Professional Documents
Culture Documents
Full TransTokyoBayHigyway PP
Full TransTokyoBayHigyway PP
TATSUOKA F.
TATSUOKA, F
Tokyo University of Science
1
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project
■ Concluding remarks
2
Trans-Tokyo Bay Highway
15.1 km-long
g toll highway
g y
3
Brief history
May 1971:
The technical investigation
started.
t t d
May 1983:
The Japanese Government
approved the construction.
October 1986:
The Trans-Tokyo Bay Highway
Corporation was established.
M 1989:
May 1989
The construction started.
December 1997:
The construction completed;
and the highway was opened to
public on 18th December.
4
Trans-Tokyo Bay Highway
5
Ukishima access
Bridge
6
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge
PLAN
PROFILE
7
Ukishima access
9
Ukishima access
10
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge
PLAN
PROFILE
11
Kawasaki man-made island
Cross-section
13
An artist’s view from underground
A ring
i space ffor a diaphragm
di h wallll
190 m
14
Kawasaki man-made island
Immediately after
Immediately before the ground excavation the end of ground excavation
15
Ground improvement
by sand compaction pile technology
16
Ground improvement by sand compaction pile technology
17
Construction of external and internal steel structures
after necessary ground improvement work
18
19
20
Filling up the ring space
with cement-mixed sand slurry
21
Construction of a diaphragm
wall in the cylindrical ring of
cement-mixed sand fill and
cement mixed in
cement-mixed in-situ
situ soft clay
22
Filled with mud slurry:
y
Why the vertical wall can
stand without support for a so
Excavation machine
large depth ?
23
24
Excavation of
the inside ground
25
Excavation of the inside ground
26
Construction of the internal structure inside the diaphragm wall
27
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge
PLAN
PROFILE
28
Two 9.5 km-long shield tunnels
29
Two 9.5 km-long shield tunnels
2 2 2 2
The world
world’ss largest diameter
at the time of construction
14.14 m
31
32
Development of shield tunnel diameter
33
Blind type
using pressurized mud
slurry
The world
world’ss largest diameter
at the time of construction
34
Shield tunnel machine
re-assembled to start
from Kawasaki m-m island
35
Two 9.5 km-long shield tunnels
36
Secondaryy inner RC lining
g
(inside the RC segments)
RC segments
37
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge
PLAN
PROFILE
38
Kisarazu man-made island
Shield
t
tunnels
l
39
Structure of TTB Highway
・Ukishima access; ・Two 9.5 km-long shield tunnels;
・Kawasaki
Kawasaki man-made
man made island; ・Kisarazu
Kisarazu man
man-made
made island;
・Bridge
PLAN
PROFILE
40
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project
■ Concluding remarks
41
One of the p
proposals
p that were not accepted
p
42
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy shipping routes;
43
44
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy crossing shipping routes;
・Poor ground conditions; and
・A high seismic activity.
45
46
47
Four difficult design factors
that controlled the structural form
・A relatively deep sea;
・Heavy crossing shipping routes;
・Poor ground conditions; and
・A high seismic activity.
48
Very high seismic activity
In Tok
Tokyoo Ba
Bay area
1923
The Great Kanto Earthquake
49
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project
■ Concluding remarks
50
Significant design and construction issues
related to geotechnical engineering - 1:
Large-scale
Large scale improvement of existing soft clay deposits
by cement mixing in place,
- controlling the strength of cement
cement-mixed
mixed soft clay; and
- in total 3.77 million m3.
51
Ground improvement techniques by cement-mixing
used in the TTB Highway project
Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 52
Ukishima access
55
Haneda airport
-restriction to the height
g of
the construction plants (50 m)
56
Conventional design for
cement-mixed soft clay:
→ Unduly conservative
design
g for huge
g masses
q – ε1 relations from U & CU
TC tests on cement-mixed
clay (aw= 20 %) (Kobayashi
& Tatsuoka, 1982).
Significant effects of
drained condition and
confining pressure (when
drained)
Normalised drained
residual strength plotted
against
i t σc’/q
’/ u for
f cement- t
mixed clay (aw= 8 %, 10 %,
14 % & 20 %) (Kobayashi
& Tatsuoka, 1982).
Nearly no effects of
confining pressure on
the undrained peak
and residual strength
at low
a o co
consolidation
so da o
pressure
Normalised undrained
peak and residual
strengths plotted
against σc’/qu for
cement-mixed clay
(Kobayashi & Tatsuoka
Tatsuoka,
1982).
