CONSTRUCTION CHECK SHEET E-012A

ELECTRICAL
POWER & AUXILLIARY
TRANSFORMER
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 44-NC-2900

SYSTEM
DESCRIPTION
POWER & AUXILIARY TRANSFORMER SYSTEM No. 005

SERVICE
TAG No.
DESCRIPTION

A. INDENT/CONTRACT No:

LOCATION: SYSTEM/DUTY: TAG NO:


TYPE: 3 PHASE 50 HZ
MANUFACTURER: SERIAL NO: YEAR OF MANUFACTURE:

CONTINUOUS RATING:
HV MVA: kV: AMPS:
LV1 MVA: KV: AMPS:
LV2 MVA: KV: AMPS:
TYPE OF COOLING: ONAN / ONAF VECTOR GROUP:
IMPEDANCE VOLT (%): HV-LV1: HV-LV2: LV1-LV2:
OLTC TYPE & RANGE:

B. INSPECTION Results

1. Inspect the transformer for mechanical damage


2. Inspect foundation fixing details and plinth level
3. Operation check of protective devices
Buchholz relay
Pressure relief device
Oil level gauge
Oil temperature indicator
Winding temperature indicator
4. Calibration on temperature indicators
5. Check transformer assembly as per General Arrangement Drawing
6. Check all joints for leakage
7. Inspect all bushings, radiator fins, joints for leakage
8. Inspect bushings for cracks
9. Inspect silica gel for blue colour
10. Inspect valves and pipe plugs for tightness
11. Inspect and ensure cleanliness of all marshalling boxes, junction boxes, etc.

Sheet 1 of 2
CONSTRUCTION CHECK SHEET E-012A
ELECTRICAL
POWER & AUXILLIARY
TRANSFORMER
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 44-NC-2900

SYSTEM
DESCRIPTION
POWER & AUXILIARY TRANSFORMER SYSTEM No. 005

SERVICE
TAG No.
DESCRIPTION

INSPECTION Results

12. Inspect bolting and gaskets, and that weatherproofing of all marshalling boxes, junction boxes, etc
and ensure that requirements of relevant specifications are met
13. Check tap changer padlocking facility
14. Check tap-changer manual operation and check continuity of winding at all tap position
15. Check polarity of transformer terminals
16. Record bushing arcing-horn gap (mm)
17. Ensure that non-metallic gland plate is provided for single core cable
18. Ensure that site inspection for cooling fan motors have been carried out and relevant construction
test sheet completed (if applicable)

19. Check and ensure correct wiring, ferruling and connections in accordance with manufacturer's
wiring/schematic diagrams

20. Check the cable earth wire or armour earth connections inside the marshalling boxes, junction
boxes, etc.

21. Check and record insulation of auxiliary & control wiring (M)
22. Check transformer earthing connections and record resistance to ring main ()
23. Check and record insulation resistance of winding (before connection of cables)
HV to Earth (M)
LV to Earth (M)
HV to LV (M)

24. Check and record insulation resistance between core and earth (M)
25. Type of cable termination
C. REMARKS / OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY CONTRACTOR ACCEPTED BY PDO