Revised Revision
Description of Revision Prepared By
Page Date
5 17/12/20 Issued for Information O.Kutuk
H.Dogan
F.Adatepe
Rev. No 0 0A 1 2 3 3A 4 5
Date 08/01/20 20/03/20 26/04/20 25/06/20 20/07/20 13/10/20 01/11/20 17/12/20
Form No:IQ389-000-AL-FRM-00076_0
VENDOR COORDINATION PACK
Table of Contents
1. GENERAL
1.1. PURPOSE
This document outlines the basic requirements expected of VENDORS with
regards to the following areas:
Document Management
Communications Protocol
Progress Meetings
Progress Report Requirements
Schedule Requirements
VMDR
Access and operation of document management system EDMS (ENKA
Document Management System).
Refer to section 8 (ATTACHMENTS) of this document for the list templates and
procedures required for VENDORS. This document is a narrative to those
attachments.
1.2. DEFINITIONS
CONTRACTOR ENKA
1.3. ACRONYMS
Acronym Description
ASNT American Society for Non Destructive Testing
CAD Computer Aided Design
COB Close of Business
CRS Comment Resolution Sheet
DFO Documentation for Operations (DFO)
EDMS ENKA Document Management System
NDT Non Destructive Testing
VMDR VENDOR Master Document Register
V1 Issued for Void
2. REFERENCES
3. DOCUMENT MANAGEMENT
Reference: Attachment 1: Data Exchange Procedure
Attachment 2: Comments Resolution Sheet (CRS)
Attachment 3: CAD Templates
Attachment 4: Vendor Document Template
Refer to attached Data Exchange Procedure (Attachment 1) provides the information about
process through which Subcontractors’/ Suppliers’ documents are captured, controlled and
managed by parties themselves on EDMS (ENKA Document Management System).
Document Numbering originated by VENDOR shall be as follows;
AABB – CC815 – EFGGG – DD-zzzz – xxx
Document numbering originated by VENDOR
AA Country Code IQ
BB Facility/Plant Code WQ
CC Originating Company Code EN815
E Discipline Code V
In case of major comments of CONTRACTOR (code C), VENDOR shall update the document for
rev C, D, and resubmit for CONTRACTOR Review & Comments with CRS within 10 working
days. This step shall be repeated until CONTRACTOR deems the document is minor or no
comment. (see the Vendor Documents Flow Chart (Attachment 10).
If after certain revision, document to be issued for void, then the document shall be
changed V1. Void shall be printed as Watermark across the document. Should a
new document be created to replace voided documents a stamp with superseded by
document number shall be filled.
Example: Current revision of document is Rev B and need to issue for Void up the
document to Rev V1, IFV (Issued for Void).
The preparer, checker and approver of a document cannot be the same person. Different
people must prepare, check and approve the document.
Revisions after Rev. B and 0 shall be marked by a vertical line in the left margin against the
revised text for the documents (red color) and cloud with revision triangle against the revised
portion for drawings. Revision B and 0 shall not have any indication of revision.
Revisions between Rev. B and Rev.0 (Rev.C, Rev.D, etc.) shall be marked by a vertical line
in the left margin against the revised text for the documents (red color) and cloud with revision
triangle against the revised portion for drawings.
After submission of Rev.0, if any re-submission is required (Rev.1A, Rev.1B, etc.), the
document shall be submitted Issued for Approval and the document shall be marked by a
vertical line in the left margin against the revised text for the documents (red color) and cloud
with revision triangle against the revised portion for drawings. After approval of Revision 1A,
1B, 2A, 2B, etc. Revision 1 and 2 shall not have any indication of revision.
Revision clouds and track changes shall be used for any revision that has an alpha-character
(C, D, 1A, 1B, 2A, 2B, etc).
Any NDT procedures have to be created and approved by a qualified ASNT III professional
and stamped with the signature and the registration number of that person. (For
applicable packages)
After revision 0, vendor shall submit all documents along with native file (word, excel, dwg,
etc.). Vendor shall follow documents requirements defined in IQWQ-EI-OSPDS-00-210102 -
Documentation for Operations (DFO).
VENDOR shall deliver As-built and handover documents asper Documentation for
Operations (DFO) and contract as-built schedule.
Category I Category I documents are for review by both COMPANY and COMPANY
Verification Agent(s). Category I documents shall be submitted to COMPANY
at each revision. Response Codes shall be provided by COMPANY with the
documents' return. COMPANY comments shall be resolved to COMPANY
satisfaction
Document Category Review Period for Rev. A Review Period for Rev. B and Above
4. PROGRESS MEETINGS
Reference: Attachment 5: Minutes of Meeting Template
The VENDOR must also provide a progress measurement system which will enable
the CONTRACTOR to track the entire scope of works and which must be aligned with
the VENDORS level 4 schedule. The schedule must be of acceptable quality and
comply with minimum COMPANY planning requirements.
All procurement items are to be reflected at a level of detail that will
enable our detailed analysis by the CONTRACTOR.
All files are to be provided in both native format and a pdf of the
respective submission.
In the event that there is any ambiguity in reporting, the VENDOR must
provide reasonable additional reporting upon request.
VENDOR shall complete the VMDR (Attachment 8) after award and submit within 2
weeks. The following information must be filled by VENDOR:
VENDOR with provide documents for operation as complete pack in accordance with
IQWQ-EI-OSPDS-00-210102 - Documentation for Operations (DFO) (Attachment 13).
EDMS is the CONTRACTORS document management system for the PW2 Project.
VENDOR is required to upload other deliverables to EDMS with transmittal.
Contact Details
Address
Tax Number
Once these details are received CONTRACTOR shall create an account for VENDOR
and further details will be provided to VENDOR on how to upload and download
deliverables from this web based document management system.
Documents are submitted through EDMS shall be recognized and reviewed as indicated
in Vendor Documents Flow Chart (Attachment 10). No documents received by Email
will be reviewed or recognized as formally issued.
Only documentation received in the correct provided project templates will be accepted
and reviewed.
EDMS training shall be provided to VENDOR document control team once set up.
All documentation from VENDOR shall have signatures to ensure the quality of each
deliverable has been checked internally by VENDOR and that their quality system has
been followed.
All documents issued shall come with an official transmittal page without which it is not
considered official. A sample transmittal template is provided (Attachment 9).
8. ATTACHMENTS
Refer to attached document templates and supporting documents to be followed by all
VENDORS for the West Qurna I Produced Water 2 (PW2) Project.