HVAC Commissioning Document – PLC

Name Hatchery Country Contact Person

ESB/PLC Commissioned by Date: dd/mm/yyyy

Part To check/measure Data


PLC power supply Supply Voltage: _______ V DC

UPS Leds: OK ⃞

Voltage to UPS: _______ V DC

Voltage to Battery: _______ V DC

Battery Voltage: _______ V DC

Fuses to all modules OK ⃞

PLC cable Connectors in the modules Connectors inserted in modules OK ⃞


connections Can open network PLC to ESB OK ⃞

ESB to Hubs OK ⃞

Termination only last Hub OK ⃞

Hub to VSD’s OK ⃞

TCP/IP connections PLC - Switch OK ⃞

HMI - Switch OK ⃞

PLC - PLC OK ⃞

IP Addresses OK ⃞

PLC Program SD Card Present OK ⃞

Working correct OK ⃞

Latest software update Installed OK ⃞

PLC Leds PWR On OK ⃞

RUN On OK ⃞

SL1 Flashing OK ⃞

ETH On OK ⃞

CAN.R On OK ⃞

All other leds Off OK ⃞

Variable Speed Correct Speed Drive Check Type OK ⃞


Drives 230V/400V OK ⃞

CAN Open connection OK ⃞

AdCO Correct CAN Open address OK ⃞

Sensors Temperature sensors Check Value OK ⃞

Check Stability OK ⃞

Check connection - Correct place OK ⃞

Calibration OK ⃞

* Make a picture of all the calibration screens

Humidity sensors Check Value OK ⃞

Check Stability OK ⃞

Check connection - Correct place OK ⃞

PPT Connected to the correct VSD OK ⃞

Values OK ⃞

HVAC Commissioning Document – PLC

2015 12 04 HVAC Commissioning PLC.docx / 1


Program Internal settings OK ⃞

Frost protection Check Value OK ⃞

Check Stability OK ⃞

Check connection - Correct place OK ⃞

Pressure switches Connected to the correct AHU and Function (Supply, extraction,
filter,…) OK ⃞

Check DI on PLC OK ⃞

Room switches Connected to the correct place OK ⃞

Check DI on PLC OK ⃞

Water tank Low level switch OK ⃞

High level switch OK ⃞

Magnetic valve filling OK ⃞ On/Off ⃞

GENERAL REMARKS: (everything not as request by Petersime specification, to do list by customer or Petersime, etc.)

You are required to send the original form back to your Global Technical Supervisor for later reference. This will allow us to

identify the correct machine and give you our best support in the shortest possible time later during the running of the

machine.

HVAC Commissioning Document – PLC

2015 12 04 HVAC Commissioning PLC.docx / 2