CONSTRUCTION CHECK SHEET E-0017A

MECHANICAL
Sheet 1 of 2
Fire Fighting Equipment
Installation
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECTS No. 44 – NC – 2900

SYSTEM
DESCRIPTION
FIRE FIGHTING SYSTEM SYSTEM No. 12

SERVICE
TAG No. E-0017
DESCRIPTION

Item Description of check Result

FIRE EXTINGUISHERS & CABINETS

Confirm that fire extinguisher cabinets are correctly mounted & in the correct location & are
01
not damaged

02 Confirm that the Fire extinguisher is the correct colour & correctly fitted & is undamaged

For a wheeled extinguisher check that the tyres are correctly inflated & the trolley operates
03
freely

HOSEREELS & CABINETS

04 Check that Hosereel cabinet is correctly installed & is in the designated position

05 Confirm doors operate freely & without obstruction

06 Confirm Hosereel runs out freely & without kinks

07 * Confirm that isolation valves operate correctly & easily & that the nozzle is not damaged

FIRE HYDRANTS & CABINETS

For hydrants & hydrant cabinets ensure that the cabinet is installed in the correct place & is
08
undamaged

09 * Confirm that the correct amount of hoses are in the cabinet

Confirm that there is no damage to the hose connections on the hydrant & that hey are the
10 *
correct type

DELUGE SKIDS & NOZZLES

Confirm that the nameplate on the deluge skid is correct & that the equipment has been
11
supplied as per the data sheet

12 Confirm that there is no damage

13 Confirm installation as per manufacturers drawings

14 * Confirm all deluge nozzles are correct as per design

15 * Confirm all valves are tagged correctly

16 * Confirm all water & air connections are correct

MONITORS

17 Confirm nameplate details are correct & that the equipment is supplied as per the data sheet

18 * Confirm installation is correct & that the elevation & traverse is as per design requirement

Item Description of check Result


CONSTRUCTION CHECK SHEET E-0017A
MECHANICAL
Sheet 2 of 2
Fire Fighting Equipment
Installation
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECTS No. 44 – NC – 2900

SYSTEM
DESCRIPTION
FIRE FIGHTING SYSTEM SYSTEM No. 12

SERVICE
TAG No. E-0017
DESCRIPTION

19 * Confirm that the nozzle is correctly installed

20 Confirm that lubrication is as per vendor instructions

21 Confirm that the foam tank & hoses are correctly fitted

22 * If a Pelton Wheel Drive is fitted ensure the exhaust is clear

23 Confirm that operating instructions are clearly visible

CO 2 SKIDS

244 Confirm installation in correct location

25 Confirm no Transit damage

26 * Confirm that the correct amount of nozzles are fitted

27 Confirm all wires & pulleys are fitted correctly

28 * Confirm no obstruction to the nozzle path

29 * Confirm adequate clearance for bottle changing

30 Confirm all bottles are certified as per the supply documents

REMARKS / OBSERVATIONS: * COMMISSIONING WITNESS POINTS

COMPLETED BY CONTRACTOR APPROVED BY JACOBS ACCEPTED BY CHEMETALL


NAME NAME NAME
COMPANY COMPANY REF. IND.
SIGN & DATE SIGN & DATE SIGN & DATE