You are on page 1of 11

Prestress Loss Diagnostics in Pretensioned Concrete

Structures with Corrosive Cracking


Lizhao Dai 1; Hanbing Bian 2; Lei Wang, M.ASCE 3; Michel Potier-Ferry 4; and Jianren Zhang 5
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Concrete cracking induced by strand corrosion can degrade bond strength and lead to prestress loss. A novel model is proposed to
predict corrosion-induced prestress loss in pretensioned concrete structures. The coupling effects of concrete cracking and bond degradation
are incorporated into the model. An experimental study is conducted to evaluate the effective prestress in eight corroded pretensioned concrete
beams under various stress levels. Experimental results are employed to validate the proposed model. Results demonstrate that the proposed
model can accurately predict prestress loss in corroded pretensioned concrete structures. Prestress loss depends on the corrosion degree.
Corrosion-induced concrete cracking may not degrade bond strength and effective prestress unless corrosion loss exceeds 6.6%. As corrosion
further progresses, bond strength and effective prestress decrease monotonically and then reduce to zero when corrosion loss reaches 34.0%.
DOI: 10.1061/(ASCE)ST.1943-541X.0002554. © 2020 American Society of Civil Engineers.
Author keywords: Pretensioned concrete structures; Strand corrosion; Corrosive cracking; Bond degradation; Prestress loss.

Introduction Numerous studies have been undertaken to assess the effects of con-
crete creep and shrinkage as well as the stress relaxation of prestressing
Prestressed concrete (PC) has been widely used in engineering strands on long-term prestress losses (Osborn et al. 2012; Kottari and
structures owing to its superior performance and high durability Shing 2014; Ward et al. 2016). Some codes also propose methods for
(Han et al. 2015; Dang et al. 2016). Unfortunately, some recent fail- evaluating the long-term prestress losses in PC structures (AASHTO
ure cases have raised concerns over the safety of existing PC struc- 2010; CEB-FIP 2010; PCI 2010). Compared with studies on long-term
tures (Li et al. 2011; Lim et al. 2016). Strand corrosion is one of the prestress losses, studies regarding corrosion-induced prestress loss
main causes of deterioration of PC structures (Pillai et al. 2014; have received little attention. Cavell and Waldron (2001) used the
Zhang et al. 2017). Corrosion can reduce strand cross section, induce strain compatibility method to estimate the residual prestress in post-
concrete cracking, degrade bond strength, lead to prestress loss, and tensioned concrete beams after tendon failure. Castel et al. (2011) in-
eventually deteriorate the capacity of PC structures (Val et al. 2009; dicated that the prestressing force loss in posttensioned concrete beams
Zhang and Yuan 2014; Biondini and Frangopol 2016). Effective pre- was proportional to the cross-section reduction of corroded strand.
stress in pretensioned concrete structures is more important than that The aforementioned studies focus on evaluating the effect
in other concrete members. Corrosion-induced cracking in existing of strand cross-section reduction on prestress loss in corroded post-
