CONSULTANCY SERVICES FOR ENHANCEMENT OF DESALINATED WATER IMPORT AND STORAGE


PROJECT TITLE: CONTRACT NUMBER: CA/CPC/0488/CNSL
FACILITIES AT MAA
KNPC TR. No.: KNPC -GS-DWSF-T-0041 Dated 26.01.2022 Date: 27.01.2022
DOCUMENT TITLE: Work Breakdown Structure & Detailed Level 5 Schedule 0488-GS-1000-G E N-G-A4-0005
ACTION
S.No. DOC. REF. ITEM DESCRIPTION KNPC COMMENTS GS RESPONSE
CODE
Activity Weight Assigned
17 Consultant to add activity id (P6) in the Activity Weight Assigned Report for easy mapping A Activity ID added to Activity assignment report
Report
Below activities to be grouped under Payment Milestone (PM01)
1-CORRESPONDENCE PROCEDURE As per article 7 Payment terms Milestone PM01 is defined as approval
2-DOCUMENT / DRAWING NUMBERING PROCEDURE of Company’s approval for resource loaded Baseline Schedule, S curve
0488-GS-1000-G EN-G- Activity Weight Assigned
18 3-FEED EXECUTION PLAN N and Progress Measurement procedure only. Hence Correspondence
A4-000S-Rev-B Report
4-SUB CONTRACTING PROCEDURE procedure, Doc / Numbering procedure, Feed execution plan, Sub
Accordingly, Consultant to update the Activity Weight Assigned Report and Progress contracting procedure are not included in PM01
Measurement Sheet.

ACTION CODES: A - CONCUR; N - NON-CONCUR; NA - NOT APPLICABLE