Professional Documents
Culture Documents
CONSULTANT:
DPR-I: Index
MAWPHU HEP, STAGE – II
INDEX
VOLUME TITLE
Volume-III Hydrology
DPR-I: Index
MAWPHU HEP, STAGE – II
TABLE OF CONTENTS
EXECUTIVE SUMMARY..............................................................................................................1
a. Introduction:.......................................................................................................................................1
b. Location of the Project:....................................................................................................................1
c. Proposed Project Layout.................................................................................................................1
d. Electro-Mechanical Equipments.....................................................................................................2
e. Power Evacuation System...............................................................................................................2
f. Hydrology:..........................................................................................................................................2
g. Site Investigation, Geology and Construction Material:...............................................................4
h. Power Potential Studies:................................................................................................................12
i. Construction Schedule...................................................................................................................12
j. Environmental Aspects..................................................................................................................13
a. Estimate of the Cost.......................................................................................................................13
b. Financial Analysis...........................................................................................................................13
SALIENT FEATURES................................................................................................................14
1. INTRODUCTION.....................................................................................................1-1
1.1. General...........................................................................................................................................1-1
1.2. Scope of the Work.........................................................................................................................1-2
1.3. Need for the Project......................................................................................................................1-2
1.3.1. Region-Wise Power Supply Position..........................................................................................1-2
1.3.2. State-wise Annual Actual Power Supply Position during 2012-13..........................................1-3
1.3.3. Actual power supply position in Meghalaya:..............................................................................1-4
1.4. Description of the Project.............................................................................................................1-4
1.4.1. Project Location.............................................................................................................................1-4
1.4.2. Approach to the Project Area.......................................................................................................1-6
1.4.3. The River System and Basin Characteristics............................................................................1-9
1.4.4. Basin Development.....................................................................................................................1-10
1.4.5. Project Proposal..........................................................................................................................1-11
2. REVIEW OF EARLIER STUDIES AND FIXATION OF PROJECT LAYOUT........2-1
2.1. Project Background.......................................................................................................................2-1
2.2. Alternative studies.........................................................................................................................2-3
2.2.1. Alternative Locations of Dam:......................................................................................................2-3
9.4.6.3. Feeders...........................................................................................................................................9-9
9.4.6.4. Station Auxiliary Transformer.......................................................................................................9-9
9.4.6.5. Station Service Transformers and Unit Auxiliary Transformers............................................9-10
9.4.7. AC Auxiliary Power System.......................................................................................................9-10
9.4.7.1. Power to Dam Site Area.............................................................................................................9-11
9.4.7.2. Power to Penstock Protection Valve House............................................................................9-11
9.4.7.3. Power to Colony and Office Area..............................................................................................9-11
9.4.8. DC Auxiliary Services.................................................................................................................9-12
9.4.9. Earthing System..........................................................................................................................9-12
9.4.10. Power, Control and Instrumentation Cables............................................................................9-12
9.4.11. Illumination System.....................................................................................................................9-13
9.4.12. Test Laboratory............................................................................................................................9-13
9.4.13. Communication System..............................................................................................................9-13
9.5. Auxiliary Mechanical Services...................................................................................................9-14
9.5.1. EOT Crane...................................................................................................................................9-14
9.5.2. Cooling Water System................................................................................................................9-14
9.5.3. Drainage and Dewatering Systems...........................................................................................9-14
9.5.4. Fire Protection..............................................................................................................................9-15
9.5.5. Ventilation and Air Conditioning................................................................................................9-15
9.5.6. Compressed Air System.............................................................................................................9-16
9.5.7. Electrical Lifts and Elevators......................................................................................................9-16
9.5.8. Workshop Equipment..................................................................................................................9-16
9.6. Power Evacuation Arrangement................................................................................................9-17
9.7. Drawings.......................................................................................................................................9-17
10. ENVIRONMENTAL AND ECOLOGICAL ASPECTS...........................................10-1
11. CONSTRUCTION METHODOLOGY....................................................................11-1
11.1. Access to Project Site & Project Components.........................................................................11-1
11.2. Project Components:...................................................................................................................11-2
11.3. Climatic Conditions:.....................................................................................................................11-2
11.4. Construction Material:.................................................................................................................11-2
11.5. Assumptions while framing the Schedule & Construction Methodology:.............................11-3
11.6. Methodology for Execution of Works........................................................................................11-3
11.6.1. Construction of Access Roads to Project Components..........................................................11-3
EXECUTIVE SUMMARY
a. Introduction:
Mawphu Hydroelectric Project, Stage - II is proposed as a run-of-river scheme on the river
Umiew in East Khasi Hills District of Meghalaya. The proposed dam site is located at about
3.17km downstream of Umduna HEP (90 MW) Power House location and the Power House
site is located at about 2km downstream of Thieddieng village on the right bank of the river.
The project is being implemented by North Eastern Electric Power Corporation Ltd, a
Government of India enterprise. The Pre-Feasibility study of the project had been carried
out by NEEPCO in the year 2010
NEEPCO Ltd. invited domestic competitive bidding for preparation of Detailed Project Report
(DPR) and Related Activities for Mawphu Hydroelectric Project (Stage-II) on 21 st May 2012
and the work was awarded to Energy Infratech Private Limited (EIPL), New Delhi in
December 2012. .
The scope of works includes Topographical survey, Geological and geo-technical survey
and investigations including sub-surface investigations namely exploratory drilling, in-situ
and lab tests, geo-physical survey in the project area.
DPR-I:Executive Summary 1
MAWPHU HEP, STAGE – II
Various proposed components of the project envisaged by the selected dam and power
house locations are given below:
A concrete gravity dam of 51m high (from the deepest foundation level) and 140m
long (at top) comprising 3 overflow blocks with spillway arrangement of 6 bays ,
each with radial gate of size 9.0m x 12.00m and 4 non-overflow blocks.
Energy dissipation arrangement is proposed with trajectory bucket.
River diversion arrangement consists of 1 no. diversion tunnel of 7m dia, Horse-
shoe shaped and 384m long, on the left bank with 18m high upstream coffer dam
and 6m high downstream coffer dam.
Power intake structure is of 16m wide and 20m high on the right bank with an
inclined trash rack.
Head Race Tunnel is of 4.80m dia, Horse-shoe shaped and 2.62km long.
Restricted orifice type surge shaft is of 10m dia and 54m high at the end of HRT
Main pressure shaft is of 3.50m dia, 869m long and branch pressure shaft is of
2.50m dia and 32m long each
Surface power house is of size 53.80m (L) x 16.0 m (W) x 30.50 m (H) housing two
vertical axis Francis turbines each of 37.50MW installed capacity
Tail race channel is of 8m wide and 51 m long (including Recovey Bay) to discharge
water into the river
132kV Gas insulated switchgear installed on the floor above the transformers
d. Electro-Mechanical Equipments
The surface power plant comprises two units of Vertical axis Francis Turbines each with
37.50MW capacity with 10% continuous overload. The rated speed of the turbines is 500rpm
with the rated head of about 232.33m. Vertical shaft synchronous generators with maximum
rated capacity of at 41.7MVA will be provided which will be directly coupled to the respective
turbines. The generation voltage selected is 11kV. The generator step up transformers are
housed upstream of the powerhouse, connected through segregated phase bus ducts. The
transformers will be further connected to the 132kV Gas insulated switchgear located on the
floor above the generator transformers.
DPR-I:Executive Summary 2
MAWPHU HEP, STAGE – II
f. Hydrology:
i. Water Availability Studies:
Available rainfall data at Shillong and Mawphlang along with observed discharge data at
Mawphlang dam site from January 1979 to December 1987 was utilized for water availability
studies. Gaps in the available rainfall and discharge data at Mawphlang filled. Consistency
checks on the data were applied. Available discharges at Mawphlang for the period 1979-80
to 1987-88 extended up to 2004-05 using rainfall-runoff relations. Based on TRMM data for
the period 1998-2009, catchment rainfall worked out to 4415 mm. Adopting runoff factor of
0.8, runoff at Mawphu II dam site comes to 3538 mm. Mean annual runoff at Mawphlang
based on observed data is 3018 mm. Hence yield correction factor for dam site comes to
1.17. The discharges at dam site were estimated by increasing Mawphlang discharges in
catchment proportion and by applying yield correction factor. Considering the withdrawal by
GSWSS, available 10-daily discharges at dam site determined by subtracting 0.5 cumecs
from the 10-daily estimated discharges at the dam site, to obtain the available discharges for
the period 1979-80 to 2004-05. From the 10-daily discharges at dam site, annual flows for
the period 1979-80 to 2004-05 worked out and arranged in descending order. % Age
dependability estimated using Weibull’s equation. 90 % & 50 % dependable flows worked
out as 887 & 1020 MCM, which correspond to the years 1996-97 & 2002-03 respectively.
10-Daily flows during 90 % dependable year (1996-97) have been used for power potential
studies.
Water availability studies have been examined and approved by CWC vide U. O. No.
4/161/2013-Hyd (NE)/104-05 dated 11/03/14.
As per BIS guidelines dams with gross storage capacity greater than 60 MCM or hydraulic
height greater than 30 m are to be designed to safely pass Probable Maximum Flood (PMF).
Since height of the dam is more than 30 m, the project is designed to safely pass the PMF.
Synthetic UG at the dam site was estimated from the basin characteristics viz. A, L, Lc, S
etc., using report for “Estimation of Design Flood for South Bank Tributaries of the
Brahmaputra, Sub-zone 2 (b)”. Since time to peak worked out as 10.1 hours which
appeared to be on the higher side for a catchment area of 320.2 sq km and having steep
slope. Hence as advised by CWC, time of concentration has been estimated using Kirpch
formula, California formula etc., which worked out to about 5 hours. Synthetic UG was
therefore developed using Sub-Zone 2 (a) report of CWC and convoluted with 1-day PMP
given by IMD. Probable Maximum Flood of 8889 cumecs has thus been estimated. Hence
design flood of 8,900 cumecs has been adopted.
As per IS - 14815:2000 for planning river diversion works for concrete dams, 1 in 25 year
flood of non-monsoon months or maximum observed during these months; whichever is
higher, is to be considered. From the available daily discharges of River Umiew at
Mawphlang (C.A. = 115 sq km) for the period 1980-81 to 1996-97, non-monsoon peaks were
DPR-I:Executive Summary 3
MAWPHU HEP, STAGE – II
worked out. The annual peaks thus obtained were subjected to frequency analysis to
determine the floods for various return periods. It is seen that 25 yr return period flood at
Mawphlang works out to 154 cumecs which is less than the observed non-monsoon flood of
174 cumecs. Hence, as per IS -14815:2000, diversion flood at Mawphlang comes to 174
cumecs. Transforming this flood using Dicken’s equation, the diversion flood at Mawphu
HEP, stage II works out to 375 cumecs.
iv. Sedimentation Studies:
Based on the topographical survey of the reservoir areas and capacities at various
elevations have been worked out. Since sedimentation observation of Umiew river at the
project site or at any other site in the vicinity are not available, sediment rate of 1mm/sq
km/yr has been adopted for the studies. From the capacity inflow ratio, trap efficiency from
Brune’s curve works out to 0.5%, which indicates that most of the sediment will not be
trapped in the reservoir and would flow downstream. Hence following measures for sediment
management have been provided in the design aspects.
Operating the reservoir at MDDL during the monsoon months to route the
incoming sediment downstream of the project site.
Provision of low level sluice spillway crest for flushing the silt downstream during
flood season.
Reservoir drawdown flushing two times every year, to ensure that live storage is
always available.
Adequate vertical separation between the water conductor intake sill level and the
sluice spillway crest level for effective silt flushing.
The project area falls in the central part of Meghalaya, where the Gneissic Complex has
multiple deformational & metamorphic episodes. In general, the grade of metamorphism
varies from the green schist to amphibolites facies. The Meghalaya plateau and the Mikir
hills occur in between the E-W aligned Eastern Himalaya to the north and the broadly NNE-
SSW Indo-Myanmar mobile belt to the east. The Northern and North-eastern boundary with
Bengal basin lies to its south. These geological domains are separated from the main
Himalayan belt by the Brahmaputra alluvium. The Mikir Hills are separated from the
Meghalaya Plateau by the alluvium tract of Kopili River and the NE-SW Kopili fault.Dauki
fault is located 12 km south of project area.
DPR-I:Executive Summary 4
MAWPHU HEP, STAGE – II
Earlier during PFR stage, several alternative sites were identified to select the most suitable
one for dam in downstream of Umiew River and Umkynrem River. As Old PFR Dam location
proposed by NEEPCO did not fulfill the environmental requirement formulated by Expert
Appraisal Committee (EAC) of MoEF, Alt-1, Alt. 2 & Alt.3 were chosen for review during site
visit. It was found that Alt-3 was a suitable location which is at about 3.1km downstream of
proposed Umduna HEP Power House location and accordingly an exploration plan was
drawn at the axis for investigation for DPR preparation. During drilling at Alt-3 location, drill
hole DH-07 encountered deep overburden on the left bank of dam axis. So, it was proposed
that the dam axis needs to be shifted slightly downstream by about 70m to avoid deep
overburden on the left abutment. Accordingly, Alt-3A has been chosen as a possible
location for further investigation works.
During pre-feasibility stage the project area was studied with the help of topographic
maps and few preliminary stage investigations. Subsequent to submission of PFR,
EIPL was entrusted detailed investigation and preparation of DPR. The Project
components have been studied in detail through geological mapping, exploratory
drilling, drifting(under Progress) and geophysical studies. Further, In-situ soil
mechanics test namely SPT and Laboratory Rock mechanics test for UCS,Young’s
Modulus and Poisson’s ratio have been got done at ATES,NEW DELHI. The
investigations carried out are tabulated below.
a. Geological Mapping
Component Scale
Dam and its appurtenant Structure 1:1000
Reservoir 1:1000
HRT 1:2500
HRT Adit portals 1:1000
b. Drilling
DPR-I:Executive Summary 5
MAWPHU HEP, STAGE – II
In addition to 3 bore holes with aggregating length of 90m for Groutability test, 18 bore holes
having cumulative lengths of 875m have been drilled so far. Out of these 18 drill holes, 11
holes with cumulative length of 445m have been drilled to explore Dam and its appurtenant
structures and 2 holes of 50m & 60 m length were drilled to explore surface Power house
whereas 4 bore holes were drilled to explore pressure shaft and Surge shaft was explored by
one hole of 110m One 40m deep hole planned to explore HRT and is under progress.
c. Water Pressure/Permeability Tests
In total 402 numbers of water pressure/water percolation tests were conducted for assessing
permeability in all the exploratory drill holes.
d. SPT
In total 106 numbers of Standard penetration test were conducted for assessing bearing
capacity of overburden, SPT were conducted in accordance with IS 2131 and results were
incorporated in the respective drill logs.
e. Groutability test
Groutability test has been carried out on the river bed (Dam foundation) to ascertain the extent
of amenability of foundation rock to systematic grouting. The pattern and depth of hole is
governed primarily by the design requirement and the nature of rock. Giving due cognizance
to variation of strike of foliation and other intersecting joints Triangular pattern was adopted for
conducting Groutability test.
f. Exploratory Drifting
The dam abutments of Alternative-3a have been planned to be investigated by excavating two
drifts.viz LBD-1 having 30m length at left bank and RBD-1 having 30m length at left bank. A
total length of 60m of drifting at the Dam location been proposed to be carried out.
g. Rock Mechanic Tests
In order to determine both physio mechanical and engineering properties such as specific
gravity, UCS, tensile strength, cohesion, friction angle, deformation modulus of the various
rock types occurring in the project area, laboratory tests on rock cores collected from drill
holes were carried out at the ATES laboratory.
h. Petrography
Specimens of rocks obtained from various rock exposures and rock cores from various drill
holes of Dam site, Surge Shaft and surface Power House were utilized by the GSI Petrology
Laboratory located at Faridabad for Petrographical studies. Furthermore, 2 silt samples were
also tested and 2 tests are under progress in same laboratory for estimating of mineral
distribution in silt samples.
i. Geophysical Studies
DPR-I:Executive Summary 6
MAWPHU HEP, STAGE – II
Geophysical explorations involving seismic refraction profiling were carried out in the project
area with a view to decipher the interface between the overburden and bedrock as well as to
determine the overburden/bedrock characteristics. In total 7 profiles aggregating length of
860m covering Dam, Power house and adit has been carried out.
j. Seismological Studies
Dept of Earthquake Engineering IIT Roorkee was entrusted the job to carry out the study for
evaluating seismic design parameters for the project components. Based on the above, the
maximum value estimated for horizontal peak ground acceleration (PGA) is 0.42gfor MCE and
0.24 for DBE condition respectively for both Horizontal and Vertical ground motion.
a. Dam
The 51m high concrete dam, from deepest foundation level, shall have a length of 139.85m
at the top. The top of the dam has been kept at El. 472m.In Dam area thickness of the
overburden ranges from 4 to 7.4 m with permeability ranges from 1.912х10 -3cm/sec to -
6.828х10-3cm/sec. Bed rock permeability values range from 1-6 Lugeon and suggests
reasonably tight foundation condition in the riverbed. In any of the drill hole no major fracture
zone or crushed/shear zone was encountered, making it suitable for laying concrete dam. In
the course of the abutment excavation, no major problem is foreseen as right bank exposes
strong granite gneiss upto EL.510m and beyond the top of dam (EL.472m).No adverse zone
was observed during surface mapping of right bank whereas for the left abutment excavation
the initial reach of the rock mass may need to be stripped and concurrent supports in the
form of rock bolts would be required. Due to presence of the unconsolidated overburden on
upper reaches of the left bank maintaining stability of cut slopes in this reach are imperative.
b. Energy Dissipator
The energy dissipator, proposed to be kept over dominantly fine to coarse grained granitic
gneiss. The In-situ permeability values of 1.86 to 3.25 Lugeon suggest fairly tight foundation
conditions and the same gets corroborate through the results of Groutability test. After
removing the bedrock a stripping depth of approx 2-3m is envisaged.
c. Coffer Dam
Upstream Coffer Dam
An Eighteen m high coffer dam has been proposed about 205 upstream of dam axis for
diversion of water through diversion tunnel .On the basis of various boreholes drilled in the
dam area particularly DH-01 and DH-02, overburden permeability is expected to range
between 1.02 to 1.2 X 10-2 cm/sec. Where as that of bedrock would vary between 3 to 6
Lugeon. In view of this, as seepage control measure, jet grouting provisions has been kept
below the coffer dam to minimize seepage into the dam pit during construction.
DPR-I:Executive Summary 7
MAWPHU HEP, STAGE – II
Downstream Coffer dam has been proposed to be located at 160m D/S of dam axis, right
abutment of the structure has been positioned utilizing the exposed rock ledge. DH-10 drilled
for subsurface investigation of the stilling basin. It is opined that thickness of overburdened,
constituted of large boulder pebbles, cobbles, gravels of granite/granitic gneiss mixed with
sand shall be of the order of 5 to 7m followed by strong to very strong quartz biotite gneiss.
Overburden permeability ranges between 3.8 & 4.8 X10 -3 cm/sec and therefore suitable
pumping arrangement shall be required during construction.
d. Diversion Tunnel
During the construction, the river water is proposed to be diverted through a 384.6m long,
7m dia. horse shoe shaped diversion tunnel on the left bank that would cater to a maximum
discharge of 375cumecs.The entire Diversion Tunnel area has been divided into three part
giving due cognizance to Geological condition, nature and extent of overburden/rock cover
(both lateral and top), condition of conspicuous joint sets, tunneling direction and proximity to
river.
DT Inlet Area
DT Inlet Area extends from RD 0- RD 65m.The DT inlet portal with invert at EL 446mm is
located in granite gneiss. Overall tunneling media for this reach estimated to be
Predominantly Class IV with patches of Class III and minor class V.
DT Intermediate Area
DT outlet Area
DT Outlet area extends from RD 328 - RD 384.6m. Overall tunneling media for this reach
estimated to be predominantly of Class III with patches of Class IV and Class V.
e. Power Intake
Water from Dam shall be diverted to head race tunnel through a power intake structure
proposed to be located on the right bank of Umiew River at about 15.0m u/s of the dam axis.
The slope defining S3 joint sets shown in the drawing has been recorded during surface
mapping and it is apprehended that this set will control the slope geometry and hence
DPR-I:Executive Summary 8
MAWPHU HEP, STAGE – II
Rock classes in various stretches of HRT have been predicted on the basis of
surface exposures details.
Based on geomechanical classification of rock mass percentage of rock class to
be encountered in HRT shall be as under.
Low cover and weak zones apart from areas where copious seepage is
anticipated are proposed to be evaluated further by advance probing.
Adequate preparedness shall be required in respect of sufficient dewatering
arrangements. Installation of concurrent support shall be resorted while
negotiating weak rock conditions as envisaged. Requirement of Grouting in few
weak reaches is foreseen particularly near the contact between Granite gneiss
and Granite.
g. Surge Shaft
The 54m deep, 10m dia, restricted orifice type surge shaft shall be accommodating in
moderately strong, moderately to highly weathered granite gneiss with biotite schist banding.
As no major shear zone was encountered during drilling as such no serious difficulty during
the excavation of shaft is anticipated. In general there is an improvement in rock strength,
weathering and opening of the joints with the depth barring few exceptions at EL.491m,
EL.482m, EL472m, EL.451m and EL.436m where RQD has been found to be low though the
recovery remains constantly high. In such area provision of consolidation grouting shall be
required for ground improvement. Considering the nature of rock encountered in drill holes
and observed rock mechanic parameters, it is anticipated that the major part of Surge shaft
shall negotiate fair to good rock with occasional patches of poor rock. The suitable rock
support ,consisting of rock bolts, SFRS and pressure relief holes shall be installed
concurrent to excavation. It is assessed that the initial and terminal part of the surge shaft
DPR-I:Executive Summary 9
MAWPHU HEP, STAGE – II
excavation would require circular steel set tied firmly to each other along periphery with back
fill concrete in view of the observed weakness especially in these two areas.
h. Pressure Shaft
One 3.5m dia, 869 m long, circular pressure shaft which includes 69m long top horizontal
pressure shaft, followed by a 171m deep vertical shaft and a 673m long horizontal pressure
shaft bifurcating into two 2.5m dia, 32m long tunnels has been envisaged for feeding two
turbines.
ROCK
STRUCTURE PERCENTAGE
CLASS
Class- II 20%
Class- V 5%
For estimation purpose the following percentage of rock class can be considered for bottom
horizontal pressure shaft from 0-540m
DPR-I:Executive Summary 10
MAWPHU HEP, STAGE – II
ROCK
STRUCTURE PERCENTAGE
CLASS
Class- II 68%
Class- V 2%
For estimation purpose the following percentage of rock class can be considered for
bottom horizontal pressure shaft from 540-673m, taking into account the nature and
extent of rock cover.
Class- II 20%
Class- V 5%
i. Power House
A surface power house having size 53.8 m x 16.0 m x 30.50 m shall be accommodated in
greyish, medium to coarse grained, strong, moderately jointed granite gneiss. The long axis
of surface power has been oriented in N119°direction i.e. perpendicular to prominent strike
of foliation (N028°-N208) and appears to have been placed suitably with respect to strike of
foliation. It is evident from drill hole data that overburden shall be of the order of 45-
50m.Coefficeint of permeability in overburden ranges from 0.29X10-3cm/sec to
2X10-3cm/sec which indicate highly pervious nature of overburden. Since overburden is of
river borne material which is indicative of a pre-existing river terrace, with presence of water
table at a depth of 12-14m. This shall make this material susceptible to instability.
Accordingly necessary measure to avoid surcharging of the overburden slope shall be
adopted during construction. Generally Core recovery in rock vary from 80-95% and RQD
vary from 30-80%.In view of above ,during excavation in selected weak media consolidation
grouting shall be resorted. However Rock mechanics test conducted on the cores samples
DPR-I:Executive Summary 11
MAWPHU HEP, STAGE – II
from power house area reveals the UCS value of 106 to 137 MPa. It is therefore concluded
that foundation of the surface power house shall be in sound rock.
The entire excavation for Power house pit shall be in bedrock having indicative RMR
(without rating adjustment) ranges from 50 to 59 computed on the basis of geotechnical
parameter collected from the outcrops and collating the finding from boreholes DH-101 and
DH-102 in which bedrock was encountered at El 268.6m and 262.2m respectively.
Tail race system including the recovery bay shall be on bed rock constituted of slightly
weathered strong to very strong, moderately jointed, grey gneiss.
To minimize the effect of some of these adversely oriented joints on excavation particularly
on the western wall, systematic rock support with rock bolts of 25mm Ø 4 to 6m long with
spacing of 2m center to center, adequate thickness of SFRS, and pressure relief
arrangement shall be required to be installed, concurrent to the excavation. Furthermore,
provision of consolidation grouting shall be made as ground improvement measure.
v. Construction Material
A reconnaissance of area around the project encompassing Umiew river, Dam site to 40 km
D/S down to Balat has been carried out to locate the most suitable rock quarries, river
shoals. After survey 10 rock quarries, 3 river terraces/shoal deposits have been identified
and explored. Representative samples collected from exploratory pits excavation have been
tested for physical parameters by ATES New Delhi. In addition sample from both the banks
which would accommodate the dam, have been got tested for use as concrete aggregates.
Sufficient Quantity of suitable construction material is available to meet the requirement of
2.23 lac cum of coarse aggregate, 1.12 lac cum of fine aggregate for production of concrete
and 0.65 lac cum of Rock fill for coffer dams. Most of the rock samples being tested suitable
for wearing surface concrete and hence entire requirement shall be meet from identified
quarry/Barrow areas.
The environment releases as per the Terms of Reference (ToR) mentioned by the Ministry of
Environment and Forests (MoEF) as given below have been considered for computing the
available discharges for power generation.
DPR-I:Executive Summary 12
MAWPHU HEP, STAGE – II
Percentage discharge
Sl.No. Period
considered
The proposed installed capacity is 75 MW (2 x 37.50 MW) with 10% continuous overload.
The annual energy generation in 90% dependable year (1996-97) is 291.62 MU. The plant
load factor is 44.39%.
i. Construction Schedule
The project has been planned to be constructed in a period of 60 months including 15
months for pre-construction activities. Main construction activity is planned to be completed
in about 45 months after accord of TEC by CEA and Environmental & Forest clearance from
MOEF. Excavation of dam below river bed level and concreting in dam up to river bed level
is the critical activity of the project. Apart from the dam, excavation of Power House is also a
critical component of the project, though it is not driving the project schedule.
Excavation of 2.62 km long HRT can be carried out from 3 faces and hence is not envisaged
to be critical, as excavation is likely to be carried out in favorable geological conditions.
j. Environmental Aspects
Environmental study is to be provided by NEEPCO, which is awaited till the completion of
the draft DPR.
DPR-I:Executive Summary 13
MAWPHU HEP, STAGE – II
b. Financial Analysis
Financial evaluation of the project has been carried out for the project operation period of
35 years. The tariff has been worked out considering the financial aspects as mentioned
below.
The first year tariff and levellised tariff have been worked out as Rs.6.94/kWh and Rs.
6.19/kWh respectively.
DPR-I:Executive Summary 14
MAWPHU HEP, STAGE – II
SALIENT FEATURES
RIVER Umiew
LOCATION
State Meghalaya
a. Dam Site
DPR-I:Salient Features 15
MAWPHU HEP, STAGE – II
HYDROLOGY
RESERVOIR
DPR-I:Salient Features 16
MAWPHU HEP, STAGE – II
DAM
SPILLWAY
DIVERSION ARRANGEMENT
DPR-I:Salient Features 17
MAWPHU HEP, STAGE – II
POWER INTAKE
Number 1 No.
Number 1
Length 2.62 km
ADITS TO HRT
DPR-I:Salient Features 18
MAWPHU HEP, STAGE – II
SURGE SHAFT
Number 1
Size 10.0 m
Height 54.00 m
PRESSURE SHAFT
Number 1
Vertical 127.00m
Adit-3 to bottom horizontal Pressure Shaft 6 m dia, D-Shaped and 455 m long
DPR-I:Salient Features 19
MAWPHU HEP, STAGE – II
POWER HOUSE
Type Surface
Number of units 2
DPR-I:Salient Features 20
MAWPHU HEP, STAGE – II
POWER EVACUATION
ENERGY GENERATION
COST
DPR-I:Salient Features 21
MAWPHU HEP, STAGE – II
construction activities)
DPR-I:Salient Features 22
MAWPHU HEP, STAGE – II
1. INTRODUCTION
1.1. General
North Eastern Electric Power Corporation Ltd (NEEPCO) awarded the work of Survey,
Investigation and preparation of Detailed Project Report (DPR) of Mawphu Hydro Electric
Project (Stage-II) to Energy Infratech Pvt Ltd. (the Consultant) on 4 th Dec 2012. EIPL has
completed more than 90% survey and investigation works and prepared the Draft Detailed
Project Report in four volumes. This volume of the DPR presents the results of the technical
feasibility study on the Mawphu HE Project (Stage-II) and appurtenant facilities including the
substation. Drawings are presented in Volume-1A. The detailed Cost estimates, hydrological
studies, geotechnical studies are presented in Volume-2, 3 and 4 respectively
This volume herein focuses on a summary of the results collected through the field activities
and their incorporation into the development of the project design. This is followed by a
description of the feasibility design itself and a presentation of the main parameters
necessary for future project development (e.g. quantities and costs estimates, economic
analysis, construction methodology and schedule, etc.).
In the following text, after a short description of the project, a short summary of the findings
from the already existing documents and the alternative studies carried out for fixing up of
layout is given in Chapter-2. Furthermore, the same chapter contains the elaboration of the
project boundary conditions and a multi‐criteria analysis for the selection of the upstream
reservoir level. This is followed by the presentation of the survey works undertaken and
development of topographical maps in Chapter-3. The collection of hydrological data, as
well as results of the hydrological analysis and analysis of the river water levels after
construction of the dam are given in Chapter-4. Summary of the main results from the
geological/geotechnical investigations and basic understanding of the project geology is
given in Chapter-5. Estimation of power potential is presented in Chapter-6. Civil
engineering structures and their design are explained in Chapter-7.
Hydro-mechanical equipments are given in Chapter-8 and the sizing of the main generating
and electrical equipments and power evacuation arrangements are given in Chapter-9.
Detailed rate analysis, estimation of quantities of various items of works and their costs are
given in Chapter-15. Finally, the financial evaluation of the project based on estimated cost
and revenues from design energy is presented in Chapter-16.
It is to be noted that the design drawings presented in Volume-1A illustrate herein the given
design at the feasibility level.
In general, the herein assigned works for the development of the Mawphu Hydro‐Electric
Project (Stage-II) consist of collection of existing documentation, review of available data
collection of the field data necessary for the development of topographical, hydrological,
geological and geotechnical documentation at an appropriate level for the selection of the
most favourable location and layout of the power plant components.
The above listed field data are processed, evaluated and used for the development of the
project layout and definition of the basic characteristics of the civil works and necessary
electro‐mechanical equipment. Based on this, estimation of the annual power production, as
well as cost estimation is done. NEEPCO has awarded the work of EIA and EMP studies to
another consultant, WAPCOS. A brief description of environmental studies is presented in
this report.
Finally, the above described feasibility study shall serve as the basis for the development of
the tender documents. Nevertheless, it is very important to emphasize that the herein
reported works are developed at the level of a feasibility study. Therefore, prior to any further
project development step it is necessary to independently check the reported results and
establish appropriate technical documentation.
Energy Peak
Region Requiremen Surplus/ Deman Surplus (+)/
Availability Met
t Deficit(-) d Deficit(-)
(MU) (MU) (MU) (%) (MW) (MW) (MW) (%)
-
Northern 300,774 273,240 -9.2 45,860 41,790 -4,070 -8.9
27,534
Western 296,475 286,683 -9,792 -3.3 40,075 39,486 -589 -1.5
- - -
Southern 281,842 238,058 38,767 31,586 -7,181
43,784 15.5 18.5
Eastern 107,457 102,510 -4947 -4.6 16,655 15,415 -1,240 -7.4
North-
11,566 10,718 -848 -7.3 1,998 1,864 -134 -6.7
Eastern
It may be seen from the above table that the actual energy requirement in North-Eastern
region is 11,566 MU whereas the energy availability is 10,718 MU. Also, the peak demand
in the region is 1,998 MW whereas the peak supply was 1,864 MW. That is, north-eastern
region faced 7.3% energy deficit and 6.7% peak shortage.
In the Northern Region, Chandigarh, Delhi and Himachal Pradesh faced negligible energy
shortage. Rajasthan, Haryana, Punjab and Uttarakhand experienced energy shortages in
the range of 3-8% whereas the shortage in Uttar Pradesh was 16.6%. The maximum energy
shortage in Northern Region was in Jammu & Kashmir and was 25%.
