Temporary Shoring System for Deep Excavation - Nova-1 at Plot Prime-1, CBD
Walton, Lahore
3. Keeping in view Lahore High Court’s Decision (refer
to the attached letter from director town planning,
LDA), it was decided that ground
anchors could not be installed at the edge of the plot towards Main
Boulevard
Gulberg while on other three sides the possibility of installation of ground
anchors is subject to
the following pre-requisites:
a.
Consent of
adjacent plot owners should be taken by Nova-1 group to install ground
anchors in
their property; LCBDDA will facilitate Nova-1 group, in every possible manner,
to
get the required consent. In addition, ground anchors shall be de-stressed
by Nova-1
construction team, if and when required by the adjacent plot owners
to allow them to safely
execute excavation works at their plot for construction
of basements.
b.
Construction of
ground anchors/shoring system should not cause any damage to the
adjacent/nearby
existing structures. In addition, shoring system should be stiff enough to keep
displacements in the adjoining ground and nearby structures within the
permissible limits; the
displacement of the adjoining ground and nearby
structure should be periodically monitored
by Nova-1 construction team.
c.
Nova-1 design
team should explain how foundation piles of adjacently proposed multi-
storey
building with fewer numbers of basements will be constructed keeping in view in
the
proposed temporary shoring system design, including spacing of ground
anchors (the
https://mail.google.com/mail/u/0/?ik=d11b3fedbf&view=pt&search=all&permmsgid=msg-a%3Ar-7018153759944645438&simpl=msg-a%3Ar-70181537… 1/3
2/19/22, 10:40 PM Gmail - Temporary Shoring System for Deep Excavation - Nova-1 at Plot Prime-1, CBD Walton, Lahore
b.
Surcharge of
adjacent structures shall be considered in the design of temporary shoring
system; in case of nearby building supported on mat foundation, the temporary
shoring
system should be designed for a surcharge pressure of approximately 15
kPa per floor.
d.
A check on axial
compressive capacity of the embedded potion of the soldier piles against
various vertical loads, including sum of the vertical component of each ground
anchor load,
dead weight of the piles, etc. should be included in the design
calculations.
e.
It should be
mentioned in the temporary shoring system drawings that displacement of
the
retention system and deformation of the adjoining ground and nearby structures
should be
continuously monitored until completion of basement works.
f.
Anchor pull-out
tests should be executed and it should be mentioned in the temporary
shoring
system drawings that anchor lengths must be finalized based on the results of
anchor
pull-out tests.
g.
It should be
mentioned in the temporary shoring system drawings/design that the system
is
designed considering 4 no. of basements; moreover, basement floor levels should
also be
shown in the drawings.
5. A comprehensive construction site access plan should
be developed in line with project requirements
which will offer efficient
constriction of the project.
https://mail.google.com/mail/u/0/?ik=d11b3fedbf&view=pt&search=all&permmsgid=msg-a%3Ar-7018153759944645438&simpl=msg-a%3Ar-70181537… 2/3
2/19/22, 10:40 PM Gmail - Temporary Shoring System for Deep Excavation - Nova-1 at Plot Prime-1, CBD Walton, Lahore
Regards,
ASIM MASUD
Chief Engineer | Head Foundation and Pavement Section
Geotechnical and Geoenvironmental Engineering
Division
National Engineering Services Pakistan (Pvt.)