Large-scale yield stress, qy, divided by qu versus effective
confining pressure divided by qu from CD TC tests on
cement-mixed clay (Kobayashi & Tatsuoka,1982)
qr/qu or
qy/qu qr/q
/ u (drained)
(d i d) for
f
design under
Design strength in static condition
A
zone A was used in
the limit equilibrium
qr/qu (undrained)
stability analysis
for seismic
design
Original ground:
qu (kg/cm2)= 0.044z – 0.88
((z= depth;
p z= 0 m at TP= 0.0).
)
(m)
66
Too large scatter in the unconfined compressive strength due to
effects of sample disturbance, not reliable:
Fi l decision
Final d i i b based d on th
the CU TC ttests.
t
wn (%) γt (gf/cm3) qmax (kgf/cm2) (t= 28 days)
Original ground:
qu (kg/cm2)= 0.044z – 0.88
((z= depth;
p z= 0 m at TP= 0.0).
)
(m)
Reliable data ? 67
Significant design and construction issues
related to geotechnical engineering - 2:
68
Ground improvement techniques by cement-mixing
used in the TTB Highway project
Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 69
Ukishima access
Embankment of
cement-mixed sand slurry
with:
ith
a) a controlled strength;
and
b) a controlled high density
to resist the buoyant
y
force of the tunnels.70
Underwater placement of
cement-mixed sand slurry
71
72
73
No previous construction experiences
74
26 August 1988 ( several years before
75
the actual construction)
26 August 1988 ( several years before
76
the actual construction)
Reduction of the strength
by absorbing
abso b g water
ate
during under-water
placement
77
Reduction of the strength by absorbing water
during
du guunder-water
de ate p placement,
ace e t, not
ot due to losing
os g tthe
e ce
cement
e t co
conent
e t
78
Sampling of large samples
(30 cm in dia) to evaluate
possible large scale effects
by possibily siginificant in-
h
homogeneityi off the
h material i l
placed under water.
79
80
Triaxial testing system
p
for 30 cm-dia. specimens
at the University of Tokyo. 81
Triaxial testing system
for small specimens
at the University of Tokyo. 82
Use of LDT with small and large specimens
83
12 cm H x 5 cm D 60 cm H x 30 cm D
Membrane
Pseudo-hinge
Instrument
Phosphor bronze LDT Gage leadwire Terminal leadwire
strain-gaged strip Active e.r.s.g.
B'
No. 1
A
D' C
No. 2
Membrane Surface
Institute of
Industrial Science,
Universityy of Tokyo,
y ,
1986
85
Summary of results from CD TC tests on large core samples
of slurry type cement-mixed sand (Uchida et al., 1993)
- Significant effects of consolidation pressure
Summary of results from CU TC tests on large core samples
of slurry type cement-mixed sand (Uchida et al., 1993)
- Insignificant effects of consolidation pressure
Essentially no scale
effects on the peak
strength !
Comparison
C i off q-’externally
’ t ll
measured axial strains from
CU TC tests using small and
large core samples from the
same mass of slurryy typeyp
cement-sand constructed in
the full-scale field
underwater
d t placement
l t test
t t
(Tatsuoka et al., 1997).
Essentially no scale
effects on the peak
strength !
Comparison
C i off q-’externally
’ t ll
measured axial strains from
CD TC tests using small and
large core samples from the
same mass of slurryy typeyp
cement-sand constructed in
the full-scale field
underwater
d t placement
l t test
t t
(Tatsuoka et al., 1997).
A typical CU TC test on a large core sample of slurry
type cement-mixed
cement mixed sand (Tatsuoka & Shibuya
Shibuya, 1991)
1991).
A typical CU TC test on a small core sample of slurry
type cement-mixed
cement mixed sand (Tatsuoka & Shibuya
Shibuya, 1991)
1991).
Einitial: the value that had been reported by an geotechnical
consultant
→ by
b ttriaxial
i i l ttests
t ffollowing
ll i th the common practice
ti att th
thatt titime
→ a significant underestimate (about 1/10) of the true value of
small-strain stiffness to be used in deformation analysis of
the cement-mixed soil in the field
The first case where:
96
The Young’s modulus value
that had been obtained by
a geotechnical
t h i l consultant:
lt t
Einitial = 0.3 Gpa
(by conventional drained TC
tests)
This value
Thi l considerably
id bl
underestimates the true
elastic modulus:
E0= 3.0 GPa
and also the value at the
operating strain !
The engineers
Th i iin charge
h off
the TTB Highway project
could become confident with
the use of this material for 97
this project !