pretensioned concrete structures may lead to prestress loss. The tensioned concrete beams. The evaluation of corrosion-induced
evaluation of prestress loss caused by corrosive cracking is necessary prestress loss is a complicated task. Except for the cross-section
for the serviceability and safety of existing concrete structures. reduction of corroded strand, concrete cracking and bond degrada-
Several factors may lead to prestress losses, such as concrete creep tion can also cause prestress loss. Additionally, posttensioned con-
and shrinkage, stress relaxation of prestressing strand, and corrosion. crete members use anchorage systems to transmit prestress, whereas
prestress in pretensioned concrete structures is built through the
1 bond stress at the strand–concrete interface. Concrete cracking and
Lecturer, School of Civil Engineering, Changsha Univ. of Science and
Technology, No. 960 Wanjiali Rd., Changsha, Hunan 410114, China; bond degradation may have a more significant impact on prestress
Doctoral Student, Laboratoire d’Etude des Microstructures et de Mécanique loss in pretensioned concrete structures than in posttensioned con-
des Matériaux, Univ. de Lorraine, Ile du Saulcy, Metz Cedex 01 57045, crete members. Evaluation of prestress loss in pretensioned con-
France. Email: lizhaod@hotmail.com crete structures caused by corrosive cracking requires further study.
2
Associate Professor, Laboratoire d’Etude des Microstructures et de
The objective of this study is to propose an analytical model for
Mécanique des Matériaux, Univ. de Lorraine, Ile du Saulcy, Metz Cedex
01 57045, France. Email: hanbing.bian@univ-lorraine.fr evaluating prestress loss in corroded pretensioned concrete struc-
3
Professor, School of Civil Engineering, Changsha Univ. of Science tures, incorporating the coupling effects of concrete cracking and
and Technology, No. 960 Wanjiali Rd., Changsha, Hunan 410114, China bond degradation. The paper is organized as follows: First, an ana-
(corresponding author). Email: Leiwang@csust.edu.cn lytical model is proposed to estimate the corrosion-induced prestress
4
Professor, Laboratoire d’Etude des Microstructures et de Mécanique loss. Then, the effective prestress in eight corroded pretensioned con-
des Matériaux, Univ. de Lorraine, Ile du Saulcy, Metz Cedex 01 57045, crete beams under various stress levels is explored by the four-point
France. Email: michel.potier-ferry@univ-lorraine.fr flexural test. Subsequently, the proposed model is validated by the
5
Professor, School of Civil Engineering, Changsha Univ. of Science and experimental results. Finally, several conclusions are drawn.
Technology, No. 960 Wanjiali Rd., Changsha, Hunan 410114, China.
Email: jianrenz@hotmail.com
Note. This manuscript was submitted on July 28, 2018; approved on
August 13, 2019; published online on January 13, 2020. Discussion period Prestress Loss Model
open until June 13, 2020; separate discussions must be submitted for in-
dividual papers. This paper is part of the Journal of Structural Engineer- Strand corrosion can induce concrete cracking and degrade bond
ing, © ASCE, ISSN 0733-9445. strength, which may further cause prestress loss. Considering

