GCC FIRE & SAFETY LAB AND HPL GENERATOR BUILDING AT MODON-3

DAMMAM, KSA
DOCUMENT No: REV. No: DATE:
Page 1 of 4
KJ-123-P-QC-ITP-0010 00 24/11/2021

Client Consultant Contractor:


GCC Electrical testing laboratory Suhaimi Desing & Lemasters Suadi Amana Contracting Co. LLC

FIRE & SAFETY LAB AND HPL GENERATOR BUILDING MODON-3


DAMMAM, KSA

INSPECTION TEST PLAN FOR STEEL STRUCTURE ERECTION WORK


Document No: - KJ-123-P-QC-ITP-010-00

Prepared By: Reviewed By: Approved By:


Signature

Name Miqdad Hussain Saddin Elbaba Bilal B

Designation QA/QC Engineer Project Manager Sr.Project Manager

CLIENT/CONSULTANT COMMENTS:
Code A – Approved Code C – Rejected (Revise & Resubmit)
Code B – Approved with Comments Code D – For Information
Remarks:

Name: Signature: Date:


__________________________________ _______________________ __________________
GCC FIRE & SAFETY LAB AND HPL GENERATOR BUILDING AT MODON-3
DAMMAM, KSA
DOCUMENT No: REV. No: DATE:
Page 2 of 4
KJ-123-P-QC-ITP-0010 00 24/11/2021

LEGEND

FI - Full Inspection by the contractor


H- Hold Point. Inspection Request is required. The Consultant shall witness and sign
for acceptance of the inspection checking form. The contractor shall not proceed
until consultant has completed inspection and signed inspection checking form. The
further following certification shall be submitted for review (e.g. Laboratory/ Third
Party Service Company).
W- Witness Point. Inspection Request is required. The consultant shall optionally
witness. The contractor can proceed with inspection even if consultant is absent. In
such cases inspection reports should be submitted for review and signature. The
further following certification shall be submitted for review (e.g. Laboratory/Third
Party Service Company).
S- Surveillance. Check advice is not required. The Consultant shall spot witness during
job execution. The clarification if any shall be spot reviewed.
A- For Approval
IFCD- Issued For Construction Drawing
N/A- Not Applicable.
R- Review of Certification
1) Manufacturer’s certificates to be submitted to Consultant
2) Manufacturer’s certificates check.
3) Laboratory’s certification to be submitted to Consultant
4) Laboratory’s certificates check.
5) Datasheet/Catalogues to be submitted to Consultant
6) Datasheet/Catalogues check.
GCC FIRE & SAFETY LAB AND HPL GENERATOR BUILDING AT MODON-3
DAMMAM, KSA
DOCUMENT No: REV. No: DATE:
Page 3 of 4
KJ-123-P-QC-ITP-0010 00 24/11/2021

LIST OF QA/QC FORMS


FORM REFERENCE DESCRIPTION Rev
1 ADM-IMS-FRM-13-09 Inspection Request 0
2 ADM-IMS-FRM-13-10 Material Receipt Inspection Request 0
GCC FIRE & SAFETY LAB AND HPL GENERATOR BUILDING AT MODON-3 DAMMAM, KSA
DOCUMENT No: REV. No: DATE:
Page 4 of 4
KJ-123-P-QC-ITP-0010 00 24/11/2021

INSPECTION TEST PLAN FOR STEEL STRUCUTRE ERECTION WORK

Verifying Party

Sub-Contractor
ITP

Contractor

Consultant
Activity Discretion Reference Documents Acceptance Criteria Inspection Record Responsibility
Code

Client
Main
1.0 Material Receiving at site
 Approved
prequalification of  Visual Inspection / Physical QC Engineer
Structural steel & ADM-IMS-FRM-13-
1.1 supplier Verification Project FI FI FI -
accessories 10
 Approved Material  As per approved material Engineer
 Approved Drawings

Lay down area for steel  Approved Method  The lay down area shall be ADM-IMS-FRM-13- Project
1.2 - S S -
structure Statement cleaned, firm and safe 10 Engineer

2.0 Preparation

 Horizontal and vertical alignment


QC Engineer
 Approved Erection and projection of anchor bolts
2.1 Survey Work ADM-IMS-FRM-13-9 Project FI FI S -
drawings should be as per approved
Engineer
drawings
QC Engineer
 Approved Method ADM-IMS-FRM-13-
2.2 Equipment  Approved by safety team Project FI FI S -
Statement 09
Engineer
GCC FIRE & SAFETY LAB AND HPL GENERATOR BUILDING AT MODON-3 DAMMAM, KSA
DOCUMENT No: REV. No: DATE:
Page 5 of 4
KJ-123-P-QC-ITP-0010 00 24/11/2021

INSPECTION TEST PLAN FOR STEEL STRUCUTRE ERECTION WORK

Verifying Party

Sub-Contractor
ITP

Contractor

Consultant
Activity Discretion Reference Documents Acceptance Criteria Inspection Record Responsibility
Code

Client
Main
3.0 Steel Erection
 Horizontally and vertically aligned
 Approved Method QC Engineer
 Bracing, girts and purlins properly ADM-IMS-FRM-13-
3.1 Braced-Bay Statement Project FI H H -
installed 09
 Approved Drawings Engineer
 Bolts and Nuts properly tightened
 Horizontally and vertically aligned
 Approved Method QC Engineer
 Bracing, girts and purlins properly ADM-IMS-FRM-13-
3.2 Remaining Frame Statement Project FI H H -
installed 09
 Approved Drawings Engineer
 Bolts and Nuts properly tightened
4.0 Finishing
QC Engineer
 Approved Method  Finishing paint as per approved ADM-IMS-FRM-13-
4.1 Touch-Up paint Project FI H H -
Statement specification 09
Engineer
QC Engineer
 Approved Method  Finishing paint as per approved ADM-IMS-FRM-13-
4.2 Fire Proofing Project FI H H -
Statement specification 09
Engineer