You are on page 1of 17

Bulletin No.

OT1 Revised
(Replaces 2005 version)
File: Overtime

Bulletin

How to Estimate the Impacts of Overtime


on Labor Productivity
Introduction Previous MCAA publications on
The cost impact of unplanned extended overtime inefficiency included
overtime work1 may exceed the histograms that depicted loss of labor
increased costs of the premium pay productivity data based on various
associated with an overtime work overtime schedules. The histograms
schedule. This impact comes in the form published in MCAA’s Bulletin Nos. 18-A
of reduced worker productivity as and 20 were based on the 1947 U.S.
compared with the productivity of work Department of Labor Bulletin No. 917, a
performed on a straight-time basis. A study of prolonged overtime worked in
mechanical contractor confronting the manufacturing sector. As several
significant periods of unplanned courts and commentators have
extended overtime work must consider recognized, the 1947 Bulletin No. 917
the reduced productivity associated with has limited application in the
working an overtime schedule. construction industry.2 As a result,
MCAA Bulletin Nos. 18-A and 20 have
A number of published studies attempt now been superseded by this version.
to quantify the decrease in labor This current publication is based on
productivity associated with working more recent studies that provide a basis
extended overtime in the construction of estimating labor inefficiencies utilizing
industry. This chapter will discuss the data provided by construction
most frequently cited studies that have contractors or from quantitative data
been used to quantify overtime labor actually measured on construction
inefficiency in the construction industry. projects.
The chapter also will set forth some
general guidelines for a mechanical Background
contractor’s consideration in assessing Often mechanical contractors are
the labor inefficiency impact of directed by an owner or general
unplanned extended overtime. The contractor to accelerate the work for a
principles set forth in this chapter can variety of reasons. Acceleration can be
provide meaningful guidance in achieved by adding crews, adding shifts,
estimating the loss of labor productivity and/or working longer hours over and
arising from overtime in the forward above 40 hours a week for the primary
pricing of change orders as well as in a crew. This latter form of acceleration is
retrospective application. known as “overtime,” and the direct
costs of this process (i.e., the overtime
payroll premium costs) are reasonably
Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 1
easy to compute. However, the indirect seeks to provide the mechanical
effects of working an overtime schedule contractor with estimated inefficiency
can be more difficult to quantify. The rates for various overtime schedules
primary indirect effect of working an seen most frequently on construction
overtime schedule is the loss of labor projects. The percent inefficiency values
productivity by the workers performing offered herein are reasonable estimates
the overtime work. The added cost in of the inefficiency impacts that can be
terms of the loss of labor productivity sustained by mechanical crews working
may, as noted above, exceed the direct various overtime schedules. The
payroll costs of supporting an overtime inefficiency percentages are to be
work schedule. The subject of this applied to all hours worked by a crew
chapter is the added inefficiency costs performing on an overtime schedule and
of working overtime. While the MCAA not just the overtime hours.3
has not prepared an empirical study
within this chapter, the better- known The construction industry generally uses
overtime inefficiency studies have been three terms to describe different
revisited herein and compared, thus overtime scenarios: shutdown or
allowing the contractor to consider turnaround projects, spot overtime, and
several sources of data in one set of extended overtime. Shutdown or
tables. turnaround projects are those in which a
system or plant is completely shut down
Overtime inefficiency is the most for the project duration, and due to the
generally accepted category of labor production value of the system or plant,
inefficiency within the construction the construction schedule is highly
industry. That is true because virtually compressed (often working 24/7 with
everyone who has worked extended multiple shifts) in order to minimize the
hours—executives, managers, technical duration of the shutdown. These
and support personal, as well as the working conditions are clearly
field labor forces—have personally felt understood during the bid/proposal
the reduced productivity effects of process, and the contractor should
overtime schedules. These effects can include the associated inefficiencies in
include fatigue, increased absenteeism, the mechanical contractor’s bid or
increased incidence of accidents, proposal.4
reduced morale, and a more negative
work attitude. Spot overtime is short in duration (from
as little as one day to a week) and is
While many prime contractors and generally not planned in advance—it is
owners may be willing to pay the usually caused by a delay or other
mechanical contractor’s direct cost of unanticipated event that requires the
overtime if the acceleration was not mechanical contractor to make up
caused by the mechanical contractor’s quantities or finish work that was not
delay, the mechanical contractor is completed during the preceding week.5
much more likely to be denied its Spot overtime is also normally worked
inefficiency costs for the overtime by only a few crews at a time—those
schedule. It is essential for the responsible for the specific work scope
mechanical contractor to establish a in question. The impact of working
range of inefficiencies that may arise as periodic and infrequent spot overtime is
a result of embarking on an overtime normally considered negligible in terms
work schedule such that payment for the of inefficiency effects. As a result, spot
direct costs as well as the inefficiency overtime is not normally calculated in
costs can be reimbursed. This chapter industry studies that attempt to quantify

