F-0003B-B

PRE-COMMISSIONING CHECK SHEET


MECHANICAL
Filters
PROJECT
DESCRIPTION
n-BUTYL LITHIUM DILUTION FACILITY PROJECT No. 44 – NC – 2900

SYSTEM
DESCRIPTION
FILTER AREA SYSTEM No. 08

SERVICE
TAG No. F-0003B
DESCRIPTION

Item Description of check Results

Confirm that the Construction check list is completed and no subsequent damage has
01 Ok
occurred

02 Confirm that Preservation has been removed Ok

03 Confirm that Correct filter element has been installed. No:- Ok

04 Confirm that Vent and drain valves are fitted and exercised Ok

05 Confirm that all lines fitted as per drawing. Ok

06 Confirm that all lines welding joints. Ok

07 Confirm that Fittings and connections complete as per vendor drawings & PEFS Ok

08 Confirm that Earthing strap is fitted

REMARKS / OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY JACOBS ACCEPTED BY CHEMETALL


NAME NAME NAME
COMPANY
SIGN & DATE SIGN & DATE SIGN & DATE