In the Western Region, Gujarat faced negligible energy shortage. Dadra & Nagar Haveli,
Chhattisgarh, Maharashtra and Goa faced energy shortage in the range of 1-4%. Daman &
Diu faced energy shortage of 6.6% whereas the maximum energy shortage in Western
Region was in Madhya Pradesh and was 9.6%.
In the Southern Region, Kerala and Puducherry faced energy shortages in the range of 1-
4% whereas the shortage in Karnataka was 13.9%. The energy shortage in the Tamil Nadu
was 17.5% and the maximum energy shortage in Southern Region was in Andhra Pradesh
and was 17.6%.
In Eastern Region, West Bengal faced negligible energy shortage and DVC, Odisha and
Jharkhand faced energy shortages in the range of 3-6%. The maximum energy shortage of
16.7% was faced by Bihar.
In the North-Eastern Region, Assam, Manipur, Tripura and Nagaland faced energy
shortages in the range of 5-7%. The maximum energy shortage in North-Eastern Region
was in Meghalaya at 12.1%.
The total peak demand of Meghalaya, during the year 2012-13, was 334 MW and the total
peak supply was 330 MW. i.e the total peak deficit was 4 MW and the same in terms of
percentage was 1.2%.
Therefore, in order to meet the increasing peak energy demand of the state as well as the
region, it is an essential requirement to utilize the hydro power potential of Meghalaya to
boost the industrial as well as overall growth in the state.
Though Mawphu HEP, Stage – II, has been planned as a Run-of-the River scheme, it would
however be possible to derive peaking benefits with the help of diurnal storage being
provided.
Mawphu HE Project (Stage-II) is located in the East Khasi Hills district of Meghalaya, a north
eastern state of India as shown in Fig 1-1 and Fig 1-2. The name of State, Meghalaya,
means “the abode of clouds” in Sanskrit. As of 2011, the state has a population of 2,964,007
and is the 23rd most populous in the country. Meghalaya covers an area of approximately
300 kilometers in length and about 100 kilometer in breadth. This state is bounded to the
south by the People’s Republic of Bangladesh and the north by India’s Assam. The capital is
Shillong, known as the “Scotland of the East” and has a population of 143,007.
About one-third of the state is forested. The Meghalaya subtropical forests ecoregion
encompasses the state; its mountain forests are distinct from the lowland tropical forests to
the north and south. It was previously part of Assam, but on 21 January 1972, the districts of
Khasi, Garo and Jaintia hills became the new state of Meghalaya.
Meghalaya is the wettest place on earth with average annual rainfall as high as 1200 cm in
some areas. The town of Cherrapunji in the Khasi Hills south of capital Shillong holds the
world record for most rain in a calendar month, while the village of Mawsynram, near the
town of Cherrapunji, holds the record for the most rain in a year.
Mawphu HEP (Stage-II) is located in a valley between Cherrapunji and Mawsynram, the
wettest region of the country (Refer Fig 1-3). A village, Mawphu is located on the right bank
of river between the dam and power house reach, therefore probably the name of the project
was given as Mawphu Project (Stage-II). This project is located downstream of Umduna HE
Project (earlier called as Mawphu HE project) being developed by a private entrepreneur.
The status of upstream project is post DPR stage.
Mawphu HEP
(Stage-II)
Mawphu Hydro Electric Project (Stage –II), is proposed as a run-of-river scheme on the river
Umiew, a tributary of the river Surma, which is a major tributary of Brahmaputra. The river
Brahmaputra is one of the biggest rivers in the world. The total length of Brahmaputra river
in India is 885km and its drainage basin in India is 1,95,000 sq. km.
Access road exists up to Cherrapunji on eastern side of the valley (left bank) and up to
Mawsynram on western side of the valley (right bank) as shown in Fig 1-4. The project site
is accessed from Mawsynram. Mawsynram is about 60km from Shillong. There is 6 km long
foot track from Mawsynram town to Thieddieng village (Refer Fig 1-5), which is very steep
(Refer Fig 1-6) and therefore no motorable road exists in this stretch. Mawsynram is located
at about 1400m above MSL and Thieddieng village is at 800m above MSL.
Fig 1-6: Access from Mawsynram to Thieddieng Village by foot track showing
steep path
However, a road of about 6km long is being constructed by State PWD from PWD office in
Mawsynram (about 2 km from Mawsynram town) to Thieddieng village and formation cutting
for about 4 km long has been completed (Refer Fig 1-7). It is expected that the this road
shall be available up to Thieddieng village prior to start of construction of this project and
therefore project road has been planned from Thieddieng village to various project
component locations.
Thieddieng village is located at mid-way of dam and power house sites of Mawphu HEP
(Stage-II). The dam site can be accessed by 2km foot path from Thieddieng village. The
nearest village to dam site is Mawphu village located on the left bank of the river, which is
also accessed from Thieddieng village. The power house site can be accessed from
Thieddieng village by about 2km (downstream) through footpath. There is no direct
connectivity between dam site and power house site. Details of approach roads to project
site are summarized in the below table.
Index Map showing location of the dam and power house is presented in Drg. No. 0933-
CDC-01A-01.
Main tributaries of Umiew up to GSWSS are Umjilling, Umtongsieum and Wah Umsaw. After
crossing this scheme project, river extends its journey for about 13 km in a gradient of about
1 in 175. Nallas like Umjaut, Umduna join in its right bank and Umlong joins in its left bank.
The discharges of these nallas increase the potential of the river to develop the proposed
Mawphu HEP, Stage - I (90 MW) Hydro Power Project. Mawphu HEP, Stage - II (75 MW)
Project lies further 13 km downstream of Mawphu HEP, Stage - I Project with additional
contributions from Umjngut & Umkynrem nallas, which join in the right bank. The total length
of the river up to the project site is 54.54 km. The river reach in between two projects
comprises of many loops and bends which gives a panoramic view to the observers. Further
the river flows towards the south below the confluence along the southern slopes of Khasi
Hills and enters Bangladesh beyond Shella in Indo-Bangladesh border and joins the River
Surma. Finally the river joins Brahmaputra and in turn flows to Bay of Bengal via
Sundarbans Delta.
The basin is bounded by Mawsynram in west, Shillong in North and Cherrapunji in east and
in fact world’s highest annual rainfall occurs at Cherrapunji and Mawsynram. The slopes of
the basin are covered with dense rainforests of coniferous and deciduous trees with a
number of small tribal villages in between. The predominant land use pattern in the
catchment area is forest of the type “Tropical Moist Deciduous”. Very small area is under
agricultural use including wet rice cultivation in the intercept valleys.
Mawphu HEP (Stage-II) is being developed by NEEPCO. A PFR was prepared by NEEPCO
in 2010 with FRL at EL 540m and TWL at EL 212m. NEEPCO has awarded the work of
preparation of Detailed Project report of Mawphu HEP (Stage-II) to Energy Infratech Pvt Ltd
in Dec 2012. During EIA/EMP clearance TOR, MoEF instructed NEEPCO to maintain a
minimum of 1 km free stretch between FRL of Mawphu HEP (Stage-II) and tail water level of
upstream project i.e. Mawphu HEP. Accordingly a new dam site was identified with FRL at
EL 470.00 m, which is about 3.17 km downstream of upstream project power house location
and will provide 1.97 km free stretch between FRL at 470.00 m and TWL of upstream project
at 542.68 m. There is no project at the downstream of the Mawphu HEP (Stage-II). There is
no change in the power house location, however the elevation of the river is found higher
than the elevation proposed in the PFR and accordingly the TWL has been fixed up at EL
232.00 m
The project envisages the construction of 51m high and 140m long (at top) concrete gravity
dam with 6 spillway bays of each 9.00m x 12.00m size with breast wall. Full reservoir level
is at EL.470.00m and MDDL is at EL.460.00m.
River diversion is carried out through a 7m dia, horse shoe shaped diversion tunnel of 384m
long proposed on the left bank. Upstream Coffer dam of 18m height is proposed to divert
the water through the diversion tunnel.
Water conductor system is provided on the right bank of a design discharge of 35.72cumecs
with 10% continuous overload and comprises a power intake and 4.8m dia, horse shoe
shaped and about 2.62km long head race tunnel, 10m dia surge shaft, 3.5m dia and 869m
long pressure shaft bifurcating into branch pressure shafts of 2.5m dia and 32m long each.
A surface power house with two vertical axis Francis turbines is provided on the right bank of
the river. The installed capacity of the project is 75MW (2 x 37.5MW) with generation of
291.62MU energy in 90% dependable year.
The total cost of the project (including IDC) is Rs. 879.83crores. The levellised tariff has
been calculated as Rs.6.19. The construction period for the project is 60 months (including
pre-construction period).
After receiving authorization from the Govt. of Meghalaya in May'2005, NEEPCO took up
detailed Survey & Investigation for preparation of DPR of Mawphu HEP (120MW). However,
as observed by GSI, NER, the dam site location as mentioned in the PFR was found to be
not suitable because of non availability of abutment and it was also advised for an alternative
location. At the same time, some of the project parameters as cited in its PFR were found to
have some discrepancy with respect to the relevant topo sheet as well as the actual field
values. Hence, NEEPCO went ahead for selection of alternate site. As a consequence, the
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-1
MAWPHU HEP, STAGE – II
whole lay out underwent alteration. After carrying out overall study of the basin, it was found
that for the other projects also, the parameters were deviating with respect to topo sheet.
Considering all the above factors and comments of CEA regarding the unviability of Umjaut
HEP (69MW), NEEPCO carried out an optimization study (Ref Fig 2-2) of the whole basin in
the following location limits.
NEEPCO prepared the DPR for Mawphu HEP (90MW) and submitted to MOP/CEA in Mar'
2007. But later on, Govt. of Meghalaya allotted this along with Umjaut HEP to a private
developer (M/s ETA Star Infrastructures Ltd.) and NEEPCO was given the downstream
Mawphu HEP (Stage-II).
In June 2012, NEEPCO invited bids from engineering consultants for detailed survey,
investigations and preparation of detailed project report of Mawphu HEP Stage-II and
awarded the work to M/s Energy Infratech Pvt. Ltd. (EIPL) in December 2012.
EIPL has studied the available PFR and found that there is very less free stretch of river
between the proposed FRL at EL 540.00 m and upstream project power house TWL at
542.68m. EIPL pointed out this issue as it is much less than that of 1 km required for
environmental considerations of MoEF. Accordingly dam site was fixed up as discussed in
following paragraphs.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-2
MAWPHU HEP, STAGE – II
The following aspects were considered in general for the selection of the dam site:
Environmental Requirements
Various alternative locations were identified to select the most suitable location for dam. As
the river is flowing through number of sharp bends (Ref Fig 2.3), the dam alternatives were
identified immediately downstream of such bends so that maximum straight reach would
remain downstream for energy dissipation point of view.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-3
MAWPHU HEP, STAGE – II
A. Old PFR Location (about 1km downstream of proposed Power House location
of upstream project - Umduna HEP)
All the above dam alternatives have been shown in Drg. No.0933-CDC-01A-03.
The river is filled up with big boulders (average ~5 m dia). Width of river is about 100
m and more than 50 % bed is exposed with in-situ rock. The river starts flowing in
sharp bend after about 300-400 m downstream of the proposed dam location.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-4
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-5
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-6
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-7
MAWPHU HEP, STAGE – II
Both the banks at this location are subdued and are covered by deep slope wash
material of unknown thickness. However sporadic bed rock exposures constituted
of granite gneiss with mica rich bands exist.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-8
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-9
MAWPHU HEP, STAGE – II
Photo 2-6 Left Bank view immediate D/s of Dam Axis, Alternative-3
PFR (2010)
Parameter of comparison Alt-1 Alt-2 Alt-3
Location
River Bed Geology 8 6 6 8
Left Abutment Geology 6 5 4 5
Right Abutment 6 8 5 8
River Width 7 6 5 8
Straight reach at upstream 8 5 5 5
Straight reach at
7 5 5 6
downstream
HRT Alignment 7 7 6 9
Flow increments 0 0 1 3
Head unutilised 10 8 7 6
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-10
MAWPHU HEP, STAGE – II
Total
59 50 44 58
Environmental aspects 0 2 10 10
Total with Environmental
considerations 59 52 54 68
From the above table, the PFR location was the preferential location without environmental
aspects. Since MoEF instructed NEEPCO to maintain a free reach of a minimum of 1 km
between two consecutive projects i.e. TWL of Mawphu (Umduna) and FRL of Mawphu HEP
(Stage-II), the PFR location does not satisfy the condition. Out of alternatives 1, 2 and 3, the
alternative-3 was chosen on the basis of above summarized points.
A) During the meeting of NEEPCO with MoEF for clearance of TOR for EIA/EMP studies,
it was the apprehension that MoEF may agree to leave a free stretch of about 250
between FRL of Mawphu (Stage-II) and TWL of Mawphu HEP. In view of this
apprehension, further reconnaissance survey was made for changing the dam site to
meet out the MoEF requirement as well as utilization of maximum potential of Umiew
river. And a new dam site, which is about 250-300 m downstream of PFR (2010)
location was finalized for further investigations. More details of the alternatives are note
described in this report as it was cancelled after receipt of written instructions of MoEF
to maintain a minimum of 1 km free stretch between FRL of Mawphu (Stage-II) and
TWL of Mawphu HEP. Therefore further investigations were made on the earlier
chosen location as Alternative-3.
In view of the above and to find a suitable location, 70m downstream of Alternate-3, a
drill hole DH-09 was drilled on the left bank. The drill hole revealed the availability of
bed rock at a shallow depth and accordingly this alignment was favored.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-11
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-12
MAWPHU HEP, STAGE – II
Fig 2-5 Section showing thick overburden along Dam Axis Alternative-3
Initially during the preparation of PFR (Jan 2014), the design flood was estimated as 6000
cumecs and accordingly spillway bays were arranged in the dam layout plan. During the
clearance of hydrological studies from CWC, CWC recommended their suggestions and
design flood (PMF) was increased to 8900 cumecs.
In order to pass the design flood through spillway with 10% gate inoperative, two more bays
were required in the earlier spillway arrangement. Therefore, to accommodate additional
number of spillway bays, the dam axis proposed in the new PFR was rotated slightly by
about 30 in the clockwise direction through centre of river to avoid hitting of water jet on the
left abutment.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-13
MAWPHU HEP, STAGE – II
As per topographical features, river takes sharp bends right from upstream of the dam to
about one kilometer downstream of the proposed Power House location. Therefore, limited
locations are available on the right bank. A flat terrace of about 70mx400m is available
between EL. 290m and EL. 300m, which is about 60m above the river bed level in that area.
This terrace is considered as an alternative for surface Power House.
Downstream of the proposed location, river takes 90 degree anticlockwise bend and joins
two nallahs from the right bank which was not found suitable for both pressure shaft and
Power House.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-14
MAWPHU HEP, STAGE – II
Fig 2-7 Power House location on the Topo sheet No. 78 0/11 of Survey of India
In view of the availability of the flat terrace, topographical and geological features, the
alternative of underground Power House may not be a techno-economic solution. Therefore,
the flat terrace is proposed for the surface power house despite the excavation of the Power
House cut slope in the range of about 80m. Since the flat bench width varies from 70m to
100m which will be sufficient for excavation in flatter slope for slope stability consideration.
And therefore, this location has been finalized.
Further, the area has been explored by drilling, geophysical survey and geological mapping.
It was found that this location is suitable for surface Power House.
Also, two alternative routes have been studied to reach Service Bay level.
In alternative-1, access road is planned from the right side of the Power House (i.e.
downstream side of the Power House with respect to the River flow). In this alternative,
access road is passing near nallah and reaches directly at Service Bay level. Road limbs
(from the access road to Service Bay) are proposed to be planned to carry out the Power
House Cut slopes excavation and to reach various levels of the berms. The cut slope of 1.5
(H) : 1(V) in overburden has been proposed for this alternative. Width of the berms has been
kept as 5m including drains. With this arrangement, the cutting for the Power House cut
slope starts from the level of 305m.
In Alternative-2, access road is planned from the left side of the Power House Complex (i.e.
upstream side of the Power House with respect to the river flow). This access road will meet
at EL. 265m near Power House and will reach the Service bay level through inclined berms.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-15
MAWPHU HEP, STAGE – II
A relatively steep slope of 1.25 (H) :1(V) has been planned for Power House cut slope to
minimize the extent of the excavation at a level of about 305m. Width of the berms has been
kept as 3m including drains except those berms which are serving the purpose road for
accessing Service Bay. The width of such berms has been kept as 6.5m. The width of the
berms below Service Bay level is kept as 5m to facilitate the construction activities for Power
House and its pit. The requirement of the slope stabilization in this alternative will be more as
compare to the Alternative -1.
The minimum dam parameters have been fixed by considering the following aspects:
In accordance with the above aspects, minimum dam parameters for Mawphu-II HEP have
been arrived as follows:
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-17
MAWPHU HEP, STAGE – II
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-18
MAWPHU HEP, STAGE – II
2.3.4.1. Cost:
For each incremental increase of FRL in steps of 5m, the dam height shall be increased.
Incremental cost of alternatives has been worked out by considering only the cost of
excavation and concreting. Rates of excavation and concreting have been taken from
nearby project.
IDC and escalation have been considered at 20% of base cost to work out the total
incremental cost.
Additional cost of E & M and minor cost of civil works i.e. land submergence have not been
accounted in the analysis.
Incremental cost calculated for Excavation and Concreting is given in Table 2-3 and Table
2-4:
Unit Cost of Mass Concrete (Rs/cum) 4300 4300 4300 4300 4300
Qty of R.C.C, Apron etc (cum) 55,000 59,000 61,500 64,000 67,000
Sub-Total Cost of R.C.C (Rs in crores) 30.80 33.04 34.44 35.84 37.52
Sub-Total Cost of HPC (Rs in crores) 7.84 7.84 7.84 7.84 7.84
Base cost for each alternative has been calculated and presented in Table 2-5.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-21
MAWPHU HEP, STAGE – II
Total cost of
construction (Rs. In 78.60 95.16 110.88 127.11 147.13
crores)
Cumulative Cost
- 16.56 32.28 48.51 68.53
(Rs in crores)
Annual cost for each alternative has been calculated and given in Table 2-6.
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-22
MAWPHU HEP, STAGE – II
Annual Cost:
2.3.4.2.Benefits:
Incremental energy benefits for each alternative of the dam have been calculated and
presented below.
Design Discharge = 37.32 cumecs (As per preliminary Power Potential Studies)
Plant Load Factor = 43.55% (As per preliminary Power Potential Studies)
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-23
MAWPHU HEP, STAGE – II
Similarly, the annual benefit for other alternatives was calculated and given in Table
2-7.
Annual Benefit
2 - 1.94 3.87 5.81 7.75
(Rs in crores)
Benefit-Cost
- 0.52 0.54 0.54 0.51
Ratio
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-24
MAWPHU HEP, STAGE – II
The selected dam parameters for the project are given below:
DPR-I: Chapter-2: Review of Earlier Studies and Fixation of Project Layout 2-25
MAWPHU HEP, STAGE – II
3. TOPOGRAPHICAL SURVEY
3.1. General
Topographical survey works carried out in the project area for the preparation of detailed
project report have been illustrated in the chapter. These include transfer of Bench Mark
from Survey of India Bench Mark to project sites and topographical survey.
At the beginning of the Study, EIPL acquired existing Survey of India topo-sheet (78-O/11)in
a scale 1:50,000 with 20-meter contour intervals. For the purpose of catchment area
calculations, other upstream topo-sheets were procured. A pre-feasibility report was
prepared by NEEPCO, which was based on 1 in 50,000 scale toposheet and no specific
terrestrial survey was carried out earlier.
The Consultant conducted detailed topographic field surveys at the Mawphu- Stage-II
project by total station. Initially the survey was conducted with the arbitrary bench mark and
then joined the survey with the Survey of India (SOI) Bench Mark. Two bench mark
locations were found in the area of power house and surge shaft of upstream project, but
could not be used due to unavailability of their co-ordinates. There were no nearby SOI
bench marks found in the project area. Two SOI bench marks are available, one at
Mawphlang and other one at Cherrapunji. Mawphlang bench mark is about 40km and
Cherrapunji is about 23.33 km from project area. Therefore the benchmark was transferred
from Cherrapunji by high accuracy auto level and was checked by closing the level traverse.
As the SOI bench mark has elevation only, Northing and Easting coordinates were taken
arbitrarily.
Control points in the project area were established by DGPS and then detailed survey was
carried out with using the control points.
Five nos permanent bench marks and 30 cement concrete pillar with coordinates marks
were established for future reference. Details of coordinates are presented in the following
table:
THIEDDIENG VILLAGE
32 361647.538 2798735.761 795.217 G-1
FOOTBALL GROUND AREA
THIEDDIENG VILLAGE (BENCH
33 361674.116 2798683.335 796.826 G-2 MARK NEAR BURIAL GROUND
AREA)
Project layout showing the locations of 5 Bench Marks is given in Fig. 3-1.
Fig 3-1 Project Layout showing 5 Bench Marks established in the Project Area
Having in mind the steep topography of the area, for the purpose of the hydro power plant
DPR stage design, the Consultant developed topographical maps with respect to contour
intervals as follows:
• Map of the reservoir area with tentative scale of 1:2,500 with contour interval of 2 m,
• Map of the project site area with tentative scale of 1:500 with contour interval of 2 m.
• Map of colony, access road etc with tentative scale of 1:1000 with contour interval of
2 m.
It is to be noted that herein produced accuracies are better than in the project’s terms of
references.
These data were primarily used for the hydraulic analysis of the tail water levels. The
location of the surveyed cross sections is given in Fig 3-2.
Fig 3-2 Locations of the River Cross Sections surveyed u/s and d/s of Dam Axis
4. HYDROLOGY
4.1. General
Mawphu Hydro Electric Power Project (Stage-II) is planned in East Khasi Hills District in the
state of Meghalaya on the River Umiew, a tributary of the River Surma, which itself is one of
the major left bank tributaries of Brahmaputra. Mawphu Hydro Electric Project (Stage-II)
envisages the construction of a concrete gravity dam of about 51 m height (from deepest
bed level) across river Umiew to utilize a net head of about 232 m for hydro power
generation. The proposed dam is located near Mawphu village, about 8 km away from
Mawsynram and 2 km away from Thieddieng village. The project is located at latitude 25⁰
18’ 32’’ N and longitude 91⁰ 38’ 19” E. The length of the head race tunnel on the right bank
of the river is about 2.62 km. The catchment area up to the dam site is 320 sq. km and the
entire catchment is rain – fed. It is proposed to install 2 units of 37.5 MW each (75 MW).
The following hydrological studies have been carried out for the Project with a view to:
Assess the availability of water for fixing the installed capacity and estimation of
power generation, by establishing a series of 10 – daily discharges at the project
site.
Design flood studies based on probable maximum precipitation for the design of
spillways & appurtenant structures.
Diversion flood studies for the construction of diversion arrangement structures
during construction.
Sediment studies and measures for sediment management have been included
in the report.
1 in 175. Nallas like Umjaut, Umduna join in its right bank and Umlong joins in its left bank.
The discharges of these nallas increase the potential of the river to develop the proposed
Mawphu Stage I (90 MW) Hydro Power Project. Mawphu Stage II (75 MW) Project lies
further 13 km downstream of Mawphu Stage I Project with additional contributions from
Umjngut & Umkynrem nallas, which join in the right bank. The total length of the river up to
the project site is 54.54 km. The catchment area plan of river Umiew up to dam site, showing
the location of gauge, discharge and rain gauge station is given in Figure 4-1. Further the
river flows towards the south below the confluence along the southern slopes of Khasi Hills
and enters Bangladesh beyond Shella in Indo-Bangladesh border and joins the River Surma.
Finally the River joins Brahmaputra and in turn flows to Bay of Bengal via Sundarbans Delta.
The basin is bounded by Mawsynram in west, Shillong in North and Cherrapunji in east and
in fact world’s highest annual rainfall occurs at Cherrapunji and Mawsynram. The slopes of
the basin are covered with dense rainforests of coniferous and deciduous trees with a
number of small tribal villages in between. The predominant land use pattern in the
catchment area is forest of the type “Tropical Moist Deciduous”. Very small area is under
agricultural use including wet rice cultivation in the intercept valleys.
2034
1834
1634
1434
Elevation (m)
1234
1034
834
634
434
0 10 20 30 40 50 60 70 80 90 100
Area above Elevation (%)
S. Approx. Coordinates
Observed Altitude Data
N Station Longitud Remarks
by Latitude (m) Availability
o e
Table 4-4: Monthly & Annual Rainfall at Shillong after filling Data Gaps (mm)
Table 4-5: Monthly & Annual Rainfall at Mawphlang after filling Data Gaps (mm)
The single mass curves of rainfall data at various stations indicated that the data
for the stations are consistent.
But the double mass curve between Kynshi and Mairang indicated that the data
2004 is not consistent with the data prior to 2004.
Since the monthly rainfall data at Mawphlang and Shillong follow the same trend,
the data at these stations has been considered for the studies.
The discharge data at Ranikore is not found to be consistent, perhaps due to the
fact that the catchment area at this site considerably large as compared to the
catchment area at Mawphlang.
The discharges of river Umiew at Mawphlang observed by PHED gave
considerably higher runoff as compared to the rainfall. Hence this data is not
considered reliable.
The discharges of river Umiew at Mawphlang observed by ASEB, when
compared with rainfall were found to be consistent. Hence this data was
considered for the study.
350
f(x) = 0.805796146984719 x + 4.07642612075787
300 R² = 0.778898963131704
250
Mawphlang Rainfall (mm)
200
150
100
50
0
150 200 250 300 350 400 450
Shillong Rainfall (mm)
1000
600
400
200
0
100 200 300 400 500 600 700
Shillong Rainfall (mm)
2500
1500
1000
500
0
200 300 400 500 600 700 800 900 1000 1100
Shillong Rainfall (mm)
800
400
200
0
150 200 250 300 350 400 450
Shillong Rainfall (mm)
1000
f(x) = 2.61498749549668 x − 230.278096757138
900 R² = 0.750718689708001
800
Mawphlang Rainfall (mm)
700
600
500
400
300
200
100
0
150 200 250 300 350 400 450 500
Shillong Rainfall (mm)
500
400
Mawphlang Rainfall (mm)
200
100
0
0 50 100 150 200 250
Shillong Rainfall (mm)
The monthly rainfall during the non-monsoon months have been determined by multiplying
the above ratio with the monsoon rainfall for the concerned year. Monthly and annual rainfall
at Mawphlang thus obtained is given in Table 4-7.
Table 4-7: Monthly & Annual Rainfall at Mawphlang after Extension (mm)
Using the available rainfall & runoff data for the concurrent period, monthly rainfall - runoff
correlation have been developed for the monsoon months of May to October. The monthly
rainfall -runoff correlations at Mawphlang, thus obtained are given in Table 4-9.
Month Equation R2
(Table 4-7) monthly flow series for the monsoon period from 1988 to 2005 has
been generated.
To estimate the runoff for non-monsoon months, average ratios of monthly non
monsoon runoff to average monsoon runoff were developed using the observed
runoff for the period 1979 – 80 to 1987 – 88. The following ratios were obtained:
0.09
0.196 0.131 0.100 0.071 0.138
8
The runoff for the non-monsoon months of November to April have been
estimated by multiplying the monthly ratios as obtained above, with the monsoon
runoff for the concerned year. Monthly flow series at Mawphlang, for the period
May 1988 to Dec. 2005 has thus been generated. The combined flow series at
Mawphlang (observed & generated) for the period 1979-80 to 2004-05 in mm is
given in Table 4-10
To generate 10 – daily flow series form the monthly series developed above,
average 10 – daily flows have been worked out from the observed 10 – daily
discharge data for the period May 1979 to April 1988. The ratio of each 10 – daily
runoff with respect to corresponding total runoff of the month has been estimated
and computations are given in Table 4-11
Monthly flows generated for the period 1988 - 2005 in Table 4-10, have been
multiplied with the corresponding monthly 10 – daily ratio to obtain the 10 – daily
flow series. This series has been converted to cumecs. The combined 10 – daily
discharges at Mawphlang; observed for the period 1979-80 to 1987-88 &
generated for the period 1988-89 to 2004-05 is given in Table 4-12
Table 4-10 Monthly & Annual Runoff at Mawphlang after Extension (mm)
As suggested by CWC, considering a runoff factor of 0.8, mean annual runoff at Mawphu
(Stage-II) dam site works out to 3532 mm (4415 X 0.8).
Table 4-14: 10-Daily Discharges at Mawphu (Stage-II) Dam Site without Considering GSWSS Withdrawals (cumecs)
Table 4-15: 10-Daily Discharges at Mawphu (Stage-II) Dam Site after Considering GSWSS Withdrawals (cumecs)
D = Percentage dependability
The computations for estimating the percentage dependability are given in Table 4-16.
Annual
% Correspondin Corresponding
S. No Year Yield
Dependability g Yield (MCM) Year
(MCM)
From Table-4-16, it is seen that 90 % and 50 % dependable annual flows work out as 853
MCM & 982 MCM, which correspond to the years 1996-97 & 2002-03 respectively.
Lc = 21.45 km
S = 36.73 m / km
tr = 1 hr
Synthetic U. G. parameters for the project have been computed using the basin
characteristics & relations given in Sub - Zone 2 (b) Report for the South Bank Tributaries of
Brahmaputra. The computations are given in Table 4-18.
It is seen that the time to peak (tp) works out as 10.1 hours, which appears to be on the
higher side for a catchment area of 320.2 sq km and having steep river bed slope. In view of
this, as suggested by CWC, tp has been estimated using Kirpich formula, California formula
etc.
As suggested by CWC, time to peak has been estimated by the following methods and the
computations are given in Table 4-19.
Kirpich
I Formula
Translation time in
L^0.77 = 4438.85 m Tc = min
Stream length in
S^-0.385 = 3.998 L = Meters
Average Bed
Tc = 346.06 Min S = Slope
Tc = 5.77 hrs
California
II Formula
hr
Difference in
Tc = 5.77 hrs H = elevation in m
Kerby's
III Equation
Tc = (6.56 LN / (3 * S)^0.5)^0.467
N = 0.65
Tc = 445.0 Min
Roughness
Constant = 0.65
Tc = 7.42 hrs N = assumed
L = Length in m
Slope of the
S = catchment
2.272 * (L X Lc /S )
qP = = 0.55 cumec
-0.409
The time of concentration estimated by various methods is summarized below in Table 4-20
Time of
Concentration 5.77 5.77 7.42 4.29 10.6
(Hrs)
4.29
Say 17
Qp = qp X A = 177 cumec
Knowing the peak & time to peak of the unit hydrograph (UH), width of UH at 50 % & 75 %
peak and base width, unit hydrograph was plotted and its volume adjusted to give 1 cm
runoff. The ordinates of unit Hydrograph thus obtained are given in Table 4-22 and the unit
hydrograph is plotted in Fig 4-9.
UH UH
Time Time
Ordinates Ordinates
(hours) (cumec) (hours) (cumec)
0 0 9 47
1 10 10 37
2 33 11 28
3 82 12 20
4 150 13 14
5 177 14 10
6 129 15 6
7 83 16 3
8 60 17 0
150
Discharge (cumecs)
100
50
11
13
16
0
10
12
14
15
17
Time (Hrs)
Since the base width of the unit hydrograph is 17 hours (< 24 hours), 1-day PMP value has
been considered for estimation of design flood.
A. 24 Hour PMP
To obtain 24 hour PMP value, clock hour correction of 15% limited to 5 cm has been applied
to the 1-Day PMP value. Thus 24-Hour PMP value works out to 135.7 cm.
B. Area Reduction Factor
1-Day SPS and PMP values given by IMD are based on point rainfall of the storm observed
at Cherrapunji on 12.07.1910. Since, catchment area up to Mawphu HEP, Stage II dam site
is 320 sq km (123.63 sq miles), area reduction factor has been applied for estimating 1-day
PMP for the catchment. Area reduction factor has been estimated using the following
equation given in the report “Estimation of Design Flood Peak – A method based on Unit
Hydrograph Principle” prepared by CWC.
P = exp (-A1/3 / 8 T ½)
Where,
P = Area Reduction Factor
A = Catchment Area in sq miles.
T = Duration of Rainfall
P = exp (- 123.63 ^ (1/3) / 8 X 24 ^ (0.5)) = 0.88
The value of P read from Table 6 of “Flood Estimation Report for North Brahmaputra Basin
Subzone 2(a)” also works out as 0.88. Hence area reduction factor of 0.88 has been
considered.
Thus 24 hour catchment rainfall after applying area reduction factor works out as 135.7 X
0.88 = 119.42 cm
C. Temporal Distribution
Temporal distribution of 24-Hour & 48-Hour design storms given by IMD is given in
Table 4-24.
