U.337 OC Piling Schedule + Scope of Work

SWR_05 (18/10-10/11) PP-Scope (Building+Fnd)


REK (Utilities)
REK (Piperack)

OC-04 Piling Schedule


• SWR-05 : 18/10 – 10/11
• SWR-04 : 11/11 – 02/12
• SWR-03 : 13/11 – 30/11
• SWR-03/04 : 20/12 – 25/12
SWR-04/05 • SWR-04/05 : 03/12 – 18/12
(03/12-18/12)

SWR_03/04
(20/12-25/12)

SWR-04
(11/11-02/12)

SWR_03
(13/11-30/11)
Main Concern SIMOP Constructbility (SWR-04)
Stell Str.

Option 1
Option 2
Option 2

SWR-04

Section A
Pump Fnd Piperack
Eq Fnd Pump Fnd

Note SWR-04
Schedule
1. Shelter Dimension L x W x H = 65 x 24 x 17 m
- Nop 2021
2. Main Stell structure erection access should be decided : OC-04 Piling Work
- From Outside Main Building (Option 1) - Des 2021
( - ) Piperack, Pump Fnd by Rekind can’t be continued and should be hold until OC-04 Piling Work + Excavation
main stell structure + Clading erection finish - Jan 2022
( + ) Main equipment can be instal soon OC-04 ….
- Feb 2022
- From Inside Main Building (Option 2) OC-04 ….
( + ) Piperack, Pump Fnd by Rekind can be continued - March 2022
( - ) UF Main equipment installation should waiting until main stell structure + - Apr 2022
- Mey 2022
Clading erection finish
- June 2022
Main Concern SIMOP Constructbility (SWR-05)

Stell Str.

Main Road
Pump Fnd.

piperack Piperack
Eq Fnd Eq Fnd SWR-04
Note SWR-04
1. Shelter Dimension L x W x H = 65 x 45 x 17 m Schedule
2. Main Stell structure erection access using Outside Building : - Nop 2021
- From Outside Main Building (Option 2) OC-04 Piling Work
( + ) Piperack, Pump Fnd by Rekind can be continued - Des 2021
( + ) Main equipment can be instal soon OC-04 ….
( - ) Equipment for main stell structure will be heaviest - Jan 2022
( - ) Pump Foundation should be hold OC-04 ….
- Feb 2022
OC-04 ….
- March 2022
- Apr 2022
- Mey 2022
- June 2022