You are on page 1of 146

Geotechnical Engineering Aspects of

Trans-Tokyo Bay Highway Project

TATSUOKA F.
TATSUOKA, F
Tokyo University of Science

1
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues


related to geotechnical engineering
- Cement-mixed soil
- Others

■ Concluding remarks
2
Trans-Tokyo Bay Highway

15.1 km-long
g toll highway
g y
3
Brief history
May 1971:
The technical investigation
started.
t t d
May 1983:
The Japanese Government
approved the construction.
October 1986:
The Trans-Tokyo Bay Highway
Corporation was established.
M 1989:
May 1989
The construction started.
December 1997:
The construction completed;
and the highway was opened to
public on 18th December.
4
Trans-Tokyo Bay Highway

5
Ukishima access

Kisarazu man-made island

Kawasaki man-made island

Bridge

6
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge

PLAN

PROFILE

7
Ukishima access

The starting point


of the shield tunnels
tunnels,
towards the center of the Tokyo8 Bay
Steel caisson:
1) to start the shield tunnel construction;
2) the ventilation tower after competition.

Approach fill, retaining shield tunnels.

9
Ukishima access

10
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge

PLAN

PROFILE

11
Kawasaki man-made island

Cross-section

Artist’s view of the completed structure


12
A huge offshore diaphragm wall;
- 98 m in int. dia.;; & 119 m in height
g

13
An artist’s view from underground
A ring
i space ffor a diaphragm
di h wallll

190 m

14
Kawasaki man-made island
Immediately after
Immediately before the ground excavation the end of ground excavation

15
Ground improvement
by sand compaction pile technology

16
Ground improvement by sand compaction pile technology

17
Construction of external and internal steel structures
after necessary ground improvement work

18
19
20
Filling up the ring space
with cement-mixed sand slurry

21
Construction of a diaphragm
wall in the cylindrical ring of
cement-mixed sand fill and
cement mixed in
cement-mixed in-situ
situ soft clay

22
Filled with mud slurry:
y
Why the vertical wall can
stand without support for a so
Excavation machine
large depth ?
23
24
Excavation of
the inside ground

25
Excavation of the inside ground

26
Construction of the internal structure inside the diaphragm wall

27
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge

PLAN

PROFILE

28
Two 9.5 km-long shield tunnels

29
Two 9.5 km-long shield tunnels

2 2 2 2

Two tubes; constructed


Th thi
The third
d one; iin th
the ffuture.
t

Eight shield tunnel machines worked simultaneously


t reduce
to d th
the total
t t l construction
t ti period.
i d
30
Blind type
using pressurized mud
slurry

The world
world’ss largest diameter
at the time of construction

14.14 m

31
32
Development of shield tunnel diameter

33
Blind type
using pressurized mud
slurry

The world
world’ss largest diameter
at the time of construction

Pressurized mud slurry


slurry.
Why ? 14.14 m

34
Shield tunnel machine
re-assembled to start
from Kawasaki m-m island

35
Two 9.5 km-long shield tunnels

36
Secondaryy inner RC lining
g
(inside the RC segments)

RC segments

37
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge

PLAN

PROFILE

38
Kisarazu man-made island

Shield
t
tunnels
l

39
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge

PLAN

PROFILE

40
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues


related to geotechnical engineering
- Cement-mixed soil
- Others

■ Concluding remarks
41
One of the p
proposals
p that were not accepted
p

42
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy shipping routes;

43
44
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy crossing shipping routes;
・Poor ground conditions; and
・A high seismic activity.

Late Holocene very soft clay

Early Holocene sand and clay

45
46
47
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy crossing shipping routes;
・Poor ground conditions; and
・A high seismic activity.

Late Holocene very soft clay

Early Holocene sand and clay

48
Very high seismic activity
In Tok
Tokyoo Ba
Bay area

1923
The Great Kanto Earthquake

49
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues


related to geotechnical engineering
- Cement-mixed soil
- Others

■ Concluding remarks
50
Significant design and construction issues
related to geotechnical engineering - 1:

Large-scale
Large scale improvement of existing soft clay deposits
by cement mixing in place,
- controlling the strength of cement
cement-mixed
mixed soft clay; and
- in total 3.77 million m3.

