You are on page 1of 15

PROJECT

ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 1/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

REVISIONS
IT: ISSUE A - PRELIMINARY C - FOR INFORMATION E - FOR CONSTRUCTION G - AS BUILT
TYPE H - CANCELED
B - FOR APPROVAL D - FOR QUOTATION F - AS PURCHASED

Rev. IT Description By Chec Appr. Aut. Date

A A INITIAL ISSUE SAG SN PCT VALE 05/11/08

B B ISSUED FOR VALE APPROVAL SAG SN PCT VALE 13/11/08


PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 2/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

CONTENTS
CHAPTER DESCRIPTION PAGE NO.
1 GENERAL INFORMATION 3
2 PROCESS DESCRIPTION 4
3 SCOPE OF SUPPLY 4
4 TECHNICAL SPECIFICATION 5
5 ELECTRICAL & INSTRUMENTATION SPECIFICATION 7
6 EXCLUSIONS 7
7 INSPECTION AND TESTING 7
8 DOCUMENT TO BE SUPPLIED BY THE SELLER 8
9 ENCLOSURE 8
APPENDIX
I. FORMAT OF PRICE SCHEDULE OF ITEMS 9
ANNEXURE
I. FORMAT FOR DEVIATION FROM TENDER DOCUMENT 10
QUESTIONNAIRE TO BE FILLED IN AND SUBMITTED
II. 11
BY SELLER
III SELLER DRAWING AND DATA REQUIREMENT 12
IV INSPECTION TEST AND CLASSIFICATION TABLE 15
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 3/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

1.0 GENERAL INFORMATION

1.1 M/s. Vale International SA (also referred to as VALE) is setting up Pellet plant of 9.0
MTPA capacity having 2 (Two) lines of induration process of 4.5 MTPA capacity at
Oman Industrial complex, city of Sohar, Oman. The plant is designed as per Grate-
Kiln technology of Kobe Steel, Ltd. for Iron ore pelletization.

This technical specification together with the reference documents describes the
requirement for manufacture and supply of 1set of Vibrating Feeder.
1.2 The following documents are attached and shall be a part of requirements of
specification:
CP-3100-G-30003_D General Instructions and Information for the Seller.
CP-3100-G-30004_A Engineering Standard- Mechanical.
EG-XXYY-M-402E-Rev.2 Engineering Standard- General Specification for Surface
Treatment and Protective and finished Painting on
Equipment.
CP-3100-G-30007_A Engineering standard- General Procedure for Shop
Inspection and Tests.
CP-3100-G-30008_A Engineering standard-Packing and Marking.
CP-3100-G-30009_A Engineering standard-Drawing and Documents.
CP-3100-G-30010_A Engineering Standard-Instruction for Schedule Control.
CP-3100-G-30012_A Engineering Standard-Shipping Instruction.
EG-0000-E-08028_0 General Specification For Low Voltage Motors.
ABB Document Interface Concept
1.3 If there are conflicts between this specification and other documents described in the
enclosure / attachments, the order of precedence shall be as follows.
(i) This Specification
(ii) Engineering Standard
(iii) Standard Specification.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 4/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

2.0 PROCESS DESCRIPTION:-

Vibrating feeder AL-3173-01 with hopper is installed at chunk crushing system ST-
3173-01 to feed the jaw crusher.
It receives raw material from the skip hoist EL-3173-01 and separates the lumps by
means of a scalping grizzly set over the hopper opening.
The vibrating pan of the feeder has also a second grated section that will permit the
passage of the small size material which is not required to go to the crusher and so
increasing the capacity of the whole system.

3.0 SCOPE OF SUPPLY

a) Vibrating feeder proper


b) Steel hopper with inclined scalping grizzly
c) Drive system
d) Trolley with connection rod and stopper for suspension
e) Spring suspension set
f) Dust protection cover (canvas)
g) Electric motor & Power transmission
h) All required instrumentation
i) Control panel.
j) Wiring materials (30m) between local control panel and motor.
k) Cable holder
l) Safety guards and mechanisms
m) Companion flanges, bolts, nuts, washers and gaskets
n) Installation bolts, nuts, washers, liners and shims
o) Initial fill of grease, where required
p) Special tools for erection and maintenance
q) Spare parts for erection and commissioning period
r) Spare part for one year normal operation.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 5/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