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 2


the lost labor productivity due to Roundtable publication entitled
unplanned extended overtime. Schedule Overtime Effects on
Construction Projects (hereinafter
Unplanned extended overtime is a referred to as “BRT”);
condition wherein the entire project, or a
significant portion of the project (e.g., all 2) The 1989 study published by the
mechanical crews), work an overtime National Electrical Contractors
schedule for an extended period of time, Association (NECA) entitled
sometimes without a planned return to a Overtime and Productivity in
normal 40-hour week. Experience Electrical Construction (hereinafter
indicates that a return to a normal 40- referred to as “NECA”);
hour schedule tends to “reset” the
productivity of a crew, such that if the 3) The 1997 study published by Dr. H.
crew returns to an overtime schedule Randolph Thomas of Penn State
after a week or two of a normal University, et al, entitled Schedule
schedule, the productivity loss would Overtime and Labor Productivity:
“reset” to that of the first week of Quantitative Analysis, published in
overtime. Thus, when utilizing any of the the June 1997 Journal of
data provided herein, it is important to Engineering and Construction
know the work schedule of the crews Management, which was based on
working overtime. If using a study that data included in a 1994 Report to
shows a progressively increasing loss of the Construction Industry Institute
productivity over time, should a crew entitled Effects of Scheduled
cease overtime and return to a straight Overtime on Labor Productivity: A
time schedule, the crew’s inefficiency Quantitative Analysis (hereinafter
upon resuming overtime work must be referred to as “Thomas”); and
reset to normal production for the first
measured period. Mechanical 4) The July 1979 United States Army
contractors should ensure that their bid Corps of Engineers publication
or negotiated proposals clearly state Modification Impact Analysis Guide,
that the base price for the work does not Publication No. EP 415-1-3
include any overtime, if in fact, no (hereinafter referred to as “the
overtime was estimated. If overtime was Corps”).
estimated and its scope exceeds
infrequent and limited spot overtime, an These studies have been in use in the
inefficiency factor should be included in construction industry for many years
the price for the work using a and have been generally accepted as
prospective estimate of inefficiency reliable measures of lost productivity
described in this chapter. due to unplanned extended overtime.6
Each has its strengths and weaknesses,
As previously noted, this chapter does including criticisms ranging from the use
not offer an empirical study based on of limited data sources to the withdrawal
new overtime loss of productivity data. of reports from publication.7 However,
Rather, this chapter reviews, analyzes, the baseline data in any of these studies
and summarizes four existing studies have never been proven to be
that have gained recognition in the inaccurate. Moreover, the concept that a
construction marketplace and have contractor’s work force becomes less
been utilized to prove claims for efficient as unplanned extended
overtime inefficiency. These studies are: overtime is worked is generally
recognized and has never been
1) The November 1980 Business disproved as an underlying fact.

