You are on page 1of 1

PREVENTIVE MAINTENANCE CHECKLIST ES Ceramics Technology

Machine Name: GENSET Work Order No: MONTH


Type/I.D No: Plant:
Location: YEAR 2020
Note: Please tick [ √ ] if found o.k and tick [ X ] and note remark if found not ok. Note [ NA ] for Not Applicable.
Item 1 Act Requirement Standard Status Remarks
1.1 Check fuel level I Max Level Above min level
1.2 Check oil leak I No leak No wear and tear
1.3 Start & test I Good condition& easy to start Working condition
1.4 Check any abnormal sound I Good condition No jerk or vibration

Report if additional work carried out : * Switch OFF the machine before work
* Be aware on slip hazards Check by
* Be aware of sharp edges Sign:
* Be aware of pinch points and crushing hazards.
* Do not remove any hydraulic fitting if still have pressure in the line. Date:
* Use LOTO procedure
Action Note:C = Cleaning, G = Greasing, I = Inspection, L = Lubricate, T = Test Run. Verify by:

Navin