Document : Troubleshooting

Flow chart for testing of valve indications of Pleiger page : 1


Ausgabe: 08/06
remote controlled valve system with EHS-Q3
QM

Before proceeding with testing in below mentioned way please ensure,


that the hydraulic pump of the EHS is running, and the respective
actuator is moving in both directions. If the actuator is moving but no
position of valve in „open“ and/or „close“ is indicated, follow this steps.

Functional test of flow switch


inside EHS-D3Q/ EHS-S3Q:
If no indication in „open“ and
„close“, Make short connection
between contact 7 and 8 direct
on plug inside of EHS, and test
again

no "close" indication Indication


no "open" indication
ok?

Yes

Checking pressure switch "P1" for Change flow switch Checking pressure switch "P2" for
„close“ indication inside EHS-D3Q/ "Q", displace short „open“ indication inside EHS-D3Q/
EHS-S3Q: connection, and test EHS-S3Q:
make short connection direct on again Make short connection direct on plug
plug inside of EHS between contact inside of EHS between contact 7 and 11
7 and 10 for simulation of „close“- for simulation of „open“-signal, and
signal, and test again test again

Yes
Indication No Indication No Indication
ok? ok? ok?

Yes No Yes

Displace short connection on plug, Adjustment of end stop of Displace short connection, change
and test again. hydraulic actuator in „close“- the respective pressure switch and
position according our test again
discription in the final
documentation

Indication No No
Indication No Indication
ok? Yes ok? ok?

Yes No Yes

Change control
module EHS-CM
and test again

Indication No
ok?

call for service


Yes

You did it!