Table 4-24: Temporal Distribution for 24-Hour & 48-Hour Storms Given by IMD
Time (Hrs) 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48
% of 24
36 55 66 74 82 89 95 100
Hrs Storm
% of 48 24 38 50 59 66 71 75 79 83 86 89 92 95 97 99 100
Hrs Storm
Since the base width of the UG is less than 24 hour, the temporal distribution of 1-day
storm given by IMD has been considered. From the temporal distribution of 24 hour storm, it
is seen that 12-hour storm value is 74 % of 24-hour value. The temporal distribution of 12 –
hour storm has been obtained by dividing the temporal distribution of 24 hour by 0.74. The
hourly values of temporal distribution of 24 and 12 hour storm thus obtained are given in
Table 4-25 and plotted in Fig 4-10.
120
100
80
Rainfall (mm)
Temporal Distribution
60 24 Hrs
Temporal Distribution
40 12 Hrs
20
0
0 5 10 15 20 25
Time (Hours)
Since the PMP is assumed to occur in two bells of 12 – hour each, the PMP occurring during
the first 12 hours and later 12 hours of each day storm are 74 % and 26 % respectively.
Hence the PMP values during the 1st & 2nd bells work out as 88.37 cm & 31.05 cm
respectively.
1 st bell (cm)
Percentage
Cumulative Incremental Effective Reverse
Time of 12 hr Critical
Rainfall Rainfall Rainfall Critical
Rainfall
%age of
Cumulative Incremental Effective Reverse
Time 12-Hour Critical
Rainfall Rainfall Rainfall Critical
Rainfall
0 0 0.00 0.00
10000
9000
8000
7000
6000
5000
Discharge (Cumec)
4000
3000
2000
1000
0
0 5 10 15 20 25 30 35 40 45
Time (Hrs)
Methodology Adopted
From Table 4-29, it is seen that considerably high flows have been observed in October. In
view of this annual peaks from 1st November to 30th April have been considered for
estimating the diversion flood. After considering the observed flood peaks for the non-
monsoon period (1st November to 30th April), mean and standard deviation have been
worked out as given in Table 4-30.
Table 4-30: Mean & Standard Deviation of the Flood Peaks (November to April)
Peak Discharge
S. No Period
(cumecs)
1 1980-81 53.9
2 1981-82 42.3
3 1982-83 19.3
4 1983-84 7.1
5 1984-85 7.7
6 1985-86 28.8
7 1986-87 42.2
8 1987-88 111.0
9 1988-89 174.4
10 1989-90 17.7
11 1990-91 12.7
12 1991-92 15.2
13 1992-93 61.5
14 1993-94 28.0
15 1994-95 16.0
16 1995-96 45.7
17 1996-97 57.7
Mean 43.6
Standard
Deviatio 42.69
n
The peak flood values obtained for the period 1980-81 to 1996-97 have been subjected to
flood frequency analysis using Gumbel’s distribution. The values of floods for various return
DPR-I: Chapter-4: Hydrology
4-43
MAWPHU HEP, STAGE – II
periods from 5 years to 100 years have been worked out. The flood values have been
transformed to Mawphu (Stage-II) HEP dam site using Dicken’s formula and the values are
given below in Table 4-31.
Table 4-31: Return Period Floods
Return
5Yr 10Yr 15Yr 20Yr 25Yr 50Yr 100Yr
Period
Yt 1.500 2.250 2.674 2.970 3.199 3.902 4.600
K 0.943 1.664 2.071 2.355 2.575 3.250 3.921
Q(Mawphlang
84 115 132 144 154 182 211
)
Q (Dam site) 181 247 284 311 331 393 455
It is seen that 25 – year return period flood at Mawphlang works out to 154 cumecs, which is
less than the observed non monsoon flood of 174 cumecs. As per IS 14815:2000, the higher
of the 25 years return period flow or the maximum observed non-monsoon flow has to be
adopted. In view of this, the diversion flood at Mawphlang comes to 174 cumecs.
Transforming this flood using Dicken’s equation, the diversion flood at Mawphu (Stage-II)
HEP dam site works out to 376 cumecs. Hence diversion flood of 375 cumecs has been
adopted.
Capacity (MCM)
180.000 160.000 140.000 120.000 100.000 80.000 60.000 40.000 20.000 0.000
480
470
Elevation (m)
460
450
440
420
410
0 20 40 60 80 100 120 140 160 180
Area (Ha m)
Operating the reservoir at MDDL during the monsoon months to route the
incoming sediment downstream of the project site.
Provision of low level sluice spillway crest for flushing the silt downstream during
flood season.
Reservoir drawdown flushing two times every year, to ensure that live storage is
always available.
Adequate vertical separation between the water conductor intake sill level and
the sluice spillway crest level for effective silt flushing.
4.
5.
5.1. Introduction
The Mawphu HE Project Stage-II is located on river Umiew in the Himalayas of East Khasi
Hill district of Meghalaya. The project area falls within Archean gneiss of Meghalaya plateau,
which is characterized by wide structural and geological diversity.
The Mawphu HE Project Stage-II is a part of a cascade development scheme on Umiew
River which is the main drainage in East Khasi Hill district. It is formed at elevation of about
1850 m. After running a considerable stretch in Meghalaya, India, it enters into Bangladesh
to reach Brahmaputra via Surma, a major tributary of River Brahmaputra. River Umiew is
joined by number of right bank tributary namely Umkynrem, Umtong and Waisu.
Approximately 232m head is available between the dam near Mawphu village and Tail Race
Tunnel outlet near Thieddieng village. The river course is circuitous, flowing with moderately
steep gradient which has been utilized for hydropower scheme. All along its course, Umiew
River flows through a narrow valley, thus providing number of prospective sites for dam
construction. River Umiew and its tributaries are mainly rain fed. Medium to heavy rainfall in
catchment area ensures significant water availability in the river.
the E-W Dauki fault system. Cretaceous to Eocene stable shelf sediments cover the
southern and eastern periphery of the plateau and southern fringe of the mikir hills which
towards east are juxtaposed with sediments of the trench facies of the Indo Myanmar mobile
belt. Almost uninterrupted intra-continental sedimentation continued along the southern
margin of the plateau till quaternary period. The occurrence of Upper cretaceous
carbonatite–ultramafic complex along a NE fracture zone in the east central part of the
plateau and in Mikir hills is noteworthy. N-S to NW-SE trending active faults /fractures
predominate in this domain.
Kopili Formation
Shale, sandstone, marl and coal
(50m)
Paleocene- Shella Formation Alternation of sandstone, limestone
Jaintia Group (600m)
Eocene
Langer Formation Calcareous shale, sandstone,
(100m.) limestone
Upper Conglomerate
Khasi Group Conglomerate
Cretaceous (25m)
Jadukata
Formation (140m) Conglomerate/sandstone
Granite
Plutons :Kyrdem
Granite pluton (479 ±
Neo
26 Ma) Nongpoh Porphyritic coarse granite,
Proterozoic-
Granite (550 ± 15 pegmatite, aplite/quartz vein
Early
Ma)Mylliem traversed by epidiorite, dolerite and
Paleozoic
Granite(607 ± 13 basalt dykes.
Ma)South Khasi
Granite (690 ± 26
Ma)
Khasi Basic-
Epidiorite, dolerite amphibolites and
Proterozoic Ultrabasic .............................
pyroxenite dykes and sills
intrusives
1. Old PFR Location (about 1km downstream of proposed Power House location of
upstream project - Umduna HEP)
During drilling at Alt-3 location, drill hole DH-07 encountered deep overburden on the left
bank of dam axis. So, it was proposed that the dam axis needs to be shifted slightly
downstream by about 70m to avoid deep overburden on the left abutment. Accordingly, Alt-
3A has been chosen as a possible location for further investigation works.
DPR-I: Chapter-5: Site Investigation and Geology 5-4
MAWPHU HEP, STAGE – II
Component Scale
Reservoir 1:1000
HRT 1:2500
5.3.3. Drilling
In addition to 3 bore holes with aggregating length of 90m for Groutability test,18 bore holes
having cumulative lengths of 875m have been drilled so far. Out of these 18 drill holes, 11
holes with cumulative length of 445m have been drilled to explore Dam and its appurtenant
structures and 2 holes of 50m & 60 m length were drilled to explore surface Power house
whereas 4 bore holes were drilled to explore pressure shaft and Surge shaft was explored
by one hole of 110m .One 40m deep hole planned to explore HRT and is under progress.
Summarized details of the bore holes drilled at the Dam site, Power House, Pressure shaft,
Surge Shaft and HRT given below and respective log of each hole is appended as
Appendix- 1 to 18.
Table 5.2 Details of Bore hole Drilled
5.3.5. SPT
In total 106 numbers of Standard penetration test were conducted for assessing bearing
capacity of overburden, SPT were conducted in accordance with IS 2131 and results were
incorporated in the respective drill logs. The data pertaining to the SPT of each drill hole are
given in Appendix 1-18.
rock types occurring in the project area, laboratory tests on rock cores collected from drill
holes were carried out at the ATES laboratory. The summarized values of engineering
properties are given in below and reports are enclosed as Annexure 2A.
Table 5.3 Summarized results of Rock mechanics test
Tensile strength
UCS (Saturated)
Slake durability
Poisson’s ratio
compressive
Unconfined
Shear
Modulus of
UCS (dry)
Elasticity
Depth
Parameter
index
Sample No.
Rock Type
C Φ
(MP
(m) (MPa) Degree (GPa) %
a)
Granitic
DH-
14.58 gneiss/Gnei 76.17 40.17 0.26
01/59
ss
Granitic
DH-
8.5 gneiss/Gnei 133.3 95.3 114.1 52.05 0.2
02/25
ss
Granitic
DH-
39.6 gneiss/Gnei 6.18 50.66
02/198
ss
Granitic
DH-
10 gneiss/Gnei 68.97 59.5
01/34
ss
Granitic
DH-
36.54 gneiss/Gnei 56.62 37
01/167
ss
Granitic
DH-
15.1 gneiss/Gnei 3.63 45.09
01/61
ss
Granitic
DH-
8.6 gneiss/Gnei 36.64
03/20
ss
Granitic
DH-
7.37 gneiss/Gnei 108.6 80.8
03/13
ss
Granitic
DH-
10.4 gneiss/Gnei 83.65
03/29
ss
Granitic
DH-
8 gneiss/Gnei 6.85 52.82
03/18
ss
Granitic
DH-
8 gneiss/Gnei 99.24
03/17
ss
Granitic
DH-
10.6 gneiss/Gnei 26.84
06/45
ss
Granitic
DH-
19.7 gneiss/Gnei 3.78 45.74
06/95
ss
Granitic
DH-
8 gneiss/Gnei 99.39
06/24
ss
Granitic
DH-
10.77 gneiss/Gnei 44.37 29.2
06/46
ss
Granitic
DH-
26.5 gneiss/Gnei 41.37
10/144
ss
HRT
rock 99.54
sample
Summarized results of Rock mechanics test (Surge shaft, Pressure shaft &Power house)
Tensile strength
Tensile strength
UCS (Saturated)
Slake durability
Poisson’s ratio
compressive
Unconfined
Modulus of
Triaxial Test
UCS (dry)
Depth
Shear
Sample No.
Rock Type
Parameter
Φ
(m) (MPa) C (GPa) %
(MPa) Degree
Granitic
DH- 48.1 0.2
58.25 gneiss/Gneis
102/267 4 2
s
Granitic
DH-
53.7 gneiss/Gneis 137 106
102/247
s
Granitic
DH-
34.5 gneiss/Gneis 79.57
102/116
s
Granitic
DH-
36.55 gneiss/Gneis 76.57
102/125
s
Granitic
DH- 103.0
55.22 gneiss/Gneis
102/249 5
s
DH-101/ Granitic
47,46.62
277,279,2 gneiss/Gneis 4.87 48.98
,46.30
81 s
Granitic
DH-
37.3 gneiss/Gneis 4.79 45.1
102/102
s
Granitic
DH-102/ 36.55,
gneiss/Gneis 2.12 37.18
125,130 37.50
s
Granitic
DH-
56.7 gneiss/Gneis 3.75 36.75
102/257
s
Granitic
DH- 34.64,
gneiss/Gneis 4.21 39.99
103/47,42 36.25
s
Granitic
DH-
34.55 gneiss/Gneis 7.1 6.1
101/209
s
Granitic
DH-
28.15 gneiss/Gneis 6.2 5.5
102/67
s
Granitic
DH-
35 gneiss/Gneis 6.3 5.5
103/39
s
Granitic
DH-
55.5 gneiss/Gneis 99.5
102/249
s
DH- Granitic
90.3,
105/236,2 gneiss/Gneis 11.2 8.5
94.5
37 s
Granitic
DH-
44.83 gneiss/Gneis 31.5
105/52
s
Granitic
DH- 99.4
44.5 gneiss/Gneis
105/50 4
s
Granitic
DH- 44. 42.
45 gneiss/Gneis
105/53 59 8
s
Granitic
DH-
63.66 gneiss/Gneis 7.13 51.9
105/133
s
Granitic
DH- 44. 23.
47.2 gneiss/Gneis
104/109 5 4
s
Granitic
DH- 28.8
46.3 gneiss/Gneis
104/104 4
s
Granitic
DH-
46.96 gneiss/Gneis 85.73
104/107
s
Granitic
DH-
44.5 gneiss/Gneis 3.43 45.21
104/92
s
Granitic
DH- 99.0
42.5 gneiss/Gneis
104/76 8
s
Granitic
DH-
46.13 gneiss/Gneis 7.8 52.62
107/92
s
Granitic
DH- 99.5
49.86 gneiss/Gneis
107/103 9
s
Granitic
DH- 42.4
45 gneiss/Gneis
107/85 2
s
Granitic
DH- 156
45.68 gneiss/Gneis 139
107/90 .6
s
Granitic
DH-
46.13 gneiss/Gneis 112.6
107/92
s
5.3.9. Petrography
Specimens of rocks obtained from various rock exposures and rock cores from various drill
holes of Dam site, Surge Shaft and surface Power House were utilized by the GSI Petrology
Laboratory located at Faridabad for Petrographical studies. Furthermore, 2 silt samples were
also tested and 2 tests are under progress in same laboratory for estimating of mineral
distribution in silt samples. The report on the so far completed studies is enclosed as
Annexure –3
earthquake data obtained from different sources reveals that 137 major earthquakes
shocked the area from 1845 to 1980. For a large number of events depths of hypocenters
are not known which has limited the scope of the present study to some extent. For better
understanding of the Seismicity of project area, Dept of Earthquake Engineering IIT Roorkee
was entrusted the job to carry out the study for evaluating seismic design parameters for the
project components. Based on the above, the maximum value estimated for horizontal peak
ground acceleration(PGA) is 0.42gfor MCE and 0.24 for DBE condition respectively for both
Horizontal and Vertical ground motion.(For details refer, Site specific design earthquake
parameters for Mawphu HE Project (Stage-II) report, Annexure 5).
5.4.1. Dam
The 51m high concrete dam, from deepest foundation level, shall have a length of 139.85m
at the top. The top of the dam has been kept at El. 472m. The FRL is expected to be at El.
470m with a submergence area at FRL of 13 hectares. The river channel flows at the center
while right bank and left flank hugging water way are occupied by River borne deposits. The
river bed is occupied by large pell mell boulders of size varying from 0.5 to 6-7m , some of
these large boulders could be colluvial blocks. The river bed was explored by six drill holes
i.e. DH-01, DH-02, DH-03, DH-05, DH-06 and DH-10. (Ref.Appendix 1 to Appendix
3,Apendix 5,6 and Appendix 10). (Ref DWG No.0933-GDC-03A-001).Based on the above
drill hole data it is inferred that in the river bed area, overburden which is mainly RBM,
thickness of which varies from 4m to 7.4m. Permeability values range from 1-6 Lugeon and
suggests reasonably tight foundation condition in the riverbed. In any of the drill hole no
major fracture zone or crushed/shear zone was encountered, making it suitable for laying
concrete dam.
On the right bank, the abutment between river bed level (El. 434 m) and El. 530 m is
approximately 55°. Along the right bank, rock outcrops of fine to medium grained granite
gneiss are occurring near the river water line were delineated in the upstream and
downstream of the dam axis. (Ref DWG No.0933-GDC-03A-001). At right bank few thick
veins of pegmatite were encountered during the surface mapping. In the course of the
abutment excavation, no major problem is foreseen as right bank exposes strong granite
gneiss upto EL.510m and beyond the top of dam(EL.472m).No adverse zone was observed
during surface mapping of right bank.
The left bank abutment slopes at 52° to 55° between river level (El. 436 m) and El. 480 m,
and subsequently flattens to 40° till El. 520 m. Upto elevation of 460m from river bed level
(El. 434m), rock is exposed on the left bank then above that, it is covered by overburden
material constituted of slope wash comprising top soil and rounded to sub-rounded pebble to
boulder grade detritus of granite gneiss, pink granite, grey granite and quartzite in a sandy to
silty matrix. Granitic gneiss belonging to Archean gneissic complex are exposed here.
Bedrock exposures are visible till El 460m after which the slope is covered by hill wash
deposits comprising rounded to sub-rounded cobble, pebble and boulder of granite gneiss,
pink granite, grey granite in a sandy to silty matrix. The thickness of the overburden has
been seen to ranges between 10.5m to 30.5m as has been observed from drill hole DH-07,
DH-08 and DH-09. In DH-07, overburden thickness of 30.5m comprising unsorted
DPR-I: Chapter-5: Site Investigation and Geology 5-12
MAWPHU HEP, STAGE – II
constituted of large boulder pebbles, cobbles, gravels of granite/granitic gneiss mixed with
sand shall be of the order of 5 to 7m and shall be followed by strong to very strong bed rock
quartz biotite gneiss. Overburden permeability is anticipated to range between 3.8 to 4.8
X10-3 cm/sec and therefore suitable pumping arrangement shall be required during
construction.
The fracture zones and shears with clay infillings below the nallah bed are also indicative of
probable water charged horizons in the area associated with less competent rock mass.
Furthermore except these seasonal nallah no indications of a any weak feature are present
on the surface which is under overburden cover. Hence provision for advance probing at
tunnel grade is being kept for probing this reach.
20 70 10
5.4.6.6. Conclusion
The approximately 2.6 km long tunnel has been proposed on the Right bank of Umiew River
in the Archean Gneissic complex forming a major constituent of the East Khasi hills in the
South Meghalaya plateau. The bed rock consists of variants of granite gneiss with Quartzo
feldspathic bands and intrusions of granite. Summary of anticipated tunneling conditions
Summary of anticipated tunneling conditions
Rock classes in various stretches of HRT have been predicted on the basis of
surface exposures details.
Based on geomechanical classification of rock mass percentage of rock class to be
encountered in HRT shall be as under.
Table 5.10 Rock Class Percentage Head race tunnel
Rock Class Percentage in HRT
Class II Class III Class IV Class V
40 45 10 5
Low cover and weak zones apart from areas where copious seepage is anticipated
are proposed to be evaluated further by advance probing.
Adequate preparedness shall be made in respect of sufficient dewatering
arrangements. Installation of concurrent support shall be required while negotiating
weak rock conditions as envisaged.
15,16,17,18.It is opined that the entire length of pressure shaft shall be in the reasonably
competent Gneiss/Quartz biotite gneiss.
ROCK
STRUCTURE PERCENTAGE
CLASS
Class- II 20%
Class- V 5%
Giving due consideration to subsurface information from exploration and results of rock
mechanic tests sufficient and suitable vertical as well as lateral rock cover exist around this
part of pressure shaft and is anticipated to negotiate generally fair to good rock with
occasional weak features manifested by thick clay filled joints encountered in one of the
boreholes.
of rock mechanics test and rock cover over the structure, this part of structure i.e from 0 –
540 m is anticipated to negotiate generally very good rock with intermediate length of fair
and patches of poor to very poor rock class.
For estimation purpose the following percentage of rock class can be considered for bottom
horizontal pressure shaft from 0-540m
Table 5.12 Percentage wise rock class in Bottom Pressure Shaft (0-540m)
ROCK
STRUCTURE PERCENTAGE
CLASS
Class- II 68%
Class- V 2%
For estimation purpose the following percentage of rock class can be considered for bottom
horizontal pressure shaft from 540-673m
Table 5.13 Percentage wise rock class in Bottom Pressure Shaft(540m to 673m)
Class- II 20%
Class- V 5%
S1 14° - 36°/090° - 143° 24°/118° Tight 10-60 & 60-200 10-20 & 8-10
S3 66° - 86°/248° - 280° 78°/261° 10-30 20-60 & 60-200 3-10 & 10-15
Rough
Tight to Planar
S4 68° - 87°/159° - 186° 80°/172° Partially 20-60 & 60-200 3-10 & 10-15
open
Two geological sections have been developed w.r.t the power house for better appraisal of
geological and geotechnical conditions. One section is developed along power house long
axis (Ref. 0933-GDC-05C-0002) while the second section has been developed across the
Power house (Ref. 0933-GDC-05C-0003).It is evident from these section that height of cut in
the rock will be around 38m whereas in overburden it will be of the order of 45-
50m.Coefficeint of permeability in overburden ranges from 0.29X10-3cm/sec to 2X10-3cm/sec
which indicate highly pervious nature of overburden. Since overburden is of river borne
material indicative of a pre-existing river terrace, presence of water table at a depth of 12-
14m will make this material more susceptible to instability. Accordingly necessary measure
to avoid surcharging of the overburden slope shall be adopted during excavation of this
material. Surface power house appears to have been placed suitably with respect to strike of
foliation.
Generally Core recovery in rock vary from 80-95% and RQD vary from 30-80%.In view of
above ,during excavation in selected weak media consolidation grouting shall be resorted.
However Rock mechanics test conducted on the cores samples from power house area
reveals the UCS value of 106 to 137 MPa. It is therefore concluded that foundation of the
surface power house shall be in sound rock.
The entire excavation for Power house pit shall be in bedrock having indicative RMR
(without rating adjustment) ranges from 50 to 59 computed on the basis of geotechnical
parameter collected from the outcrops and collating the finding from boreholes DH-101 and
DH-102 in which bedrock was encountered at El 268.6m and 262.2m respectively.
The initial part at NSL exhibits consistent presence of overburden material characterized by
the presence of recent fluvial material constituted of sand gravel silt etc where as terminal
stretch of TRC is seem to be occupied by outcrops of gneiss. Minimum excavation level from
at draft tube is El ± 219 m from where channel approaches further through recovery bay
with reverse gradient to meet the river at EL ± 230m. The entire excavation for recovery bay
and TRC shall be in bedrock having indicative RMR (without rating adjustment) ranges from
50 To 59 computed on the basis of geotechnical parameter collected from the outcrops and
collating the finding from boreholes DH-101 and DH-102 in which bedrock was encountered
at El 268.6m and 262.2m respectively.
In view of this it opined that tail race system including the recovery bay shall be on bed rock
constituted of slightly weathered strong to very strong, moderately jointed, grey gneiss.
To minimize the effect of some of these adversely oriented joints on excavation particularly
on the western wall, systematic rock support with rock bolts of 25mm Ø 4 to 6m long with
spacing of 2m center to center, adequate thickness of SFRS, and pressure relief
arrangement shall be required to installed concurrent to the excavation. Furthermore,
provision of consolidation grouting shall be made as ground improvement measure.
5.5.1. Introduction
During DPR stage investigation of Mawphu stage – II availability of construction material was
studied giving due consideration to the requirement, lead distance and the impact of the
same on environment.
The estimated quantity of concrete & shotcrete required for the construction of Concrete
Dam, Diversion Tunnel, Pressure Shaft, Power House and other appurtenant structures of
the project is 2.2 Lac m3. The requirement of construction material (coarse and fine
aggregate) for various structures of the project has been worked out and is as under:
Usable
Total material
Estimated which can Assumed
Qty from be Material shortage
Source Excavation extracted Req. in of Action Required
Sl
(solid (Assuming Lac m3 material
volumes) in 60% in Lac m3
Lac m3 wastage) in
Lac m3
Rock Quarry
Dam , MWR/DS-II and
Power *CA(W)-0.1 MWR/DS-I and needs
intake, *CA-1.5 to be acquired for
1 Diversion 1.6 1.0 *FA-0.8 1.4 Dam works. Blending
Tunnel, with crushed fine
with inlet Total-2.4 aggregate MWG-I
and outlet shall be used, if
required
Material from MWR-
Coffer Rockfill
nil nil 0.65 DS-III and MWG-III
2 Dam 0.65
needs to be utilized
Additionally, if
*CA-0.23 required MWR/HRT-I
or MWR/PS-I quarry
*FA-0.12
HRT and 0.15 in shall be utilizes.
3 0.86 0.5
Adits excess Alternatively, Power
House excavation
Total-0.35 material can also be
used
Surge
Shaft, *CA-0.4
Pressure
To be utilized from
Shaft with *FA-0.2 Power House
4 Adits, 1.87 1.1 0.5 in excavation i.e.
Power excess MWR/PH-3
House and
Tail Race Total-0.6
Channel
* CA- Coarse aggregate, CA (W)- Coarse aggregate (wearing surface), FA- Fine aggregate
Rock Quarry
1 near Waisu MWR/DS-I 0.3km 3 Km
nala 1.0
Rock Quarry
2 in Reservoir MWR/DS-II 0.7km 3 Km
Area .60
Rock Quarry
3 Left bank,
MWR/DS-III 0.1km 3km
Dam Dam/DT
Excavation
Rock Quarry
4 right bank,
MWR/DS-IV 0.1km 3km
Dam/PI
1.0
Excavation
River bed
5 material, Dam MWG-III 0.1km 3km
Site .70
Granite
6 boulders near MWR/HRT-I 2 km 1.5km
HRT Adit-1 .19
HRT
Rock quarry
7 near Umblai MWR/HRT-II 3km 2km
bridge .92
Rock Quarry
Pressure
8 near Pressure MWR/PS-I 3 km 1km
shaft
shaft adit 1.0
Rock Quarry
on
9 MWR/PH-I 4km 4km
Mawsynram 6.0
Road
Rock Quarry
Power
10 on
house MWR/PH-II 4km 4km
Mawsynram 3.2
Road
Rock quarry
11 near Power MWR/PH-III 3km 0.1km
house 1.1
All in
12 Aggregates
MWG-I 45km 45km
deposit near 1.10
Balat
Balat
Fine
13 aggregates
MWG-II 45km 45km
deposit in .57
Balat
Coarse and fine aggregate samples collected from different river terraces and rock quarries
were tested for complete range of physical parameters as well as alkali aggregate reactive
test. On the basis of test result of the various sample and estimated quantity of available
coarse and fine aggregate, it can be concluded that sufficient quantity of various construction
material of suitable quantity is available within a reasonable distance from both power house
and Dam site. As narrow gorge and steep gradient of the river negates the possibility of
locating good number of prospective shoal deposits, it will be imperative to bank upon the
crushed sand to cater the requirement of major part of fine aggregate. However, if need be,
to maintain the proper grading of fine aggregate blending of river sand of appropriate
selected grain size range from Balat Shoal deposit can be made. To enlarge the data base
beyond BOQ for construction material survey few more samples from the dam area have
also been collected and shall be perused once the report is received. The samples except
MWR/HRT-II, collected and tested from the entire project area in this campaign, confirm its
suitability as both wearing and non wearing surfaces and also in regards to their alkali
aggregate reactivity status being tested innocuous. However, MWR/ HRT-II collected from
granitic area are observed to be marginally deficient with respect to impart value, Loa
Angeles abrasion value, crushing value i.e. 27.61, 38.6 and 29.4 respectively. In view of this,
to take care of in homogeneity of the granitic material, it is proposed to collect more samples
during construction or in pre-construction stage from the granitic area to decipher its possible
utility as wearing surface, through segregation once the report becomes available.
A serious efforts were made to assess the suitability of the excavated material anticipated to
be generated during construction of the project. This would not only have a positive impact in
the project cost but also shall ensure minimum adverse impact on environment.
4.
5.
6.
6.1. General
Mawphu Hydro Electric Project (Stage-II) is proposed on the river Umiew in East Khasi Hills
District of Meghalaya. The proposed dam site is located at about 3.17km downstream of
Umduna HEP (90 MW) Power House location and the Power House site is located at about
2km downstream of Thieddieng village on the right bank of the river.
Mawphu HEP (Stage-II) is planned as a run of river scheme. However, with diurnal storage
available it will be possible to have peaking operation.
The power potential studies have been carried out for working out optimum installed capacity
and other related project features.
The environment releases as per the Terms of Reference (ToR) mentioned by the Ministry of
Environment and Forests (MoEF) are as below:
During monsoon months i.e. from June to September, the water to be released from the
Dam has to be 30% of the river discharge. During transition months i.e. post monsoon of
October and November, and pre monsoon of April and May, the water to be released has to
be 25% of the river discharge and during non monsoon months i.e. from December to
March, the water to be released will be 20% of the river discharge. Copy of letter no
NEEPCO/ HoP/ S&I/ Mawphu/ T-29/ 2013-2014/838 dated 19.07.2013, indicating minimum
environmental flow is enclosed Annexure 6-2.
The 90% and 50% dependable year have been obtained from the following relations:
Where n is the number of years for which discharge data is available, which is 26.
The year 1996-97 and 2002-03 works out to be the 90% and 50% dependable years
respectively.
The discharges of 90% and 50% dependable years are shown in Annexure 6-4. 90%
dependable year discharges after deducting the environment releases are indicated in Table
6-1 below.
Table 6-1 90% Dependable Year Discharges after deducting the Environmental
Releases
(m3/s)
30 158.88 5.30
35 177.24 5.06
40 195.32 4.88
45 211.98 4.71
50 227.29 4.55
55 242.05 4.40
60 256.35 4.27
65 269.54 4.15
70 280.58 4.01
75 291.62 3.89
DPR-I: Chapter-6: Power Potential Study 6-4
MAWPHU HEP, STAGE – II
30 158.88 5.30
80 302.66 3.78
85 312.73 3.68
Table 6-3 Ratio of incremental energy (∆AE) and increment in installed capacity (∆IC)
Fig 6-1 Graph between incremental energy (MU/MW) and installed capacity
From the Fig 6-1 above, it is seen that the optimum installed capacity lies between 70MW
and 80MW as beyond 80MW there is sharp fall in incremental energy.
Basic parameters with installed capacity of 70, 75 and 80MW are mentioned hereunder:
The potential exploited with various installed capacities is indicated in the Table 6-5 given
below:
35 47.60
40 52.45
45 56.92
50 61.04
55 65.00
60 68.84
65 72.38
70 75.35
75 78.31
80 81.28
85 83.98
Keeping in view the techno-economic viability as well as optimum exploitation of the site,
75MW i.e. selected as the optimum installed capacity.
With installed capacity of 75MW energy computation has been carried out for years in hydro
chronological order and shown in the table below.
Table 6-6 Annual energy generation with 75MW installed capacity in various
hydrological years
8 1995-96 319.60
9 1986-87 249.47
10 2001-02 323.39
11 1983-84 248.21
12 1981-82 286.44
13 2002-03 296.85
14 1982-83 256.72
15 2000-01 312.53
16 1992-93 286.21
17 1997-98 277.67
18 1993-94 256.07
19 2003-04 273.04
20 1979-80 223.00
21 1985-86 253.93
22 1980-81 275.88
23 1998-99 240.75
24 1996-97 291.62
25 1990-91 310.33
26 1994-95 230.71
Average 295.52
From the table above, it is found that certain years yield a lower annual energy due to flow
pattern despite of higher annual flows. Considering the long term Project life cycle, it is seen
that the average energy worked from all the available hydrological years is higher than the
90% dependable year annual energy.
The annual plant load factor for the Project is worked out as below:
Annual Energy Generation
PLF = X 100
Installed Capacity X 365 X 24
i.e. 44.39%.
Firm power is the power considering the average inflows in the lean period from December
to March after deducting the mandatory releases.
75 ×100
Design Discharge= =35.72
9.8 × 0.9212× 232.33
Thus, the storage required = 35.72 x 3 x 3600 ~ 0.386 Million cubic meters
The available live storage between the full reservoir level and the minimum draw down level
is about 0.8 Million cubic meters. The additional storage available would be utilized to meet
contingencies.
6.8. SUMMARY
The summary of the data for the optimum installed capacity is as below:
Installed capacity 75 MW
1.
