You are on page 1of 1

CONSTRUCTION CHECK SHEET F-0003A-A

MECHANICAL
Filter
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 44 – NC – 2900

SYSTEM
DESCRIPTION
FILTER AREA SYSTEM No. 07

SERVICE
TAG No. F-0003A
DESCRIPTION

Item Description of check Result


01 Nameplate details are in accordance with data sheet Ok
02 Check equipment is supplied as per the data sheet Ok
03 Check for transit damage Ok
04 Check that the installation location is correct Ok
05 Check filter is installed as per the design drawings & vendor instructions Ok
06 Check that the holding down bolts are fitted and torque settings are correct Ok
07 Check external condition of filter Ok
08 Check external fittings are correctly installed on filter Ok
09 Check earthing is correctly fitted and to specification
10 Check vent / drain valves are fitted correctly Ok
11 Check cross over valve is fitted correctly Ok
12 Check filter is internally clean Ok
13 Check all filter elements are fitted correctly Ok
14 Check all filter elements condition Ok
15 Check all filter elements types are correct & record details Ok
16 Check inlet & outlet pipe work supports are secure / adequate Ok
REMARKS / OBSERVATIONS * COMMISSIONING WITNESS POINTS

COMPLETED BY CONTRACTOR APPROVED BY JACOBS ACCEPTED BY CHEMETALL


NAME NAME NAME
COMPANY COMPANY
SIGN & DATE SIGN & DATE SIGN & DATE

You might also like