© ASCE 04020013-1 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


ρ ¼ 6ΔA=Ap ð1Þ

where ΔA = area loss of a single wire; ΔA ¼ 2=3πðR20 − R2ρ Þ;


Ro and Rρ = radiuses of wire before and after corrosion, respec-
tively; and Ap = cross-sectional area of uncorroded strand.
Corrosion products have larger volume than the consumed iron,
and may expand outward. Some corrosion products fill pores and
cracks, and others contribute to expansive pressure (Bhargava et al.
2006). By the volume equivalent principle, the volume reduction of
corroded strand per unit length ΔV w can be written as
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

1
ΔV w ¼ ðΔV c þ ΔV e Þ ð2Þ
γ−1

where γ = rust expansion ratio; ΔV w ¼ 4πðR20 − R2ρ Þ; ΔV c = vol-


Fig. 1. Concrete cracking due to strand corrosion. ume of corrosion products per unit length that fill in cracks and
pores; and ΔV e = concrete volume change per unit length, with
ΔV e ¼ 4πðR2t − R20 Þ, in which Rt = radius of the wire with corro-
sion products.
The volume of corrosion products per unit length ΔV c that fill
the effects of concrete cracking and bond degradation is still
in cracks and pores (Bhargava et al. 2006) is as follows:
important in prestress loss evaluation. In this section, corrosion-
induced cracking is first estimated, considering the softening ΔV c ¼ 4πðRt − Ro ÞðRu − Rt Þ ð3Þ
behavior of cracked concrete. Then, the bond strength of corroded
strand is evaluated from the contributions of adhesion stress, con- where Ru = radius of the cracked region.
finement stress, and expansive pressure. Subsequently, a prediction The concrete displacement uc induced by expansive pressure is
model for prestress loss is proposed, incorporating the coupling given as
effects of concrete cracking and bond degradation.
ðγ − 1ÞAp ρ
u c ¼ R t − R0 ¼ ð4Þ
4πðRu þ R0 Þ
Concrete Cracking Induced by Strand Corrosion
The expansion of corrosion products can lead to cover cracking. Fig. 1 shows that before cover cracking, the concrete cover
Numerous studies indicate that the corrosion-induced cracking pro- consists of two regions: a cracked inner region and an uncracked
cess in reinforced concrete (RC) structures can be reasonably ex- outer region. The hoop stress σθ ðtÞ and the radial displacement uðtÞ
of uncracked concrete, respectively (Wang and Liu 2006), are as
plained by the thick-walled cylinder theory (Bhargava et al. 2006;
follows:
Li and Yang 2011). Additionally, this theory has been widely used
for estimating the transfer length in pretensioned concrete beams  
R2 P R2
(Abdelatif et al. 2015; Ramirez-Garcia et al. 2017). Therefore, the σθ ðtÞ ¼ 2 u u 2 1 þ 2c ð5aÞ
ðRc − Ru Þ t
thick-walled cylinder theory was used in the present study to model
concrete cracking.  
Dai et al. (2016) experimentally investigated the corrosion- R2u Pu R2c
uðtÞ ¼ ð1 þ vc Þ þ ð1 − vc Þt ð5bÞ
induced cracking of PC beams, and found that slight corrosion Ec ðR2c − R2u Þ t
could induce cover cracking owing to the large diameter of strand.
Corrosion pits on the strand surface were scarce, and their depth where Pu = expansive pressure at the interface between cracked and
and width were small. Similar findings were observed in Mangual uncracked regions; t = radius of the concrete in the uncracked
et al. (2013) and the present study. In the proposed model, the region, Ru ≤ t ≤ Rc , where Rc ¼ R0 þ C, and C = concrete cover;
average mass loss of segmental strand in different positions, rather and Ec and vc = elastic modulus and Poisson ratio of concrete,
respectively.
than local corrosion loss, is employed to predict the local strand
With the stress distribution equivalence principle, the tensile
prestress variation. Thus, the limited number of corrosion pits
stress of concrete σθ ðRu Þ at Ru should be equal to the tensile
has little effect on prestress prediction. Additionally, some studies
strength of concrete ft , that is, σθ ðRu Þ ¼ f t . The expansive pres-
indicate that the assumption for uniform corrosive pressure at the
sure Pu can be obtained by Eq. (5a) as follows:
bond interface is reasonable for concrete cracking prediction
(Li and Yang 2011; Chen and Nepal 2016). Therefore, corrosion R2c − R2u
products are assumed to be distributed uniformly around strand Pu ¼ f t ð6Þ
R2c þ R2u
in the present model.
When the tensile stress in the circumferential direction induced Substituting Eq. (6) into Eq. (5b), the radial displacement uðtÞ of
by corrosion expansion exceeds the concrete tensile strength, con- uncracked concrete can be calculated. It is assumed that the radial
crete is assumed to crack. Fig. 1 shows concrete cracking due to displacement uðrÞ of cracked concrete still satisfies the linear dis-
strand corrosion. Seven-wire steel strand is generally used as pre- tribution principle, which can be expressed as
stressing steel in PC structures. The contact area between the outer  
wire and concrete is equal to two-thirds of the surface area of the f t R2u R2c
uðrÞ ¼ ð1 þ vc Þ þ ð1 − vc Þr ð7Þ
wire. The outer wires would be first corroded when the strand is Ec ðR2c þ R2u Þ r
under environmental erosion, as shown in Fig. 1. The strand
corrosion loss ρ can be expressed as where r = radius of the concrete in the cracked region, R0 ≤ r ≤ Ru .