Annual energy generation in 90% 291.62 MU
2.
dependable year
Mont Perio Da 1979- 1980- 1981- 1982- 1983- 1984- 1985- 1986- 1987- 1988- 1989- 1990- 1991- 1992- 1993- 1994- 1995- 1996- 1997- 1998- 1999- 2000- 2001- 2002- 2003- 2004- Avera
h d ys 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 ge
May I 10 12.59 4.84 17.70 4.32 10.47 4.25 5.98 7.80 18.65 58.01 10.56 29.91 12.85 9.76 6.86 9.19 24.82 4.42 8.16 0.19 38.99 26.76 8.19 16.65 4.69 12.28
II 10 9.66 5.30 44.70 4.71 6.21 4.65 12.82 13.44 6.27 71.59 13.12 36.97 15.95 12.13 8.57 11.44 30.69 5.56 10.17 0.36 48.14 33.08 10.20 20.63 5.89 15.24
III 11 10.25 5.43 96.84 16.14 7.54 6.14 11.61 6.05 21.29 118.8 22.05 61.51 26.73 20.41 14.50 19.26 51.12 9.53 17.16 0.92 80.01 55.07 17.21 34.47 10.08 25.56
1
Jun I 10 2.89 15.72 42.49 40.53 15.82 21.61 92.54 18.52 106.2 60.74 36.58 34.48 46.96 40.69 55.00 46.23 60.74 39.53 30.58 12.74 24.50 66.65 36.18 72.13 68.98 31.54
8
II 10 16.79 44.99 26.59 83.58 18.39 238.2 70.07 52.41 42.42 103.5 62.51 58.95 80.14 69.49 93.81 78.90 103.5 67.52 52.31 22.00 41.98 113.6 61.82 122.9 117.5 53.93
4 6 6 0 1 6
III 10 53.23 24.58 89.12 91.27 26.30 74.30 71.14 94.98 142.4 113.5 68.54 64.63 87.86 76.19 102.8 86.50 113.5 74.03 57.36 24.15 46.05 124.5 67.79 134.7 128.8 59.14
6 2 3 2 2 2 5
Jul I 10 120.7 51.57 140.5 149.1 170.8 301.3 136.9 30.05 292.5 173.4 256.0 49.87 62.00 125.2 129.2 44.24 80.90 101.4 129.5 112.0 174.8 39.01 147.1 123.2 114.5 248.4
4 4 0 6 1 3 9 1 3 6 2 6 2 2 7 7 1 9 9
II 10 36.30 96.80 140.6 60.53 87.85 204.3 51.21 61.96 87.13 102.8 152.0 29.44 36.66 74.27 76.62 26.10 47.89 60.12 76.80 66.40 103.7 22.99 87.29 73.05 67.92 147.5
7 0 9 1 6 3
III 11 114.1 68.77 109.7 89.90 121.1 150.5 106.4 74.40 422.9 156.5 231.1 44.98 55.93 113.0 116.6 39.89 72.99 91.56 116.8 101.0 157.8 35.17 132.8 111.2 103.4 224.3
6 0 0 4 4 1 2 2 5 3 9 9 4 3 0 1 1
Aug I 10 34.02 56.65 56.59 105.6 104.0 82.31 28.12 40.66 96.32 121.6 34.03 42.85 54.77 40.42 33.56 43.72 81.84 44.20 65.08 89.31 65.20 55.55 50.25 47.23 25.01 40.51
0 7 5
II 10 35.39 138.3 53.75 29.72 56.94 39.26 40.37 39.56 318.9 151.3 42.42 53.39 68.20 50.36 41.83 54.47 101.8 55.06 81.02 111.1 81.16 69.17 62.59 58.82 31.21 50.48
6 3 4 5 3
III 11 32.33 57.40 98.82 37.05 100.0 41.93 95.50 57.92 71.34 119.2 33.35 42.00 53.68 39.61 32.89 42.85 80.22 43.31 63.79 87.54 63.90 54.44 49.25 46.28 24.51 39.70
3 4
Sep I 10 102.5 62.61 19.66 38.06 104.0 73.88 31.58 313.9 96.41 70.54 86.41 44.84 146.7 75.08 67.68 33.08 72.69 29.24 67.46 64.03 26.06 52.16 70.95 40.49 34.88 67.35
0 7 8 3
II 10 132.8 87.88 11.78 166.0 56.94 274.0 35.00 96.22 67.20 77.69 95.15 49.40 161.5 82.69 74.54 36.46 80.05 32.24 74.30 70.53 28.73 57.46 78.14 44.61 38.44 74.18
5 7 6 5
III 10 100.6 54.31 38.09 28.42 100.0 34.48 95.50 109.9 201.4 63.84 78.21 40.56 132.8 67.96 61.25 29.91 65.79 26.44 61.05 57.95 23.55 47.20 64.21 36.62 31.54 60.95
8 0 3 4 4
Oct I 10 90.13 38.94 10.47 16.47 22.98 19.14 14.38 27.21 57.92 52.60 78.16 54.00 100.3 30.80 19.86 38.47 21.22 80.34 24.95 41.41 66.98 50.64 49.52 20.67 57.93 140.0
6 3
II 10 46.56 45.81 8.78 21.35 57.76 14.28 11.61 27.18 63.98 52.55 78.07 53.94 100.2 30.76 19.84 38.43 21.20 80.26 24.92 41.36 66.91 50.59 49.47 20.65 57.87 139.8
5 8
III 11 22.07 52.13 12.75 26.50 18.45 24.93 10.57 19.89 24.44 37.40 55.63 38.39 71.48 21.84 14.03 27.31 15.00 57.19 17.66 29.41 47.66 36.00 35.20 14.61 41.20 99.79
Nov I 10 27.80 19.85 10.47 12.59 13.41 16.34 10.64 14.44 28.63 24.71 20.68 11.80 18.78 13.97 13.79 9.95 16.09 12.85 13.98 13.31 17.14 14.08 15.43 14.82 13.72 22.14
II 10 7.12 14.90 8.78 10.67 11.09 14.32 9.99 9.98 19.93 17.18 14.35 8.13 13.02 9.65 9.52 6.83 11.14 8.86 9.65 9.19 11.87 9.73 10.67 10.25 9.47 15.38
III 10 2.69 13.21 7.35 10.38 8.91 9.95 9.50 8.04 16.15 13.91 11.60 6.53 10.52 7.77 7.66 5.47 8.98 7.13 7.77 7.39 9.58 7.83 8.60 8.26 7.62 12.44
Dec I 10 2.37 11.84 6.99 6.83 7.19 10.93 8.33 7.06 14.24 12.25 10.21 5.72 9.25 6.82 6.73 4.78 7.89 6.25 6.82 6.49 8.42 6.88 7.56 7.25 6.69 10.95
II 10 1.84 9.56 22.82 6.44 5.62 7.06 7.80 7.93 15.93 13.72 11.45 6.44 10.38 7.66 7.56 5.39 8.86 7.03 7.67 7.29 9.45 7.73 8.48 8.14 7.52 12.27
III 11 1.81 8.00 8.91 4.55 5.49 6.50 8.10 5.61 11.41 9.81 8.16 4.53 7.38 5.42 5.34 3.77 6.28 4.96 5.42 5.15 6.71 5.46 6.01 5.77 5.31 8.76
Jan I 10 3.11 4.84 8.16 6.66 3.93 4.91 5.49 7.67 12.04 9.24 7.69 4.25 6.95 5.09 5.02 3.54 5.91 4.66 5.10 4.84 6.32 5.14 5.66 5.42 4.99 8.25
II 10 2.95 5.57 7.06 5.88 3.28 5.26 7.58 15.42 12.14 10.56 8.80 4.90 7.96 5.85 5.77 4.08 6.78 5.36 5.85 5.56 7.24 5.90 6.49 6.22 5.74 9.43
III 10 2.79 4.23 5.26 4.91 3.28 4.87 6.53 6.86 11.03 8.12 6.74 3.71 6.09 4.45 4.39 3.07 5.17 4.07 4.45 4.22 5.53 4.49 4.95 4.74 4.36 7.24
Feb I 10 1.91 3.76 3.57 4.48 2.56 3.57 7.51 5.72 11.29 7.53 6.25 3.42 5.65 4.11 4.05 2.83 4.79 3.76 4.11 3.90 5.12 4.15 4.58 4.38 4.03 6.71
II 10 2.40 3.71 4.84 3.73 2.43 4.32 6.99 5.07 10.34 7.15 5.93 3.23 5.35 3.89 3.84 2.67 4.53 3.55 3.89 3.69 4.85 3.93 4.33 4.15 3.81 6.37
III 8 2.17 2.94 3.77 3.24 2.98 3.77 5.04 3.77 7.28 5.05 4.75 2.55 4.28 2.69 3.04 2.09 3.61 2.44 3.09 2.92 3.87 2.71 3.45 3.30 3.02 4.48
Mar I 10 1.91 3.69 3.76 3.99 3.21 3.02 7.25 4.45 12.36 7.15 5.93 3.23 5.35 3.89 3.84 2.67 4.53 3.55 3.89 3.69 4.85 3.93 4.33 4.15 3.81 6.37
II 10 1.75 4.57 4.65 3.93 8.62 5.30 5.88 4.16 14.87 8.75 7.27 4.01 6.57 4.81 4.74 3.33 5.59 4.40 4.81 4.57 5.97 4.85 5.34 5.12 4.72 7.81
III 11 1.62 5.37 14.74 7.58 10.67 5.04 4.65 3.34 9.92 10.21 8.50 4.73 7.69 5.65 5.57 3.94 6.55 5.17 5.65 5.37 7.00 5.70 6.27 6.01 5.54 9.12
Apr I 10 1.68 6.76 6.05 3.28 2.07 7.51 4.16 5.79 25.13 10.13 8.43 4.69 7.63 5.60 5.53 3.91 6.50 5.13 5.61 5.33 6.94 5.65 6.22 5.96 5.50 9.05
II 10 3.57 3.15 13.54 7.54 1.94 9.37 3.80 4.16 11.84 9.57 7.96 4.42 7.20 5.28 5.21 3.67 6.13 4.84 5.29 5.02 6.55 5.33 5.86 5.62 5.18 8.55
III 10 4.94 4.22 20.54 17.44 18.45 7.61 4.09 9.20 32.33 19.09 15.96 9.06 14.49 10.75 10.60 7.62 12.39 9.88 10.75 10.24 13.21 10.84 11.88 11.41 10.55 17.10
Avera cume 29.10 28.95 32.79 31.48 33.36 48.31 29.02 33.91 67.08 53.06 44.57 25.71 40.82 30.39 30.05 21.83 34.94 27.94 30.36 28.91 36.86 30.68 33.45 32.22 29.89 47.59 35.13
ge cs
MCM 920.6 917.0 1048. 994.4 1060. 1522. 922.2 1068. 2134. 1688. 1416. 816.1 1288. 962.6 950.4 690.6 1106. 886.9 963.3 918.4 1177. 970.3 1061. 1020. 945.9 1514. 1114.
5 3 65 3 08 37 2 57 30 44 59 0 55 6 0 3 51 8 9 9 51 0 31 46 7 72 13
mm 2877. 2865. 3277. 3107. 3312. 4757. 2881. 3339. 6669. 5276. 4426. 2550. 4026. 3008. 2970. 2158. 3457. 2771. 3010. 2870. 3679. 3032. 3316. 3188. 2956. 4733. 3481.
04 72 04 60 75 41 93 28 69 38 86 31 73 30 00 23 84 81 61 28 72 18 59 93 14 49 65
Unrestricted
Sl.No. Year Dependability Remarks
Energy
1 1987-88 1,220.61 3.85
2 1988-89 965.44 7.69
3 1984-85 879.12 11.54
4 2004-05 866.01 15.38
5 1989-90 811.08 19.23
6 1991-92 742.78 23.08
7 1999-00 670.71 26.92
8 1995-96 635.78 30.77
9 1986-87 617.06 34.62
10 2001-02 608.76 38.46
11 1983-84 607.01 42.31
12 1981-82 596.59 46.15
13 2002-03 586.29 50.00 50% depenedable year
14 1982-83 572.91 53.85
15 2000-01 558.22 57.69
16 1992-93 553.03 61.54
17 1997-98 552.47 65.38
18 1993-94 546.76 69.23
19 2003-04 543.96 73.08
20 1979-80 529.50 76.92
21 1985-86 528.05 80.77
22 1980-81 526.82 84.62
23 1998-99 526.03 88.46
24 1996-97 508.44 92.31 90% dependable year
25 1990-91 467.78 96.15
26 1994-95 397.32 100.00
II 10 5.6 20.6
II 10 67.5 122.9
II 10 60.1 73.0
II 10 55.1 58.8
II 10 32.2 44.6
II 10 80.3 20.6
II 10 8.9 10.2
II 10 7.0 8.1
II 10 5.4 6.2
II 10 3.6 4.2
II 10 4.4 5.1
II 10 4.8 5.6
ENERGY GENERATION IN 90% DEPENDABLE YEAR AT VARIOUS INSTALLED CAPACITIES Annexure 6-5
Installed Capacity
Design discharge (cumecs)
Mo T Da 90% Power Energy 30 35 40 45 50 55 60 65 70 75 80 85
nth D ys DY Unrestr Unrestr
(cum icted icted
ecs)
MW MU P,30 E,30 P,35 E,35 P,40 E,40 P,45 E,45 P,50 E,50 P,55 E,55 P,60 E,60 P,65 E,65 P,70 E,70 P,75 E,75 P,80 E,80 P,85 E,85
May I 10
3.30 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66 6.93 1.66
II 10
4.20 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12 8.82 2.12
II 11
I 7.13 14.96 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95 14.9 3.95
6 6 6 6 6 6 6 6 6 6 6 6
Jun I 10
27.65 58.05 13.93 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 58.0 13.9 58.0 13.9 58.0 13.9 58.0 13.9 58.0 13.9 58.0 13.9
0 0 0 0 0 0 0 0 0 5 3 5 3 5 3 5 3 5 3 5 3
II 10
47.25 99.20 23.81 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II 10
I 51.80 108.76 26.10 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Jul I 10
71.05 149.17 35.80 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II 10
42.07 88.33 21.20 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II 11
I 64.12 134.62 35.54 30.0 7.92 35.0 9.24 40.0 10.5 45.0 11.8 50.0 13.2 55.0 14.5 60.0 15.8 65.0 17.1 70.0 18.4 75.0 19.8 80.0 21.1 85.0 22.4
0 0 0 6 0 8 0 0 0 2 0 4 0 6 0 8 0 0 0 2 0 4
Aug I 10
30.94 64.96 15.59 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 64.9 15.5 64.9 15.5 64.9 15.5 64.9 15.5 64.9 15.5
0 0 0 0 0 0 0 0 0 0 0 6 9 6 9 6 9 6 9 6 9
II 10
38.57 80.98 19.44 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 80.9 19.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 4
II 11
I 30.31 63.64 16.80 30.0 7.92 35.0 9.24 40.0 10.5 45.0 11.8 50.0 13.2 55.0 14.5 60.0 15.8 63.6 16.8 63.6 16.8 63.6 16.8 63.6 16.8 63.6 16.8
0 0 0 6 0 8 0 0 0 2 0 4 4 0 4 0 4 0 4 0 4 0
Sep I 10
20.44 42.92 10.30 30.0 7.20 35.0 8.40 40.0 9.60 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3 42.9 10.3
0 0 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0 2 0
II 10
22.54 47.32 11.36 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 47.3 11.3 47.3 11.3 47.3 11.3 47.3 11.3 47.3 11.3 47.3 11.3 47.3 11.3 47.3 11.3
0 0 0 0 0 2 6 2 6 2 6 2 6 2 6 2 6 2 6 2 6
II 10
I 18.48 38.80 9.31 30.0 7.20 35.0 8.40 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31 38.8 9.31
0 0 0 0 0 0 0 0 0 0 0 0
Oct I 10
60.23 126.45 30.35 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II 10
60.23 126.45 30.35 30.0 7.20 35.0 8.40 40.0 9.60 45.0 10.8 50.0 12.0 55.0 13.2 60.0 14.4 65.0 15.6 70.0 16.8 75.0 18.0 80.0 19.2 85.0 20.4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
II 11
I 42.90 90.07 23.78 30.0 7.92 35.0 9.24 40.0 10.5 45.0 11.8 50.0 13.2 55.0 14.5 60.0 15.8 65.0 17.1 70.0 18.4 75.0 19.8 80.0 21.1 85.0 22.4
0 0 0 6 0 8 0 0 0 2 0 4 0 6 0 8 0 0 0 2 0 4
Nov I 10
9.68 20.31 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88 20.3 4.88
1 1 1 1 1 1 1 1 1 1 1 1
II 10
6.68 14.01 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36 14.0 3.36
1 1 1 1 1 1 1 1 1 1 1 1
II 10
I 5.33 11.18 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68 11.1 2.68
8 8 8 8 8 8 8 8 8 8 8 8
Dec I 10
5.04 10.58 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54 10.5 2.54
8 8 8 8 8 8 8 8 8 8 8 8
II 10
5.60 11.76 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82 11.7 2.82
6 6 6 6 6 6 6 6 6 6 6 6
II 11
I 4.00 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22 8.40 2.22
Jan I 10
3.76 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89 7.89 1.89
II 10
4.32 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18 9.07 2.18
II 10
I 3.28 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65 6.89 1.65
Feb I 10
3.04 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53 6.38 1.53
II 10
2.88 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45
II 8
I 1.92 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77 4.03 0.77
Mar I 10
2.88 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45 6.05 1.45
II 10
3.52 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77 7.39 1.77
II 11
I 4.16 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31 8.73 2.31
Apr I 10
3.83 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93 8.03 1.93
II 10
3.60 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81 7.56 1.81
II 10
I 7.43 15.59 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74 15.5 3.74
9 9 9 9 9 9 9 9 9 9 9 9
Tot
al 372.38 158.8 177. 195. 211. 227. 242. 256. 269. 280. 291. 302. 312.
8 24 32 98 29 05 35 54 58 62 66 73
NOT Net discharges used after deducting environment releases
E:
Annexure 6-6
Annexure 6-7
7.
7.1. General:
Mawphu Hydroelectric project (Stage-II) is a run of the river scheme proposed on Umiew
River in East Khasi Hills district of Meghalaya. The project is proposed to utilize a net head
of about 232m and design discharge of 35.72 cumecs for generation of 75 MW (2 x 37.5
MW). The project is being implemented by North Eastern Electric Power Corporation Ltd, a
Government of India enterprise.
This chapter deals with feasibility stage (DPR stage) design of various civil engineering
structures of the project.
The selected project layout comprises a concrete gravity dam on Umiew River and an intake
structure on the right bank for diversion of 35.72 cumecs of water for power generation. The
reservoir is proposed to have 0.8 MCM of live storage and 1.2km long at FRL. Water is
diverted from the river and is conveyed through right bank head race tunnel to the surge
shaft. Surge shaft is proposed at the junction of HRT and pressure shaft to take care of the
transient conditions in the water conductor system. A pressure shaft, which will be bifurcated
near the power house, will feed water to two vertical axis Francis turbines each of 37.5 MW
installed capacity housed in surface power house.
A concrete gravity dam of 51m high from the deepest foundation level with low level
spillway comprising 6 bays each with radial gate of size 9.00m (W) x 12.00m (H) to
pass the design flood of 8900 cumecs.
Temporary river diversion works comprise a Horse Shoe shaped diversion tunnel of
7m diameter, about 384m long on the left bank and 18m (Maximum) high upstream
and 6m high downstream cofferdams.
One number of Horse Shoe shaped Head Race Tunnel of 4.8m dia and 2622m long
up to Surge Shaft
One number of restricted orifice type Surge Shaft of 10m dia and 54m high
One number of circular Pressure Shaft of 3.5m dia and 869m long which bifurcates
into 2.5m dia and 32m long pressure shafts to feed two turbine units
A Surface Power House of 53.8m (L) x 16.0m (W) x 30.5m (H) housing two Vertical
Axis Francis Turbines and Generator units of 37.50 MW each
One tail race channel of 8m wide and 51m long (including recovery bay) to discharge
the water into the river
Spillway Arrangement:
The width of the river is about 73m. Dam height and basic parameters have been decided
based on techno-economical considerations as described in Section-2.3 in Chapter-2. The
height of the dam is 38m from the average river bed level and spillway crest is proposed at
about 9m above the average river bed level. The design flood (PMF) is 8900 cumecs.
Spillway of 79m long including piers and abutments are required to pass the design flood
with one gate inoperative condition. Therefore, the whole river width shall be
accommodated with spillway blocks or overflow (OF) block and the length of NOF (non over-
flow) is less.
Foundation Condition:
The foundation rock of dam area comprises Quartz Biotite Gneiss/Gneiss. The bed rock is
hard, moderate to closely jointed rock mass. The foundation rock is strong and is suitable
for adoption of a concrete gravity dam. Investigation data also indicates the suitability of
foundation condition for concrete gravity dam.
Quarries and shoals are available/identified at various places near the dam axis. Rock
quarry near the Weisu nallah which is about 400m u/s of dam axis and rock quarry in the
reservoir area which is at about 1000m u/s of dam axis are some of the quarries identified in
addition to other quarries. From the preliminary assessment, it is expected that apart from
excavated quantity in the dam area, these available quarries and shoals near the dam axis
will satisfy the maximum requirement of coarse and fine aggregates for the concrete dam.
Therefore, availability of construction material will not be a constraint for concrete gravity
dam.
A concrete gravity dam has been finalized considering the following aspects:
The dam height of 38m (from average river bed level) is required to meet out live
storage for peaking requirements. and rock is available at shallow depth therefore
barrage is not considered as a suitable diversion structure.
Concrete gravity dam of 140m long (at top) and 51m high (from the deepest foundation
level) with its top at EL.472.00m.
2 Non-Overflow (NOF) blocks have been proposed on the left bank side. The length of first
NOF block has been kept as 17.75m and of second block as 15.0m. The height of the
blocks varies from 6.25 to 36.5m.
2 NOF blocks have been proposed on the right bank side. The lengths of blocks are 15.0m
and 13.25m. The height of the blocks varies from 7m to 43m.
A downstream slope of 0.8 (H):1 (V) is proposed for the NOF section based on the
preliminary design.
3 Overflow (OF) blocks have been proposed with 6 bays (controlled by radial gates) utilizing
the available width of the river. The pier width has been kept as 3.0m.
Considering the minimum dam height requirement arrived, the hydraulic head of Mawphu
HEP (Stage-II) dam is greater than 30m and hence as per the above classification, the dam
falls under the category of large dam. Also, cl: 3.1.3 of IS 11223 specifies the inflow flood to
be adopted to design the spillway based on the classification of dam as given below.
Intermediate SPF
Large PMF
Accordingly, Mawphu HEP (Stage-II) dam being large, PMF has been considered as the
inflow flood to design the spillway and the same has been arrived as 8900 cumecs (Refer
Hydrology Report).
The ogee profile consists of two quadrants, the upstream quadrant and the downstream
quadrant. Upstream quadrant of the ogee spillway conforms to the elliptical equation and
downstream profile conforms to the parabolic equation as per cl: 4.1.3.1 IS 6934:1998 and
joins with the bucket profile tangentially.
Elliptical equation used for the upstream quadrant of the ogee spillway and X & Y
coordinates of the equation are given below:
X 23 Y 23
2
+ 2 =1
A 3 B3
Table 7-3 X and Y coordinates of the upstream quadrant elliptical equation
X Y
0.00 4.500
1.00 4.509
2.00 4.400
3.00 4.212
4.00 3.934
5.00 3.544
6.00 3.000
7.00 2.190
8.00 0.000
Parabolic equation used for the downstream profile of the ogee spillway and X & Y
coordinates of the equation are given below:
X2 = 4 Hd Y
DPR-I: Chapter-7: Civil Engineering Structure 7-6
MAWPHU HEP, STAGE – II
X (m) Y (m)
5 0.272
10 1.089
15 2.451
20 4.357
25 6.808
30 9.804
35 13.344
40 17.429
45 22.059
50 27.233
For ease of reference, the computed water surface elevation is tabulated below:
Head losses in the HEC RAS system are accounted for by bulk Manning coefficients and
other geometric properties e.g. contraction and expansion coefficients multiplied by changes
in velocity head of the river. Manning’s values were estimated from physical data about the
stream and floodplain. Adopted coefficient values varied from transect to transect depending
The analysis involves the solution of the partial differential equations of mass and
momentum to predict the movement of water in the Umiew river using the detailed
knowledge of the river geometry at a discrete number of points along the river that was
generated during the cross sections survey. The theoretical basis and detailed equations
employed by the HEC‐RAS system to compute one dimensional surface profiles are
extensively documented in the Hydraulic Reference Manual.
For purposes of computing the tail water curves below the proposed dam site, steady state
hydraulic computations were performed for PMF discharge profile.
The tail water curve at PMF flow below the proposed Mawphu HEP (Stage-II) is developed
from the software. This curve is given below.
Fig 7-7 Tail Water Rating Curve at 100m d/s of Dam Axis
Water surface elevation for various discharges at 100m d/s of dam axis is tabulated below.
Detailed geotechnical investigations carried out at site indicate that at the dam axis,
overburden depth ranges from 6m to 8.4m; bedrock is generally weathered and moderately
to highly jointed near the overburden bedrock interface. Based on the generally high core
recovery of more than 80% noted in most of the Dam axis drill holes (i .e. DH-03, DH-05
and DH-09) after 2 to 3m, a minimum stripping depth of 3m in riverbed has been envisaged.
Inspection of the surface conditions of the abutments indicate generally weathered and
some distressing of the left bank rockmass with minimal stripping limit, which ranges up to 5-
6m. The right bank in comparison appears to be stronger and stripping limit accordingly may
confined to 2m to 3m depth only. Permeability values range from 1-6 Lugeon suggests good
foundation condition in the riverbed. Hence stripping depth at bed level is confined to the in-
situ weathered zone which is observed to lie within 3m as recorded from the core data.
However, presence of fractured & sheared horizons will call for consolidation by means of
effective grouting to attain a tight foundation. In addition to the two lines of the curtain
grouting holes planned to be resorted through gallery Further more in view of the presence
of the thick overburden to the tune of the 30.5, (i.e. El 457.91m) a line of permeation
grouting holes extended into the farthest point of the excavation on left bank u/s of axis shall
be helpful to minimise the seepage through the thick overburden into the dam pit.
Excavation Treatment
Foundation Strengthening
Seepage Control and Drainage
The details of treatment are summarized below; however, techniques and engineering
solutions would be expected to be varied in response to actual ground conditions
encountered along the dam axis.
Dental concreting and mass concrete infilling will be made wherever required after
excavation.
Consolidation grouting with 5m deep holes at 3m c/c spacing is mainly proposed for
foundation treatment to homogenize the blasted rock mass in the dam foundation and filling
up of the discontinuities.
The construction of grout curtains will require testing and grouting programmes to be
designed and carried out as part of the construction works.
At downstream of grout curtain, 75mm dia pressure relief holes/ drainage holes with varying
depth (about 75% of depth of grout curtain) are proposed to reduce the uplift pressure in the
dam.
A foundation gallery of size 2.0mx2.25m is provided to collect seepage water from the
foundation and body of the dam. It is also used for drilling and grouting the foundations and
inspection of dam structure. The total length of the foundation gallery is 178m and is
provided covering all the dam blocks.
The riparian flow release as shown in the above table is calculated from the 90%
dependable year and is proposed to be carried out with five PVC pipes through piers of the
spillway from upstream to downstream.
Depth of flow (d1) entering the bucket has been calculated using momentum equation.
Sequent depth of hydraulic jump has been calculated from the depth of flow (d 1) entering the
bucket and Froude’s number for various discharges ranging from 10% to 100% of
4450cumecs. It was found that tail water depth is much lower than the sequent depth. Also,
sound geological condition is expected in the river bed. In view of these two reasons,
trajectory bucket type energy dissipator is proposed for dissipating the energy downstream
of the dam spillway.
The invert level of the bucket and lip elevation have been kept at EL.432 and EL.436m
respectively. The radius of the bucket has been fixed as 30m and the lip angle as 30
degree. As the tail water level of 438.89m is higher than the bucket lip level, the lip has
been given a slope of 1 in 10. However, in order to ensure the proper behavior of the
energy dissipator careful model studies should be done during detailed engineering stage.
From the view point of stability of the bucket i.e to take care of uplift pressure, 25mm dia
rock anchors of 3.0m long at 3.0m c/c are proposed to tie the trajectory bucket with the
foundation rock.
in the bucket. The height of the training wall shall be verified with the hydraulic model
studies.
Recommendations for the seismic parameters as mentioned in the study are as follows:
As per section-7.4 of the seismic study report, design seismic coefficients for the dam
may be taken as αh = 0.24 and αv = 0.16 for horizontal and vertical components
respectively.
Factor of safety against sliding and overturning for MCE condition should not be less
than 1 and for DBE conditions, this factor of safety is limited to 1.2.
As per section-7.5.2, for concrete gravity dam, the maximum tension under DBE may
be limited to 12.5% of the ultimate compressive strength. The maximum tension
under MCE may be allowed to exceed 50% more than those specified for DBE.
The PGA values for the MCE and DBE conditions are estimated as 0.53g and 0.28g
for horizontal and 0.35g and 0.19g respectively for vertical components.
Mawphu HEP (Stage-II) dam is of 51m high from deepest foundation level. The deepest
foundation level for overflow block is 421m and for non-overflow block is 429m. The stability
analysis has been carried out for the maximum overflow and non-overflow block.
The purpose of the design criteria is to provide technical basis and guidance to carry out
Stability Analysis of Concrete Gravity Dam. This section includes stability requirements,
design data, loading conditions and references followed for the stability analysis of the
Concrete Gravity Dam.
7.3.14.1.1. Stability requirements for the concrete gravity dam are given
below:
i). The Overflow as well as Non-overflow block shall be safe against sliding on any
plane or combination of planes within section, or within the foundation.
ii). The Overflow as well as Non-overflow block shall be safe against Overturning on
any plane or combination of planes within section, or within the foundation.
iii) The safe unit stresses in the concrete of the OF and NOF section or in the
foundation material shall not be exceeded.
Permissible Tensile Stresses for different loading conditions are tabulated below:
Load Case A
NIL 0
and B
Refer to Section 7.5 of Report on Site Specific Earthquake Parameters prepared by the
IIT, Roorkee.
Since, site specific seismic design parameter is being used in the stability analysis,
allowable tensile stress as recommended by IIT, Roorkee will be used.
Site specific study to determine seismic parameter at Mawphu dam site has been carried
out at IIT, Roorkee. The following Peak Ground Acceleration (PGA) values have been
recommended:
The PGA values for the MCE and DBE conditions are estimated as 0.53g and 0.28g
for horizontal and 0.35g and 0.19g respectively for vertical components.
41.3 22.0
Case B 5 Safe 7 safe 6.32 safe 1.77 safe
42.1 21.1
Case C 3 Safe 1 safe 6.18 safe 1.75 safe
44.1 65.5
Case D - H → V ↑ 7 Safe 6 safe 38.73 safe 12.57 safe
46.0 72.1
Case D - H → V ↓ 9 Safe 0 safe 39.43 safe 25.88 safe
28.8 80.8
Case D - H ← V ↑ 7 Safe 6 safe 38.73 safe 26.40 safe
48.2 10.9
Case E - H → V ↑ 7 Safe 2 safe 7.16 safe 1.55 safe
50.1 17.4
Case E - H → V ↓ 9 Safe 6 safe 7.31 safe 1.71 safe
34.6 33.0
Case E - H ← V ↓ 4 Safe 1 safe 12.65 safe 1.90 safe
32.7 26.4
Case E - H ← V ↑ 2 Safe 7 safe 12.40 safe 1.72 safe
40.6
Case F 3 Safe 5.73 safe 16.47 safe 1.36 safe
Case G - H → V 46.7
↑ 9 Safe -4.20 safe 13.17 safe 1.24 safe
Case G - H → V 48.7
↓ 1 Safe 2.34 safe 13.34 safe 1.35 safe
Again Again
st st Agai
Against
Load max min nst
Load combination Loading Condition Overtur
case base base slidin
ning
press press g
ure ure
(FRL+TWL+No
Load earthquake+Silt+upl Taking Moment about
49.21 21.49 4.91 1.78
case B ift(drain operative downstream
condition)
(MWL+Max
TWL+No
Load Taking Moment about
earthquake+Silt+upl 49.26 21.16 4.91 1.77
case C downstream
ift (drain operative
condition)
Horizontal earthquake
condition(towards
downstream)+vertical
earthquake force 86.37 22.19 33.30 17.33
Downward (Taking
Moment about
downstream)
Horizontal earthquake
Load+Earthquake) condition(towards
Upstream)+vertical
110.2
earthquake force -1.68 33.30 Infinity
4
Downward
(Taking Moment about
downstream)
Horizontal earthquake
condition(towards
Upstream)+vertical 100.6
-1.65 34.00 21.79
earthquake force upward 2
(Taking Moment about
downstream)
Horizontal earthquake
condition(towards
downstream)+vertical
earthquake force 71.86 3.63 5.07 1.55
Downward (Taking
Moment about
downstream)
Horizontal earthquake
condition(towards
Upstream)+vertical
36.79 29.11 9.34 1.73
earthquake force upward
(Taking Moment about
downstream)
(MWL+max
Load TWL+Silt+uplift Taking Moment about
46.33 11.28 13.05 1.48
case F (drains inoperative downstream
condition)
Horizontal earthquake
condition(towards
downstream)+vertical
69.02 -15.70 9.13 1.22
earthquake force upward
(Taking Moment about
downstream)
Horizontal earthquake
condition(towards
downstream)+vertical
earthquake force 68.98 -6.08 9.26 1.34
Downward (Taking
(FRL+min Moment about
Load TWL+Silt+EQ+uplift downstream)
case G (drains inoperative Horizontal earthquake
condition) condition(towards
Upstream)+vertical
earthquake force 41.37 21.54 17.44 1.59
Downward
(Taking Moment about
downstream)
Horizontal earthquake
condition(towards
Upstream)+vertical
33.92 19.40 17.19 1.48
earthquake force upward
(Taking Moment about
downstream)
a. Codes:
i. IS 6512 : 1984 – Criteria for Design of Solid Gravity Dam
ii. IS 1893 : 1984 – Criteria for Earthquake Resistant Design of Structures
iii. IS 1893 : 2002 – Criteria for Earthquake Resistant Design of Structures (Part-
1 General Provision and Buildings)
b. Technical Documents:
i. Site Specific Design Earthquake Parameters prepared by IIT, Roorkee for
Mawphu HEP (Stage-II) Site, Meghalaya
ii. USBR – Design of Gravity Dams
Three 300m wide PVC water stops are arranged on the upstream face of the dam
transverse joints. The spacing between the water stops is 0.3m. The first water stop is at
0.5m from the upstream face with its bottom part embedded into the dam foundation with a
depth of 0.5m and the top elevation is 0.5m below the dam top (EL. 471.50m).