51
Ground improvement techniques by cement-mixing
used in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3


Ordinary DMM Cement: 140 kg/m3
W/C ratio: 100 % Ka asaki m-m
Kawasaki m m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248


W/C ratio: 100 % Kisarazu m-m
m m isl.
isl 289
Kawasaki m-m isl. 168

Slurry type cement


cement-mixed 1 177 kg/m3
mixed Sand: 1,177 Ukishima Access 11,028
028
sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351
original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118
Sea water: 505 kg/m3

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 52
Ukishima access

Very soft clay improved


by in-situ cement-mixing,
achieving a controlled
strength; i.e.,
a) strong enough for
the stability of the
structure; and
b) weak enough for
53
smooth tunnelling.
54
Cement mixing in place
of soft clay deposits

55
Haneda airport
-restriction to the height
g of
the construction plants (50 m)

56
Conventional design for
cement-mixed soft clay:

Allowable stress method


ensuring
i ththe working
ki stress
t
evaluated by the elastic
theory be smaller than the
allowable stress, equal to
about 1/6 of unconfined
compressive strength

→ Unduly conservative
design
g for huge
g masses
q – ε1 relations from U & CU
TC tests on cement-mixed
clay (aw= 20 %) (Kobayashi
& Tatsuoka, 1982).
Significant effects of
drained condition and
confining pressure (when
drained)

→ The in-situ stress-strain


behaviour is largely
different from the
unconfined compression
test

→ Need for triaxial tests

q – ε1 relations from U & CU


TC tests on cement-mixed
clay (aw= 20 %) (Kobayashi
& Tatsuoka, 1982).
Following the principle
of effective stress, as
ordinary soils

Peak stress envelops from


U and CD & CU TC tests
on uncemented clay and
cement-mixed clay (aw=
8 %, 10 %, 14 % & 20 %)
(T t
(Tatsuoka
k & Kobayashi,
K b hi
1983).
Significant effects of
confining pressure on
the drained peak
strength

→ Not used in the design


g
to take into account
effects of progressive
failure

Normalised drained peak


p
strength plotted against σc’
for cement-mixed clay
(Kobayashi & Tatsuoka,
1982).
Significant effects of
confining pressure on
the drained residual
strength

→ Used in the design


g as
the conservative strength

Normalised drained
residual strength plotted
against
i t σc’/q
’/ u for
f cement- t
mixed clay (aw= 8 %, 10 %,
14 % & 20 %) (Kobayashi
& Tatsuoka, 1982).
Nearly no effects of
confining pressure on
the undrained peak
and residual strength
at low
a o co
consolidation
so da o
pressure

Normalised undrained
peak and residual
strengths plotted
against σc’/qu for
cement-mixed clay
(Kobayashi & Tatsuoka
Tatsuoka,
1982).
Large-scale yield stress, qy, divided by qu versus effective
confining pressure divided by qu from CD TC tests on
cement-mixed clay (Kobayashi & Tatsuoka,1982)
qr/qu or
qy/qu qr/q
/ u (drained)
(d i d) for
f
design under
Design strength in static condition
A
zone A was used in
the limit equilibrium
qr/qu (undrained)
stability analysis
for seismic
design

Normalised drained and qy/qu (Y1: drained)


undrained residual
strengths & drained yield
stress plotted against
σc’/q
’/ u (Tatsuoka
(T t k & 0 σc’/qu
Kobayashi, 1983)
Ukishima access

Very soft clay improved


by in-situ cement-mixing,
achieving a controlled
strength; i.e.,
a) strong enough for the
stability of the
structure; and
b) weak enough for
smooth tunnelling.65
Controlled shear strength of cement-mixed soft clay

wn (%) γt (gf/cm3) qmax (kgf/cm2) (t= 28 days)

Compressive strength after cement


mixing
: qu by unconfined compression tests
x : qmax by CU TC tests

Original ground:
qu (kg/cm2)= 0.044z – 0.88
((z= depth;
p z= 0 m at TP= 0.0).
)

(m)