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 3


undermined its underlying data. A
The four studies presented in this positive facet of this study is that its data
chapter as a basis for estimating a were based upon payroll records of the
contractor’s loss of labor productivity workers compared to actual units of
show striking similarities in their results. material installed on the project by those
These studies and the resulting curves workers. This study provided overtime
are not offered as precise or exact loss of productivity data over a 12-week
forecasts of impacts. Rather, they are period at various overtime intensity
reasonable guidelines to be used to levels and demonstrated that, in
estimate a loss of labor productivity general, inefficiency increases as the
caused by overtime. The courts and overtime schedule extends in duration.
boards of contract appeals have clearly
set forth the principle that a contractor National Electrical Contractors
does not have to prove its loss of labor Association (NECA)
productivity with mathematical precision, NECA provides the user with various
but can offer a reasonable estimate of overtime models measured over a 16-
its damages.8 These studies offer just week period. The underlying data for
that—a source from which to prepare a NECA was gathered by surveying
reasonable estimate of inefficiency electrical contractors who were
damages arising from unplanned members of the association.9 The
extended overtime. survey data was compiled and
presented as tables and graphs showing
In some cases a measured mile expected overtime productivity losses as
analysis can be performed that will “Low,” “Average,” and “High” for each
compute, by use of the contractor’s one-week period. These categories
project payroll and field records of allow the user to factor the weekly
installed material, a comprehensive loss inefficiency by gradients defining more
of labor productivity comparing actual precise levels of impacts. For instance,
impacted and non-impacted production if the contractor had been given
on the jobsite. When a measured mile substantial notice of the implementation
analysis can be performed, such an of overtime to allow some pre-planning
analysis usually subsumes all types of to lessen the effects of the overtime, the
inefficiency categories on a project. contractor could select a “Low” or
Therefore, if a measured mile labor “Average” impact. Alternatively, if the
productivity study is utilized, there is no overtime schedule imposed upon the
need for a separate inefficiency analysis contractor created havoc on the project
for overtime loss of productivity using site, or if there was stiff competition for
industry studies. overtime on nearby projects, the
contractor could select a “High” impact
Discussion of the Four Studies category. Like BRT, NECA
Business Round Table (BRT) demonstrates decreasing labor
The BRT is a study of a Proctor & productivity as the overtime schedule
Gamble construction project that extends in duration.
experienced overtime during the course
of the work. The BRT has been Dr. H. Randolph Thomas, P.E.
frequently cited as a reasonable (Thomas)10
guideline to predict loss of labor Thomas compared various overtime
productivity. While the BRT is inefficiency data with those
sometimes criticized because it is based independently derived from studies
on only one project, its critics have not prepared under his supervision.
Interestingly, Thomas opined that: “…it

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 4


is concluded that the BRT curve is a the aforementioned study was based on
reasonable estimate of the minimum data collected on the project site by site
loss of productivity. For projects personnel.
experiencing worsening degrees of
distress and disruption, the loss of The U.S. Army Corps of Engineers
productivity will probably be greater.”11 (“the Corps”)
Thomas tracked labor inefficiency The United States Army Corps of
caused by overtime in the mechanical Engineers (“the Corps”) study included
and electrical trades. In order to attempt an overtime loss of productivity graph
to accurately isolate the effects of showing predicted losses of labor
overtime on labor productivity, Thomas productivity for various work schedules
removed projects where overtime over a four-week period. Similar to the
occurred at the outset of the work, other reports cited herein, the Corps
projects that suffered from adverse labor showed declining productivity as the
action, and projects on which there were overtime schedule was extended. The
an “inordinate” number of changes in Corps’ overtime inefficiency graph was
scope or other conditions that would widely used to calculate impact and
exacerbate the inefficiencies arising inefficiency claims until the Corps
strictly from overtime. formally withdrew this publication
several years ago for unspecified
Thomas’ comparative curve utilized in reasons. It is noteworthy that Publication
EP 415-1-3, which contained the Corps’ indicates that the actual productivity was
overtime study, has never been equal to the planned productivity; a PI >
repudiated by the Army Corps of 1.0 indicates that the actual productivity
Engineers, but was withdrawn without exceeded (was better than) the planned
any criticism of the underlying data used productivity; and a PI < 1.0 indicates
in the overtime inefficiency graph. Thus, that the actual productivity was less than
the Corps study and curve are included (worse than) the planned productivity.
herein to compare its findings with those
of other overtime charts. In all cases, the PI during a normal 40-
hour work week is assumed to be 1.0.
Presentation of Data The PI during a given overtime schedule
The following charts present the loss of is then indicated on the chart over a
productivity as determined by the four number of weeks of consecutive
referenced studies. The loss of overtime. If a chart indicates a PI of 0.90
productivity is presented in terms of a for a given week, that shows a 10% loss
Productivity Index, or PI, such that of productivity for that week (1.00 – 0.90
= 0.10, and 0.10 ÷ 1.00 = 10%).

