You are on page 1of 1

W-0002B

PRE-COMMISSIONING CHECK SHEET


MECHANICAL
Heat Exchanger
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 40 – NC – 2900

SYSTEM
DESCRIPTION
HEAT EXCHANGER SYSTEM No. 11

SERVICE
TAG No. W-0002
DESCRIPTION

Item Description of check Results

01 Confirm that the Construction check list is completed and no subsequent damage occurred

02 Confirm that the Preservation is removed

03 Check operability of all valves associated with the vessel

04 Confirm earth bonding completed

05 Confirm that Inspection doors / Manway(s) closed out with correct gaskets and bolting

06 Check that the correct material has been used for drain/vent plugs

Check that threaded holes for pulling eyes in contact with the fluid are plugged off with
07
dummy bolts

08 Check that impingement protection, K provided, is properly installed

Check that the extended bolt ends for bolt tensioning (external as well as internal) are
09
properly protected

10 Check that the test flange/ring & any other special tools are available and properly stored.

New heat exchangers which have been tested at the Manufacturer's works in accordance
with the design test pressures need not be re-tested after installation, unless required by
11
local regulations. It is good practice, however, to test the tightness of the floating head and
channel flanges. Pneumatic testing at a pressure of 1 bar (g) is normally sufficient

12 Confirm all connections & isolations are as per PEFS and correct gaskets fitted

13 Confirm all safety relief devices fitted & certification available

14 Confirm spare gaskets available for plate type exchangers

REMARKS / OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY JACOBS ACCEPTED BY CHEMETALL


NAME NAME NAME
COMPANY
SIGN & DATE SIGN & DATE SIGN & DATE

You might also like