4.0 TECHNICAL SPECIFICATION


DESCRIPTION / ITEM Nº Unit AL-3173-01
Quantity 1
Installation Outdoor
Receives from Skip-hoist EL-3173-01
Discharges to Jaw crusher BR-3173-01
Reference drawing 3100-L-00002
Material to be handled
- Type Chunks
- Bulk density t/m³ 2,0 to 2,3
- Size distribution (feed to the scalping +50mm: 100%
mm
grizzly) +100 x 200mm:50%
- Size distribution (passing the scalping
mm <250
grizzly)
- Moisture content (Wet Basis) % Max. 1,0
- Temperature °C 50°
- Repose angle 30° to 40°
Operation and construction data
Capacity rated t/h 30
Type Electromechanical Horizontal Heavy Duty
Size 600mm wide x 2700mm long
Vibrating frequency Seller to inform
Amplitude Seller to inform
Drive unit Unbalanced weight

End grate opening mm 50,8 (2”)


Hopper capacity m³ 7,5
Scalping grizzly opening mm 250
Drive Power kW Seller to inform
Equipment weight
- Feeder and drive N Seller to inform
- Hopper, grizzly and Seller to inform
N
structure
Total Weight N Seller to inform
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 6/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

4.1 General Parameters


a) Vibrating feeders shall be designed, manufactured and supplied in accordance with
relevant International Standards where applicable in addition to the requirement
mentioned herein.
b) The feeders shall be of robust construction and of balanced design.
c) Seller shall make his own calculation in respect of motor kilowatt to ensure satisfactory
performance of the equipment.
d) Standardization of components and assemblies shall be carried out to the maximum
possible extent to ensure interchangeability.
e) Vibrating feeders shall be of electro-mechanical. The vibrating units of the feeders
shall be of unbalanced motor type.
f) The troughs of the feeders shall be of tray type construction and shall be made out of
minimum 10 mm thick MS plate. 12 mm thick Hardox-400 liner shall be provided
inside the trough along its length and cross section. The trough liner shall be provided
with adequate side guard to avoid spillage. The equipment will be provided with
enclosed dust proof vibrators (unbalanced masses).
g) All the feeders shall be of suspended type as specified in Technical Parameters. Each
vibrating feeder shall be supplied complete with suspension rods, ropes, turn buckets
etc.
h) Each vibrating feeder shall be supplied complete with four numbers of suspension
rods / ropes and turn- buckles etc. Feeders shall be provided with safety wire ropes to
prevent dropping of equipment in case of failure of the rod or turn-buckle suspenders.
i) Lifting eyes shall be provided for lifting and erection of vibrating feeder.
j) The Seller shall ensure that minimum amount of assembly is necessary for erection
and commissioning of equipment at site. Site welding etc. shall be avoided as far as
possible.
k) All equipment shall be designed such that all components are easily accessible for
inspection, repair and maintenance.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 7/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

5.0 ELECTRICAL & INSTRUMENTATION SPECIFICATION


Technical requirements, general information and minimum instructions for the supply
of electric low voltage motors for VALE projects refer enclosed doccument,
EG -0000-E–08028_A General Specification for Low Voltage Motors

The electrical and instrumentation specifications are provided in the enclosed


document,
CP-0000-J-40000 Instrumentation Design Criteria

6.0 EXCLUSION
The following shall be for Seller’s scope,
1) Civil and building works
2) Erection work
3) Support structure for Vibrating feeder’s suspension

7.0 INSPECTION AND TESTING:-

a) Inspection & testing of equipment shall be carried out by Seller in witness of Buyer or
an authorized agent of Buyer at the works of supplier during manufacturing and on
final product to ensure conformity of the same with the acceptable criteria of technical
specification, approved drawings, authenticated manufacturing drawings and
reference national / international standards.
b) Buyer reserves the right to verify the quality program and entire product
characteristics during manufacturing to assure the intended and specified quality of
the product.
Refer the enclosed document CP-3100-G-30007_A “Engineering Standard- General
Procedure for Shop Inspection and Tests” and as per Annexure-IV.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 8/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

8.0 DOCUMENTS SUPPLIED BY THE SELLER


The Seller shall submit the documents in accordance with the attached documents
CP-3100-G-30009_A “ Engineering Standard- Drawing and Documents”. In addition of
above, the Seller shall submit the documents in accordance with the schedule
mentioned in Annexure-III “Seller Drawings and Data Requirement”.

9.0 ENCLOSURE
Not Applicable
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 9/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

APPENDIX-1
FORMAT OF PRICE SCHEDULE OF ITEMS

Sl.No. Description UoM Qty. Price/Unit Total

VIBRATING FEEDER AS PER


THE TECHNICAL
1 Nos 2
PARAMETERS MENTIONED IN
THE ABOVE SPECIFICATION

ERECTION &
2 COMMISSIONING SPARES, IF
ANY
SUPERVISION OF ERECTION Man
3 *1
AND COMMISSIONING days
4 SUB TOTAL
SPARES FOR ONE YEAR
5
NORMAL OPERATION
6 GRAND TOTAL

*1: To be specified by Seller


PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 10/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

ANNEXURE I

FORMAT FOR DEVIATIONS FROM TENDER DOCUMENT

Sl. Clause No. Seller’s Deviations Reason for


No. Deviations

The Seller hereby certifiy that the above mentioned are the only deviations from the
tender documents.