As noted above, the curves were


generally within the same relative order
of magnitude. Using the average of the
four studies, the table of PI at the
where Productivity is in terms of work bottom of this page was developed.
hours expended per unit of work
installed. In this case, a PI of 1.0

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 5


Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 6
Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 7
Application
Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 8
The Prospective Application As described herein, the NECA tables
When the period(s) of extended list three impact intensity levels for each
overtime have been determined, the overtime schedule: “Low,” “Average,”
mechanical contractor can find the chart and “High.” For the PI values shown in
for the applicable work schedule and the following table, the “Average” values
determine a reasonable range of listed in the NECA tables were utilized.
productivity loss by reading the PI for Where two different work weeks
the given week of consecutive extended resulted in the same number of total
overtime and subtracting it from the hours (e.g., a 60-hour work week
“normal” value of 1.0. For instance, a PI resulting from a 12-hour per day five-
of 0.60 equates to a inefficiency day schedule versus a 10-hour per day
estimate of 40% (1.00 – 0.60 = .40 x six-day schedule), the PI values derived
100% = 40%). In a prospective, or from the source data were averaged
forward priced analysis, the resulting between the two working schedules.
percentage of productivity loss is Further, from weeks 13 through 16, only
multiplied against the estimated number the NECA PI values were available.
of hours to be worked during that week
When inefficiency factors are applied to
to identify the estimated impact of estimated hours in a forward priced or
working extended overtime. In a prospective analysis, the user multiplies
retrospective analysis (i.e., an analysis the factor percentage against the
prepared after the fact using actual labor estimated hours for the overtime and for
hours), the formula for computing a the straight time worked by the overtime
conservative inefficiency estimate is crews. For instance, if a contractor
discussed in a following subsection. expects to work a 50-hour work week
with 25 mechanics for five weeks, the
computation appears in the forward

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 9


pricing table above. MCAA’s labor inefficiency factors, were
prepared with the anticipation that these
Based on a forward priced, or factors would be applied to forward-
prospective, estimate of overtime priced change order requests.12 Thus,
inefficiency, the contractor would the percent inefficiency factor would be
request compensation for 552 labor utilized as a multiplier against the
hours of lost labor productivity. estimated hours to provide the forecast
loss of productivity. However, when
The Retrospective Application using tables and factors in a
Retrospective analyses are performed retrospective manner (i.e., applying
after the overtime hours have been these factor percentages to actual
spent. For a retrospective example, let payroll hours), an adjustment must be
us assume that a contractor was made in order to eliminate overstating
directed to put its mechanical crews on
overtime during construction of a the inefficient hours. The use of the
retrospective formula adjusts for the fact
processing plant. The contractor’s that the inefficient hours are already
planned working hours were a 40-hour embedded within the actual labor hours
week, and in an effort to maintain used in the retrospective computation.
schedule the contractor placed the Multiplying the inefficiency factor against
mechanical crews on a five-day 10-hour the actual hours that also include the
shift over an 11-week period. In inefficient hours results in an
calculating the retrospective (performed overstatement of the estimated
after the fact) loss due to unplanned inefficiency.
extended overtime, the contractor
should apply the formula and 1) Identify the individual craft
procedures described below. persons who worked unplanned
extended overtime.
Most inefficiency tables, such as the