For Mawphu HEP dam, the concrete zoning has been proposed considering the following
zoning principles
The concrete strength indicators in all zones shall meet the requirements of
the bearing capacity of the dam
Concrete with the same or similar working conditions shall have the same
material index as far as is possible
Material zoning shall minimize the disturbance to the construction and will be
favorable for the improvement of the construction progress and at the same
time facilitate construction control.
According to the above zoning principles and by analogy with experience in other projects,
the dam body is zoned as follows:
Concrete Grade M15, A40 is used for the dam body and according to the anti-seepage
requirement, Concrete Grade M25, A40 is used for the upstream face.
Concrete Grade M60, A40 is used for abrasion resistance of the spillway crest, overflow face
and Concrete Grade M25, A40 is used for piers, training walls, breast walls and bridge deck
slab on the dam crest. Locations and concrete grade proposed for the entire dam structure
are tabulated below.
Max. Aggregate
Sl.No. Locations Concrete Grade
Size (mm)
Overflow and Non-overflow
1 sections (except 2m u/s and M15,A80 80
1.5m d/s face and bed)
2m thick u/s and 1.5m thick d/s
2 M25,A40 40
face
In some of the projects, polyurea coating has been provided in the spillway for abrasion
resistance. More studies will be made at advanced stage of designing for consideration of
polyurea coating on the basis of performance of past projects and techno –economic
grounds.
Bridge (RCC deck type) is proposed over the spillway (overflow blocks) as a functional
requirement. A gantry crane has been provided over the spillway bridge for lifting the stop
log gates of the spillway. Spillway Bridge will be designed for single lane class ‘AA’ loading
or gantry crane loadings (Gantry loading on the bridge due to break down torque condition of
the stop-log gates). From the above mentioned loadings, the critical case shall be
considered while designing the spillway bridge.
MWL EL.470.50m
FRL EL.470.00m
MDDL EL.460.00m
Concrete Gravity Dam details are shown in the drawings given in Table 7-13.
2.
0933-CPC-03A-002-R0 Concrete Gravity Dam – Plan
7.4. Reservoir:
The gross storage capacity of the reservoir at FRL is 1.55 MCM and at MDDL is 0.75 MCM.
The live storage capacity is 0.8 MCM. The submergence area and the length of reservoir is
13 ha and 1.2km respectively. Reservoir area is demarcated with survey pillars. Reservoir
Area-Capacity curve is shown below.
510
500
490
480
Elevation (m)
470
460
450
440
430
0 100 200 300 400 500 600
The Mawphu HEP (Stage–II) will require a construction period of approximately in 45 months
(excluding period of pre-construction activities). The river needs to be diverted to facilitate
the construction of Dam and appurtenant works.
As the project involves the construction of a concrete gravity dam, during the diversion
period, it would be desirable to complete the structure up to the river bed level and during
the monsoon season, flood may be allowed to pass through the partially constructed
concrete dam blocks. This would help in drastic reduction in the diversion flood. Being a
concrete dam, the monsoon flood is unlikely to cause any damage to the structure and
further construction of the dam above the bed level can be continued during the next non-
monsoon period.
Diversion flood of 375 cumecs has been estimated for the non monsoon period with 25 year
return period, which is adopted for preliminary planning for the preparation of DPR.
The width of the river is about 73m. Diverting the design flood of 375 m 3/s requires larger
base width, which leads to the lesser width available for the construction in the 1st stage.
Excavation for the construction of the dam blocks adjacent to the diversion channels needs
lot of dewatering during the construction. Also, if the diversion arrangement is proposed
nearer to the dam, it will be very difficult to construct downstream key of the spillway and
apron.
Also, as the crest level of the spillway bay is approximately 10 m above the river bed, the 2 nd
stage river diversion through the constructed bays requires a coffer dam of larger height.
Even though this could be overcome by the provision of under sluices in the dam body, due
to the presence of the large boulders in the river bed, the option of providing the under sluice
is ruled out.
In view of the above facts, stage diversion arrangement is not considered suitable.
Rock is exposed on the right bank of the river. However, as the power intake is provided on
the right bank, it is likely to cause interference if the diversion tunnel is also provided on the
right bank. Therefore, it is proposed to keep the diversion tunnel on the left bank. However,
there is a concave bend towards the left bank upstream of the dam axis and hence during
the non-monsoon period, flow in the river will hug along the right bank. Therefore, the
provision of diversion tunnel inlet on the left bank downstream of the bend is not considered
appropriate. Hence, it is proposed to keep the diversion tunnel inlet on the left bank
upstream of the bend (which is about 200m upstream of the dam axis) where rock outcrop is
exposed. This leads to the reduction in the length of the tunnel.
One diversion tunnel of 7.0 m dia, horse shoe shaped is proposed on the left bank. The
length of the tunnel is about 384m. The inlet is kept at EL. 446.00 and outlet is at EL.
429.50. The invert levels are about 1.0 m above the average river bed level at the proposed
location.
One gate of size 8.00 m x 8.00 m for the opening at inlet shall be provided to facilitate the
closure of the tunnel and plugging of the tunnel before reservoir filling. The gate shall be
operated with hoist at EL. 457.50 m.
On the basis of various boreholes drilled in the dam area particularly DH-01 and DH-02,
overburden permeability is expected to range between 1.02 to 1.2 X 10-2 cm/sec whereas
that of bedrock would vary between 3 to 6 Lugeon. In view of this as seepage control
measure jet grouting provisions has been kept below the coffer dam to minimize seepage
into the dam pit during construction.
between 3.8 to 4.8 X10-3 and therefore suitable pumping arrangement shall be required
during construction.
There is a small nallah (Weisu nallah) on the right bank upstream of the bend. Therefore, it
is proposed to place the upstream coffer dam immediately downstream of the nallah which
facilitates the diversion of the flow in the nallah as well as in the river to the tunnel. The
upstream coffer dam is placed about 200 m u/s of dam axis, with its top at EL 457.50 m and
5.00 m top width. U/s Cofferdam is proposed to be founded on overburden. The maximum
height of the coffer dam is 18m from the river bed level. 1.0 m thick impervious to semi-
pervious material is provided on the river bed and on the u/s face with the slope of 1.5H:1V.
The central core of the coffer dam is filled with clay. To facilitate the construction of the
coffer dam, closure dyke is also proposed with the top at EL. 450.00.
The deepest foundation level for main dam is expected at about 13m and the location of the
coffer dam is at about 200m upstream of the dam axis. Hence the seepage at the d/s is not
much anticipated. However, one row of permeation grouting is proposed to arrest the
seepage.
The downstream coffer dam is of 6m high with its top level at EL. 434, which is proposed to
be located at about 170 m d/s of the dam axis with the top width of 3.0 m.
The river closure is made with a cofferdam constructed as an embankment fill from the left
bank. The fill will consist of rock boulders of various sizes, with some fines allowed.
Upstream slope will be about 1:1 (i.e.: the natural slope or the angle of repose of rock-fill).
The downstream slope will also be a natural slope, but due to the water flow through the
abutment will probably not be as steep as the upstream side.
At the time of closure of river, the flow may be as less as 10-20 m 3/s. The water velocities in
the closure section of the cofferdam will be quite high and large blocks of rock, about 1‐1.5
m nominal diameter with a weight of at least 3‐4 tonnes, will be required to complete the
closure. However, for major parts of its construction, smaller diameters may be sufficient.
This depends on the actual conditions encountered (especially the riverbed profiles, and
river flows). At some point, the water level of the river will rise. Consequently, the leak rate
through the embankment will increase. The downstream side may probably need ballasting
with boulders or gabions.
The drawings related to the diversion works are given in the following table.
Operational platform of 18m wide has been provided at the top of intake structure and shall
be used for the operation of trash cleaning machine and gates.
Minimum Submergence:
The entrance of the intake structure should be sufficiently submerged so as to avoid vortex
formations in front of the inlet section. Vortices intruding into the pressure shaft adversely
affect the turbines and the operation of the plant. Therefore, in order to have intake
DPR-I: Chapter-7: Civil Engineering Structure 7-33
MAWPHU HEP, STAGE – II
structure free of vortex, the centre line of the intake inlet should be located in such a way
that minimum submergence requirements are met as per IS 9761:1995.
Hydraulic design calculation of Power Intake and Trash Rack are given in Annexure-7-2 and
7-3 respectively.
Average cross sectional area of river from crest elevation to MDDL for initial 300 m reach of
reservoir is about 1600 sqm. This area will be increased to about 3000 sqm for reservoir
upto FRL.
Limiting discharges have been worked out by trial and error for flow through velocity of 25
cm/s and 35 cm/s corresponding to settling of particles of coarser than 0.2 mm and 0.3 mm
respectively.
Velocities are worked out for various discharges and tabulated below.
Required length of reservoir for settlement of particles coarser than 0.2 mm has been
worked out as about 220 m for MDDL operating conditions and 340 m for FRL conditions.
The length of reservoir is about 1.2 km and a reservoir of 300-400 m length may be
considered as desilting chamber.
From the above table, it may be seen that the reservoir will work as a desilting chamber for
removal of >= 0.2 mm and >=0.3 mm particle for maximum discharge of 400 cumecs and
550 cumecs respectively for MDDL operations.
It is expected that during high flows, the silt concentration will be high and will require shut
off the plant. Therefore even provision of desilting chamber along the diverted water
conductor system, the plant needs to be shut-off.
Continuous silt flushing shall be made through closest spillway gate by releasing minimum
environmental flow of 30% of inflow. Also, reservoir flushing will be carried out prior and
after the monsoon with drawdown of reservoir. However, detailed studies will be carried out
at detailed design stage and to be verified by physical model test.
In view of the above, desilting arrangement has been proposed through reservoir itself in
lieu of separate desilting chamber.
1,600
1,400
1,200
1,000
800
600
400
200
-
2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0
HRT Diameter (m)
In Mawphu HEP (Stage-II), the size of the tunnel is 4.8m. The size of the tunnel also
influences the shape of the tunnel. Circular shaped tunnel is hydraulically and structurally
suitable but it does not satisfy the functional requirements. D-shaped tunnel is appropriate
from hydraulic and functional point of the view whereas it is not suitable from structural point
of view. Therefore, horse-shoe shape which provides sufficient base for construction facility
and is hydraulically as well as structurally suitable, has been adopted for HRT.
In view of the surface works of power intake, the intake portal may not be available for
construction of HRT throughout the time and therefore the HRT may fall on critical path.
Being underground excavation, any unforeseen adverse geological conditions may push put
this activity on further criticality. In view of this, an intermediate adit of D-Shaped, 6m dia and
78m long has been provided at RD. 862m. The junction of adit divides the HRT as 873 m
upstream up to intake and 1749 m downstream upto surge shaft. The HRT follows along the
right hill slope and maximum rock cover available along the alignment is around 250m.
The supporting system comprises of rock bolts, SFRS and steel ribs as mentioned in Table
7-17 In the class-IV and V zones, pre-grouting with microfine cement may be required.
DPR-I: Chapter-7: Civil Engineering Structure 7-37
MAWPHU HEP, STAGE – II
Forepoling, will be resorted as per requirement while boring in class V type of rock. Probe
drilling shall be resorted for identifying the problem areas and suitable prior remedial
measure shall be kept ready before hand.
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
I – Very Good
rock RMR: Generally no support required except spot bolting and
0
100-81 SFRS at local region.
Q: 100 to 40
II – Good rock 4m long
50mm in
RMR: 80-61 40 rock bolt, 5 2.0 m Nil
crown
Q: 40 to 10 Nos
III – Fair rock 100 mm 4m long
RMR: 60-41 45 in crown rock bolt, 7 1.75 m Nil
Q: 10 to 4 and sides Nos
4m long Lattice Pre-grouting
IV – Poor rock 100 mm
rock hollow Girder @ with micro
RMR: 40-21 10 in crown 1.5 m
core SDA, 9 1000 mm fine cement
Q: 4 to 1 and sides
Nos c/c
Pre-grouting
4m long
V – Very Poor 100 mm ISHB 150 & Fore-
rock hollow
rock RMR: <20 5 in crown 1.5 m @ 500 mm poling 32
core SDA, 9
Q: 1 to 0.1 and sides c/c dia, 6m long,
Nos
3m c/c
PCC concrete lining of 250 thick has been provided. Reinforcement will be required in the
concrete lining in low cover areas, adit junctions, vicinity of surge shaft and geologically
weak reaches. A provision of reinforced lining in 130m (about 5%) of tunnel length has been
kept.
Consolidation grouting is provided in class-IV and V and contact grouting is provided for the
entire length of the tunnel.
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
I – Very Good
rock RMR: Generally no support required except spot bolting and
0
100-81 SFRS at local region.
Q: 100 to 40
II – Good rock 4m long
50mm in
RMR: 80-61 20 rock bolt, 5 2.0 m Nil
crown
Q: 40 to 10 Nos
III – Fair rock 100 mm 4m long
RMR: 60-41 65 in crown rock bolt, 7 1.75 m Nil
Q: 10 to 4 and sides Nos
4m long Lattice
IV – Poor rock 100 mm
rock hollow Girder @
RMR: 40-21 10 in crown 1.5 m
core SDA, 9 1000 mm
Q: 4 to 1 and sides
Nos c/c
4m long
V – Very Poor 100 mm ISHB 150
rock hollow
rock RMR: <20 5 in crown 1.5 m @ 500 mm
core SDA, 9
Q: 1 to 0.1 and sides c/c
Nos
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
I – Very Good
rock RMR: Generally no support required except spot bolting and
0
100-81 SFRS at local region.
Q: 100 to 40
II – Good rock 4m long
50mm in
RMR: 80-61 20 rock bolt, 5 2.0 m Nil
crown
Q: 40 to 10 Nos
III – Fair rock 100 mm 4m long
RMR: 60-41 70 in crown rock bolt, 7 1.75 m Nil
Q: 10 to 4 and sides Nos
IV – Poor rock 10 100 mm 4m long 1.5 m Lattice
RMR: 40-21 in crown rock hollow Girder @
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
core SDA, 9 1000 mm
Q: 4 to 1 and sides
Nos c/c
V – Very Poor Not
rock RMR: <20 0 Available
Q: 1 to 0.1
Details of Head Race Tunnel are given in the below drawings:
Niches are proposed in the HRT for the convenience of the vehicle crossing and temporary
storage of the materials and these niches will be backfilled with lean concrete.
In the case of Mawphu HEP (Stage-II), L=2622m and H = 232m, giving L/H of 11.30.
b. Another criterion is based on the acceleration time of the hydraulic system. The
acceleration time (Ta) of a hydraulic system is given by the equation
Therefore, in Mawphu HEP (Stage-II), out of above two types of surge tanks, orifice type
tank, being advantageous compared to simple tank, is provided.
A factor of safety of 1.60 has been considered as per IS: 7396 (Part-1)-1985, which yields an
area of 16.12 m2 equivalent to 4.53m dia. Accordingly, a 10.0m dia surge shaft has been
provided.
Transient conditions have been analyzed using the computer program 'WHAMO' (Water
Hammer and Mass Oscillation) developed by US Army Corps of Engineers. WHAMO
provides dynamic simulation application of fluid distribution systems in hydro power plants.
The transient analysis has been carried out to determine the maximum upsurge and down
surge levels in the surge tank with respect to different loading/unloading of generating units
corresponding to load acceptance and load rejection conditions when reservoir is at FRL
(EL. 470 m) and at MDDL (EL. 460 m).
The surge levels have been computed with respect to the 100% load rejection and
acceptance and various other combinations of specified load acceptance and rejection to
arrive at the maximum and minimum water levels anticipated in the surge shaft, under worst
conditions as per IS: 7396.
Result of transient analysis using WHAMO is given in Table 7-21.
Table 7- 21 Results of Surge Analysis
Upsurge
Downsurge
Graphs showing the Water Surface Elevations Vs Time for each loading case are given
below.
Considering a free board of 3.0 m, top of the surge shaft is kept at EL. 492.00 m MSL and
adequate water cushion below the minimum down surge level, bottom of the surge shaft at
EL. 438.00 m MSL. The diameter of orifice is adopted as 2.80 m.
In the proposed surge shaft location, the slope of the natural surface is in the range of 25 to
30 degree. Based on the drill hole data in the location and in the pressure shaft alignment,
about 27m thick overburden is expected in the proposed location. Therefore, the whole
overburden is required to be removed and the surge shaft is provided in the in-situ rock.
The overburden slopes mentioned above would contain rock blocks of partially disintegrated
rock confined within a clayey matrix. While excavating these zones instability is anticipated
to get initiated, especially when the material will be saturated. As such the dressed slopes
need to be provided with suitable drainage and soil anchors for stability.
DPR-I: Chapter-7: Civil Engineering Structure 7-45
MAWPHU HEP, STAGE – II
From El 507m to El 492m i.e. top of the surge shaft, the excavation shall be in moderately
strong, moderately to highly weathered granite gneiss with biotite schist banding. As no
major shear zone was encountered during drilling as such no serious difficulty during the
excavation of shaft is anticipated. In general there is an improvement in rock strength,
weathering and opening of the joints with the depth barring few exceptions at EL.491m,
EL.482m, EL472m, EL.451m and EL.436m where RQD has been found to be low though the
recovery remains constantly high. In such area provision of consolidation grouting shall be
required for ground improvement.
Considering the nature of rock encountered in drill holes and observed rock mechanic
parameters, it is anticipated that the major part of Surge shaft shall negotiate fair to good
rock with occasional patches of poor rock. The suitable rock support consists of rock bolts,
SFRS and pressure relief holes shall be installed concurrent to excavation.
It is assessed that in the initial and terminal part of the surge shaft excavation would require
circular steel set tied firmly to each other along periphery with back fill concrete in view of the
observed weakness especially in these two areas.
Provision for consolidation grouting for 50% of the height & contact grouting for the entire
height is made to strengthen rock mass around the surge shaft and to achieve proper
contact between shotcrete, concrete lining and the rock surface.
The diameter of the branch pressure shafts have been fixed in such a way that the velocity is
in line with the main pressure shaft. Velocity through pressure shaft works out to around
3.71m/sec.
In the old PFR, surface penstock was proposed. Considering thick overburden and vertical
bends throughout the surface alignment, underground pressure shaft is proposed. Two
alternatives, one, connecting the top and bottom horizontal pressure shaft with an inclined
shaft and another, connecting the two with a vertical shaft were examined. It was found that
the length of the bottom horizontal pressure shaft is relatively less with an inclined shaft and
is suitable from economic considerations. However, from construction point of view, as
vertical pressure shaft is preferable, the same is proposed. The general layout of the
pressure shaft is given in Fig 7-20 and L-Section in Fig 7-21.
Steel liner for pressure shaft has been discussed in H & M chapter.
The vertical pressure shaft shall pass through rock with superincumbent cover including
overburden of 84m near top bend of pressure shaft EL. 490.5m. The subsurface information
from exploration and results of rock mechanic tests indicate that sufficient and suitable
vertical as well as lateral rock cover exist around vertical pressure shaft and is anticipated to
negotiate generally fair to good rock with occasional weak features.
The bottom horizontal pressure shaft shall pass through rock with superincumbent cover
including overburden varying from 230m near vertical pressure shaft side to 72m near power
house side. For the first 540m of bottom pressure shaft, rock cover above structure can be
varying between 37m (EL. 272.5 m) near power house and 205.9 m (EL. 480.7m) near
vertical pressure shaft. The subsurface information from exploration and results of rock
mechanics test indicate that sufficient rock cover exists over the structure and bottom
horizontal pressure shaft is anticipated to negotiate generally very good rock with
intermediate length of fair and patches of poor to very poor rock class as 68% in class-II,
25% in class-III, 5% in class-IV and 2% in class-V for the first 540m length and 20% in class-
II, 65% in class-III, 10% in class-IV and 5% in class-V.
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
I – Very Good
rock RMR: Generally no support required except spot bolting and
0
100-81 SFRS at local region.
Q: 100 to 40
II – Good rock 2.5m long
50mm in
RMR: 80-61 60 rock bolt, 5 2.0 m Nil
crown
Q: 40 to 10 Nos
III – Fair rock 100 mm 2.5m long
RMR: 60-41 30 in crown rock bolt, 7 1.75 m Nil
Q: 10 to 4 and sides Nos
2.5m long Lattice Pre-grouting
IV – Poor rock 100 mm
rock hollow Girder @ with micro
RMR: 40-21 6 in crown 1.5 m
core SDA, 9 1000 mm fine cement
Q: 4 to 1 and sides
Nos c/c
Pre-grouting
2.5m long
V – Very Poor 100 mm ISMB 200 & Fore-
rock hollow
rock RMR: <20 4 in crown 1.5 m @ 500 mm poling 32
core SDA, 9
Q: 1 to 0.1 and sides c/c dia, 6m long,
Nos
3m c/c
Lengt Remarks
Rock bolt (25Ø)/ Anchors
h Steel Ribs/
Rock mass SFRS
Longitudina Lattice
Rating (mm)
% Length (m) l Spacing Girder
(m)
I – Very Good
rock RMR: Generally no support required except spot bolting and
0
100-81 SFRS at local region.
Q: 100 to 40
II – Good rock 1.5m long
50mm in
RMR: 80-61 20 rock bolt, 5 2.0 m Nil
crown
Q: 40 to 10 Nos
III – Fair rock 100 mm 1.5m long
RMR: 60-41 65 in crown rock bolt, 7 1.75 m Nil
Q: 10 to 4 and sides Nos
1.5m long Lattice Pre-grouting
IV – Poor rock 100 mm
rock hollow Girder @ with micro
RMR: 40-21 10 in crown 1.5 m
core SDA, 9 1000 mm fine cement
Q: 4 to 1 and sides
Nos c/c
Pre-grouting
1.5m long
V – Very Poor 100 mm ISMB 150 & Fore-
rock hollow
rock RMR: <20 5 in crown 1.5 m @ 500 mm poling 32
core SDA, 9
Q: 1 to 0.1 and sides c/c dia, 6m long,
Nos
3m c/c
To facilitate pressure shaft construction activities, one adit (Adit-2A) (taken as a branch from
Adit-2 to HRT) is provided at top horizontal pressure shaft downstream of the surge shaft.
One erection chamber of size 8m x 8m x 8m is provided at top end of vertical pressure shaft
to facilitate ferule erection activities. One adit, Adit-2B (another branch from Adit-2 to HRT)
is provided to access the erection chamber.
Another adit (Adit-3) is provided to bottom horizontal pressure shaft (downstream of the
bottom end of vertical pressure shaft) to facilitate construction of the same. Considering the
topography of the pressure shaft area, as suitable level for Adit-3 portal is not available
nearby, Adit-3 is required to be kept a bit away from the pressure shaft alignment.
All the three adits (Adit-2A, 2B and 3) provided for the pressure shaft are of 6m dia, D-
Shaped and 108m, 81m and 455m long respectively.
Control Block of size 11.80 m (L) x 16 m (B) x 23.50 m (H) is provided on the left side of the
Power House. Transformer/GIS Hall of size 59.42 m (L) x 12 m (B) x 18 m (H) is proposed
upstream of the Machine Hall. 51m long tailrace channel including Recovery Bay is
proposed to discharge Power house water back into the Umiew River.
Power House plan at Service Bay level is given in Fig 7-22 and the Cross Section through
centre line of Unit is given in Fig 7-23.
Two geological sections have been developed w.r.t the power house for better appraisal of
geological and geotechnical conditions. It is evident from these section that height of cutting
in the rock will around 38m whereas in overburden it will be of the order of 45-
50m.Coefficeint of permeability in overburden ranges from 0.29X10-3cm/sec to 2X10-3cm/sec
which indicate highly pervious nature of overburden. Since overburden is of river borne
material indicative of a pre-existing river terrace, presence of water table at a depth of 12-
14m will make this material more susceptible to instability. Accordingly in view of very high
rainfall, the project area receives , elaborate and effective slope stabilisation measure to
avoid surcharging of the overburden and erosion of slope due to storm water shall be
adopted to maintain long term stability of the cut slope.
Surface power house has been placed suitably with respect to strike of foliation. However in
view of sub parallelism of width wise excavation line of service bay viz-a –viz. the strike of
foliation and dip of foliation being towards excavation, plane failure is anticipated. In view of
the same notwithstanding the limited cutting at service bay section appropriate support
measures needs to be kept in provision which would include 6m long rock bolts with spacing
of 2 to 3m.
Apart from this foliation, S2(030/71) joint set striking almost parallel to the power house
alignment ,dipping steeply from upstream wall of power house towards the power house pit
and has the potential to create unstable wedge due to toppling effect in the upstream wall.
The set combining with other limiting planes would generate plane failure on the downstream
wall of Power house. Accordingly necessary support measure should be kept in provision of
suitable length of rock bolt, SFRS and pressure relieve arrangement. In view of
predominance of adversely oriented joints enhancement of support in the form of longer rock
bolts exceeding 6m may have to be installed in the top one third portion of rock slope.
However the same shall be decided during the progressive excavation of the pit.
As can be seen from slope stability analysis for back slope, set S2 (030/71) is seem to
contribute in formation of unstable wedges by topple failure which have a tendency to fail
toward the valley side or into the excavation. Apart from this toppling failure sliding wedge
failure also expected to be occur for the given cut slope by intersection of the joint set
S4(172/80) and joint set S3 (261/78) in which sliding direction of wedge is 222/75.
Permeability in rock ranges from 2-5 Lugeon indicating its fairly tight nature of
discontinuities. However, higher Lugeon reported only from the overburden bedrock
interface or from the fractured zones. Accordingly pressure relieve arrangement in each wall
of the power house shall be made.
Generally Core recovery in rock vary from 80-95% and RQD vary from 30-80%.In view of
above during excavation in selected weak media consolidation grouting shall be resorted.
However Rock mechanics test conducted on the cores samples from Power House area
reveals the UCS value of 106 to 137 MPa. It is therefore concluded that foundation of the
surface power house shall be in sound rock.
The entire excavation for Power house pit shall be in bedrock having indicative RMR
(without rating adjustment) ranges from 50 To 59 computed on the basis of geotechnical
parameter collected from the outcrops and collating the finding from boreholes DH-101 and
DH-102 in which bedrock was encountered at El 268.6m and 262.2m respectively.
and discharge the rain water to a suitable location. Cut slope of 1 (H) : 6(V) has been
planned for the rocky starta with adequate slope support in the form of SFRS, Anchor bolts
and Drainage holes with filters.
The basic dimensions of the Power House Complex are given in Table 7-27.
Table 7-27 Basic Dimensions of the Power House
1. Length 53.8 m
The Machine Hall consists of various floors at different levels for housing the electro-
mechanical equipments. The centre line of turbine spiral casing is set 4000 mm below the
minimum tail water level (TWL) of EL.231m. The various floor levels are as given in the
table below:
Floor at EL. 224.00m: MIV Floor Level-This floor level houses two numbers
of spherical type valves & their associated piping,
operating mechanism and hydrostatic lubrication
system. A runner removal gallery has been provided
adjacent to MIV. Two hatches have been provided in
the floors above MIV floor to facilitate the removal of
runner and installation/maintenance of MIV
respectively.
Floor at EL.230.50m: Turbine Floor Level- The area available between the
units is utilized to accommodate oil pressure system
for main inlet valve operation. There are two hatches
near the upstream wall – one for the runner and other
for the spherical valve removal.
Floor at EL. 235.00m: Generator Floor- This floor houses bus duct, LAVT
cubicle, excitation transformer, brake and carbon dust
collection unit and neutral grounding cubicle. The oil
pressure unit for turbine is also located on this floor.
DPR-I: Chapter-7: Civil Engineering Structure 7-58
MAWPHU HEP, STAGE – II
7.11.4.4.1 General:
The water from the turbines shall be discharged back into the Umiew River through Draft
Tubes, Tail Pool and Tail Race Channel. The width of the each draft tube is 4.50 m at B-
Line. The length of the Tail Pool is 35m and width is varying from 27m to 8m. At the end of
the Tail Pool, a control section (Broad crested weir) which is having 8m length across the
flow with finished level of 230.20m has been envisaged. The same has been selected
based on the available minimum river bed level near Tail Race outfall level at 230m.
DPR-I: Chapter-7: Civil Engineering Structure 7-59
MAWPHU HEP, STAGE – II
The finished invert elevation of Tail Pool near the Draft Tubes is 221.54 m and the Tail Pool
invert is kept at an adverse slope till it reaches at control section at an elevation of 230.20 m.
The Tail Pool will have vertical RCC guide walls on both the sides. After the Tail Pool, a Tail
Race Channel shall be provided to discharge water finally into the Umiew River. The Tail
Race Channel up to the river bank is about 17m long and 8m wide.
The minimum tail water level is EL. 231.00 m and the normal tail water level is EL. 232.00 m.
Two draft tube gates of size 4.50 m (W) x 2.35 m (H) are provided at the end of the draft
tube. These gates will be operated by gantry crane.
The initial part at NSL exhibits consistent presence of overburden material characterized by
the presence of recent fluvial material constituted of sand gravel silt etc where as terminal
stretch of TRC is seem to be occupied by outcrops of gneiss.
Minimum excavation level from at draft tube is El ± 219 m from where channel approaches
further through recovery bay with reverse gradient to meet the river at EL ± 230m.
The entire excavation for recovery bay and TRC shall be in bedrock having indicative RMR
(without rating adjustment) ranges from 50 To 59 computed on the basis of geotechnical
parameter collected from the outcrops and collating the finding from boreholes DH-101 and
DH-102 in which bedrock was encountered at El 268.6m and 262.2m respectively.
In view of this it opined that tail race system including the recovery bay shall be on bed rock
constituted of slightly weathered strong to very strong, moderately jointed, grey gneiss.
To minimize the effect of some of these adversely oriented joints on excavation particularly
on the western wall, systematic rock support with rock bolts of 25mm Ø ,4 to 6m long with
spacing of 2m center to center, adequate thickness of SFRS, and pressure relief
arrangement shall require to be installed concurrent to the excavation. Furthermore,
provision of consolidation grouting shall be made as ground improvement measure.
Fig7-24 River Layout near Power House from the HEC-RAS Software
Head losses in the HEC RAS system are accounted for by bulk Manning coefficients and
other geometric properties e.g. contraction and expansion coefficients multiplied by changes
in velocity head of the river. Manning’s values were estimated from physical data about the
stream and flood plain. Adopted coefficient values varied from transect to transect
depending on factors such as channel roughness, alignment, vegetation, presence of deep
pools, channel irregularities etc. An average value of 0.04 is considered in the analysis.
Boundary conditions are necessary to establish the starting water surface at both ends of the
river stream. In the absence of gauge discharge curve, the upstream and downstream
boundary conditions were assumed to be a normal flow depth Mixed flow analysis (allowing
for supercritical and subcritical flow within the reach) were undertaken.
The analysis involves the solution of the partial differential equations of mass and
momentum to predict the movement of water in the Umiew River using the detailed
knowledge of the river geometry at a discrete number of points along the river that was
generated during the cross sections survey. The theoretical basis and detailed equations
employed by the HEC‐RAS system to compute one dimensional surface profiles are
extensively documented in the Hydraulic Reference Manual.
For purposes of computing the tail water rating curve at the proposed power house site,
steady state hydraulic computations were performed for PMF discharge profile.
The tail water rating curve at PMF flow at Power House site for Mawphu HEP (Stage-II) is
developed from the software. This curve is given below.
248
Legend
244
242
W.S. Elev (m)
240
238
236
234
232
230
0 2000 4000 6000 8000 10000
Q Total (m3/s)
The River cross section at RD.2000 m, near Power House at PMF flow below the proposed
Mawphu HEP (Stage-II) is developed from the software.