Signature :

Name :

Designation :

Company seal :
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 11/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

ANNEXURE II

QUESTIONNAIRE TO BE FILLED IN AND SUBMITTED BY THE SELLER

01. Seller’ s name and address.


02. Quotation number and date.
03. Total estimated transporting weight of items offered by Seller (in tonnes).
04. Weight and dimension of the heaviest single package.
05. Special transport requirement.
06. Special storage requirement.
07. Available spare capacity
08. Necessary fixing details of the equipment with insert details of bolts to be
provided on the floor or on the supports structures
09. Required GA drawings.
10. List of exclusions / deviations from technical specification, if any
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 12/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

ANNEXURE III
SELLER DRAWINGS and DATA REQUIREMENT COMMON
Req'D Req'd after Contract
Ref.
Sr. with
Description of documents Doc. Initial Certified Final
No. Proposal
(*2)
p Time p Time p Time p
1 Proposal 4
2 Seller's Technical Specification of Equipment (*1) 4 2 WO 4 2WA 4 2WB 5
3 Painting Specification List 2 WO 4 2WA 4 2WB 5
4 Arrangement Drawings (*1) 4 3 WO 4 2WA 4 2WB 5
5 Outline drawings of Respective Equipment (*1) 4 3 WO 4 2WA 4 2WB 5
6 Cross Section with Parts Description 3 WO 4 2WA 4 2WB 5
7 Fabrication Drawing for Local Fabrication (*1) WO WA WB
8 Local Fabrication B / o List WO WA WB
9 Foundation Drawing and Loading Data (*1) 2 WO 4 2WA 4 2WB 5
10 Piping Drawings / Flow Diagram 3 WO 4 2WA 4 2WB 5
#1
11 Name Plate Drawing WO WA
12 Detailed Calculations 2 WO 4 2WA 4 2WB 5
13 Utility Data Sheet 4 2 WO 4 2WA 4 2WB 5
14 Lubricant Data sheet 7 WO 4 2WA 4 2WB 5
15 Special Tool list for Erection and Maintenance 10WO 4 2WA 4 2WB 5
16 Consumable List for Erection and commissioning 4 10WO 4 2WA 4 2WB 5
17 Erection and Installation Manual 10WO 4 2WA 4 2WB 5
18 Match Mark Drawing 10WO 4 2WA 4 2WB 5
19 Operation and Maintenance Manual (*4) 10WO 4 2WA 4 2WB 5
20 Spare parts list 4 2 WO 4 2WA 4 WB
21 Proforma Packing List 4 6 WV 4
22 Packing List 3 WV 4 2WV 4
23 Master Packing List #2 3 WV 4 2WV 4
24 Bulky Cargo List 3 WO 4 4WV 4
25 Other Shipping Documents Refer to ES - 09
26 Quality Assurance Organization and Program 5 WO 2WA 4
27 Application for Witnessed Inspection and Test 3 WB
28 Application For Surveyance (Packing Inspection) 3 WB
#3
29 Inspection and Test Manual at shop 10WO 2WA 4
30 Inspection and Test Report 1 WI 2
31 Performance Test Procedure at site 15WO 2WA 4 WB
32 List of Person in Charge #4 2 WO
33 Status (Progress) Report (*3)
34 Manufacturing Schedule (*1) 4 2 WO 2WA 4
35 Sub-order Status Report (*3)
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 13/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

36 Expediting Trouble Report


37 Seller's Document List 5 WO 2WA 4
38 Minutes of Meeting #1 1 WM
39 Other as Specified - WO WA WB
40 Deviation List #1 4 -
3
41 As - built Dwg #1 -
WH 2

WA : Specified week af ter initial drawings are approved


Remarks WB : Specified week before inspection
Abbr. : O : Original WI : Specified day after inspection
P : Number of Print WM : Specified Week after meeting
With electronic data WO : Specified Week after order award
(Auto Cad) for Drawing WS : Specified Week after order shipment
WV : Specified Week before surveyance
Note : WH : Specified Week before hand - over to the owner
*1 Buyer's approval is required before starting manufacture. And these documents are subjected
to Liquidated Damages for Delay of Document Submission
*2 Reference document symbol means as follows :
#1 : ENGINEERING STANDARD FOR DRAWINGS AND DOCUMENTS (ES - 10 )
#2 : ENGINEERING STANDARD FOR PA CKING AND MARKING ( ES - 08 )
#3 : ENGINEERING STANDARD FOR INSPECTION AND TEST ( ES - 07 )
#4 : INSTRUCTION FOR SCHEDULE CONTROL ( ES - 11 )
*3 Every Month
*4 For Operation and Maintenance manual, manufacturer's original catalogues, brochures shall be
included.
Note : For Final Document : Seller shall submit two CD in which electronic data for all documents
are stored respectively.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 14/15
PELLET SYSTEM - GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