66
Too large scatter in the unconfined compressive strength due to
effects of sample disturbance, not reliable:
Fi l decision
Final d i i b based d on th
the CU TC ttests.
t
wn (%) γt (gf/cm3) qmax (kgf/cm2) (t= 28 days)

Compressive strength after cement


mixing
: qu by unconfined compression tests
x : qmax by CU TC tests

Original ground:
qu (kg/cm2)= 0.044z – 0.88
((z= depth;
p z= 0 m at TP= 0.0).
)

(m)

Reliable data ? 67
Significant design and construction issues
related to geotechnical engineering - 2:

Construction of large embankments by using


- cement-mixed sand slurry with a controlled strength
at the ramp sections.
sections

68
Ground improvement techniques by cement-mixing
used in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3


Ordinary DMM Cement: 140 kg/m3
W/C ratio: 100 % Ka asaki m-m
Kawasaki m m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248


W/C ratio: 100 % Kisarazu m-m
m m isl.
isl 289
Kawasaki m-m isl. 168

Slurry type cement


cement-mixed 1 177 kg/m3
mixed Sand: 1,177 Ukishima Access 11,028
028
sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351
original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118
Sea water: 505 kg/m3

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 69
Ukishima access

Embankment of
cement-mixed sand slurry
with:
ith
a) a controlled strength;
and
b) a controlled high density
to resist the buoyant
y
force of the tunnels.70
Underwater placement of
cement-mixed sand slurry

71
72
73
No previous construction experiences

→Placement test in a ship-building dock; and block-


sampling from the deposit to obtain specimens for
laboratory stress-strain tests to evaluate the strength
and stiffness

74
26 August 1988 ( several years before
75
the actual construction)
26 August 1988 ( several years before
76
the actual construction)
Reduction of the strength
by absorbing
abso b g water
ate
during under-water
placement

77
Reduction of the strength by absorbing water
during
du guunder-water
de ate p placement,
ace e t, not
ot due to losing
os g tthe
e ce
cement
e t co
conent
e t

78
Sampling of large samples
(30 cm in dia) to evaluate
possible large scale effects
by possibily siginificant in-
h
homogeneityi off the
h material i l
placed under water.

It was found after TC tests


on these large samples and
small samples that it was not
the case.

79
80
Triaxial testing system
p
for 30 cm-dia. specimens
at the University of Tokyo. 81
Triaxial testing system
for small specimens
at the University of Tokyo. 82
Use of LDT with small and large specimens

83
12 cm H x 5 cm D 60 cm H x 30 cm D
Membrane

Pseudo-hinge

Instrument
Phosphor bronze LDT Gage leadwire Terminal leadwire
strain-gaged strip Active e.r.s.g.
B'
No. 1
A
D' C
No. 2

Heart of LDT Teflon tube protection


PB strip
(includes electric resistance strain gages, Front face (tension side)
(Front)
terminals, wiring, sealant)

Scotch tape used to fix wire No. 3


A'
D
p
on the specimen surface No. 4
C' B

Back face (compression side)

Instrument Leadwire (Back)

Membrane Surface

LDT; Local deformation transducer (Goto et al


al., 1991)
1991).
84
Dr. Goto,S.; the inventor of
LDT (local deformation transducer)

Institute of
Industrial Science,
Universityy of Tokyo,
y ,
1986

85
Summary of results from CD TC tests on large core samples
of slurry type cement-mixed sand (Uchida et al., 1993)
- Significant effects of consolidation pressure
Summary of results from CU TC tests on large core samples
of slurry type cement-mixed sand (Uchida et al., 1993)
- Insignificant effects of consolidation pressure
Essentially no scale
effects on the peak
strength !

But large scale effects


on the stiffness → Why?

Comparison
C i off q-’externally
’ t ll
measured axial strains from
CU TC tests using small and
large core samples from the
same mass of slurryy typeyp
cement-sand constructed in
the full-scale field
underwater
d t placement
l t test
t t
(Tatsuoka et al., 1997).
Essentially no scale
effects on the peak
strength !

But large scale effects


on the stiffness → Why?

