+LL3+ Seismic 868 1109 188
DOWNWARD SEISMIC IN TRANS
DIRECTION
CASE 5 DL+SIDL1+SIDL2+ seismic 802 -76 1361
CASE 6 DL+SIDL1+SIDL2+LL1+ seismic 889 -261 1439
CASE 7 DL+SIDL1+SIDL2+LL2+ seismic 820 -76 1437
CASE 8 DL+SIDL1+SIDL2+LL3+ seismic 868 -251 1546
UPWARD SEISMIC IN LONG DIRECTION
CASE 9 DL+SIDL1+SIDL2+ Seismic 626 1283 2
CASE 10 DL+SIDL1+SIDL2+LL1+ Seismic 713 1098 80
CASE 11 DL+SIDL1+SIDL2+LL2+ Seismic 644 1283 78
CASE 12 DL+SIDL1+SIDL2+LL3+ Seismic 692 1109 188
UPWARD SEISMIC IN TRANS DIRECTION
CASE 13 DL+SIDL1+SIDL2+ Seismic 626 -76 1361
CASE 14 DL+SIDL1+SIDL2+LL1+ Seismic 713 -261 1439
CASE 15 DL+SIDL1+SIDL2+LL2+ Seismic 644 -76 1437
CASE 16 DL+SIDL1+SIDL2+LL3+ Seismic 692 -251 1546
COMBINATION FOR DESIGN OF ABUTMENT (SLS)
FORCES AT MOMENTS ARE CALCULATED AT PILE CAP TOP LEVEL
Axial load M LL M TT
CASES Pu( KN ) KNm KNm
SEISMIC Max LL 820 1283 78
CASE Max TT 868 -251 1546
DESIGN SUMMARY
PIER SIZE
Diameter (D) mm 2100
Area of abutment mm2 3.46E+06
SECTION R/f
Longitudinal reinforcement
p % 0.5 of Ag
Ast required mm2 17318
PROVIDE 36 X 25mm dia bars .
Diameter of bar mm 25
Total number 36
Ast provided mm2 17671
Transverse reinforcement
As per Clause 16.2.3 of IRC 112:2011
Minimum diameter of Tie bar =max {0.25D / 8mm}
0.25D mm 6.25
Adopt 10mm diameter Helical reinforcement.
Pitch of lateral tie mm 150mm at centre
75 mm at ends
SALIENT RL’s:
Deck level = 571.905m
Bearing top level = 569.530m
Abutment cap top Level = 569.113m
Abutment bottom Level = 561.462m
Depth of pile cap = 1.8m
GL = 561.962m
Pile cap bottom level = 559.662m
LBL = 561.962m
Expansion Gap = 0.05m
Dia of the abut = 2.1m
Length of pile cap = 5.1m
Width of pile cap = 5.1m
Thickness of wearing coat = 0.065m
Height of deck+girder = 2.31m
Thickness of bearing = 0.1m
Height of pedestal = 0.2m
Total Height from w/c to cap top =2.792m
Span EJ to EJ = 30m
LOAD CALCULATION:
LL(max reaction)
ClassA 24.11 23.08 0.81 4.2 0.84 198.19
Class2A 48.22 46.16 0.81 2.45 1.67 231.23
70R 46.93 44.86 0.81 2.905 1.67 266.64
Class3A 65.1 62.31 0.81 0.7 2.26 89.19
70R+classA 63.93 61.41 0.81 0.91 2.26 113.82
LL(max moment)
ClassA 41.52 0 0.81 4.2 33.63 174.4
Class2A 83.05 0 0.81 2.45 67.27 203.47
70R 85.15 0 0.81 2.905 68.97 247.37
Class3A 112.11 0 0.81 0.7 90.81 78.48
70R+classA 114.01 0 0.81 0.91 92.35 103.75
SUMMARY
TRANSVERSE DIRECTION RL MOMENT ABOUT FL. ABUTMENT
BOTTOM
H Lev Mt Lev Mt
t m t-m m t-m
WIND ON SUP STR @ 570.72 16.40 11.06 181.27 9.26 151.76
WIND ON MOVING LOAD@ 573.41 10.36 13.74 142.32 11.94 123.68
WIND ON ABUTMENT 568.36 0.37 8.70 4.00 6.90 3.18
CAP@
SEISMIC LOAD -
T= 2*(D/1000*F) ^0.5
T = Time period
D = Appropriate Dead load & Live Load
F = Horizontal force to be applied at superstructure mass to produce 1mm deflection at top
of pier.