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 10


The contractor’s payroll records should
identify those individual craft labor who 2) Apply the applicable percentage
worked at least 50 hours a week during tables above for the applicable
the period of unplanned overtime. It overtime period (in this case
5/10s) to the craft hours subject to
should not be assumed that every lost productivity due to
worker recorded on the daily craft report unplanned extended overtime
actually worked overtime during a given using the retrospective formula.
week. Note that the number of workers
working over 40 hours declines with In this retrospective example using
each successive week, indicating that actual payroll data, the result is as
some members of the crew did not work shown in the table at the top of the
50 hours. The result of such a following page.
calculation is shown in the table below.
In this example, the contractor lost 748
Note that when the crew moved back to craft hours due to working unplanned
the normal 40-hour week, the “OT week extended overtime caused by the
clock” started over at Week 1 on March attendant overtime inefficiency over an
27, 2010, and no hours were subject to 11-week period using a retrospective
any lost efficiency in the preceding two analysis approach. In order to produce a
weeks. This was due to the fact that the conservative inefficiency estimate, it is
crew was able to recover during the recommended that when actual labor
normal work weeks ending March 13 payroll hours are used, as would be the
and 20. Thus, when overtime work case in a retrospective analysis, the
resumed for the week ending March 27, retrospective formula should be utilized,
2010, the “Week 1” percentages were as described below.
utilized.

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 11


The retrospective formula appears as: Thus, in cases where a mechanical
actual labor hours - (actual labor hours ÷ contractor is asked to forward price an
(1 + the percent inefficiency factor)), or overtime change order request, both the
as an example from the table above: direct payroll and the inefficiencies
1,250 – (1,250 ÷ 1.05) = the inefficient should be included. The content of this
hours, or 1,250 - 1,191 [the efficient chapter provides the guidelines for
hours] = 59 inefficient hours in a retro forward pricing an overtime-inefficiency
spec tive analysis. This formula solves change order request. In cases where
for the ef fi cient hours [1,191] in the the extent of the overtime is unknown,
equation and then al lows the user to the mechanical contractor, at a
subtract the efficient hours from the minimum, should include an express
total, yielding the inefficient hours [59]. reservations clause in the change order
proposal.
Preparation of the Request for
Equitable Adjustment For example:
It is not unusual for a general contractor
or owner to request that a mechanical This change order proposal
contractor provide a prospective cost represents the direct additional
proposal to accelerate a construction payroll costs arising from the
project. However, such requests are requested overtime schedule. No
often limited to the added payroll costs overtime inefficiencies are included
attendant to the overtime schedule. in this proposal.Amalgamated
When a mechanical contractor is asked Mechanical Contractors expressly
to submit a proposal to engage in reserves its rights to request
overtime on a prospective basis, the compensation for labor efficiencies
attendant estimated labor inefficiencies attendant to the requested overtime
must be added to the direct payroll costs schedule. A revision to this change
of the overtime schedule. order proposal containing the costs
for overtime labor inefficiencies will

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 12


be forwarded for processing as soon order request, the contractor takes off
as these costs can be computed. We pipe, fittings, and appurtenances based
estimate that the labor inefficiencies on a scope of added work provided by
arising from this overtime schedule the general contractor or owner. The
will not be less than ____ %.13 labor is derived there from and the final
pricing is added to the change order
There may be occasions when the proposal.
general contractor or owner denies the
opportunity to supplement a change In like fashion to the fullest extent
order request based on future events. possible, overtime change order
Such prohibitions also may be a part of requests should be based on a fixed
the contract or printed on the change scope. A fixed scope means that the
order forms themselves as “full accord general contractor or owner will provide
and satisfaction” clauses. If the the mechanical contractor with the
mechanical contractor is prohibited from number of days of overtime and the
submitting supplemental change order number of hours per day that are to be
requests, such as for labor inefficiencies worked in order to form a basis for the
arising from an overtime schedule, then forward-priced change order. Once the
forward pricing of the overtime fixed scope is known, then the
inefficiencies may be the only option. mechanical contractor can estimate the
added payroll costs and the expected
For example: loss of labor productivity using the
tables included herein. The tables refer
The overtime pricing contained only to estimated overtime inefficiency
herein includes the added payroll and do not include inefficiencies arising
costs for the overtime schedule from other categories of impacts, such
provided by your office. Furthermore, as unanticipated trade stacking,
this change order proposal contains reassignment of manpower
a loss of labor productivity estimate (“disruption”), lack of site access, or
based on the overtime schedule that other inefficiency factors. Refer to the
we have received from your firm. The chapter titled “How to Use the MCAA
proposed overtime schedule Labor Factors” for a more complete
provided by your office is the basis listing of potential inefficiency factors to
of our estimate for direct and consider when preparing a change order
inefficiency costs associated with request or a claim.
this change order request.
Amalgamated Mechanical In summary, it is essential that the
Contractors expressly reserves the mechanical contractor define, in its
right to submit a separate change proposal, what costs are and are not
order proposal in the event the included in its overtime change order
overtime schedule changes in any request. Obviously, if the general
manner from that upon which we contractor or owner direct an overtime
have relied in the pricing of this acceleration effort without a requirement
proposed change order. for a prospective change order proposal,
and with only the requirement to provide
It is recommended that the forward- the proof of overtime payroll costs for
priced (prospective) overtime change reimbursement, the mechanical
order request be treated, to the fullest contractor must make it clear that in
extent possible, in the same manner as addition to the actual payroll costs, a
a “sticks and bricks” change would be request for reimbursement of its
priced. In a “sticks and bricks” change overtime inefficiency costs will be