Comparison
C i off q-’externally
’ t ll
measured axial strains from
CD TC tests using small and
large core samples from the
same mass of slurryy typeyp
cement-sand constructed in
the full-scale field
underwater
d t placement
l t test
t t
(Tatsuoka et al., 1997).
A typical CU TC test on a large core sample of slurry
type cement-mixed
cement mixed sand (Tatsuoka & Shibuya
Shibuya, 1991)
1991).
A typical CU TC test on a small core sample of slurry
type cement-mixed
cement mixed sand (Tatsuoka & Shibuya
Shibuya, 1991)
1991).
Einitial: the value that had been reported by an geotechnical
consultant
→ by
b ttriaxial
i i l ttests
t ffollowing
ll i th the common practice
ti att th
thatt titime
→ a significant underestimate (about 1/10) of the true value of
small-strain stiffness to be used in deformation analysis of
the cement-mixed soil in the field
The first case where:

1. LDT was used for a practical


case; and
2 the
2. th elastic
l ti modulus
d l ffrom
triaxial tests exhibits nearly
the same value with that
from the field shear wave
velocity.

96
The Young’s modulus value
that had been obtained by
a geotechnical
t h i l consultant:
lt t
Einitial = 0.3 Gpa
(by conventional drained TC
tests)
This value
Thi l considerably
id bl
underestimates the true
elastic modulus:
E0= 3.0 GPa
and also the value at the
operating strain !

The engineers
Th i iin charge
h off
the TTB Highway project
could become confident with
the use of this material for 97
this project !
Shear modulus vs shear strain relations from monotonic
and cyclic loading triaxial tests on core samples (30 cm in
diameter) from test fills of slurry type cement-mixed sand
(Tatsuoka & Shibuya, 1991).
Strains in the cement-mixed fill lower than 0.05 % (estimated
by FEM earthquake response analysis) →
Nearly linear behaviour at small strains
Importance
p of elastic modulus &d its accurate measurements

99
Evaluation of the stress-strain properties of
cement-mixed soil filled in the field

to confirm whether fills of cement-mixed soil


as considered at the design stage were
actually constructed

100
Underwater placement work of slurry type cement-
mixed
i d sand d at Ukishima
Uki hi A
Access and
d Kisarazu
Ki man-
made island (Uchida et al., 1993).

Vessel conveying materials Vessel having Tremmie piles


Vessel having a mixing
(capacity: 1,000
1 000 – 2,000
2 000 m3) ((capacity:
p y 3,000
, ton))
plant
l t (production
( d ti capacity: it
450 m /hour)
3

TP 0.0 m

Lift ((m))
Vessell carry mud
V d slurry
l
(capacity: 2,000 m3)

Mound produced on
the sea bed
14 m

Rotary core tube sampling at


Original shore
th Ukishima
the Uki hi A
Access; protection works
a) to obtain undisturbed 5m

samples; and N1 N2

Trans Tokyo Bay


y
b) to measure shear wave Steel caisson

Highway
velocities.

H
S2
Shield
S1 tunnels*
(*) th
the ttop one in
i thi
this
figure has not been
constructed)

102
Comparison of elastic the Young’s moduli from triaxial
compression
p tests ((E0) and those from field shear wave velocities
(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access

E0 and Ef are similar !

103
Comparison of elastic the Young’s moduli from triaxial
compression
p tests ((E0) and those from field shear wave velocities
(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access

E0 and Ef are similar !

104
Completed Kawasaki man-made island

Filling of slurry type


Cement-mixed sand 193 m
189 m
35 m 2.8 m 2.8 m 98 m 2.8 m 2.8 m 35 m
4m 4m
Outer jacket Filling Outer jacket
TP – 6 m Upper RC slab
TP 5 m
TP 0 m TP 0m
Inner wall

46.7 m
TP – 28 m Steel pipe

74.2 m
Steel pipe
sheet pile sheet pile
Slab SCP
SCP DMM
DMM TP – 41.7 m

21.5 m
6m
TP – 73 m
Bottom RC slab
90 m Thickness= 2.8 m
Thickness= 2.8 m
4m 98 m 4m
Continuous diaphragm wall (L= 119 m)

TP - 114 m
Filling up the ring space
with cement-mixed sand slurry,
Kawasaki man-made island