Shear modulus vs shear strain relations from monotonic
and cyclic loading triaxial tests on core samples (30 cm in
diameter) from test fills of slurry type cement-mixed sand
(Tatsuoka & Shibuya, 1991).
Strains in the cement-mixed fill lower than 0.05 % (estimated
by FEM earthquake response analysis) →
Nearly linear behaviour at small strains
Importance
p of elastic modulus &d its accurate measurements
99
Evaluation of the stress-strain properties of
cement-mixed soil filled in the field
100
Underwater placement work of slurry type cement-
mixed
i d sand d at Ukishima
Uki hi A
Access and
d Kisarazu
Ki man-
made island (Uchida et al., 1993).
TP 0.0 m
Lift ((m))
Vessell carry mud
V d slurry
l
(capacity: 2,000 m3)
Mound produced on
the sea bed
14 m
samples; and N1 N2
Highway
velocities.
H
S2
Shield
S1 tunnels*
(*) th
the ttop one in
i thi
this
figure has not been
constructed)
102
Comparison of elastic the Young’s moduli from triaxial
compression
p tests ((E0) and those from field shear wave velocities
(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access
103
Comparison of elastic the Young’s moduli from triaxial
compression
p tests ((E0) and those from field shear wave velocities
(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access
104
Completed Kawasaki man-made island
46.7 m
TP – 28 m Steel pipe
74.2 m
Steel pipe
sheet pile sheet pile
Slab SCP
SCP DMM
DMM TP – 41.7 m
21.5 m
6m
TP – 73 m
Bottom RC slab
90 m Thickness= 2.8 m
Thickness= 2.8 m
4m 98 m 4m
Continuous diaphragm wall (L= 119 m)
TP - 114 m
Filling up the ring space
with cement-mixed sand slurry,
Kawasaki man-made island
106
A typical test result on an undisturbed sample
of cement-mixed
cement mixed sand (slurry type)
3 200
LDT
MPa)
Pa)
Deviator stress, q (M
107
Initial Young’s modulus, E0, based on locally measured axial
strains vs initial Young’s modulus, Einitial, based on externally
measured d axial
i l strains
t i ffrom CU TC ttests t off specimens
i
prepared in the laboratory and core sample from Kawasaki
man-made island
island, slurry type cement-mixed sand (Tatsuoka et
al., 1997).
109
Significant design and construction issues
related to geotechnical engineering - 2:
110
Ground improvement techniques by cement-mixing
used in the TTB Highway project
Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435
cement-mixed sand g 3
Cement: 100 kg/m
Anti-segregation
adhesive 110 g/m3 111
Underwater placement of
dry mixture of cement-mixed sand
(Ki
(Kisarazu man-maded iisland):
l d)
a lower cost and a low quality
112
Underwater placement of dry
mixture of cement-mixed sand
(Ki
(Kisarazu man-made l d) a new
d iisland):
method to minimize the segregation
of material during placing
Special double-chute
113
Underwater placement of
dry mixture of cement-mixed sand
(Ki
(Kisarazu man-maded iisland)
l d)
114
Comparison of elastic the Young’s
moduli from triaxial compression
p
tests (Eo) and those from field
shear wave velocities (Ef) at the
fill off cement-mixed
t i d
sand (dry type), Kisarazu
man-made island
Emax defined
d fi d ffor strains
t i lless
than 0.001 % from triaxial
compression tests using LDTs
on undisturbed samples (kgf/cm2)
G0 values from
RCT
BS+DC
CU TC tests 5000
Local axial strain measurements
or softrockss)
versus 1000
G0=E0/{{2(1+ν)} (MPa)
Range for Soft rocks and
Gf from
(BS+DC) and clays
)
:2 TS
(1
BS
10
10 100 1000 5000
2 117
Gf=ρ(V )
s vh
(MPa)
Summary of E0 versus qpeak relations from triaxial tests,
TTB project (Tatsuoka et al., 1997).
The strength and deformation characteristics* of
cement-mixed soil could be made similar without
a large difficulty to those of natural sedimentary soft rock.
