You are on page 1of 1

HVAC Commissioning Document – Ducting

Name Hatchery Country Contact Person

AHU/Rooms Commissioned by Date: dd/mm/yyyy

Part To check/measure N/A Data


Air Ducting Connections circular duct ⃞ Siliconed with white silicone OK ⃞

Connections rectangular ducts ⃞ Sealing strips OK ⃞

Are all connections air tight? ⃞ Check before insulating OK ⃞

Insulation ⃞ Check all seams OK ⃞

OKA’s Silicone around the sealing strip ⃞ OK ⃞

No screws are blocking the OKA's ⃞ OK ⃞

The OKA's can be opened easily by hand ⃞ OK ⃞

There is no debris on top of the OKA's ⃞ OK ⃞

The OKA's are functioning correctly during extraction ⃞ OK ⃞

Inspection Above and under ventilators ⃞ OK ⃞


hatches Above and under OKA's ⃞ OK ⃞

Before CVD ⃞ OK ⃞

Before Air Dampers ⃞ OK ⃞

Before DSLAM ⃞ OK ⃞

Roof Exhausts Remove the cover of the roof exhausts ⃞ OK ⃞

Water tight roof covers at exhausts ⃞ OK ⃞ Inform the customer if there is a water leak OK ⃞

GENERAL REMARKS: (everything not as request by Petersime specification, to do list by customer or Petersime etc.)

You are required to send the original form back to your Global Technical Supervisor for later reference. This will allow us to

identify the correct machine and give you our best support in the shortest possible time later during the running of the

machine.

HVAC Commissioning Document – Ducting

2015 12 04 HVAC Commissioning Ducting.docx / 1