106
A typical test result on an undisturbed sample
of cement-mixed
cement mixed sand (slurry type)

3 200

LDT
MPa)

Pa)
Deviator stress, q (M

Deviator sttress, q (kP


1.5 100
External

CU TC (σc’= 127 kPa) CU TC (σc’= 127 kPa)


D
0 0
0 0.5 1.0 0 0.005 0.01
strain, ε1 (%)
Axial strain (LDT) ε1 (%)
Axial strain (LDT),

107
Initial Young’s modulus, E0, based on locally measured axial
strains vs initial Young’s modulus, Einitial, based on externally
measured d axial
i l strains
t i ffrom CU TC ttests t off specimens
i
prepared in the laboratory and core sample from Kawasaki
man-made island
island, slurry type cement-mixed sand (Tatsuoka et
al., 1997).

Confirmation that the


external axial strain
measurement in TC tests is
utterly
l unreliable
li bl to
accurately evaluate the
stiffness at small strains of
cement-mixed soil.
Comparison of elastic the
Young’s
g moduli from triaxial
compression tests (E0) and
those from field shear wave
velocities
l iti (Ef) in
i th
the fill off
cement-mixed sand (slurry
type) Kawasaki man-made
type),
island

E0 and Ef are similar !

109
Significant design and construction issues
related to geotechnical engineering - 2:

Construction of large embankments by using


- cement-mixed sand slurry with a controlled strength
at the ramp sections; and
- dry cement-mixed sand at the flat place of
Kisarazu man-made
man made island.
island

110
Ground improvement techniques by cement-mixing
used in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3


Ordinary DMM Cement: 140 kg/m3
W/C ratio: 100 % Ka asaki m-m
Kawasaki m m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248


W/C ratio: 100 % Kisarazu m-m
m m isl.
isl 289
Kawasaki m-m isl. 168

Slurry type cement


cement-mixed 1 177 kg/m3
mixed Sand: 1,177 Ukishima Access 11,028
028
sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351
original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118
Sea water: 505 kg/m3

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 111
Underwater placement of
dry mixture of cement-mixed sand
(Ki
(Kisarazu man-maded iisland):
l d)
a lower cost and a low quality

112
Underwater placement of dry
mixture of cement-mixed sand
(Ki
(Kisarazu man-made l d) a new
d iisland):
method to minimize the segregation
of material during placing

Special double-chute

113
Underwater placement of
dry mixture of cement-mixed sand
(Ki
(Kisarazu man-maded iisland)
l d)

114
Comparison of elastic the Young’s
moduli from triaxial compression
p
tests (Eo) and those from field
shear wave velocities (Ef) at the
fill off cement-mixed
t i d
sand (dry type), Kisarazu
man-made island

E0 and Ef are similar !


115
Summary of elastic Young’s moduli
of the cement-treated soils in the TTB Project

Emax defined
d fi d ffor strains
t i lless
than 0.001 % from triaxial
compression tests using LDTs
on undisturbed samples (kgf/cm2)

Ef from field shear wave velocity Vs (kgf/cm2)


116
TS=fixed-piston thin-wall sampling Cement-treated soil
BS=block sampling Slurry Dry DMM
DC=direct coring RCT
RCT=rotary
RCT rotary coring BS+DC
Sedimentary soft rock
Kazusa Kobe Sagara Miura Tokoname Uraga-A Uraga-B

G0 values from
RCT
BS+DC

CU TC tests 5000
Local axial strain measurements

or softrockss)
versus 1000

G0=E0/{{2(1+ν)} (MPa)
Range for Soft rocks and

5 for clays and 0.42 fo


C
Cement-treated
t t t d soils
il

Gf from
(BS+DC) and clays

field shear wave


velocities 100
Pleistocene clay site
(ν=0.5

Tokyo Osaka OAP Suginami


bay bay
)
:1
(1

)
:2 TS
(1

BS
10
10 100 1000 5000
2 117
Gf=ρ(V )
s vh
(MPa)
Summary of E0 versus qpeak relations from triaxial tests,
TTB project (Tatsuoka et al., 1997).
The strength and deformation characteristics* of
cement-mixed soil could be made similar without
a large difficulty to those of natural sedimentary soft rock.
(* should be measured accurately)