SELLER DRAWINGS and DATA REQUIREMENT ELECTRICAL and INSTRUMENT

Req'D Req'd after Contract


Sr. with
Description of documents Remarks Proposal Initial Certified Final
No.
p Time p Time p Time p
1 Specification Of Electrical Equipment and Instrument (*1) 4 4 WO 4 3WA 4 2WB 5
2 List of Electrical Equipment, Motor and Instrument (*1) 4 4 WO 4 3WA 4 2WB 5
3 Control Panel Specificati on and Drawings (*1) WO WA WB
4 Process Instrument Diagram ( PID ) (*1) WO WA WB
5 Single Line Diagram (*1) WO WA WB
6 Elementary Dia gram (*1) WO WA WB
7 Operation and I nter Lock Scheme Diagram (*1) WO WA WB
8 Internal Connection Diagram (*1) WO WA WB
9 Outline Drawing Of Electrical Equipment (*1) 4WO 4 3WA 4 2WB 5
10 Instrument Loop Diagram (*1) WO WA WB
11 Instrument Location Diagram WO WA WB
12 Instrument Installation Details WO WA WB
13 Interconnecti ng Diagram Of Wiring and Tubing (*2) WO WA WB
14 Layout of Electric Room WO WA
15 Layout Of Control Room WO WA
16 Wiring Layout Drawing (*2) WO WA
17 Layout Of Electrical and Instrument Raceway (*2) WO WA
18 Grounding Layo ut Drawing (*2) WO WA
19 Lighting Layout Drawing (*2) WO WA
20 Communication system Layout Drawing WO WA
21 Fire Alarm System Layout Drawing WO WA
22 Cable List and Cable Schedule For Elect. Eq. and Inst. (*2) WO WA WB
23 Civil Design Information WO WA WB
Remarks
O : Original
Abbr.
:
P : Number of Print WB : Specified week before inspection
With electronic data (Auto Cad) for Drawing WO : Specified week after order award

WA : Specified week after initial drawings are approved

Note
*1 Buyer's approval is required before starting manufacture. And these documents are subjected to Liquidated
:
Damages for Delay of Document Submission

*2 If Wiring materials are Supplied by Seller.


Note : For Final Document : Seller shall submit two CD in which electronic data for all documents are stored
respectively.
PROJECT
ESSAR P-0220
ENGINEERING SERVICES LTD.
TÍTLE VALE Nº PAGE
SOHAR PELLETIZING PLANT
ET-3173-M-45003 15/15
PELLET SYSTEM- GENERAL
EESL DMS Nº REV.
TECHNICAL SPECIFICATION OF VIBRATING FEEDER
DETAILED ENGINEERING 1027 60 0100 TSP 27 H 002 B

INSPECTION AND TEST CLASSIFICATION TABLE AT SHOP ANNEXURE IV


Equipment Name : VIBRATING FEEDER

1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
Non-destructive
Inspection and Test
Examination

Heat Treatment Inspection

Chemical test of test piece


(incl. welding inspection)
Dimensional Inspection

Insulation Resistance
Temporary Assembly

Rust Prevention and


Mechanical Running
Welder Qualification

Phase-relation Test

Quantity Inspection
Control Circuit Test
Welding Procedure

Painting Inspection

Packing Inspection
Material Inspection
Review of Material

Dielectric Strength
Performance Test
Qualification Test

Magnetic Particle
Visual Inspection

Liquid Penetrant

Hydrostatic Test

Pneumatic Test

Functional Test
Balancing Test
No-Load Test
Radiographic
Examination

Examination

Examination

Examination
Equipment Name

Polarity and
Inspection
Certificate

Load Test
Ultrasonic

Leak Test
(Part or Component)
to be inspected and
Test

Test

Test

Test
tested

VIBRATING FEEDER S S/B B S S S


R R R R R R
MECHANICAL PARTS S S/B S/B
R R R
MAIN BODY S/B S/B
` R R

ELECTRICAL PARTS S/B S/B S/B S/B S/B S/B


(MOTOR, CONTROL PANEL, ETC.) R R R R R R

Note
Remarks : Marks :
D
S : Seller's own inspection and/or test
B: Inspection and/or test under witness of the Buyer's representative
C
Rev. S/B : Inspection and/or test under spot witness of the Buyer's representative
R : The Seller shall submit the report to the Buyer. (Subseq uently it will be submitted to the Client by the Buyer.)
B
X : The Seller may not submit the report to the Buyer.
A

You might also like