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 13


submitted for payment.
Mechanical contractors should not
Conclusions accelerate to mitigate schedule slippage
A sustained and unplanned overtime that was not caused by the mechanical
schedule can result in a substantial loss contractor’s fault or negligence on a
of labor productivity. The mechanical voluntary basis. If a mechanical
contractor may be entitled to recover the contractor is directed by a general
associated costs, in addition to the contractor or owner to accelerate the
direct overtime premium payroll costs. work by commencing an extended
The current available data on overtime work schedule in order to
inefficiency resulting from unplanned overcome delays not caused by the
extended overtime, when properly mechanical contractor, a specific notice
utilized, provide the mechanical is necessary. While most construction
contractor with a reasonable basis to contracts contain pro visions that require
estimate such losses in either the the mechanical contractor to follow the
prospective or forward pricing of an direction of a general contractor or
original estimate or a scope change, or owner to accelerate the work,15 such
in a retrospective application. The direction and the ensuing acceleration
inefficiency factor will vary depending on must be accompanied by clear and
the amount of overtime to be performed, timely notice that includes a statement
the number of mechanics required, and that the mechanical contractor is
the duration of the unplanned extended proceeding under protest and that a
overtime. Additionally, other inefficiency claim will be filed for reimbursement of
factors may occur simultaneously, such all costs as soon as those costs can be
as stacking of trades, reassignment of computed. If a mechanical contractor is
manpower, or site access restrictions. placed in a position of constructively
Such additional impacts can be accelerating16 a project to overcome
separately estimated using the MCAA delay that has not been caused by the
inefficiency factors described in this acts or omissions of the mechanical
manual.14 contractor, the review of these
conditions by the contractor’s upper
Crew considerations also can affect management and counsel is highly
overtime inefficiency levels. Such advisable.
considerations include whether or not to A schedule time impact analysis may be
place the entire crew on over time even an essential factor in demonstrating that
if only a definable portion of the work the mechanical contractor is not critically
requires acceleration (i.e., the critical delaying a project. This is important in
path activities), whether or not rest properly deflecting responsibility for the
intervals can be interspersed into the costs of acceleration in that the party
overtime schedule to allow for one or controlling the critical path in a delayed
more weeks of straight time work, or schedule is usually the party that is
whether certain activities that would be found responsible for the costs to
subject to overtime acceleration can be mitigate the delay. One primary means
scheduled for a second-shift crew. of delay mitigation is overtime. If the
These sorts of considerations are made mechanical contractor is being charged
on a project-specific basis and can with the acceleration costs, or the
affect the amount of inefficiency payment for the direct and indirect costs
sustained by a mechanical contractor of acceleration are being withheld on the
resulting from performing the work on an basis that the mechanical contractor
overtime schedule. was the responsible party, the
contractor can employ a schedule time