10000
10,000

10,000
10000
1000
1,000 E0/qpeak= 1,000
E0/qpeak= 1,000
MPa)
MPa)
(M
EE0 (M
o

E /q = 100
E00/qpeakpeak= 100 1,000
1000
100
100

MPa)
E0 (MPa)
E0 (M
Sedimentary softrocks
Sedimentary soft rocks E0/qpeak
100
100 E /q
0 peak
10
10 = 1,000
0.1
0.1 1 1 10 10 100 100 = 1,000 EE00/q/qppeak= 100
qpeak (MPa) peak= 100
qpeak (MPa)
Cement-mixed soil
Cement-mixed soils
Cement-mixed soil having 10
10
0.1
0.1 1 1 qpeak (MPa)10
10 100 100

a controlled
t ll d strength;
t th made
d qpeak (MPa)

intentionally weak 119


Strength of cement-mixed soil: between soil and concrete

1,000

Artificially produced materials


Manus clay (TC; Jardine,
Jardine 1985)
London clay (TC; Jardine, 1985)
100 Sand (monotonic torsional shear, n= 0.5)
Sand (monotonic drained TC)
Gravel (monotonic drained TC)
S d silt
Sandy il (monotonic
( i drained
d i d TC)

10 Cement-mixed sand in TTB highway project


(core samples from full-scale tests)
Pa)

dry type
E0(GP

slurry type

1
E0/qpeak= 1,000
Steel (SS41)
Hard rock core
0.1 (ultrasonic for E0)
Concrete
Mudstone (Sagamihara)*
Mudstone (Sagara)*
0.01 E0/qpeak= 100 Sand/mudstone (Sagara)*
*:: Sedimentary soft rock

0.01 0.1 1 10 100 1,000 120


qpeak (MPa)
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues


related to geotechnical engineering
- Cement-mixed soil
- Others

■ Concluding remarks
121
Significant design and construction issues
related to geotechnical engineering - 3:

Construction of shield tunnels;;


a) Consecutively in very stiff cement-mixed soil and very soft
clay at a very shallow depth

122
Ukishima access

Two tunnels
A sudden largeg changeg from Ukishima
in the cutting torque of
shield machine ((tonf-m))
123
Ring number (one ring= 1.5 m)
Ukishima access

Very soft clay


with a very thin
overlaying soft clay

A danger of floating up
of the tunnels by large buoyant
force acting
g to the tunnels,,
compared to a small surcharge;
prevented by placing weight
i the
in th ttunnels
l andd careful
f l
tunnelling work. 124
Significant design and construction issues
related to geotechnical engineering - 3:

Construction of shield tunnels with the world’s largest


g diameter;;
a) successively in stiff cement-mixed soil and very soft clay at a
very shallow depth; and
b) underground connection of shield machines with the help of
ground freezing to shorten the drive of each tunnel.

Locations of tunnel connection

125
Two 9.5 km-long shield tunnels

126
Underground connection of shield machines
with the help of ground freezing

Longitudinal section

Cutting
g face Cutting
g face

Second arrived First arrived

shield tunnel shield tunnel

Freezing pipe

Frozen zone
127
Significant design and construction issues
related to geotechnical engineering - 4:

A huge offshore
diaphragm wall;
- 98 m in int.
int dia.;
dia ; &
- 119 m in height
for Kawasaki
man-made island.

An artist’s
artist s view
from the beneath 128
Construction of the internal structure inside the diaphragm wall

129
Construction of
the internal structure

130
Deep well system to avoid Observation
the ground failure by seepage Drainage
g wells wells

Diaphragm
wall

A-sandy
layer

Thin clay layer

B-sandy layer

Thick clay layer C-sandy


layer
131
Observation
Drainage
g wells wells

Diaphragm
wall

A-sandy
layer

Thin clay layer

A serious seepage B-sandy layer


accident;
C-sandy
Start of unusual g
ground layer Thick
c cclay
ay layer
aye
water spouting 132
14th Nov. 1993
Time histories of ground water spouting
and water depth inside the diaphragm wall

Depth of water
Amount of inside the
spouting ground water diaphragm wall
(m3 per day) (m)