Longitudinal Direction Transverse Direction
d FL^3/3EI
Height of pier (upto cap) 8.07 m
F 116 KN 161 KN
D 7185 KN
Length of the Pier 2.10 m
Width of the Pier 2.10 m
Area of Pier Ap 3.464 m2 3.464 m2
Inertia Ip 1.0 m4 0.955 m4
E of concrete 3.00E+07 KN/m2
CG of superstructure H2 9.528 m 8.07 m
Pier Cap top level H1 8.07 m
Pier top level 569.11 m
At top of pier d 1.00 mm 1.00 mm
T 0.50 sec 0.42 sec
Ah (Z/2)*(Sa/g)*(I/R)
Seismic Zone III
Z 0.16
I 1.2
R(medium soil) 3
Sa/g 2.00 2.38
Ah 0.064 0.076
1) BASIC COMBINATION
LOAD CASE FACTORED FORCES/MOMENTS
V ML MT
t t-m t-m
NORMAL
CASE 1 DL+SIDL1+SIDL2 1136 0 0
CASE 2 DL+SIDL1+SIDL2+LL1 1330 -326 134
CASE 2 DL+SIDL1+SIDL2+LL2 1311 -225 156
CASE 1 DL+SIDL1+SIDL2+LL3 1278 -341 400
DOWNWARD WIND DIRECTION
CASE 5 DL+SIDL1+SIDL2+WIND 1159 24 139
CASE 6 DL+SIDL1+SIDL2+LL1+WIND 1353 -274 385
CASE 7 DL+SIDL1+SIDL2+LL2+WIND 1334 -174 406
CASE 8 DL+SIDL1+SIDL2+LL3+WIND 1301 -289 651
UPWARD WIND DIRECTION
CASE 9 DL+SIDL1+SIDL2+WIND 1113 24 139
CASE 10 DL+SIDL1+SIDL2+LL1+WIND 1307 -274 385
CASE 11 DL+SIDL1+SIDL2+LL2+WIND 1288 -174 406
CASE 12 DL+SIDL1+SIDL2+LL3+WIND 1254 -289 651
2) SEISMIC COMBINATION
LOAD CASE FACTORED FORCES/MOMENTS
V ML MT
t t-m t-m
DOWNWARD SEISMIC IN LONGI
DIRECTION
CASE 1 DL+SIDL1+SIDL2 + Seismic 1280 2212 2
CASE 2 DL+SIDL1+SIDL2+LL1+ Seismic 1377 2049 69
CASE 2 DL+SIDL1+SIDL2+LL2+ Seismic 1368 2099 80
CASE 1 DL+SIDL1+SIDL2+LL3+ Seismic 1351 2042 202
DOWNWARD SEISMIC IN TRANS
DIRECTION
CASE 5 DL+SIDL1+SIDL2+ seismic 1281 0 2208
CASE 6 DL+SIDL1+SIDL2+LL1+ seismic 1378 -163 2275
CASE 7 DL+SIDL1+SIDL2+LL2+ seismic 1368 -112 2286
CASE 8 DL+SIDL1+SIDL2+LL3+ seismic 1351 -170 2408
UPWARD SEISMIC IN LONG DIRECTION
CASE 9 DL+SIDL1+SIDL2+ Seismic 992 2212 2
CASE 10 DL+SIDL1+SIDL2+LL1+ Seismic 1089 2049 69
CASE 11 DL+SIDL1+SIDL2+LL2+ Seismic 1079 2099 80
CASE 12 DL+SIDL1+SIDL2+LL3+ Seismic 1062 2042 202
UPWARD SEISMIC IN TRANS DIRECTION
CASE 13 DL+SIDL1+SIDL2+ Seismic 991 0 2208
CASE 14 DL+SIDL1+SIDL2+LL1+ Seismic 1088 -163 2275
CASE 15 DL+SIDL1+SIDL2+LL2+ Seismic 1079 -112 2286
CASE 16 DL+SIDL1+SIDL2+LL3+ Seismic 1062 -170 2408
COMBINATION FOR DESIGN OF ABUTMENT (SLS)
FORCES AT MOMENTS ARE CALCULATED AT PILE CAP TOP LEVEL
Design Calculations:
L/D = 6295/2100 = 2.99 < 12,
Therefore, according to IRC 112- 2011,
Abutment is designed as a pedestal column subjected to Biaxial bending using Design aids SP-16.