© ASCE 04020013-2 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


deformed bar, is further developed to estimate the bond stress of
corroded strand. Considering the corrosion effects, the bond stress
of corroded strand τ η can be written as

τη ¼ τa þ τb þ τc ð11Þ

where τ a = adhesion stress at the bond interface; τ b = confinement


stress from the surrounding concrete; and τ c = bond stress induced
by expansive pressure.
Adhesion stress at the bond interface is related to interface co-
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

hesion. The profile shape of strand is similar to that of deformed bar


Fig. 2. Stress-strain curve of concrete in tension. (Wang et al. 2016). Based on the diameter equivalence principle,
the characteristics of deformed bar ribs are translated into prestress-
ing strand geometry to calculate the adhesion stress of strand in
Cracks can lead to the softening of concrete tensile strength. The the present study. The adhesion stress of corroded strand can be
bilinear softening curve proposed by Pantazopoulou and Papoulia expressed (Chen and Nepal 2016) as follows:
(2001) is employed to describe the stress–strain relationship
of cracked concrete, as shown in Fig. 2. The hoop stress σθ ðrÞ of kAr ½cot δ þ tanðδ þ θÞ
τa ¼ fcoh ð12Þ
cracked concrete can be written as πDsr
8
>
> Ec εθ ðrÞ; εθ ðrÞ ≤ εct where k = number of transverse ribs; D = strand diameter; Ar = rib
>
>  
>
> area in the plane at right angles to strand axis; δ = rib orientation;
< f 1 − 0.85 εθ ðrÞ − εct ; ε < ε ðrÞ ≤ ε
t ct θ 1 sr = rib spacing; θ = friction angle between strand and concrete;
σθ ðrÞ ¼ ε1 − εct ð8Þ
>
>   and fcoh = coefficient of adhesion stress.
>
> εu − εθ ðrÞ
>
> The confinement stress from the surrounding concrete can be
: 0.15f t ε − ε ; ε1 < εθ ðrÞ ≤ εu
u 1 given (Coronelli 2002) as follows:

where εθ ðrÞ = hoop strain of cracked concrete; εct and ε1 = strains kCr tanðδ þ θÞ
τb ¼ px ð13Þ
of concrete corresponding to tensile strength and 15% of tensile π
strength, respectively; and εu = ultimate strain of concrete.
Before cover cracking, the expansive pressure would be bal- where Cr = shape factor constant; and px = maximum pressure at
anced by the residual tensile stress by cracked concrete and the bond failure.
confining stress by uncracked concrete (Wang and Liu 2006; The bond stress induced by expansive pressure can be written as
Han et al. 2016). The expansive pressure Pc at the strand–concrete
τ c ¼ kc Pc ð14Þ
interface can be expressed as
Z R where kc = friction coefficient between corroded strand and cracked
u
Pc R0 ¼ P u Ru þ σθ ðrÞdr ð9Þ concrete.
R0
The bond strength of corroded strand depends on adhesion
After cover cracking, the expansive pressure would be resisted stress, confinement stress, and expansive pressure, which can be
by the residual tensile strength by cracked concrete. The expansive estimated by Eqs. (11)–(14). The bond mechanisms of corroded
pressure Pc can be rewritten as strand described in this part will be used for the evaluation of
Z R effective prestress in the transfer region.
c
Pc R0 ¼ σθ ðrÞdr ð10Þ
R0
Corrosion-Induced Prestress Loss
The expansive pressure during concrete cracking relates to
A model for corrosion-induced prestress loss can be proposed by
the degree of strand corrosion, which can be calculated by
considering the combined effects of concrete cracking and bond
Eqs. (9) and (10).
degradation. Corrosion-induced prestress loss in the present study
is defined as the difference between the effective prestress in un-
Bond Degradation Due to Strand Corrosion corroded strand and that in corroded strand. The effective prestress
in corroded strand could be evaluated with the strain compatibility
The bond between strand and concrete is attributed to adhesion, and force equilibrium equations in the beam section.
friction, and mechanical interlock (Briere et al. 2013). The initial When the prestressing force in pretensioned concrete structures
bond stress is due to adhesion, which disappear once slip occurs is released, the strand prestress will transfer to the concrete through
(Abdelatif et al. 2015; Ramirez-Garcia et al. 2017). After the strand the bond stress at the strand–concrete interface. One-half of the
slips, strand twisting occurs together with longitudinal slip. The beam is discretized into several segments to analyze the stress
strand’s bond mechanism is similar to that of a deformed bar based variation in corroded strand, as shown in Fig. 3.
on the experimental investigation by Wang et al. (2016). The differ- It can be seen that the segments of the half beam are numbered
ence is that the deformed bar has no twisting effects during the from 1 to n. For an arbitrary segment i, the stress of corroded strand
slip process. fp;i can be written as
Corrosion can change the geometrical shape of strand.
Corrosion-induced cracking can reduce the confinement effects fp;i ¼ fp;iþ1 − Δf p;i ð15Þ
of concrete. These factors would affect the bond behavior of cor-
roded strand. In the present study, a model proposed by Chen and where Δfp;i = local stress variation in the corroded strand at
Nepal (2016), which is used to predict the bond stress of corroded segment i, 1 ≤ i ≤ n.

