Hazard Identification (HazID):

Project: Construction of Parallel Taxi Track (PTT), Date: XX.XX.XXXX


Rapid Exit Taxiway (RET) and Apron for parking
of 08 nos. Code “C” Aircraft at XXXX Airport.

Hazard: Prolonged construction activity of huge volume Hazard #: 01


in operational area.

Consequences of Hazard:
Inadequate planning / incorrect scheduling of proposed construction activity may
lead to unorganized and unsafe environment for flight operation.

Existing Risk Controls:


Entire construction activity is carefully planned giving due consideration to flight
safety. MOWP is developed.
Severity: E Likelihood: 2 Initial Risk Classification: IV

Potential Risk Controls (may include improving existing controls) to achieve


ALARP:
Concept/Design and Execution level approval for entire project is requested from
DGCA. However Commissioning level approval shall be obtained in two phases.
Special efforts shall be made to expedite the construction of all link taxiways
connecting Parallel Taxi Track to Runway.
Severity: E Likelihood: 1 Residual Risk Classification: IV

Comments:

Signature of Residual Risk Accepting Authority


XYZ
Airport Director