Axial load M LL M TT
CASES Pu( KN ) KNm KNm
SEISMIC Max LL 12800 22120 20
CASE Max TT 13680 -1120 22860
c) Top Steel
Reinforcement
i) 12mm Ø @110mm c/c 47 5.1 213.333
(07) @.89 kg/m
i) 12mm Ø @110mm c/c 47 5.1 213.333
(06) @0.89 kg/m
d) Side Steel
Reinforcement
i) 10mm Ø @200mm c/c 18 5.1 56.6406
(8a) @ 0.617 kg/m
ii 10mm Ø @200mm c/c 18 5.1 56.6406
(08) @ 0.617 kg/m
5158 kg
ABSTRACT SHEET :-
SUM- 3876469.8
b) Steel Reinforcement
i) 32mm ø @ 160mm c/c 18 11.5 1308.24
@ 6.32 Kg/m (05)
ii) 20mm ø @ 160mm c/c 20 11.64 628.56
@ 2.7 Kg/m (04)
iii) 16mm ø @ 150mm c/c 21 12.1 401.478
@ 1.58 Kg/m (07)
iv) 8L-10mm ø Stirrups 70 3.2 138.208
@150 c/c @ 0.617 Kg/m
(08)
v) 8L-12mm ø Stirrups 96 3.2 273.408
@110 c/c @ 0.89 Kg/m
(8a)
5500 Kg
3 Pier 1
a) Cement Concrete (M-35) 3.46 1 5.3 18.338
18.338m3
b) Steel Reinforcement
i) Straight Bars 20mm ø @ 44 8.9 967.252
2.47 Kg/m (01)
ii) Ring Bars 10mm ø @ 40 6.6 162.888
75mm c/c @ 0.617 Kg/m
(02)
iii) Ring Bars 10mm ø @ 14 6.6 57.0108
150mm c/c @ 0.617 Kg/m
(2a)
2374.5Kg
4 Pier Cap 1
a) Cement Concrete (M-35)
i) Rectangular Shape 10.5 3.2 0.75 25.2
ii) Trapezoidal Shape 10.5 3.2 0.75 15.36
40.56 m3
b) Steel Reinforcement
i) 32mm ø @ 160mm c/c 18 11.5 1308.24
@ 6.32 Kg/m (05)
ii) 20mm ø @ 160mm c/c 20 11.64 628.56
@ 2.7 Kg/m (04)
iii) 16mm ø @ 100mm c/c 30 12.1 573.54
@ 1.58 Kg/m (07)
iv) 8L-10mm ø Stirrups 70 3.2 138.208
@150 c/c @ 0.617 Kg/m
(08)
v) 8L-12mm ø Stirrups 96 3.2 273.408
@110 c/c @ 0.89 Kg/m
(8a)
2922 Kg
ABSTRACT OF SHEET:-
S. No. Item Quantity Per Rate Amount (Rs)
(Rs)
1 Abutment
i) Cement Concrete (M-35) 37 cu.m 5511 203907
ii) Steel Reinforcement 2374.5 kg 38.5 91418.25
2 Abutment Cap
i) Cement Concrete (M-35) 64.5 cu.m 5511 355459.5
ii) Steel Reinforcement 5500 kg 38.5 211750
3 Pier
i) Cement Concrete (M-35) 18.4 cu.m 5511 101402.4
ii) Steel Reinforcement 2374.5 kg 38.5 91418.25
4 Pier Cap
i) Cement Concrete (M-35) 40.56 cu.m 5511 223526.16