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 14


impact analysis to identify the party greater detail in the chapter on “Time
causing the critical path delay. Impact Analysis—Measuring Project
Delay,” many general contractors and
A schedule analysis also may be helpful owners are including broad waiver
in demonstrating, to the extent that the language on change order forms and on
mechanical contractor’s activities are the monthly payment applications. The
not controlling the critical path of the contractor should take great care to limit
current project schedule, that overtime this waiver language to matters that it
demanded by a general contractor or deems have been settled and take
owner will have no mitigating effect on express exception to each unsettled
the forecast end date of the project. It is item, such as a pending inefficiency
an accepted axiom of construction claim.
Critical Path Method (CPM) scheduling
that reducing the duration (i.e., by way Overtime inefficiency costs for extended
of overtime acceleration) of a path of periods of unanticipated overtime may
logic that does not control the critical exceed the payroll costs of overtime
path has no effect whatsoever on the premium. The mechanical contractor
end date of the overall project. Put should employ every reasonable
another way, the end date of a CPM management tool including issuing
schedule can only be foreshortened by proper and timely notice, keeping
accelerating work on the controlling comprehensive records, performing
critical path. If the mechanical contractor schedule analyses, taking exception to
can demonstrate that its work is not on, broad waiver language, and timely
or even near, the controlling critical submittal of change order requests to
path, accelerating those non-critical help ensure that the contractor’s right to
activities will have no mitigating effects recover all of its overtime costs are
on a project that is behind schedule and preserved and that payment will be
will represent potentially substantial forthcoming.
economic waste.
1
We are unaware of any data showing the
The mechanical contractor should difference in impact, if any, between
clearly note in its bid or change order “planned” and “unplanned” overtime.
proposal whether or not overtime has Generally, planned overtime has been
included in the base contract estimate and
been included in its lump-sum pricing,
was accounted for in the baseline CPM
and if so, to what extent it was included. schedule. Unplanned overtime, which is the
If a contractor includes extended subject of this chapter, occurs when no
periods of overtime in a lump-sum bid or overtime, or only very limited overtime for
change proposal, the attendant loss of equipment setting or start-up tasks, was
labor productivity should be evaluated contemplated under the terms of the base
and if deemed appropriate, the costs contract and is implemented during the
should be included in the lump-sum course of construction.
price for the work. At a minimum, the 2
contractor’s right to claim for such cost See, e.g. Appeal of J.A. Jones Constr. Co.,
00-2 BCA ¶ 31000, ENGBCA Nos. 6386,
impacts should be preserved.
6387, 6390; 2000 WL 1044011 (Eng. BCA
2000) (“The study itself states that it was
Preservation of the contractor’s right to based upon prolonged overtime schedules
be reimbursed for its overtime in manufacturing plants and that it may not
inefficiency costs, on projects where the be applicable to construction projects.”)
other party refuses to pay for such
3
overtime inefficiency costs, is of The well-accepted axiom is that the
paramount importance. As described in inefficiency effects of overtime affect the