(* should be measured accurately)
10000
10,000
10,000
10000
1000
1,000 E0/qpeak= 1,000
E0/qpeak= 1,000
MPa)
MPa)
(M
EE0 (M
o
E /q = 100
E00/qpeakpeak= 100 1,000
1000
100
100
MPa)
E0 (MPa)
E0 (M
Sedimentary softrocks
Sedimentary soft rocks E0/qpeak
100
100 E /q
0 peak
10
10 = 1,000
0.1
0.1 1 1 10 10 100 100 = 1,000 EE00/q/qppeak= 100
qpeak (MPa) peak= 100
qpeak (MPa)
Cement-mixed soil
Cement-mixed soils
Cement-mixed soil having 10
10
0.1
0.1 1 1 qpeak (MPa)10
10 100 100
a controlled
t ll d strength;
t th made
d qpeak (MPa)
1,000
dry type
E0(GP
slurry type
1
E0/qpeak= 1,000
Steel (SS41)
Hard rock core
0.1 (ultrasonic for E0)
Concrete
Mudstone (Sagamihara)*
Mudstone (Sagara)*
0.01 E0/qpeak= 100 Sand/mudstone (Sagara)*
*:: Sedimentary soft rock
■ Concluding remarks
121
Significant design and construction issues
related to geotechnical engineering - 3:
122
Ukishima access
Two tunnels
A sudden largeg changeg from Ukishima
in the cutting torque of
shield machine ((tonf-m))
123
Ring number (one ring= 1.5 m)
Ukishima access
A danger of floating up
of the tunnels by large buoyant
force acting
g to the tunnels,,
compared to a small surcharge;
prevented by placing weight
i the
in th ttunnels
l andd careful
f l
tunnelling work. 124
Significant design and construction issues
related to geotechnical engineering - 3:
125
Two 9.5 km-long shield tunnels
126
Underground connection of shield machines
with the help of ground freezing
Longitudinal section
Cutting
g face Cutting
g face
Freezing pipe
Frozen zone
127
Significant design and construction issues
related to geotechnical engineering - 4:
A huge offshore
diaphragm wall;
- 98 m in int.
int dia.;
dia ; &
- 119 m in height
for Kawasaki
man-made island.
An artist’s
artist s view
from the beneath 128
Construction of the internal structure inside the diaphragm wall
129
Construction of
the internal structure
130
Deep well system to avoid Observation
the ground failure by seepage Drainage
g wells wells
Diaphragm
wall
A-sandy
layer
B-sandy layer
Diaphragm
wall
A-sandy
layer
Depth of water
Amount of inside the
spouting ground water diaphragm wall
(m3 per day) (m)
Depth of
Increase in the
water in the
rate of ground
diaphragm
water spouting
wall
Amount of
spouting
ground water
Start of pouring
Start of unusual sea water into
spouting of the inside of the
ground water diaphragm wall
Depth of water
Amount of inside the
spouting ground water diaphragm wall
(m3 per day) (m)
Depth of
Increase in the
water in the
rate of ground
diaphragm
water spouting
wall
Amount of
spouting
ground water
Start of pouring
Start of unusual sea water into
spouting of the inside of the
ground water diaphragm wall
135
Restart of construction
after a delay of six months
136
137
Geotechnical Engineering Aspects of Trans-
Tokyo Bay Highway Project
■ Concluding remarks
138
Brief history
May 1971 (25):
The technical investigation
started.
May 1983 (37):
The Japanese Government
approved the construction.
October 1986 (40):
The Trans-Tokyo Bay Highway
Corporation was established.
May 1989 (43):
The construction started.
December 1997 (51):
The construction completed;
and the highway was opened to
public on 18th December. 139
CONCLUDING REMARKS-1
140
CONCLUDING REMARKS-2
142
CONCLUDING REMARKS-4
a)) The accident would have become a fatal one for the
success of the project if relevant measures were not
taken promptly.
y
b) The accident might have not taken place if the
hydraulic gradient in the ground inside and
immediately below the diaphragm wall had been
made substantially lower, for example, by making the
bottom of the diaphragm wall substantially deeper
143
than the actual one.
Thank you very much for your attentions !
144
Terima kasih atas perhatian anda !
Home page:
http://geotle.t.u-tokyo.ac.jp/index-j.html 145
REFERENCES
・Uchida
Uchida,K.,K Shioi,Y.,
Shioi Y Hirukawa,T.
Hirukawa T and Tatsuoka,F.
Tatsuoka F (1993),
(1993) “The
The
Trans-Tokyo Bay Highway Project - A huge project currently
p , Proc. of Transportation
under construction”,, Invited Paper, p
Facilities through Difficult Terrain, Balkema, pp.57-87.
・ Tatsuoka,
T t k F.F (2010):
(2010) “Cement-mixed
“C t i d soils
il iin T
Trans-Tokyo
T k Bay
B
Highway project”, Soils and Foundations, Vol.50, No. 6, pp.785-
804
146