EG PF 2
270 Crit PF 2
WS PF 2
Ground
260
Elevation (m)
Bank Sta
250
240
230
0 100 200 300 400 500
Station (m)
The maximum observed flood value in last 25 years is 248 cumecs. The dam falls in the
category of large dam and therefore, the dam and spillways have been designed for PMF of
8900 cumecs. It is expected that the SPF will be of the order of 6000 cumecs accordingly the
Service Bay level has been decided.
As it is evident from the HEC-RAS analysis, the High Flood Level (HFL) corresponding to
6000 cumecs discharge is 239.50m at Power House location. A free board of about 1m has
been considered and Service Bay level has been kept at EL. 240.50m.
7.12 Instrumentation
Instrumentation is proposed in order to monitor the behavior of various components of
the project at various stages:
Piezometers are used to measure pore water pressure in the foundations, concrete structure
or in overburden of a tunnel. Pore pressure gauges are provided in the spillway bay to
measure the pore water pressure. The same have also been proposed in the Power House.
Joint Meters
Joint meters are provided in the joints between the blocks of the Dam to measure the
movement between the concrete blocks.
Tilt Meter
Tilt meter is attached to the structures for monitoring tilting of the structures. These
instruments are provided in all piers and abutments.
Water Level Recorder
The automatic and mechanical type water Level Recorders are proposed in the Dam. These
instruments are provided in the upstream and downstream of the proposed dam site to
record the water levels.
Load Cell
These are used to determine the loads carried by the rock bolt and rock anchors. These
instruments are provided in Power Intake, Water Conductor System and Power House
Complex.
Multi-Point Bore Extensometer (MPBX)
MPBX having three points (overt and side walls) have been proposed to be installed in the
underground excavation to measure sub-surface displacements in the rock mass
surrounding the excavation.
Tape Convergence Stud
For measurement of the earth quake vibrations in the project area and consequent damage
to the structure, Strong motion Accelerograph has been proposed with triaxial sensors
located at various points in the Dam and in the free field.
Plumb Line
Direct plumb line has been proposed to be installed in the dam block to measure any tilt of
dam structure. Similarly inverted plumb line has been proposed in gravity dam block to
measure any displacement of the dam block with respect to a stable rock in the foundation
below.
Inclinometer
Inclinometers have been proposed in both left and right bank of the valley at dam site and at
different locations in the hill nose cutting upstream of the dam. These instruments will give a
measurement of the lateral movements at different depths.
Shotcrete Radial Pressure Cell and Shotcrete Strain Gauge
These are used to measure stress and strain in the shotcrete and these have been proposed
in the Diversion tunnels and Pressure shaft tunnels at various locations along the length of
the tunnels.
Stress Meters, Strain Meters and No Stress-Strain Meters
Stress meters, Strain meters and No Stress-Strain meters will measure the stress and strain
developed inside the mass concrete and these may help in watching the structural behavior
of the various structures and their foundations. Any adverse change in stress-strain will
indicate the stress condition and accordingly timely remedial measures can be under taken.
Installation of Stress Meter, Strain Meter and No Strain-Stress Meter are proposed in groups
at various locations in the gravity dam, power house complex and other places.
Temperature meters have been provided to measure temperature gradient across concrete
to assess resultant stresses, if any.
Armored mutlicore cables shall be used for all wiring and SDI-12 digital interfaces used to
convert the instrument signals to digital form for easy communication of signals from all
sensors over just a 3-core or 6-core cable system up to the dam top.
All instrument data shall be monitored automatically through a Data Acquisition System
located on the dam top control room. The data shall be transmitted in real time automatically
through the internet and made available to project authorities and their authorized personnel
round the clock, anywhere around the world.
The detailed technical specifications of various instruments shall be finalized during design
stage.
Annexure- 7-1
Hydraulic Design of Dam Spillway (Breast wall type spillway) Ogee type
Spillway Bays:
Crest Level of Spillway
443 443 m
Bay =
Assumed no. of Spillway
6 5 no.
Bays =
Width of each bay = 9 9 m
Height of each bay = 12 12 m
Bottom level of Breast wall in
455 455 m
spillway bay =
Assumed width of piers with
5 5 m
joint =
No. of piers with joint = 2 2 no.
Assumed width of piers without
3 3 m
joint =
No. of piers without joint
5 3 no.
=
Total Length of Overflow
79 m
Section including end piers =
Design Calculation:
1 Size of Spillway Bays:
a Considering all bays:
bay
6 9 m each 54 m
s of
Pier
2 5 m each 10 with joint
of
DPR-I: Chapter-7: Civil Engineering Structure 7-68
MAWPHU HEP, STAGE – II
Pier without
5 3 m each 15
of joint
Total length of Overflow Section = 79 m
Width of Flow = 73 m
Considering 1 Gate
b
inoperative:
bay
5 9 m each 45 m
s of
Pier
2 5 m each 10 with joint
of
Pier without
3 3 m each 9
of joint
Discharge through
ii
Spillway Bays:
Opening height, D = 12.00 12.00 m
Coefficient of
a
Discharge:
The coefficient of the discharge Cb is calculated based on H/Hd as per
cl:6.5.1 IS 6934:1998
Q = Cb * L*D*(2g*(Hc+
10644 8975 cumecs OK
(Va2/2g)))0.5
cumecs/
Discharge per 'm' width q = 197.11 199.44
m
Annexure- 7-2
1 Design Input:
Full Reservior Level, FRL = 470 m
Minimum Draw Down Level, MDDL = 460 m
Turbine setting level/Min TWL = 205.3 m
Number of Intakes = 1
b Size of opening:
b2 = 0.2143be 1.29 m
b2 provided = 0.75 m
c Shape of Opening:
i Profile of the roof and floor:
X2 Y2
1
(1.1D ) 2 ( 0.291D ) 2
a1 = 1.1D 5.28 m
b1 = 0.291D 1.40 m
X2 Y2
1
(0.55be ) 2 (0.2143be ) 2
a2 = 0.55 be 3.30 m
b2 = 0.2143 be 1.29 m
Annexure- 7-3
1 Design Input:
Design Discharge, Q = 35.72 cumec
Provision of Desilting Chamber = NO
No. of Trash Rack = 1.00 no.
Discharge through each trash rack with 10%
39.29 cumec
0verload=
Minimum Draw Down Level = 460.00 m
Centre line of intake = 454.00 m
Sill level of Trash Rack = 452.00 m
No. of Trash Rack Panel = 2.00 no.
Clear Width (assumed) of each panel = 5.00 m
2 Design Calculations:
a Trash Rack Arrangement:
Total width (clear) of all the panels of Trash Rack = 10.00 m
Thickness of mid pier = 2.00 m
No. of mid piers = 1.00 no.
Thickness of end pier = 2.00 m
Top of Intake = 472.00 m
Top level of bell mouth opening = 461.00 m
Sill level of trash rack provided = 452.00 m
Height (vertical) of Trash Rack arrangement from top
9.00 m
of Slab =
Height (vertical) of Trash Rack arrangement from
8.00 m
MDDL =
Angle of Trash Rack with vertical = 10.00 deg
Actual Length (inclined length) of Trash Rack = 8.12 m
Net height of Trash Rack without beam = 8.12 m
Total width of Intake including end piers = 16.00 m
c) Considering no clogging
Area for no clogging, Anet = 56.86 m2
Velocity based on no clogging, V = 0.691 m/sec
Annexure- 7-4
Ste
Rock Rock el Rein
Exacavti Exacavati Concre Shotcre Rock Reinf. Cont. Cont. Consoli. Consoli.
Concrete Shotcrete Rock Bolt Anch Anchor Rib Steel Ribs f. Total Cost
Diameter (m) on Qty on Cost te Qty te Qty Bolt Cost Grouting Grouting Grouting Grouting
Cost (Rs) Cost (Rs) Cost (Rs) or Qty Cost s Cost (Rs) Qty (Rs)
(cum) (Rs) (cum) (cum) Qty (m) (Rs) (m) Cost (Rs) (m) Cost (Rs)
(m) (Rs) Qty (t)
(t)
1,7 3,588,6 7,8 184,539,6
3.0 34539 78367993 5567 28739979 3045 43284675 5015 3896325 1180 939200 70 6896210 30 2543993 16,282,620
48 44 66 39
2,6 5,382,9 7,8 201,203,7
3.2 38270 86834342 5914 30536227 3219 45758085 6686 5195100 1573 1252267 74 7259168 32 2702993 16,282,620
22 66 66 68
2,6 5,382,9 7,8 214,895,9
3.4 42193 95734862 6262 32332476 3393 48231495 6686 5195100 1573 1252267 77 7622127 33 2861992 16,282,620
22 66 66 05
2,6 5,382,9 10,48 234,449,7
3.6 46307 105069554 6610 34128725 3567 50704905 6686 5195100 1573 1252267 81 7985085 35 3020992 21,710,160
22 66 8 53
2,6 5,382,9 10,48 249,010,2
3.8 50612 114838417 6958 35924973 3741 53178315 6686 5195100 1573 1252267 85 8348044 37 3179991 21,710,160
22 66 8 33
2,6 5,382,9 10,48 280,704,5
4.0 57429 130305784 9241 47712855 4001 56874215 6686 5195100 1573 1252267 90 8892481 40 3378741 21,710,160
22 66 8 69
2,6 5,382,9 10,48 298,411,3
4.2 62212 141160077 9676 49958166 4175 59347625 8358 6493875 1967 1565334 94 9255440 41 3537740 21,710,160
22 66 8 83
2,6 5,382,9 10,48 314,940,5
4.4 67188 152448541 10111 52203477 4349 61821035 8358 6493875 1967 1565334 98 9618398 43 3696740 21,710,160
22 66 8 26
2,6 5,382,9 10,48 331,903,8
4.6 72354 164171177 10546 54448788 4523 64294445 8358 6493875 1967 1565334 101 9981356 45 3855740 21,710,160
22 66 8 41
2,6 5,382,9 10,48 349,301,3
4.8 77712 176327985 10981 56694099 4697 66767855 8358 6493875 1967 1565334 105 10344315 47 4014739 21,710,160
22 66 8 28
3,4 7,177,2 13,11 394,732,5
5.0 86107 195377269 13829 71400885 4958 70477970 8358 6493875 1967 1565334 110 10888752 49 4213489 27,137,700
96 88 0 61
3,4 7,177,2 13,11 413,664,5
5.2 91943 208619506 14351 74095258 5132 72951380 8358 6493875 1967 1565334 114 11251711 51 4372488 27,137,700
96 88 0 39
3,4 7,177,2 13,11 434,642,5
5.4 97971 222295915 14873 76789631 5306 75424790 10029 7792650 2360 1878401 118 11614669 53 4531488 27,137,700
96 88 0 31
3,4 7,177,2 13,11 454,442,8
5.6 104190 236406495 15395 79484004 5480 77898200 10029 7792650 2360 1878401 122 11977628 55 4690487 27,137,700
96 88 0 53
DPR-I: Chapter-7: Civil Engineering Structure 7-75
MAWPHU HEP, STAGE – II
Design Input:
Economical Diameter
Net
Annual Annual Total
Total Cost Annual Head Energy Cost of Cost
Diameter (m)
(Rs) Charges (Rs) Loss (m) Loss @ Energy Annual
Specified Loss (Rs) (Rs)
PLF (MU)
184,539 2 147,921,
3.0 17.16 21.13
,639 7,680,946 953 1,756
201,203 3 104,972,
3.2 12.18 15.00
,768 0,180,565 801 1,352
214,895 3 76,067,
3.4 8.82 10.87
,905 2,234,386 120 1,083
234,449 3 56,150,
3.6 6.51 8.02
,753 5,167,463 774 913
249,010 3 42,138,
3.8 4.89 6.02
,233 7,351,535 982 795
280,704 4 32,095,
4.0 3.72 4.59
,569 2,105,685 681 742
298,411 4 24,775,
4.2 2.87 3.54
,383 4,761,707 123 695
314,940 4 19,357,
4.4 2.25 2.77
,526 7,241,079 609 666
331,903 4 15,292,
4.6 1.77 2.18
,841 9,785,576 776 651
349,301 5 12,204,
4.8 1.42 1.74
,328 2,395,199 260 646
394,732 5 9,830,
5.0 1.14 1.40
,561 9,209,884 349 690
413,664 6 7,986,
5.2 0.93 1.14
,539 2,049,681 246 700
434,642 6 6,539,
5.4 0.76 0.93
,531 5,196,380 619 717
454,442 6 5,394,
5.6 0.63 0.77
,853 8,166,428 466 736
474,677 7 4,480,
5.8 0.52 0.64
,346 1,201,602 304 757
519,387 7 3,744,
6.0 0.43 0.53
,538 7,908,131 800 817
546,584 8 3,148,
6.2 0.37 0.45
,063 1,987,609 699 851
DPR-I: Chapter-7: Civil Engineering Structure 7-77
MAWPHU HEP, STAGE – II
568,787 8 2,662,
6.4 0.31 0.38
,219 5,318,083 264 880
594,830 8 2,262,
6.6 0.26 0.32
,711 9,224,607 768 915
617,902 9 1,932,
6.8 0.22 0.28
,211 2,685,332 692 946
669,113 10 1,658,
7.0 0.19 0.24
,224 0,366,984 422 1,020
693,719 10 1,429,
7.2 0.17 0.20
,215 4,057,882 305 1,055
724,186 10 1,236,
7.4 0.14 0.18
,918 8,628,038 937 1,099
749,661 11 1,074,
7.6 0.12 0.15
,253 2,449,188 652 1,135
777,167 11 937,
7.8 0.11 0.13
,386 6,575,108 126 1,175
803,510 12 820,
8.0 0.10 0.12
,064 0,526,510 080 1,213
Minimum 645.995
Annexure- 7-5
Design Input:
Cost of Materials and Energy:
Unit cost of Excavation, Ce = 5234 Rs/cum
Unit cost of Concrete (M15, A40),
5163 Rs/cum
Cc =
Unit cost of Steel, Cs = 177.00 Rs/kg
Cost of 1 kWh Energy, Cp = 6.80 Rs
Efficiency:
Overall efficiency of Plant, e = 0.9212
Joint efficiency of Penstock, ej = 0.95
Grade 3 Material, σa =
From IS 11625-1986, Clause No.6
Economical diameter of Penstock
is given by,
22
2.36 * 10 6 * Q 3 * n 2 * e * p f * C p
D 3
121 * H * C s * (1 i )
(1.39 * Ce ) (0.6 * Cc ) p
a *ej
Annexure 7-5
1 Power Intake:
a Trash Rack Loss: (Clause 4.2 IS : 4880 (Part-III) -1976)
i Without Clogging:
k = (1.45 - 0.45R -R2) 0.65
Gross area of the racks and supports = 81.23 sqm
Net area through the rack bars = 56.86 sqm
Velocity through the Trash Rack opening = 0.63 m/s
R (net area through the rack bars/gross area of the racks 0.70
DPR-I: Chapter-7: Civil Engineering Structure 7-82
MAWPHU HEP, STAGE – II
and supports)
hTrash Rack = k*VTR2/(2g) 0.013 m
b Loss at Entry:
Area, A = 23.04 sqm
Velocity, V = 1.55 m/s
where, ke = 0.20
hentrance = (ke*Vintake2)/2g 0.025 m
Bend-2
Deflection angle, α = 19.00 deg
Radius of Curvature of bend, Rb = 75.00 m
Rb/D = 15.21
k= 0.04
hbend (= k*V2/2g) 0.007 m
3 Surge Shaft:
a Loss due to Gate groove:
Loss co-efficient due to gate, kg = 0.10
Velocity through gate = 2.92 m/s
Head loss due to gate groove = 0.043 m
4 Penstock:
a Loss due to Transition (Downstream of Surge Shaft):
ii Branch Penstock-2:
Area, A = 4.91 sqm
Wetted Perimeter, P = 7.85 m
Velocity, V = 3.64 m/s
Hydraulic mean radius, R = A/P 0.63 m
Manning's Coefficient (as per DPR) = 0.010
2 2 4/3
Loss due to friction ,hf = (v *n *L)/R 0.079 m
Total Friction Loss in Penstock = 1.515 m
Bend-2:
Deflection angle, α = 50.00 deg
Radius of Curvature of bend, Rb = 15.00 m
Rb/D = 4.29
k= 0.10
2
hbend (= k*V /2g) 0.070 m
Bend-3:
Deflection angle, α = 5.00 deg
Radius of Curvature of bend, Rb = 15.00 m
Rb/D = 4.29
k 0.10
hbend (= k*V2/2g) 0.070 m
ii Bifurcation:
Discharge in Branch Penstock, qb = 17.885
Discharge in Main Penstock, q = 35.770
qb/q = 0.500
Angle of divergence = 34.000 deg
Coefficient, k = 0.52
h = (k*V /2g)
2
0.366 m
8. HYDRO-MECHANICAL EQUIPMENTS
8.1. General
Following hydro-mechanical equipments consisting of various types of gates, stoplogs,
hoists, gantry cranes, and steel lined pressure shaft have been envisaged to divert and
control Umiew river waters during construction to regulate reservoir levels and facilitate the
maintenance of the Turbine Generator units and various other components of project during
operation.
Type of Sealing arrangement and seals. Downstream Sealing: Music Note Type
Teflon Cladded Rubber Seal for top &
For 7.0 m horseshoe shaped diversion tunnel, one gate of size 8.0m x 8.0m is proposed at
the inlet portals to facilitate regulation during diversion and plugging before commissioning of
the project. This gate is provided with rope drum hoist and designed as fixed wheel type gate
having downstream skin plate and downstream sealing. The sill level of gate is kept at EL.
446.00m and the gate is to be designed for a head of 24.0m corresponding to FRL El.
470.00m.
The gates shall be of fabricated steel construction consisting of downstream skin plate,
horizontal girders and vertical stiffeners spaced according to design loads, end vertical
girders and wheel assemblies mounted in between end vertical girders. The gate shall have
two lifting points and shall be provided with seals on downstream sides. Side & Top seals
shall be of Teflon Cladded rubber music note type and bottom seal shall be of rubber wedge
type. The Top corner seals shall be provided of minimum 200mm depth.
The rubber seals shall be manufactured and supplied in accordance with IS: 11855: 2004
and IS: 15466: 2004. The seals shall be fastened to gate using stainless steel bolts/counter
sunk screws and nuts. To limit lateral sway of the gate during operation, two guide shoes
shall be provided one on each side of the gate, which will remain engaged with embedded
guides.
On the other hand hoist capacity of the gate is determined for their operation during
diversion and shall be calculated for water head corresponding to Cofferdam top level of El.
457.50m.
The gate is operated by independent electrically operated rope drum hoist of capacity not
less than 120 T consisting of central drive unit (electric motor), reduction units, shaft, rope
drums, etc. Provision in the hoist mechanism shall also be made to operate it manually in the
event of power failure. The hoists shall be installed on Hoist Bridge supported on columns
above top of piers. Access stair cases shall be provided for access to the hoist bridge on
both the sides. Controls for all the hoists shall be housed in a control room located near the
gates. The gates shall also be operated locally from local control panel on regulating
platform supported on columns.
The minimum speeds of travel of gate shall be: for opening 0.50 m/min., for lowering 0.50
m/min. and for last 30 cm, travel in lowering speed of 0.15 m/min.
The gate shall be designed and manufactured in accordance with the provisions made in IS:
4622: 2003 (Recommendations for structural design of fixed wheel gates). Hoist shall fulfill
all the requirements as specified in IS: 6938:2005.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the gate are shown in
Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A01-0101-R0 and 0933-HDC-A01-0102-
R0 respectively.
Stoplog units shall be required to be lowered in the stoplog groove of a particular bay, the
radial gate of which is under inspection/maintenance. The stoplogs shall be lowered under
flowing water conditions and lifted under balanced head condition. Inspection, maintenance
and repairs of radial gate shall be planned to be started and completed preferably in lean
period. Each stop log unit shall be self closing i.e. by gravity under its own weight. The stop
log units shall be handled by a gantry crane of adequate capacity.
For the maintenance of 6 nos. Spillway Radial gates, one sets of stoplogs, each set
consisting of 7 units of size 9.0m x 2.4m shall be provided.
No of Opening 6.0
Type of Sealing arrangement and seals. Downstream Sealing: Music Note Type
Rubber Seal for top & sides and wedge
type seal for Bottom as per IS: 11855 &
IS 15466
When not in use the stop logs shall be stored on latches in the grooves above FRL and one
stoplog storage bay provided on Dam Block No. 2. One no. automatically engaging and
disengaging lifting beam shall be provided to facilitate operation of the stoplogs with the help
of gantry crane.
The stop log units for Spillway Radial gates shall be of fabricated steel construction with
upstream skin plate and downstream sealing. The units shall be capable of use in any of the
6 openings. The stop log units shall normally be lowered in flowing water condition and lifted
in balanced head conditions when water level is at Full Reservoir Level El. 470.00m or below
it. Balance head condition shall be created by providing fill-in valve in the top most unit of
stoplog. All the stop log units except the top unit and bottom unit shall be inter-changeable.
Each Stoplog unit shall be formed by two end vertical girders interspaced with horizontal
girders spaced according to the design loads. The upstream face shall be covered with a
skin plate. The top of each unit is provided with two lifting lugs for engaging and disengaging
automatic lifting beam. Each of five interchangeable Stoplog units and 1 no. bottom unit shall
be provided with the music note type rubber seal for sides and wedge type for bottom. Music
note type rubber seals shall also be provided for sides and top and wedge type rubber seal
for bottom of top unit of Stop logs. The seals shall be fastened to gate using stainless steel
bolts/csk screws and nuts. The rubber seals shall be manufactured and supplied in
accordance with IS: 11855: 2004 and IS: 15466: 2004.
To limit the sway of the gate during operation, two guide shoes shall be provided on each
side of the stoplog units, which will remain engaged with embedded guides.
The stoplog units shall be operated by electrically operated gantry crane of capacity not less
than 35 T consisting of central drive unit (electric motor), reduction units, shaft, rope drums,
etc. Provision in the hoist mechanism shall also be made to operate it manually in the event
of power failure. The hoists shall be installed on gantry structure which can moves on rails at
top of gate grooves. Access stair cases shall be provided for access to the hoist bridge on
both the sides.The minimum speed of travel of gate shall be: for opening 0.50 m/min., for
lowering 0.50 m/min. and for last 30 cm. travels in lowering 0.30 m/min. Provision in the hoist
mechanism shall also be made to operate it manually in the event of power failure.
These stoplogs shall be designed and manufactured in accordance with the provisions made
in IS: 4622: 2003 (Recommendations for structural design of fixed wheel gates).
Gantry Crane shall fulfill all the requirements specified in IS: 3177.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the stoplogs are
shown in Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A02-0201-R0 and 0933-HDC-
A02-0202-R0 respectively.
The Spillway radial gates shall normally remain in closed position during power generation.
When the water level in the reservoir starts rising above the Full Reservoir Level i.e. EL
470.00m the FRL will be maintained by operating these gates. The spillway radial gates shall
also be operated to flush out the deposited silt during the periods of heavy discharges.
No of Opening 6 Nos.
No of Gates 6 Nos.
The sill of gate has been kept at El. 442.90m.The radial gates will be operated by an
hydraulic hoists of adequate capacity; consisting of power pack and shall have twin hydraulic
cylinders one on each side of the gate. The gates shall be operated locally with a power
pack from the control room, which would be located on top of the dam in a room. The
hydraulic cylinder hanging bracket elevation is kept at EL. 461.01m.The cylinder shall be
connects on downstream of the skin plate. The power pack shall have provision to operate
gate of adjacent bays. The trunnion shall be located at EL. 454.80m such that it is at least
1.5 m higher than the nape. Provision in the hoist mechanism shall also be made to operate
it manually in the event of power failure.
In general, each gate shall consist of structural steel frame formed by girders transmitting the
load to radial arms. The skin plate shall be supported on closely spaced vertical stiffeners
transmitting water load to horizontal girders. The horizontal girders shall transmit the load to
load bearing anchors through the arms and trunnion. Anti friction, self-lubricating type
bearings/bushings of make GGB, Deva or Lubrite shall be provided for the trunnion. To
reduce the hoist capacity for the operation of gates, the radius of the radial arms is kept as
large as possible. Radial gate assembly shall be of welded construction, except the
connection between skin plate assembly and arms which will be bolted to facilitate erection
adjustments.
The each radial gate shall be operated by hydraulically operated hoist. The hydraulic hoist
shall be consist of two hydraulic cylinders and a central drive unit. The capacity of each
hydraulic cylinder shall be not less than 150T. Access stair cases and supporting structure
shall be provided for access to the hydraulic cylinders on both the sides. The minimum
speeds of travel of gate shall be: for opening 0.50 m/min., for lowering 0.50 m/min. and for
last 30 cm. travels in lowering 0.15 m/min.
To limit the sway of the gate during operation, guide rollers shall be provided on each side of
the gate. Each radial gate trunnion support beam shall be suitably anchored to the pier. The
gate shall be provided with dogging devices to hold the gate in fully raised position when the
hoist is disconnected from the gate during maintenance.
The radial gates shall have Music note type Teflon cladded rubber seals for side, double
stem type Teflon cladded rubber seal for top and wedge type rubber seal for bottom. The
seals shall be fastened to gate using stainless steel bolts/csk screws and nuts. The seals
shall be designed and manufactured as per IS: 11855: 2004 and IS 15466: 2004.
These radial gates shall be designed in accordance with IS: 4623: 2000 (Recommendations
for Structural Design of Radial Gates) & Hydraulic Hoist shall fulfill all the requirements
specified in IS: 10210.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the radial gate are
shown in Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A03-0301-R0 and 0933-HDC-
A03-0302-R0 respectively.
Each of the ten trash rack sets corresponding to each opening would be aligned along to the
right bank of dam and shall be inclined at 10 degrees with the vertical to facilitate cleaning of
the T-racks mechanically. All the trash rack panels will be kept in a straight line so that one
single unit of trash rack cleaning machine could be used for all the units.
Trash racks panel shall be cleaned with the help of a trash cleaning machine (TRCM) which
shall also have log grappling attachment for removing the trees. The trash cleaning machine
shall be hydraulically operated.
Key plan, General arrangement, Panels and Embedded Parts Details of the trash racks are
shown in Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A04-0401-R0 and 0933-HDC-
A04-0402-R0 respectively.
The Emergency gate shall be provided for emergency conditions in case of malfunctioning of
Intake Service gates and for the maintenance of Service gates.
The gate shall be of fabricated steel construction having upstream skin plate and upstream
sealing. The gate shall be raised in balanced head conditions. So the gate shall have fill-in
valve arrangement to create balanced head conditions. However the gate shall be designed
to close under water flowing condition by gravity and shall have wheel assemblies for
transferring the load.
Side & Top seals shall be of music note type rubber seals and bottom seal shall be of flat
wedge type rubber seals. The rubber seals shall be manufactured and supplied in
accordance with IS: 11855: 2004 and IS: 15466: 2004. The seals shall be fastened to gate
using stainless steel bolts / counter sunk screws and nuts. To limit lateral sway of the gate
during operation, two guide shoes shall be provided on each side of the gate, which will
remain engaged with embedded guides.
The gate is operated by independent electrically operated rope drum hoist of capacity not
less than 20 T consisting of central drive unit (electric motor), reduction units, shaft, rope
drums, etc. Provision in the hoist mechanism shall also be made to operate it manually in the
event of power failure. The hoists shall be installed on Hoist Bridge supported on columns
above top of piers. Access stair cases shall be provided for access to the hoist bridge on
both the sides. Controls for all the hoists shall be housed in a control room located near the
gates. The gates shall also be operated locally from local control panel on regulating
platform supported on columns.
The minimum speed of travel of gate shall be: for opening 0.50 m/min., for lowering 0.50
m/min.
The gate shall be designed and manufactured in accordance with the provisions made in IS:
4622: 2003 (Recommendations for structural design of fixed wheel gates). Hoist shall fulfill
all the requirements as specified in IS: 6938:2005.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the gate are shown in
Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A05-0501-R0 and 0933-HDC-A05-0502-
R0 respectively.
Type of Sealing arrangement and seals. Downstream Sealing: Music Note Type
Teflon Cladded Rubber Seal for top &
sides and wedge type seal for Bottom as
per IS: 11855 & IS 15466
The gate shall be of fabricated steel construction having downstream skin plate and
downstream sealing. The gate shall be raised under unbalanced head conditions. However
gate shall be designed to close under water flowing condition by gravity and shall have
wheel assemblies for transferring the load.
Side & Top seals shall be of music note type Teflon cladded rubber seals and bottom seal
shall be of flat wedge type rubber seals. The rubber seals shall be manufactured and
supplied in accordance with IS: 11855: 2004 and IS: 15466: 2004. The seals shall be
fastened to gate using stainless steel bolts / counter sunk screws and nuts. To limit lateral
sway of the gate during operation, two guide shoes shall be provided on each side of the
gate, which will remain engaged with embedded guides.
The gate is operated by independent electrically operated rope drum hoist of capacity not
less than 30 T consisting of central drive unit (electric motor), reduction units, shaft, rope
drums, etc. Provision in the hoist mechanism shall also be made to operate it manually in the
event of power failure. The hoists shall be installed on Hoist Bridge supported on columns
above top of piers. Access stair cases shall be provided for access to the hoist bridge on
both the sides. Controls for all the hoists shall be housed in a control room located near the
gates. The gates shall also be operated locally from local control panel on regulating
platform supported on columns.
The minimum speed of travel of gate shall be: for opening 0.50 m/min., for lowering 0.50
m/min.
The gate shall be designed and manufactured in accordance with the provisions made in IS:
4622: 2003 (Recommendations for structural design of fixed wheel gates). Hoist shall fulfill
all the requirements as specified in IS: 6938:2005.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the gate are shown in
Drawing No: 0933-HDC-GNL-0001-R0, 0933-HDC-A06-0601-R0 and 0933-HDC-A06-0602-
R0 respectively.
The gate shall be of fabricated steel construction having downstream skin plate and
downstream sealing. The gate shall be raised in balanced head conditions. The gate shall
have fill-in valve arrangement to create balanced head conditions. So the gate shall have fill-
in valve arrangement to create balanced head condition. However gate shall be designed to
close under water flowing condition by gravity and shall have wheel assemblies for
transferring the load.
Side & Top seals shall be of double stem type rubber seals and bottom seal shall be of flat
wedge type rubber seals. The rubber seals shall be manufactured and supplied in
accordance with IS: 11855: 2004 and IS: 15466: 2004. The seals shall be fastened to gate
using stainless steel bolts / counter sunk screws and nuts. To limit lateral sway of the gate
during operation, two guide shoes shall be provided on each side of the gate, which will
remain engaged with embedded guides.
The gate is operated by independent electrically operated rope drum hoist of capacity not
less than 20 T consisting of central drive unit (electric motor), reduction units, shaft, rope
drums, etc. Provision in the hoist mechanism shall also be made to operate it manually in the
event of power failure. The hoists shall be installed on Hoist Bridge supported on columns
above top of piers. Access stair cases shall be provided for access to the hoist bridge on
both the sides. Controls for all the hoists shall be housed in a control room located near the
gates. The gates shall also be operated locally from local control panel on regulating
platform supported on columns.
The minimum speed of travel of gate shall be: for opening 0.75 m/min., for lowering 0.75
m/min.
The gate shall be designed and manufactured in accordance with the provisions made in IS:
4622: 2003 (Recommendations for structural design of fixed wheel gates). Hoist shall fulfill
all the requirements as specified in IS: 6938:2005.
General Arrangement, Seal and Embedded Parts Details of the gate are shown in Drawing
No: 0933-HDC-A07-0701-R0 and 0933-HDC-A07-0702-R0 respectively.
Pressure shaft steel liner with transition, bends, branch pipes, manholes, Thrust collar etc.
having the following data:
The Steel Liner shall be designed for the internal water pressure which includes Static as
well as Dynamic Head and external water pressures corresponding to FRL. The Boiler
Quality / Pressure vessel grade steel has been considered for the fabrication and erection of
steel as per design requirements and codes requirement.
The General Arrangement and Plan of penstock is shown in Drawing No: 0933-HDC-A08-
0801-R0 and 0933-HDC-GNL-0002-R0 respectively.
The gates shall be of fabricated steel construction having downstream skin plate and
downstream sealing considering flow from the Tailrace side. The gate shall be raised under
balanced head conditions. However gate shall be designed to close under water flowing
condition by gravity and shall have wheel assemblies for transferring the load.
Side & Top seals shall be of music note type rubber seals and bottom seal shall be of flat
wedge type rubber seals. The rubber seals shall be manufactured and supplied in
accordance with IS: 11855: 2004 and IS: 15466: 2004. The seals shall be fastened to gate
using stainless steel bolts / counter sunk screws and nuts. To limit lateral sway of the gate
during operation, two guide shoes shall be provided on each side of the gate, which will
remain engaged with embedded guides.