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 15


worker while he or she works the straight- in amount. ‘Thus, courts have recognized
time schedule as well as the overtime that a plaintiff may recover even where it is
schedule. apparent that the quantum of damage is
unavoidably uncertain…or difficult to
4
Similarly, on a non-overtime-based project ascertain.’ The courts have recognized that
estimate, the mechanical contractor should ascertainment of damages, especially lost
qualify in its bidding documents if the bid productivity, is not an exact science. When
excludes overtime work. the responsibility for damages is proven, it is
not essential that the amount of damages be
5
The delay or event causing the mechanical ‘ascertainable with absolute exactness or
contractor to engage in spot overtime may mathematical precision.’” (and cases cited
not arise from the fault or negligence of the therein).
mechanical contractor. For instance, the
9
mechanical crews may be required to work It is a generally accepted axiom in the
spot overtime installing sleeves in slab pours construction industry that inefficiency
because the concrete contractor was impacts sustained by the mechanical trades
delayed and was required to accelerate, are similar in nature to the inefficiency
thus requiring the sleeving crew to work impacts sustained by the electrical trades
alongside on an overtime basis. given reasonably comparative adverse
conditions.
6
See, e.g., Ace Constructors v. United
10
States, 70 Fed.Cl. 253, 281-283 (Cl.Ct. Dr. H. Randolph Thomas, P.E. is a
2006), aff’d, 499 F.3d 1357 (Fed.Cir. professor of civil engineering at Penn State
2007)(contractor entitled to recover lost University, author or co-author of a series of
productivity due to overtime based on BRT); well recognized published papers on labor
Appeal of Harbison & Mahony, 68-1 BCA ¶ inefficiency, and frequent expert witness on
6880, ENGBCA Nos. 2819, 2820, 1968 WL the subjects of labor productivity and
436 (Eng. BCA 1968)(allowing claim for construction management.
overtime inefficiency based on NECA);
11
Appeal of States Roofing Co, 10-1 BCA ¶ Thomas, et al, “Scheduled Overtime and
34356, ASBCA No. 54860, 2010 WL 292732 Labor Productivity: Quantitative Analysis”
(ASBCA 2010)(Thomas study recognized); Journal of Construction Engineering and
Appeal of Sante Fe Engineers, Inc., 86-3 Management, June 1997.
BCA P 19092, ASBCA No. 29362, ASBCA
12
No. 28058, 1986 WL 20062 (ASBCA 1986), As a conservative approach, it has been
aff’d, 818 F.2d 856 (Fed.Cir. 1986)(allowing assumed that the NECA overtime tables, as
inefficiency claim using the Corps study). well as other published tables designed for
use as forward-pricing guides, require the
7
See, e.g., Hensel Phelps Const. Co. v. use of the retrospective formula when
General Services Admin, 01 BCA ¶ 31249, applying such factors to actual labor hours.
GSBCA No. 14744, GSBCA No. 14877,
13
2001 WL 43961 (General Services BCA The estimated inefficiency percent can be
2001)(“the Modification Impact Evaluation derived from the data and tables contained
Guide of the Corps of Engineers is not in this chapter.
recognized by GSA and, indeed, no longer
14
used by the Corps.”) While the Corps has The “Overtime” component (Item No. 15)
removed its Modification Impact Evaluation listed on the MCAA inefficiency factors table
Guide EP 415-1-3 from publication, it has in the chapter on “Factors Affecting Labor
not repudiated any of the data contained in Productivity” herein was designed to give
that publication. general guidance in forward-pricing overtime
inefficiency. It is recommended that the
8
See, e.g., B.Bramble, et al, Construction more specific estimates of impacts
Delay Claims, §5.07, p. 5-53(3d ed. 2000) contained in this chapter be applied to
(“Where the damages are directly overtime inefficiency analyses due simply to
attributable to the breach, they are often the increased level of specificity offered by
recoverable even though they are uncertain the studies and tables contained in this

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 16


chapter.
15
A subcontractor’s refusal to comply with
an acceleration directive provided by a
general contractor or owner, in the presence
of contractual authority to issue such a
directive, may result in a termination for
default. Before a direct, contractually proper
acceleration order from a general contractor
or owner is disregarded, the mechanical
contractor should consult with construction
counsel to evaluate the various courses of
action.
16
Constructive acceleration is a condition
wherein a contractor is directed to
accelerate to mitigate a delay not caused by
the contractor at no additional cost. In
anticipation of a claim to recover the costs of
the constructive acceleration, the contractor
takes express exception to the acceleration
directive, provides notice of a claim, and
then executes the acceleration as directed.
The submission of the claim for added costs
occurs as soon as the contractor can
compute the added costs either while the
acceleration is taking place, or after the
acceleration has concluded. The steps that
should be taken to perfect a constructive
acceleration claim are best set forth by the
contractor’s counsel.

Prepared by Paul Stynchcomb, PSP,


CFCC of FTI Consulting, Dr. Mike
Pappas, P.E., PhD of Pappas Consulting,
Inc. and Jarad Kriz, CCM, LEED® AP
(BD+C), PSP of FTI Consulting with peer
review performed by: Robert Beck,
Executive Vice President of John W.
Danforth Company; Michael Cables,
Executive Vice President of Kinetics
Systems Inc.; James Durant, President
and CEO of Trautman & Shreve; Richard
Freeman, Executive Vice President of
Stromberg Metal Works; Matthew Hahr,
Senior Vice President of John J. Kirlin,
LLC; Michael Loulakis, Esq.,
President/CEO of Capital Project
Strategies; Michael Mack, Vice Chairman
of John J. Kirlin, LLC; and Adam Snavely,
President and CEO of The Poole & Kent
Corporation.

Copyright, Mechanical Contractors Association of America, Inc., Revised 2011. 17

You might also like