First stage Second stage

Depth of
Increase in the
water in the
rate of ground
diaphragm
water spouting
wall
Amount of
spouting
ground water

Start of pouring
Start of unusual sea water into
spouting of the inside of the
ground water diaphragm wall

Date for a period from 14 November to 4th December 1993 133


Time histories of ground water spouting
and water depth inside the diaphragm wall

Depth of water
Amount of inside the
spouting ground water diaphragm wall
(m3 per day) (m)

First stage Second stage

Depth of
Increase in the
water in the
rate of ground
diaphragm
water spouting
wall
Amount of
spouting
ground water

Start of pouring
Start of unusual sea water into
spouting of the inside of the
ground water diaphragm wall

Date for a period from 14 November to 4th December 1993 134


Sea water poured to reduce the hydraulic gradient in the
ground inside and immediately below the the diaphragm wall

135
Restart of construction
after a delay of six months

136
137
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues


related to geotechnical engineering
- Cement-mixed soil
- Others

■ Concluding remarks
138
Brief history
May 1971 (25):
The technical investigation
started.
May 1983 (37):
The Japanese Government
approved the construction.
October 1986 (40):
The Trans-Tokyo Bay Highway
Corporation was established.
May 1989 (43):
The construction started.
December 1997 (51):
The construction completed;
and the highway was opened to
public on 18th December. 139
CONCLUDING REMARKS-1

The Trans-Tokyo Bay Highway was constructed;


a) in a relatively deep sea;
b) crossing heavy shipping routes;
c) under poor ground conditions; and
d) with a high seismic activity.

Several geotechnical engineering design and


construction problems had to be solved for the
success of the project.

140
CONCLUDING REMARKS-2

The ground improvement by four types of


cement-mixing technologies solved a number of
potential technical problems;

1) in-situ cement mixing of very soft clay;


a) conventional type deep mixing method (DMM);
and
b) low strength-type DMM;
and
2) embankment using;
a) slurry type cement-mixed sand; and
b) dry mixture type cement-mixed sand.
sand
141
CONCLUDING REMARKS-3
Successful construction of shield tunnels
with the world’s largest
g diameter,
overcoming several difficult technical problems,
including:g
a) successive tunnelling in very stiff cement-mixed
soil and veryy soft clay;
y
b) a very shallow depth in a very soft clay with
a danger
g of floatation of the tunnels; and
c) underground connection of shield machines with
the help of ground freezing to reduce the shield
tunnel drive.

142
CONCLUDING REMARKS-4

The construction of an offshore diaphragm wall with an


int. dia. of 98 m and a height
g of 119 m was delayed
y
a half year by a serious seepage accident in the ground
inside the diaphragm
p g wall.

a)) The accident would have become a fatal one for the
success of the project if relevant measures were not
taken promptly.
y
b) The accident might have not taken place if the
hydraulic gradient in the ground inside and
immediately below the diaphragm wall had been
made substantially lower, for example, by making the
bottom of the diaphragm wall substantially deeper
143
than the actual one.
Thank you very much for your attentions !

144
Terima kasih atas perhatian anda !

Home page:
http://geotle.t.u-tokyo.ac.jp/index-j.html 145
REFERENCES
・Uchida
Uchida,K.,K Shioi,Y.,
Shioi Y Hirukawa,T.
Hirukawa T and Tatsuoka,F.
Tatsuoka F (1993),
(1993) “The
The
Trans-Tokyo Bay Highway Project - A huge project currently
p , Proc. of Transportation
under construction”,, Invited Paper, p
Facilities through Difficult Terrain, Balkema, pp.57-87.

・Tatsuoka,F., Uchida,K., Imai,K., Ouchi.T. and Kohata,Y. (1997),


“Properties
Properties of cement-treated soils in Trans-Tokyo Bay Highway
project”, Ground Improvement, Thomas Telford, Vol.1, No.1,
pp
pp.37-58.

・ Tatsuoka,
T t k F.F (2010):
(2010) “Cement-mixed
“C t i d soils
il iin T
Trans-Tokyo
T k Bay
B
Highway project”, Soils and Foundations, Vol.50, No. 6, pp.785-
804
146

You might also like