The gate is operated by independent electrically operated rope drum hoist of capacity not
less than 13 T consisting of central drive unit (electric motor), reduction units, shaft, rope
drums, etc. Provision in the hoist mechanism shall also be made to operate it manually in the
event of power failure. The hoists shall be installed on Hoist Bridge supported on columns
above top of piers. Access stair cases shall be provided for access to the hoist bridge on
both the sides. Controls for all the hoists shall be housed in a control room located near the
gates. The gates shall also be operated locally from local control panel on regulating
platform supported on columns.
The minimum speed of travel of gate shall be: for opening 0.50 m/min., for lowering 0.50
m/min.
The gate shall be designed and manufactured in accordance with the provisions made in IS:
4622: 2003 (Recommendations for structural design of fixed wheel gates). Hoist shall fulfill
all the requirements as specified in IS: 6938:2005.
Key Plan, General Arrangement, Seal and Embedded Parts Details of the gate are shown in
Drawing No: 0933-HDC-GNL-0003-R0, 0933-HDC-A08-0801-R0 and 0933-HDC-A08-0802-
R0 respectively.
9.1. General
Mawphu Hydro Electric Project (Stage-II) envisages installation of 75MW comprising of 2
(Two) generating units of 37.5 MW each. The generating equipment would be installed in a
surface powerhouse.
The powerhouse will comprise of the Service Bay, Machine Hall, Generator Floor, Turbine
Floor, Transformer Deck (located at the upstream of the powerhouse), 145kV Gas Insulated
Switchgear will be installed in the GIS hall, at the floor above the transformer deck and the
Control Block will be located on one side of the powerhouse.
The terminal equipment for 132kV double circuit transmission line would be placed in the
pothead yard located near the powerhouse. The connection between pothead yard and
145kV Gas Insulated Switchgear would be made through 145kV XLPE cables to be laid in a
cable duct/trench. 132kV equipment located at the pothead yard will consist of capacitive
voltage transformers, wave traps, lightening arrestors, gantry structure etc.
Both the generating units will be provided with 10% continuous overload capacity as per
CEA grid connectivity regulations.
The water from the unit draft tubes will be routed back to the river through a tail pool.
The general arrangement of the powerhouse showing the powerhouse structure, pothead
yard and approach roads is shown in the powerhouse complex layout.
The equipment layout at various floors is shown in the powerhouse layout drawings.
9.2. Turbine
Based upon the turbine selection criteria for a head range from 239m to 219.8m, Vertical
Francis type turbine is the appropriate choice in this case. Accordingly, 2 (Two) Vertical shaft
Francis type turbines, each having rated output to match the generator output of 37.5MW at
its terminals with rated speed of 500rpm and operating at a rated head of 232m are
proposed to be installed in the Power House.
The runner and other critical under water components of the turbine will be of 13:4 Cr/ Ni
Stainless steel with high resistance to silt abrasion.
The turbines will have a weighted average efficiency of about 93% and the peak efficiency of
about 94%.
The turbines will have provision of runner removal to facilitate repairs as and when required.
The runner removal will be done from the bottom, by dismantling the draft tube cone
assembly and after installation of temporary rails and supports to lower the runner.
Operating levels
9.2.1. Heads
Based on the head calculations enclosed with the Civil Design Chapter, the following heads
are derived.
Maximum net head = 237.51m
Minimum net head = 221.97m
Based on the best practices published by CEA,
Design head = Minimum net head + (2/3) x (Maximum – Minimum net head)
= 232.33m say 232m.
9.2.3. Governors
Each turbine will be provided with a digital, microprocessor type PID governor. The
governing system will be connected to and be fully compatible with the power station control
and monitoring equipment. It will be possible to control turbines from main control room in
auto mode and from unit control board (UCB) in manual as well as auto mode.
The inlet valve will comprise of valve body and rotor, double acting servomotor(s) for
opening and closing operation of the valve, control gear for operation, penstock inlet pipe,
outlet pipe with compensator and dismantling joint, and other essential accessories and
auxiliaries viz. by-pass valves, sealing valve, air valve, piping with valves, for water, air and
oil, master switch, slide valves with electromagnets etc.
A dismantling joint will be provided with MIV on the downstream end to facilitate installation
and dismantling of the valve and to permit replacement of the upstream and downstream
seals and gaskets.
The Bypass valve would facilitate opening of the MIV under same water pressure at the
upstream and downstream ends.
The valve opening and closing time will be adjustable to a closing time range of 50-60 sec.
and opening time range of 50-120 sec.
The valve will be designed for automatic control with electric start and stop impulses from
the control room. In addition to automatic control, independent manual control system will
also be supplied for local operation.
Lugs and Lifting Eyes will be provided for convenience in handling the assembled valve.
9.3. Generators
It is proposed to provide 2 (Two) numbers of three phase 41.7MVA, 0.9 power factor, salient
pole type vertical shaft synchronous generators conforming to IEC 60034, directly coupled
with the respective turbine shafts operating at a generation voltage of 11kV.
The choice of generation voltage will be further reviewed during detailed engineering stage
in consultation with the manufacturers.
The generators will be suspended type with a guide and thrust bearing installed above the
rotor and a guide bearing below the rotor.
The generator stator and rotor windings will be provided with Class F insulation but
temperature rise with maximum output will be limited to that corresponding to Class B
insulation.
The generators will be provided with a water based cooling system. The generator phase
terminals will be brought out of the barrel for connection to Isolated Phase Bus Ducts. The
generator terminals will also be brought out for formation of neutral. The neutral of the
generators will be grounded through distribution type transformer with a secondary resistor.
Digital static excitation system will be provided for each generator. The excitation system will
consist of excitation transformers, AVRs, Thyristor bridges etc and conform to IEEE 421.
The generator shaft will be adequate in size and strength to operate at maximum runaway
speed and to withstand the short circuit stresses without excessive vibration or distortion and
will be suitable for direct coupling with turbine.
The generator will be provided with adequate moment of inertia so that speed rise on
sudden load throw off is limited within 50% and pressure rise in the penstock remains limited
within 35%.
Each generator will be complete with auxiliary equipment like lubrication oil system, heater,
brakes, brake dust collection system, fire fighting system etc. Generators will be provided
with RTDs, thermostats and sensors and Dial type thermometers for temperature monitoring
of core, windings and bearing pads. The efficiency for which the generator is expected to
operate will be about 98.5%.
Online monitoring equipment will also be provided for the following:
Vibration monitoring,
Shaft current monitoring,
Stator winding partial discharge monitoring, and
Rotor air gap monitoring.
Important Parameters
Frequency 50 Hz
Transformers will be provided with off circuit tap changer at the HV side, with range of +2.5%
to -7.5% in four steps, each of 2.5%.
The transformers will be installed on rails which will provide movement of the transformers
from their respective positions to the service bay. Necessary jacking and pulling
arrangements will be provided for the transformers. Fire protection wall will be provided
between the transformers as per TAC guidelines.
The bus ducts will be naturally air cooled and the temperature rise limits shall be as per IS
8084 and as below:
Bus duct conductor – Aluminium – 40 deg C above ambient temperature
Bus duct enclosure – Aluminium – 30 deg C above ambient temperature
The bus ducts will be complete with continuous type Aluminium enclosure, conductor
supported on support insulators with self aligning arrangement, wall frame assembly, seal off
bushing, flexible connections at the termination points, the tap off bus ducts for connection
with LAVT cubicle, Excitation Transformer, Unit
Auxiliary Transformer etc.
On the neutral side, the bus ducts, after forming star will be connected with the neutral
grounding cubicle which will house the grounding transformer and the grounding resistor.
The bus bar scheme adopted is double bus scheme with a bus coupler. The single line
diagram indicating generating units, step up transformers, 145kV GIS, transmission line
feeders is enclosed as Drawing number 0933 EDB A00 0001.
The GIS equipment will be located on the floor above the step up transformers in the
transformer deck. The connection between the transformers and the GIS bays would be
done through 145kV SF6 gas insulated bus ducts (GIBD). Important parameters of the 145kV
GIS are as below:
Rated system voltage – 145kV,
System frequency – 50Hz,
Short circuit withstand capability – 40kA for 1s,
Grounding – effectively earthed,
Rated power frequency withstand voltage (1 min) line to earth – 275kVrms,
Impulse withstand voltage (1.2/ 50µs) line to earth – 650kVp,
The short circuit withstand capacity would be firmed up after system studies during detail
engineering.
The feeder bay will be connected with 145kV XLPE cables through SF6 – Cable bushing.
The station control level will include functions for overall and centralized control of the
station. Typical functions will be supervision and monitoring of the machine conditions,
recording the operation/ faults and providing logs and operational information to assist
operators. The system will have provision for generation of customized trend reports. There
will be a provision for event logging with time stamping at a least count of 1ms.
The local control level will be unit control board, which will be the local control centre for
overall sequence of operation of the units. At start up or shutdown, it will execute a set of
sequence programs. Based on the process criteria, it will generate commands for drive
control or functional groups for execution of program. It will check for presence of all required
criteria before it issues a particular command. The execution time will also be monitored and
if execution time exceeds the stipulated time limit, a trip or an alarm command will be issued.
It will be possible to control the unit from the unit control board in fully automatic mode, step
by step mode and manual mode.
Equipment, control level will have local control board/ cubicle to control the equipment
directly.
The data transmission between the station control level and the local control level will be
accomplished by means of LAN with high speed large capacity data bus of optical fibre
cables.
A mimic bus diagram board will be provided to depict the status and operational information
of the transmission lines, the EHV bus, the generating units and the station service circuits in
real time and to operate the equipment with functional switches. Dam water level indicators
will also be provided on this board.
The whole system will have a total redundancy in the main CPUs, programmable controllers
of the local control units, LAN system and power supply units. Even if one group has a
failure, the backup group will instantly succeed the operation seamlessly.
The architecture drawing of control and monitoring system showing the bus topology and
tentative equipment connectivity is shown in drawing number 0933 EDE A20 0001.
9.4.6.1. Generators
The following protections will be provided for the generators:
Differential (87G)
95% stator earth fault (64G1)
100% stator earth fault (64G2)
Backup impedance (21G)
Negative phase sequence (46G)
9.4.6.3. Feeders
The 132kV feeders will be provided the following protections:
Distance protection (21),
Directional instantaneous definite minimum time (IDMT) type earth
fault relay,
Two stage over voltage protection,
The incomings to the SSB will be interlocked and the SSB bus will be provided with bus
coupler to avoid charging of the bus with two different sources. The SSB will be located in
the Control block at the Service bay floor level.
The UABs will be supplied auxiliary power from the UAT (500kVA, 11/ 0.433kV, dry type
transformer) and also be connected with SSB.
Unit auxiliary board will be provided for each unit and will be installed on the generator floor,
below the machine hall. The major loads of the UAB will be;
Cooling water pumps,
Oil Pressure Unit/s (Governor and MIV),
Governor,
Excitation System,
Hydrostatic pressure lube oil system,
Generator transformer oil pump,
Brake dust fan and carbon dust collector system feeders, etc.
Emergency power will be catered by 1 (One) nos. of 750kVA, 415V diesel generating set
which will be located near the powerhouse at service bay elevation.
For automatic operation of the pumps, level controllers will be provided in the dewatering
and drainage sumps.
In addition, for protection against flooding, two submersible pumps of adequate capacity
along with necessary level sensors for automatic starting will be installed on the MIV floor
and the control panels for these pumps will be located in the control block. The drawing
showing the schematic of drainage and dewatering system is enclosed as drawing number
0933 EDD A52 0001.
Provisions mentioned in Clause 39 of 'The Technical Standards for Construction of Electric
Plants and Electric Lines', Publication of CEA have been taken care of for the protection of
powerhouse against flooding. These provisions have been discussed in Annexure 9-1.
Ventilation system will be compliant with IS 4720 and the air duct construction will be as per
IS 655. The system will be designed as per ASHRAE guidelines.
Mechanical Workbench,
Power hacksaw,
Drilling machine,
Grinding machine,
Welding set etc,
9.7. Drawings
Sl.No. Title Drawing Number
Annexure 9-1
1. Drainage system shall be designed with Drainage pumps and piping with suitable
capability of discharging normal sizes considering normal seepage from
seepage from power station walls, walls, floors, leakages from turbine seals,
floors, leakages from “turbine shaft water from back flushing of cyclone
seals”, water from back flushing of separator(s) with additional margin will be
cyclone separator(s) (if provided) etc. provided.
with an additional margin of at least
The system will be compliant with IS 4721
50%.
2000, Code of practice for drainage and
dewatering of surface/ underground hydro
electric power stations.
2. For standby drainage capacity and also 2 numbers of additional flood water
for flood protection purposes, equal discharge pumps will be provided at the
number of additional pumps of same MIV floor, which will evacuate any flood
capacity as that of drainage capacity water above the Max tail water level.
provided for powerhouse is provided in
a separate sump at the lowest floor.
3. Use of submersible type pumps, Submersible type pumps will be used for
suitable for submergence of minimum drainage and dewatering.
20m may be made mandatory for
drainage and dewatering system. In
case of silt prone power station, at least
one slurry pump may be provided.
5. A mild steel pipe of suitable size shall Additional drainage pipe will be
be embedded in the access tunnel to embedded in the draft tube deck with
provide alternate route to discharge NRV and gate valve with outlet above
flood water from underground power highest flood level.
station directly into the river. In surface/
sub surface power stations, additional
drainage pipe(s) may be embedded in
the draft tube deck wall/ draft tube pier
with NRV and gate valve with outlet
above highest flood level.
6. In case of power stations (with head The penstock tapping has been avoided
above 100m), tapings from penstocks for supply for cooling and fire fighting.
shall be avoided and water for cooling,
fire fighting etc. be lifted from the
tailrace.
7. Cooling water, fire fighting and Sizing of valves will be done suitably to
drainage/ dewatering system shall have suit safe operating conditions of the
case steel valves suitable for a system.
pressure of 1.5 times of design
pressure.
8. All electrical panels for drainage/ The electric panels shall be located in the
dewatering pumps, SST, DC battery Control block at floor above the maximum
etc. in the power station shall be placed flood water level.
at level of Machine hall or above.
Thieddieng
Nearest Village to project site Access road (under construction) is available from
Mawsynram for about 4km towards Thieddieng,
thereafter – about 6km through foot track
Dam Site
However, for construction purposes the working season is considered from November to
May.
To avoid the delay and allow the construction contractor to start the work on project
components as soon as after the mobilization is completed, it is planned to take up the
construction of the access road immediately after the TEC and Environment / Forest
clearance is available for the project. The construction of access roads can be carried out
concurrently with the process of preparing the bid documents and inviting the tenders and
selecting the Contractor for the construction of the project.
Upon award of work to the contractor, the access roads can be handed over to the
contractor on “AS is WHERE IS” basis and further construction of these access roads can be
taken up by the Contractor.
Construction of Project
The construction of the project can be taken by deploying qualified and well experienced
contractors
a) Supply of concrete: 1 no batching plant will mix concrete for the dam and other
appurtenant structures. The rated output of the batching plant shall be 60 m 3/ hr. Mix
design should be verified before concrete mixing and implemented in batching plant
strictly. The batching plant has been designed for double shift production, however if
required, batching plant can also work on three shift production
b) Aggregate processing Plant: All the aggregate cannot be obtained from natural
materials, so an aggregate processing system will be set up to produce aggregates. The
peak production rate of this system would correspond to peak concrete production rate.
Usually the aggregate processing system is designed for double shift production. The
capacity of producing is 110t/h .At the peak period of concrete placement, the aggregate
system can work on three shifts for production.
c) Network of access roads will be developed to Dam site and appurtenant structures,
Batching plant & Aggregate processing plant to facilitate the movement of construction
equipment.
d) Adequate no. of Diesel Gensets shall be mobilized to cater for the construction power of
the equipment. Air compressors shall be mobilized for supply of air for pneumatic
equipments.
One diversion tunnel of 7.0 m dia, horse shoe shaped is proposed on the left bank.
The length of the tunnel is about 384m. The inlet is kept at EL. 446.00 and outlet is at
EL. 429.50. The invert levels are about 1.0 m above the average river bed level at
the proposed location.
One gate of size 8.00 m x 8.00 m for the opening at inlet shall be provided to
facilitate the closure of the tunnel and plugging of the tunnel before reservoir filling.
The gate shall be operated with hoist at EL. 457.50 m.
U/s Cofferdam is proposed to be founded on overburden. The maximum height of the
coffer dam is 18m from the river bed level. 1.0 m thick impervious to semi-pervious
material is provided on the river bed and on the u/s face with the slope of 1.5H:1V.
The central core of the coffer dam is filled with clay. To facilitate the construction of
the coffer dam, closure dyke is also proposed with the top at EL. 450.00.
The deepest foundation level for main dam is expected at about 13m and the location
of the coffer dam is at about 200m upstream of the dam axis. Hence the seepage at
the d/s is not much anticipated. However, one row of permeation grouting is
proposed to arrest the seepage.
The downstream coffer dam is of 6m high with its top level at EL. 434, which is
proposed to be located at about 170 m d/s of the dam axis with the top width of 3.0
m.
The equipment used for rock open excavation of slope for Inlet and outlet structure shall also
be used for excavation of abutment and foundation of Dam
Excavated slopes shall be protected by applying shotcrete and installing rock bolts / rock
anchors as per site requirements and provisions shown in the construction drawing.
The material recovered from the excavations will be selected according to its technical
characteristics; the material suitable to be used as backfill material or embankment material
will be reused as much as possible in such activities; the material suitable for being used as
aggregate for concrete works will be hauled to the crushing plant for reduction to size; the
materials not suitable for any working activity will be disposed off into the designated muck
dumping site.
65 sec
= 60 m3 / hr
= 4.2 Hrs
It is planned to deploy Dumper LPK1616 – HD or equivalent, having the capacity of 16T &
Box capacity of 7 cum.
= 6.4 m3
= 1.28 m3
Estimating Cycle time for One dumper for dumping the Muck in muck disposal area
and back
= 22.5min
= 14.22 m3 / hr
Explosives
= 266.67m
Since 1 blast is planned every 12 hrs, hence no of drill rigs required = 2 nos
One additional hydraulic drill required for installation of rock bolts / rock anchors
Aggregate processing plant is adequate to meet the requirement of concreting at both fronts
simultaneously.
The procedure for concreting would be: Foundation clearance— surveying and setting out—
formwork erection— reinforcement and water stop installation— inspection- transportation of
concrete— concrete pouring— formwork removal— curing.
Concrete will be transported from the batching plant at dam site by 6m 3 capacity transit
mixer and then placed by concrete pump BP 350 or equivalent, leveled and vibrated finally
by manpower.
= 15 m3 / hr
3 Bulldozer No. 1
Excavation will be carried out from Inlet and outlet end simultaneously. Full face excavation
will be implemented using drilling and blasting method. Drill hole by 2 boom drill jumbo, load
the mucks by 1 m3 side-dumping loader and transport mucks by 16T Dumper. Since the
river diversion is on the critical path of the project, independent set of equipments shall be
deployed for carrying out excavation from each face.
( 2 boom drill
7 No of boom available for drilling 2nos
jumbo)
( 1 min / hole , 35
11 Moving boom to next hole and aligning 35min
holes/boom)
10 sec / .5m of
12 Blow hole 37 min
drilling
( 112m / 147
14 Operating time 0.60 m / min
min)
50mni / hr x 0.76
16 Hourly production of drilling 30.4 m/ hr
m/min
Table 11-5 : Estimation of Mucking Time, and Requirement of 16T tippers for Mucking
(1.0 x 80% x 60
i) Production by loader 70 m3 / hr
x 50 ) / 35 sec
8 No of 16 T tippers required
Assuming 1m3 of
b) Allowable qty. of Muck that can be carried 6.4 m3
muck = 2.5 T
production = 70
cum/hr
Speed = 20kmph
d) Haul Time for disposing muck 9 min
Distance = 3Km
Speed = 20kmph
f) Return time 6 min
Distance = 3Km
Total
Survey
Ventilatio Face time
& Drillin Explosive Rock
Time n& Mucking clearin for
setting g charge Support
Defuming g each
out
cycle
It is planned to carry out the lining in diversion tunnel using a 12 m long gantry. The shutter
shall move from Inlet toward the outlet, and concrete shall be feed from outlet end of the
tunnel. This arrangement will facilitate in carrying out concreting & HM work at Inlet,
simultaneously with the tunnel concreting.
Concrete will be transported from the batching plant at dam site by 6m 3 capacity transit
mixer and then placed by concrete pump (BP 350 or equivalent), leveled and vibrated finally
by manpower.
Table 11-7 : Estimating the requirement of 6 cum Transit mixers for DT lining
of concrete
forms pipe line
U/s Cofferdam is proposed to be founded on overburden. The maximum height of the coffer
dam is 18m from the river bed level. 1.0 m thick impervious to semi-pervious material is
provided on the river bed and on the u/s face with the slope of 1.5H:1V. The central core of
the coffer dam is filled with clay. To facilitate the construction of the coffer dam, closure dyke
is also proposed with the top at EL. 450.00.
Materials from excavation of Diversion Tunnel, DT inlet and outlet will be used for
cofferdams. Clay will be obtained from the borrow area. The material will be loaded by the
excavator 1.6m3, and transported by the 16T dumper. Bulldozer will be used to spread, level
and compact. Filling of the cofferdam will be carried out in layers of no more than 100cm
each. Compaction roller will be used to compact in layers. Total quantity of fill material to be
placed in the coffer dam = 71,690 cum.
cum/hr
Table 11-11 : Major construction equipment Planned for Coffer dam construction
Quantit
Description Unit
y
Bulldozer Set 2
2 Non-Overflow (NOF) blocks have been proposed on the left bank side. The length of first
NOF block has been kept as 17.75m and of second block as 15.0m. The height of the
blocks varies from 6.25 to 36.5m.
2 NOF blocks have been proposed on the right bank side. The lengths of blocks are 15.0m
and 13.25m. The height of the blocks varies from 7m to 43m.
DPR-I: Chapter-11: Construction Methodology 11-37
MAWPHU HEP, STAGE – II
3. From river bed level to deepest foundation level = 1,03,000 cum
i. Open excavation
The open excavation in abutment above HFL involving quantity of 34,000 cum shall be taken
up prior to river diversion works. The excavation of abutments below the HFL shall be taken
up after the river diversion is achieved. Excavation in river bed shall also be taken up after
the river diversion has been achieved. Some access roads will be built before the
construction of the dam in order to meet the requirement of traffic.
The open excavation will be carried out according to the principle of “excavating from top to
down and by layers and benches. The earth and heavily weathered rock will be directly
excavated by 1.6m3 excavator, and the muck will be collected by bulldozer and transported
by 16T dumper. The rock excavation in the slope shall be taken up using deep-hole bench
drilling and blasting method. The height of bench for blasting will be 3m so that rock support
measures can be installed easily. The width of temporary berm created after blast of each
bench shall be about 3m to allow easy movement of equipments for next operation, The
slope will be drilled by hydraulic drill such as ROC. After each bench is blasted, while the
muck is being collected by 1.6m3 excavator and transported by 16T Dumpers, drilling for
next bench blast and installation of rock support measures shall be taken up simultaneously.
The drilling pattern shall be such that per blast 500 m 3 of rock is blasted and there shall be
two such cycles/day ( i.e. one blast in 12 Hrs ) . The blasting pattern shall be decided as per
the site conditions, however assuming a 1m x 1m grid pattern with 3.2 m of vertical depth
would be close approximation to the pattern to be adopted at site.
Excavated slopes shall be protected by applying shotcrete and installing rock bolts / rock
anchors as per site requirements and provisions shown in the construction drawing.
The material recovered from the excavations will be selected according to its technical
characteristics; the material suitable for being used as aggregate for concrete works will be
hauled to the crushing plant for reduction to size; the materials not suitable for any working
activity will be disposed off into the designated muck dumping site.
65 sec
= 60 m3 / hr
= 8.4 Hrs
It is planned to deploy Dumpers LPK1616 – HD or equivalent, having the capacity of 16T &
Box capacity of 7 cum.
= 6.4 m3
= 1.28 m3
Estimating Cycle time for One dumper for dumping the Muck in muck disposal area
and back
= 22.5min
= 14.22 m3 / hr
c) Requirement of Hydraulic drill for carrying out drilling in Rock for Excavation
Explosives
= 0.9375 m3 / m of rock
= 534m
Since 1 blast is planned every 12 hrs, hence no of hydraulic drill required = 4 nos
One additional Hydraulic rill required for installation of rock bolts / rock anchors
The procedure for concreting is as following: Foundation clearance— surveying and setting
out— formwork erection— reinforcement and waterstop installation— inspection— concrete
pouring— formwork removal— curing.
Concrete shall be transported from batching by 6m3 transit mixers and shall be placed
through tower crane with 3m3 bucket .
Total quantity of concrete to be placed in dam =
Peak placement of concrete in the dam would be when the concrete in poured in the
overflow blocks 3,4 and 5 below the river bed level. Following is planned for pouring the
concrete :
Concrete shall be placed in lift heights of 1.5m. In each lift concrete shall be poured
in layers of 0.5m height.
Subsequent lift in same block will be placed every 5 days ( 120 hrs) after the
previous pour is completed – 2 day for green cutting, curing, 3 days for preparing the
lift including moving forms and installing all materials as per design ( water stops,
contact grouting installations, reinforcement steel if any, cleaning of surface)
The capacity of batching plant for producing concrete and no. of transit mixers of 6m 3
capacity for transporting concrete shall be adequate enough to prevent the formation of cold
joint when the concrete in the particular lift is being poured. This criteria defines how much
concrete in mass pour must be place before cold joint conditions occurs (vibrators cannot
penetrate into fresh concrete without breaking). The cold joint production requirement is
based on the size of pour i.e its width perpendicular to river flow and height of lift ( 1.5m) that
concrete is placed in. Cold joint criteria will be observed when pouring block in dam
foundation, in block 3,4,5 below the river bed level and it will be based on the widest block.
The widest block in dam occurs in block 4 & 5 below the foundation level and it is 26m.
Based on 26m block width ( in direction perpendicular to flow of river), layer of 2.5m wide -
in direction along the flow of river and 0.5m thick layers, time required for cold joint
DPR-I: Chapter-11: Construction Methodology 11-42
MAWPHU HEP, STAGE – II
formation as 1.5 hrs, cold joint production requirement for placing mass concrete in dam for
1.5 m lifts is 87 m3 / hr. For details see figure below.
Planned rate of concrete production (15% above the minimum required) = 100 cum / hr.
Assuming efficiency of Batching Plant output = 80%, thus capacity of batching plant required
= 120 cum / hr.
ii) Design of Aggregate processing Plant at Dam Site ( To meet peak production by
Batching Plant 40000 cum )
Coarse Fine Total Aggregate
Concrete
Structure Aggregate Aggregate (Corse +fine)
qty.(cum)
(cum) (cum) (cum)
Dam (peak
requirement 40000 40000 20000 60000
of aggregate)
Total Aggregate requirement (cum) 60000
60000 x 1.8
Quantity in Tonnes
= 1,08,000
Assuming 125% peak requirement of aggregate (1.25 x
1,35,000
1,08, 000) Tonnes
1,35,000/(25x24)
Aggregate requirement per hour (Tonnes/hr)
= 225
Efficiency of aggregate processing plant 80%
Required capacity of processing plant (Tonnes/hr) (225/0.8) = 281
So install 2 aggregate processing plant of 170 Tonnes/hr Capacity &
110 TPH ( second APP can be shifted along with batching plant to Adit 2 /
surge shaft location)
3 Excavator 1.6 m3 No 2
5 Tower Crane No 2
The water conductor system includes a horse shoe shaped Head Race Tunnel (HRT) of
finished diameter 4.80 m. The length of HRT is 2.62 Km. Tunneling is proposed to be carried
out by drilling & blasting method (DBM). Rock support, comprising of shotcrete, rock bolting
and steel sets would be proposed as per site conditions.
Before taking up actual tunnel excavation, portal construction and slope stabilization at the
adits would be required. This shall involve open excavation, rock bolting, shotcreting etc. 2
Construction Adits are proposed along the alignment of HRT to facilitate the excavation of
HRT. The RD of each Adit and distance between them is given as under:
Excavation shall be carried out from 3 faces and each face shall have independent set of
construction equipments. During the excavation of tunnel, suitable niches will also be
excavated at regular intervals which will facilitate in passing of construction vehicles during
the construction of tunnel
Full face excavation will be implemented using drilling and blasting method, and smooth
blasting will be carried out to control the excavation perimeter. Drill hole by 1 boom drill,
load the mucks by 1 m3 side-dumping loader and transport mucks by 16t Dumper.
The cycle of excavation by drilling & blasting shall be :
( 1 boom drill
7 No of boom available for drill 1nos
jumbo)
( 1 min / hole , 35
11 Moving boom to next hole and aligning 55 min
holes/boom)
10 sec / .5m of
12 Blow hole 45 min
driling
( 137.5 / 240
14 Operating time 0.57 m / min
min)
m/min
137.5m / 30.4 m/
Total time taken for drilling 4.8 hrs
hr
(0.8 x 80% x 60
i) Production by loader 55 m3 / hr
x 50 ) / 35 sec
8 No of 16 T tippers required
Assuming 1m3 of
b) Allowable qty. of Muck that can be carried 6.4 m3
muck = 2.5 T
Loader
c) Time for loading one dumper 7 min production = 55
cum/hr
Speed = 20kmph
d) Haul Time for disposing muck 12 min
Distance = 4 Km
Speed = 20kmph
f) Return time 12 min
Distance = 4 Km
Average cycle time for Full face excavation in class 1,2 and 3 rock
Total
Survey
Ventilatio Face time
& Drillin Explosive Rock
Time n& Mucking clearin for
setting g charge Support
Defuming g each
out
cycle
In class 4 & 5 rock, dus to installation of Ribs and other support, the Rock support time shall
be 5.5 hrs and overall cycle time shall be about 15.5 hrs.
Concrete will be transported from the batching plant at dam site by 3m 3 capacity transit
mixer and then placed by concrete pump (BP 350 or equivalent ), leveled and vibrated finally
by manpower.
It is also proposed to install a Batching plant of 30 cum/ hr capacity at Adit-1 to facilitate the
concreting of the tunnel.
Estimating the requirement of Transit Mixers :
Shifting Fixing
& bulkhead Pumping Total time
Setting Shutter
Time Fixing & by for each
time removal
of concrete concrete cycle
forms pipe line
Table 11-14 : Major Equipment deployment for Construction of Head Race Tunnel;
Considering the dimension of surge shaft and ease of construction, the surge shaft will be
excavated in 2 phases. After reaching to surge shaft axis, initially a 2.5 m diameter pilot hole
will be drilled through the height of the shaft. The hole will be drilled from bottom to top by a
raise climber and mucking will be carried out from bottom by gravity. The pilot hole can then
be enlarged to the full diameter of the shaft by segmental benching (Drilling & Blasting
method) from top. The mucking for enlargement will be through the pilot hole by gravity and
then tipping by dumpers through the adit. Men and material will be lowered from top using
winch operated hoist. Concrete lining of surge shaft will be carried out using self climbing
shutters.
Horizontal pressure shaft shall be excavated in similar way as the HRT is being excavated.
Excavated slopes shall be protected by applying shotcrete and installing rock bolts / rock
anchors as per site requirements and provisions shown in the construction drawing.
The material recovered from the excavations will be selected according to its technical
characteristics; the material suitable to be used as backfill material or embankment material
will be reused as much as possible in such activities; the material suitable for being used as
aggregate for concrete works will be hauled to the crushing plant for reduction to size; the
materials not suitable for any working activity will be disposed off into the designated muck
dumping site.
65 sec
= 60 m3 / hr
= 8.4 Hrs
It is planned to deploy Tippers LPK1616 – HD or equivalent, having the capacity of 16T &
Box capacity of 7 cum.
= 6.4 m3
= 1.28 m3
Estimating Cycle time for One dumper for dumping the Muck in muck disposal area
and back
= 22.5min
= 14.22 m3 / hr
f) Requirement of Hydraulic drill for carrying out drilling in Rock for Excavation
As already explained above, the rock excavation in the slope shall be taken up using deep-
hole bench drilling and blasting method. The height of bench will be 3m so that rock support
measures can be installed easily. The width of berm created after excavation shall be about
3m to allow easy movement of equipments for next operation,. The slope will be drilled by
hydraulic drill such as ROC. After each bench is blasted, while the muck is being collected
by 1.6m3 excavator and transported by 16T Dumpers, drilling for next bench blast and
installation of rock support measures shall be taken up simultaneously. The drilling pattern
shall be such that per blast 500 m3 of rock is blasted and there shall be two such cycles/day.
The blasting pattern shall be decided as per the site conditions, however assuming a 1m x
1m grid pattern with 3.2 m of vertical depth would be close approximation to the pattern to be
adopted at site.