ii) Steel Reinforcement 2922 kg 38.5 112497
SUM- 1391378.56
2 Steel
Reinforecement
(a) Reinforcement at
Bottom including
bending in RCC
work
(i) 12mm Ø 400 11.2 3987.2 3987.20kg
@150mm c/c (02)
@ 0.89kg/m Main
bars
(ii) 10mm Ø 55 60.1 2049.41 2049.41kg
@150mm c/c (05)
@ 0.62Kg/m bars
(iii) 12mm Ø 33 60.2 1768.074 1768.07kg
@150mm c/c (06)
@ 0.89kg/m bars
(iv) 12mm Ø 12 61.2 653.616 6530616kg
@200mm c/c (07)
@ 0.89kg/m bars
(v) 12mm Ø 334 4 1189.04 1189.04kg
@180mm c/c (03)
@ 0.89kg/m bars
(vi) 16mm Ø (08) 12 60.1 1139.496 1139.49kg
@ 1.58kg/m
(vii) 16mm Ø 5 12.2 96.38 96.38kg
@180 mm c/c (1a)
@ 1.58kg/m
(viii) 20mm Ø 10 12.2 305 305kg
@180mm c/c (1b)
@ 2.5kg/m
(ix) 4 Legged 55 2.8 95.48 95.48kg
10mmØ @200mm
c/c
@ 0.62 kg/m (09)
Total 11283.696 11284Kg
(b) Reinforcement at
Top including
bending in RCC
work
(i) 16mm Ø 335 12.2 6457.46 6457.5kg
@180mm c/c (01)
@ 1.58kg/m Main
bars
(ii) 16mm Ø @180 10 12.2 192.76 192.76kg
mm c/c (1a)
@ 1.58kg/m
(iii) 20mm Ø 10 12.2 305 305kg
@180mm c/c (1b)
@ 2.5kg/m
(v) 12mm Ø 334 4 1189.04 1189.04kg
@180mm c/c (03)
@ 0.89kg/m bars
(v) 10mm Ø 334 4 828.32 829Kg
@200mm c/c (04)
@ 0.62kg/m bars
(v) 16mm Ø 55 3.36 291.984 292kg
@200mm c/c (4a)
@ 1.58kg/m bars
(vi) 4 Legged 55 2.8 95.48 95.48kg
10mmØ @200mm
c/c
@ 0.62 kg/m (09)
Total 9360.044 9361Kg
SUM- 2205621.5
2 Steel Reinforecement
a) Reinforcement at
Bottom including bending
in RCC work
b) Reinforcement at top
including bending in RCC
work
SUM- 4085615
When the cost of pier equals cost of main girders and cross -girders of one span, then total cost of
the bridge comes out to be minimum.
C=Ca+nCp+LCf+LCt.
Indian Standards:-
Road Bridges.
3. “IRC:112-2011” Code of practice for concrete Road Bridges.
(Fourth revision)
Books:-
6. “Dr. B.C. Punmia & Er. A.K. Jain” Reinforced Concrete Structures.
Detailed Design And Detailing Report of GRADE SEPARATOR AT CH. 88+638 OF NAGDA-
DHAR-GUJRI ROAD SECTION OF SH-31 TO TWO LANE FROM KM. 68+800 TO
KM.138+300.