Explosives
= 0.9375 m3 / m of rock
= 534m
Since 1 blast is planned every 12 hrs, hence no of hydraulic drill required = 4 nos
One additional Hydraulic rill required for installation of rock bolts / rock anchors
The procedure for concreting is as following: Foundation clearance— surveying and setting
out— formwork erection— reinforcement and waterstop installation— inspection— concrete
pouring— formwork removal— curing.
Concrete shall be transported from batching by 6m3 transit mixers and shall be placed by
concrete pump (BP 350).
Concreting in power house shall go concurrently with the erection of E&M equipments.
3 Excavator 1.6 m3 No 2
2 Excavator 1.6 m3
10 Compaction roller
15 Tower Crane 6T
22 Raise climber
24 Jack Hammers
Monsoon Season – Jun to October. Due to heavy rainfall in the region, construction
activities for surface works like Dam & Power house would be significantly impacted
during the monsoon season. The underground works would also be impacted, though
relatively less as compared to surface construction works. However, as the construction
agency would remain mobilized at site during the monsoon season, the construction
activity shall be continued with less progress. For preparing the schedule, it is assumed
that :
o Surface works - Production in wet season ( Monsoon period) shall be 30% of
production achieved in dry season for surface works.
o Underground Works - Production in wet season ( Monsoon period) shall be 50%
of production achieved in dry season for underground works.
Work shall be carried out in 3 shifts of 8 hrs each, with 80% job efficiency factor i.e 50
min / hr.
The works shall commence in the Non monsoon season. The open excavation in rock and
overburden will be carried out according to the principle of “excavating from top to down and
by layers and benches”. The drilling pattern shall be such that per blast 250 m 3 of rock is
blasted and there shall be two such cycles/day ( i.e. one blast in 12 Hrs) .
Concreting in the DT inlet shall be taken up along with the lining works in the Diversion
tunnel after excavation of DT is completed. The procedure for concreting would be:
Foundation clearance— surveying and setting out— formwork erection— reinforcement and
water stop installation— inspection- transportation of concrete— concrete pouring—
formwork removal— curing. The lift height would be around 1.5m. The average cycle time for
pouring concrete in one lift of height 1.5 meter shall be 2 days and average quantity of
concrete per poured shall be 110 cum.
B) Diversion Tunnel
Excavation will be carried out from Inlet and outlet end simultaneously. Full face excavation
will be implemented using drilling and blasting method. Average cycle time for excavation in
class 1,2 and 3 is worked out as 16.2 hrs and average cycle for excavation in class 4 & 5
rock has been worked out as 19 hrs.
Total no of days
Average rate
Class of Rock required to
of Progress
complete
It is planned to carry out the lining in diversion tunnel using a 12 m long gantry. The shutter
shall move from Inlet toward the outlet, and concrete shall be feed from outlet end of the
tunnel. This arrangement will facilitate in carrying out concreting & HM work at Inlet,
simultaneously with the tunnel concreting. The average cycle time for concrete lining shall be
26.7 hrs. and average rate of progress per day shall be 10.78 m/ day.
U/s Cofferdam is proposed to be founded on overburden. The maximum height of the coffer
dam is 18m from the river bed level. . The central core of the coffer dam is filled with clay.
Materials from excavation of Diversion Tunnel, DT inlet and outlet will be used for
cofferdams. . Filling of the cofferdam will be carried out in layers of no more than 100cm
each. Compaction roller will be used to compact in layers. Total quantity of rock fill in the
coffer dam is equal to 71,690 cum and targeted average rate of placing rock fill shall be 4320
cum.
Abutment above HFL involving quantity of 34,000 cum shall be taken up prior to river
diversion works. The excavation of abutments below the HFL shall be taken up after the river
diversion is achieved. Excavation in river bed shall also be taken up after the river diversion
has been achieved. The excavation in riverbed shall be undertaken only in non monsoon
season. The works have been planned accordingly. The open excavation will be carried out
according to the principle of “excavating from top to down and by layers and benches. The
drilling pattern shall be such that per blast 500 m 3 of rock is blasted and there shall be two
such cycles/day ( i.e. one blast in 12 Hrs).
Concreting in Dam :
The procedure for concreting in dam is as following: Foundation clearance— surveying and
setting out— formwork erection— reinforcement and waterstop installation— inspection—
concrete pouring— formwork removal— curing.
Total quantity of concrete to be placed in dam =
From Deepest foundation level to river bed = 52,125 cum
From river bed level to Dam top = 86,875 cum
Total =1,39,000 cum
Peak placement of concrete in the dam would be when the concrete in poured in the
overflow blocks 3,4 and 5 below the river bed level. Following is planned for pouring the
concrete :
Concrete shall be placed in lift heights of 1.5m. In each lift concrete shall be poured
in layers of 0.5m height.
Subsequent lift in same block will be placed every 5 days ( 96 hrs) after the previous
pour is completed – 1 day for green cutting, curing, 3 days for preparing the lift
including moving forms and installing all materials as per design ( water stops,
contact grouting installations, reinforcement steel if any, cleaning of surface)
DPR-I: Chapter-11: Construction Methodology 11-63
MAWPHU HEP, STAGE – II
Quantity of concrete in each lift of from foundation upto River bed level is worked out in
below table.
Average
Lift Average Average width in
Total Qty Total Qty Total Qty
no width in X- width in X-
From To of of of
section X-section section
Concrete Concrete Concrete
( Autocad) ( Autocad) ( Autoca
d)
Schedule for placing concrete in each lift from foundation upto river bed level is
shown in the table :
Month -1 Month -2
Da
Day Block -3 Block -4 Block -5 y Block -3 Block -4 Block -5
1 1568.00 1 2 2630.00 4
2 1 2 3 1 5
3 2 1716.00 3 4 2 2622.00
4 3 1 4 5 3 1
5 0.00 4 2 5 1857.00 4 2
6 1 5 3 6 1 5 3
7 2 2327.00 4 7 2 2630.00 4
8 3 1 5 8 3 1 5
9 4 2 1915.00 9 4 2 2630.00
10 5 3 1 10 5 3 1
11 0.00 4 2 11 2057.00 4 2
12 1 5 3 12 1 5 3
13 2 2630.00 4 13 2 2630.00 4
14 3 1 5 14 3 1 5
15 4 2 2115.00 15 4 2 2630.00
16 5 3 1 16 5 3 1
17 358.00 4 2 17 2057.00 4 2
18 1 5 3 18 1 5 3
19 2 2630.00 4 19 2 1753 4
Month -1 Month -2
Da
Day Block -3 Block -4 Block -5 y Block -3 Block -4 Block -5
20 3 1 5 20 3 5
21 4 2 2314.00 21 4 1753
22 5 3 1 22 5
23 1128.00 4 2 23 1371
24 1 5 3 24
25 2 2630.00 4 25
26 3 1 5 26
27 4 2 2514.00 27
28 5 3 1 28
29 1649.00 4 2 29
30 1 5 3 30
25494.00 26620.00
For concreting above the river bed level, as there would be heavy reinforcement, it is
expected that average rate of concreting / month shall be around 10,000 cum / month.
The water conductor system includes a horse shoe shaped Head Race Tunnel (HRT) of
finished diameter 4.80 m. The length of HRT is 2.62 Km. Tunneling is proposed to be carried
out by drilling & blasting method (DBM) .Rock support, comprising of shotcrete, rock bolting
and steel sets would be proposed as per site conditions.
Before taking up actual tunnel excavation, portal construction and slope stabilization at the
adits would be required. This shall involve open excavation, rock bolting, shotcreting etc. 2
Construction Adits are proposed along the alignment of HRT to facilitate the excavation of
HRT. The RD of each Adit and distance between them is given as under:
Full face excavation will be implemented using drilling and blasting method. Average cycle
time for excavation in class 1,2 and 3 is worked out as 16. hrs and average cycle for
excavation in class 4 & 5 rock has been worked out as 19 hrs.
As 2 Adits have been provided, excavation shall be carried out from 3 faces and each face
shall have independent set of construction equipments. It is also assumed that the in each
face, 85% of the rock shall be in class 1, 2 and 3. Length of Excavation of each face shal
be as :
It is planned to carry out the lining in tunnel using a 1 no 12 m long gantry from, as the
construction of HRT is not on the critical path and hence deployment of shutter at two
additional faces will only increase the cost of the equipment. Lining can be carried out from
Intake towards Surge shaft. Adit 1 shall be plugged after the crossover of junction to prevent
accumulation of diesel fumes in the Tunnel . The average cycle time for concrete lining shall
be 25.5 hrs. and average rate of progress per day shall be 11.30 m / day.
Quantity in Concreting
The excavation works shall commence immediately after completing the mobilization. The
open excavation in rock and overburden will be carried out according to the principle of
“excavating from top to down and by layers and benches”. The drilling pattern shall be such
that per blast 500 m3 of rock is blasted and there shall be two such cycles/day ( i.e. one blast
in 12 Hrs) .
After completing the excavation & sub structure concreting, the erection of turbines &
generators shall be taken up, which will take about 12 months for each machine.
Superstructure Concreting shall continue with the erection of E&M equipment as and when
required.
13.1. General
Mawphu Hydroelectric Project, Stage - II is proposed as a run-of-river scheme on the river
Umiew in East Khasi Hills District of Meghalaya. The proposed dam site is located at about
3.17km downstream of Umduna HEP (90 MW) Power House location and the Power House
site is located at about 2km downstream of Thieddieng village on the right bank of the river.
13.2. Transportation:
The nearest broad gauge railway station is at Guwahati which is about 180 km from project
site.
State Highway is available from Shillong to reach Mawsynram, which is a small town at
about 60km from Shillong. Mawsynram is connected with Thieddieng village through about
6km long foot track. Road construction is in progress from Mawsynram towards Thieddieng
village and about 4km long formation cutting from Mawsynram has been completed. The
dam site can be accessed from Thieddieng (at about 2km) through footpath. The power
house site is also accessed from Thieddieng village (at about 2km) through footpath. There
is no direct connectivity between dam site and power house site.
By Air:
The project area can be accessed from Guwahati airport, which is at about 120 km from
Shillong, the capital of Meghalaya.
Construction Facilities for Mawphu HEP (Stage-II) have been divided into the following
components:-
c) Workshops
d) Warehouses/Stores Complex
f) Explosive Magazines
h) Land Requirement
i) Construction Power
j) Telecommunication
Five bridges, two permanent bridges of about 100m long and three temporary bridges of
about 50m long each have been proposed. In addition, 20 nos. of culverts at nallah
crossings have also been proposed.
1. 1200
Access Road From Adit-1 Portal To Dam Site
2. 2500
Access Road from Adit-3 portal to Adit-1 portal
Residential accommodation for staffs during construction and subsequently during operation
is necessary. Thus, the Residential Complexes are proposed near Dam site and Power
House site, which will accommodate dwelling units of different types for officers and staff.
Guest House would also be located in the Power house area.
Contractor’s colony and Labor colony would be at Dam, Adit-1 portal as well as power house
complex with all amenities.
13.3.3. Workshops
Central workshop for heavy earth moving equipment and transport vehicles shall be set up
at the project site. The area shall be developed considering open space and parking area.
The workshop shall comprise of covered/semi-covered repair sheds.
The workshop shall comprise facilities for the engine repairs and overhauling, transmission,
torque converter repair shops, auto-electrical shops, machine shop, tyre repair shop, welding
and fabrication shops, chassis repairs, body and seat repairs, denting/painting, maintenance
yard etc.
Space for construction of stores for Cement, Steel and other materials including chemicals
will be identified in a relatively flatter area on the right bank of River. The steel and other
store items like bitumen etc. which do not require covered area would be kept outside in
open. For the purpose of cement storage, covered sheds shall be developed enabling
storage of adequate quantity of cement.
The construction of various hydraulic structures like concrete dam, intake, power house etc.
will involve large excavation that would be disposed off in designated muck disposal areas
shown in the drawing no. 0933-CDC-01A-005-00, appended in Volume-IA of this report.
Muck arising from the cutting for roads would be utilized for filling wherever required and the
remaining would be disposed off in the nearby identified areas. The total area identified for
muck disposal for the whole project components is about 15.25 Ha.
In order to cater for blasting requirements of various work sites, it is planned to provide one
permanent explosive magazine along with proportionate quantity of detonators. Two portable
site magazines of 500 kg capacity will also be provided to cater to the day to day
requirement of explosives.
All safety codes and regulations prescribed by the Govt. in this respect will be followed and
magazines will be suitably guarded round the clock. Necessary approvals will be taken from
the concerned authorities for these magazines. Magazine areas have been proposed one on
right bank at Dam site, one between Adit 1 and 2. Magazine areas have been shown in the
drawing 0933-CDC-01A-005-00 appended in Volume-IA of this report.
Various installations like crushing plant, batching and mixing plant etc. are to be put up by
the contractor near the working sites.
Aggregate Crushing plant will be provided for aggregate preparation from excavated material
from surface and underground works. The details are given below:
Crushing plant of 1 no.170 TPH and 1 no.110 TPH Capacity will be located at
dam site.
Crushing Plant of 1 no. 170TPH and 1 no. 40 TPH will be placed near Power
house site.
As per requirement of concreting at various work sites, batching and mixing plants are
planned as under:
B & M plant of 2 nos. 60 cum/hr capacity at Dam site to meet the peak
production of concrete.
Site for fabrication of pressure shaft ferrules will be provided by the erection contractor of
pressure shaft on the right bank, u/s of Power House complex.
Land required for residential and non-residential buildings for the construction of the
approach roads, project components, workshops, stores, muck disposal, magazines,
construction plant facilities etc, will be acquired.
Muck Dumping
Adit 2 2.0
Adit 3 2.0
Magazine
Total 110
The possibility of tapping the local grid power will also be studied during the tendering stage,
wherein the capability of the local grid to supply construction power can be assessed based
on the loads and distribution system of nearby areas.
13.3.10. Telecommunication
The different work sites of the project offices, stores, laboratories, workshops and residences
etc will be connected by a telecommunication network including telephones for all offices
and residences of senior officers etc. The telecommunication facilities will also be provided
between the project & various major cities of India.
13.3.12.2.Fire Station
Two Fire stations of suitable size each are proposed; one at dam site and other at power
house site. These Fire stations will be fully equipped with modern fire fighting equipments.
Skilled Security Personnel will be used for firefighting Process.
14.1. Introduction
The major components of Mawphu Hydro Electric Project (Stage-II) comprise of Concrete
Gravity Dam, Power intakes, HRT, Pressure Shafts, Surface Power House. The project will
be completed in 60 months including 15 months for infrastructure development. Keeping in
view the schedule for the completion of Project and also to achieve the set targets and cover
all aspects involved in construction of the project, an organisation with dedicated workforce
is proposed so that the mega project can be completed within the schedule. The proposed
organisation structure has a built-in mechanism for review and monitoring of different
construction activities. The organisation team will perform to the best of its ability to achieve
the following objectives:
Satisfactory construction of the project
Compliance of Client’s requirement as well as local standards
Meeting project time schedule and budget
Conformance of Quality standards, design and drawing
Resolve technical issues / cost gaps
The Infrastructure works will be looked after by an AGM/DGM who will report to GM and will
be assisted by Senior Managers.
Senior Managers would be assisted by Managers/Dy. Managers. Senior
Engineers/Engineers would be reporting to Manager/Dy. Managers. Surveyors will also be
involved in the infrastructure development and will report to Senior Managers.
Electrical works during infrastructure development stage, including construction power and
liaison will be looked after by AGM/DGM. He will be assisted by 2 Senior Managers. Senior
managers will be assisted by Managers/ Dy. Managers and Senior Engineers/Engineers will
be reporting to Managers/Dy. Managers.
The main geological study of the project will be looked after by Senior Manager (Geology)
who will be reporting to GM (P). Senior Manager will be assisted by Manager/Dy. Manager
and further they will be assisted by two geologists during initial stage.
Environmental officer, Land Acquisition officer and quality control officer responsible for
environmental side of the project, acquisition of land and quality aspects respectively will
report to Senior Manager (Environment & CDM).
There will be a separate cost control division which will be headed by an AGM/DGM
(Finance) in association with a Senior Manager (Finance). The finance wing will be
responsible for overall financial management of the project. Senior Manager (Finance) will
be assisted by 2 Deputy Manager and 2 numbers of Accounts Executives.
The human resources department will be responsible for keeping personal records of the
employees posted in the project, public relations, labour and industrial relations and legal
matters. It will be headed by a Senior Manager/Manager (HR/Admin) who shall report to
AGM (Liasioning & Administration).
The project organization during the initial phase of one year would have the following
officers:
A brief description of the modules and various support departments are given below:
The construction of the project requires mammoth quantities of steel, cement and other
construction materials. These are not locally available and will have to be transported from
various parts of India. Accordingly, a number of godowns and stores will be planned at
Project Monitoring is the most crucial activity of any project and is concerned with activities
related to project monitoring and coordination. Billing and quality control wings will be
associated with the project monitoring.
The human resources department will be responsible for keeping personal records of the
employees posted in the project, public relations, labour and industrial relations and legal
matters. Furthermore, provision for medical facilities to cater to the specialized / emergency
treatments and residential facilities for construction workers, personnel and their families
etc., have been made under Administration wing. It will be headed by an AGM/DGM
(Liaisoning & Administration) and he will be assisted by one Senior Manager and further one
Dy. Manager will assist the Senior Manager.
Environmental officer, Land Acquisition officer and quality control officer responsible for
environmental side of the project, acquisition of land and quality aspects respectively will
report to Senior Manager (Geology). Since the project is located in a remote and tribal
region, in order to implement the Local area Development Program and Environmental
Management Plan, a dedicated team is required at the Project. The CDM aspect of the
project will also be covered by the Environmental wing.
Finance:
The finance wing will be responsible for overall financial management of the project. The
finance wing is concerned with accounting, auditing budgeting and financial control. It is to
be headed by an AGM/DGM (Finance) who will be assisted by 1 Senior Manager and two
numbers of Dy. Managers. There will be a separate cost control division which will be
headed by a Senior Manager (Finance) in association with a Senior Manager (Technical).
S.
No. Description Strength
Dy. Manager/ Asst. Manager (Project
4. Monitoring) 1
5. Dy. Manager/ Asst. Manager (Quality Control) 1
6. Dy. Manager/ Asst. Manager (Billing) 1
B. Environmental and Land Acquisition:
1. Dy. Manager/ Asst. Manager (Environment) 1
C. Finance:
1. Senior Manager/Manager (Finance) 1
2. Dy. Manager/ Asst. Manager (Finance) 1
3. Accounts Officer 1
D. Human Resource and Administration:
1. Senior Manager/Manager (Human Resource) 1
2. Senior Manager/Manager (Liaison) 1
3. Dy. Manager/ Asst. Manager (Liaison) 1
4. Executive 1
5. Doctor 1
6. Security & Safety Officer 1
7. Junior Executive 2
E. Stores and Purchase:
1. Manager (Incharge) 1
2. DM/AM 1
3. Executives 1
Total 21
It is also proposed that Running and Maintenance (R & M) of colonies and office complexes
and also services like security, R & M of telephone exchanges, equipment repairs, R & M of
inspection vehicles etc. may be entrusted preferably to local contractors. This would help in
keeping down the costs in addition to giving the local people a sense of participation in the
construction of the project.
A technical review committee of renowned experts drawn from various organizations will
constitute this committee. They will advise the project team through the project head on all
critical aspects of project planning, design and construction activities.
The monthly progress review meeting will be held once a month where details of progress and
shortfalls will be discussed. Necessary strategy for achieving targets as per the project
schedule will be formulated. All stake holders in the project will participate in the progress
review meeting and provide with the necessary inputs.
In the O & M period, the main thrust will be on operation and maintenance of the project. The
duties of personnel are defined with reference to three broad categories i.e operation,
maintenance and miscellaneous work. The operation staff is considered for 3 + 1 shift. One
Senior Manager (Civil) will look after the work of operation and maintenance in Dam area,
Gauge and flood warning system.
GM/AGM/DGM (Electrical), Power House complex would be assisted by two senior managers.
The Senior Managers would have the following work distribution:
Operation in Power House Area
Maintenance in Power House Area
The Senior Manager in charge of operation works would be assisted by four Managers/ Dy.
Managers who will work in shifts. The Senior Manager in charge of maintenance work would
be assisted by two Managers/Dy. Managers. One Manager/Dy. Manager will look after the
work of control and instrumentation and the other Manager/Dy. Manager will look after the
work of Electrical maintenance and mechanical maintenance. All Managers/Dy. Managers will
be assisted by required numbers of Senior Engineers/Engineers/Junior Engineers. The
project dispensary will be headed by ACMO/DCMO assisted by two medical officers and he
will report to the AGM/DGM (Electrical), Power House complex.
The other divisions include head quarter township maintenance both civil and electrical, store,
procurement and quality assurance and safety. All will be headed by Managers.
During the O & M period, the strength would be as follows:
S. No. Description Strength
1. GM/AGM/DGM 1
2. Senior Manager/Manager /ACMO 2
3. Dy. Manager/ Asst. Manager 6
4. Senior Engineer / Engineer / Junior Engineer 6
5. Accounts Executives 2
Personnel officer / Public Relation Officer / Law
6. Officer 1
The proposed Organization Chart of the project has been enclosed at Annexure 14.1 along
with the detailed chart of different modules.
Annexure 14.1
15.2.1. General
The estimate has been prepared to arrive at the capital cost of Mawphu HE Project,
Stage - II. The base date of the estimate is March 2014. The Cost Estimate is divided
into Civil and Electrical Works. The cost estimate for Transmission works has not
been considered in this study.
15.2.3. I – Works
Under this heading, provision has been made for various components of the Project.
15.2.4. A-Preliminary
Under this heading, "provision has been made for surveys and investigations to be
conducted to arrive at the optimum of the project components.
15.2.5. B-Land
This covers the provision for acquisition of land for construction of the project,
structures, colonies, offices etc. The provision has been kept in the estimate as per
actual.
15.2.6. C– Works
This covers the cost of Concrete Gravity Dam, Spillway, Coffer Dams, Diversion
Tunnel, Inlet & Outlet Portal and Plug along with associated Hydro-Mechanical
equipments.
15.2.8. K – Buildings
Buildings, both residential and non-residential have been provided under this head.
Under the permanent category only those structures have been included, which will
be subsequently utilized for the running and maintenance of the project utilities. The
costs are worked out on plinth area basis for the type of construction involved as per
prevailing rates in project area.
15.2.9. M – Plantation
The provision under this head covers the plantation programme including Gardens
etc. required for beautification as considered necessary downstream of Dam and
appurtenances around Power House and other important structure. The provision is
made on the lump sum basis.
15.2.10. O– Miscellaneous
The provision under this head covers the capital cost & maintenance of Electrification,
Water supply, Sewage disposal and drainage works, Recreation, Medical, Fire fighting
equipments, Inspection vehicles, School bus, Pay van, Visit of dignitaries, welfare
works etc.
15.2.13. R– Communication
Provision under this head covers the cost of construction of roads and bridges for
project works. The road widths have been planned to cater to the anticipated traffic
including carriage of equipment for the Project. The cost of roads is based on the
present rate structure prevalent in the area of the Project, for the type of construction
involved.
Annexure 15-1
ABSTRACT OF COST
S. Item Cost (In Rs
ITEM
No. Code Lakhs)
A CIVIL AND HM WORKS:
1 DIRECT CHARGES
i I-WORKS
A Preliminary & Pre-Operative Expenses 3455.00
B Cost of Land 2010.64
C Civil Works
River Diversion (Diversion Inlet, Outlet and Coffer
C1 940.50
Dam)
C2 River Diversion (Diversion Tunnel) 1501.93
C3 Dam 19122.92
J Power Plant Civil Works
J1 Power Intake 1180.23
J2 Head Race Tunnel 4299.70
J3 All adits of WCS 428.40
J4 Surge Shaft 1352.24
J5 Pressure Shafts 8777.90
J6 Power House 5126.07
K Buildings 2032.00
M Plantation 25.00
O Miscellaneous 1105.00
P Maintenance during Construction @ 1% of C, J, K 447.70
Q Special Tools & Plants 149.26
R Communication 4800.00
X Environment and Ecology 2000.00
Y Losses on stock @ 0.25% of C, J, K 112.00
TOTAL I-WORKS 58866.49
ii Establishment Charges @ 6% of I-Works less Land 3411.35
iii Tools & Plants @ 0.5% of I-Works less Land 284.28
iv Suspense -
v Receipts and Recoveries (-) -152.75
2 INDIRECT CHARGES
16.1. Introduction
Mawphu Hydro Electric Project, Stage - II is proposed as a run-of-river scheme on
the river Umiew in East Khasi Hills District of Meghalaya. The proposed dam site is
located at about 3.1km downstream of Umduna HEP (90 MW) Power House location
and the Power House site is located at about 2km downstream of Thieddieng village
on the right bank of the river.
The Project is estimated to cost Rs. 7700.05 Million at May 2014 Price Level
including Rs.2156.53 Million on C-Civil works, Rs. 2116.54 Million on J-Works, Rs.
1419.45 Million on Electrical Works, Rs. 1098.26 Million on IDC including Financing
Charges. Sale price of energy generated at powerhouse at bus bar has been worked
out as Rs. 6.19/unit at May 2014 P.L. (Excluding transmission cost)
3552.5
H-8 1155.01 71.06 2400.77 1155.01 4 236.86
4873.3
H-9 539.00 86.30 2471.83 539.00 4 287.68
5619.1
H-10 308.00 93.93 2558.13 308.00 0 313.09
6146.2
2652.05 6
Total 7700.05 1098.27
Hard Cost = 7,700.05 87.5% Loan 6,146.26
IDC = 1,098.267 12.5% Equity 2,652.05
Total = 8,798.319 Total 8,798.32
16.4. Financing
The project shall be financed at the rate of interest of 12% p.a. For analysis purpose 70% of
capital cost is considered as debt and balance is equity.
16.7. The Assumptions taken for working out the Tariff are as follows: -
Project Life
The project life has been taken as 35 years for all the above cases as per prevailing Indian
Hydropower policy.
Interest rate
The interest rate of 12.00% has been reckoned for working out the financial return. The
interest during construction has also been capitalized as 70% loan and 30% equity.
Return on Equity
For working out the unit cost of energy, the return on equity has been taken at 16.5% as per
prevailing practice of Govt. of India.
Depreciation
In accordance with the current practice, deprecation has been calculated at a rate of 5.28%
for first 12 years and the remaining value is spread out for the remaining life of the project
i.e. 23 years.
Operation and Maintenance charges
According to the current practice, 2.5% of capital cost has been taken for operation and
maintenance charges with an annual escalation of 5.72%.
Auxiliary and Transformation Losses
The auxiliary and transformation losses have been taken as 1.2% of the design energy in a
90% dependable year. (Design Energy= 283.34MU, Unit Sold = 283.34*(1-1.2%) =
279.94MU)
Other Miscellaneous assumptions
With above assumptions the tariff for the project for 90% dependable year comes out
to be: -
ANNEXURE-16.1
CALCULATION OF TARIFF FOR 90% DEPENDABLE YEAR AT BUS BAR
1 2 3 4 5 6 7 8 9 10 11 12 13
1 414.96 414.96 547.04 712.65 219.96 18.33 32.99 323.90 48.78 1943.39 279.94 1.000 1943.39 279.94 XA 6.94
2 414.96 414.96 547.04 662.86 232.54 19.38 34.88 317.62 48.34 1905.74 279.94 0.884 1685.01 247.52 XA 6.81
3 414.96 414.96 547.04 613.06 245.84 20.49 36.88 311.48 47.95 1868.85 279.94 0.782 1461.00 218.85 XA 6.68
4 414.96 414.96 547.04 563.27 259.90 21.66 38.99 305.46 47.59 1832.76 279.94 0.691 1266.83 193.50 XA 6.55
5 414.96 414.96 547.04 513.47 274.77 22.90 41.22 299.59 47.28 1797.52 279.94 0.611 1098.56 171.09 XA 6.42
6 414.96 414.96 547.04 463.68 290.49 24.21 43.57 293.86 47.01 1763.18 279.94 0.540 952.76 151.27 XA 6.30
7 414.96 414.96 547.04 413.88 307.10 25.59 46.07 288.30 46.79 1729.78 279.94 0.478 826.45 133.75 XA 6.18
8 414.96 414.96 547.04 364.09 324.67 27.06 48.70 282.90 46.62 1697.38 279.94 0.422 717.04 118.26 XA 6.06
9 414.96 414.96 547.04 314.29 343.24 28.60 51.49 277.67 46.51 1666.04 279.94 0.374 622.28 104.56 XA 5.95
10 414.96 414.96 547.04 264.50 362.87 30.24 54.43 272.64 46.45 1635.82 279.94 0.330 540.22 92.45 XA 5.84
11 414.96 414.96 547.04 214.70 383.63 31.97 57.54 267.80 46.45 1606.78 279.94 0.292 469.17 81.74 XA 5.74
12 414.96 414.96 547.04 164.91 405.57 33.80 60.84 263.17 46.51 1578.99 279.94 0.258 407.65 72.27 XA 5.64
13 125.20 125.20 547.04 132.50 428.77 35.73 64.32 212.35 40.61 1274.12 279.94 0.228 290.84 63.90 XA 4.55
14 125.20 125.20 547.04 117.47 453.30 37.77 67.99 214.10 41.58 1284.59 279.94 0.202 259.27 56.50 XA 4.59
15 125.20 125.20 547.04 102.45 479.23 39.94 71.88 216.09 42.63 1296.54 279.94 0.178 231.37 49.96 XA 4.63
16 125.20 125.20 647.75 87.43 506.64 42.22 76.00 235.50 45.98 1413.00 279.94 0.158 222.95 44.17 XA 5.05
17 125.20 125.20 647.75 72.40 535.62 44.63 80.34 238.03 47.19 1428.16 279.94 0.140 199.24 39.05 XA 5.10
18 125.20 125.20 647.75 57.38 566.25 47.19 84.94 240.84 48.49 1445.07 279.94 0.123 178.25 34.53 XA 5.16
19 125.20 125.20 647.75 42.35 598.64 49.89 89.80 243.97 49.88 1463.82 279.94 0.109 159.65 30.53 XA 5.23
20 125.20 125.20 647.75 27.33 632.89 52.74 94.93 247.42 51.36 1484.53 279.94 0.096 143.15 26.99 XA 5.30
21 125.20 125.20 647.75 12.31 669.09 55.76 100.36 251.22 52.95 1507.30 279.94 0.085 128.51 23.87 XA 5.38
22 125.20 125.20 647.75 0.00 707.36 58.95 106.10 255.84 54.72 1535.03 279.94 0.075 115.72 21.10 XA 5.48
23 125.20 0.00 647.75 0.00 747.82 62.32 112.17 262.94 56.87 1577.64 279.94 0.067 105.15 18.66 XA 5.64
24 125.20 0.00 647.75 0.00 790.60 65.88 118.59 270.45 59.14 1622.69 279.94 0.059 95.63 16.50 XA 5.80
25 125.20 0.00 647.75 0.00 835.82 69.65 125.37 278.39 61.54 1670.31 279.94 0.052 87.04 14.59 XA 5.97
26 125.20 0.00 647.75 0.00 883.63 73.64 132.54 286.78 64.08 1720.66 279.94 0.046 79.27 12.90 XA 6.15
27 125.20 0.00 647.75 0.00 934.17 77.85 140.13 295.65 66.77 1773.89 279.94 0.041 72.26 11.40 XA 6.34
28 125.20 0.00 647.75 0.00 987.60 82.30 148.14 305.03 69.61 1830.17 279.94 0.036 65.92 10.08 XA 6.54
29 125.20 0.00 647.75 0.00 1044.09 87.01 156.61 314.94 72.61 1889.66 279.94 0.032 60.18 8.91 XA 6.75
30 125.20 0.00 647.75 0.00 1103.82 91.98 165.57 325.43 75.79 1952.56 279.94 0.028 54.98 7.88 XA 6.97
31 125.20 0.00 647.75 0.00 1166.96 97.25 175.04 336.51 79.14 2019.05 279.94 0.025 50.27 6.97 XA 7.21
32 125.20 0.00 647.75 0.00 1233.71 102.81 185.06 348.22 82.69 2089.35 279.94 0.022 45.99 6.16 XA 7.46
33 125.20 0.00 647.75 0.00 1304.27 108.69 195.64 360.61 86.44 2163.67 279.94 0.019 42.11 5.45 XA 7.73
34 125.20 0.00 647.75 0.00 1378.88 114.91 206.83 373.71 90.41 2242.24 279.94 0.017 38.58 4.82 XA 8.01
35 125.20 0.00 647.75 0.00 1457.75 121.48 218.66 387.55 94.60 2325.30 279.94 0.015 35.38 4.26 XA 8.31
7859.08 14752.06 2384.37 XA