© ASCE 04020013-3 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

Fig. 3. Stress variation in corroded strand.

The contact area between the outer wire and concrete can be
expressed as S ¼ 4=3πRρ;i li , where Rρ;i = residual radius of
corroded wire at segment i; and li = segment length. The local
stress variation in the corroded strand is given as
6S
Δf p;i ¼ τ ð16Þ
Ap;i ðηÞ η

where Ap;i ðηÞ = residual cross-sectional area of the corroded strand


at segment i.
For corroded pretensioned concrete structures, the strand pre-
stress at the beam end is zero, that is, fp;1 ¼ 0. The tension force Fig. 4. Strain distribution in the beam cross section.
of the corroded strand T p;i can be expressed as
T p;i ¼ f p;i Ap;i ðηÞ ð17Þ bottom of beam, respectively; and as0 = distance from the center
of gravity of compressive reinforcements to the top of beam.
After corrosion, the strand strain change Δεp;i at segment i can The stress–strain behavior of steel reinforcements can be de-
be written as scribed by an elastic-plastic constitutive model (El-Tawil et al.
2001) as follows:
T pi T p;i 
Δεp;i ¼ − ð18Þ Es ε s εs ≤ εsy
Ep Ap Ep Ap;i ðηÞ fs ¼ ð21Þ
f sy þ Esp ðεs − εsy Þ εs > εsy
where T pi = initial prestressing force of the uncorroded strand at
segment i; and Ep = elastic modulus of strand. where fs and fsy = stress and yield strength of steel reinforcements,
When the stress of the corroded strand reaches the effective pre- respectively; εs and εsy = strain and yield strain of steel reinforce-
stress, the concrete strain change Δεc;i at the strand position should ments, respectively; and Es and Esp = elastic and hardening modu-
be equal to the strand strain change Δεp;i so that strain compati- lus of steel reinforcements, respectively.
bility is maintained, that is, Δεc;i ¼ Δεp;i . After corrosion, the The forces of steel reinforcements in the tension and compres-
0
concrete strain εcp;i at segment i is given as sion zones, Fs;i and Fs;i , respectively, are
 
T pi 1 e2p Fs;i ¼ As fs ðεs;i Þ ð22aÞ
εcp;i ¼ þ − Δεc;i ð19Þ
Ec A I
0
Fs;i ¼ As0 fs ðεs;i
0
Þ ð22bÞ
where ep = eccentricity of the strand; A = cross-sectional area of
intact concrete; and I = inertia moment of the gross section of intact where As and fs ðεs;i Þ = section area and stress of steel reinforce-
concrete. ments in the tension zones, respectively; and As0 and fs ðεs;i 0 Þ =
This study primarily investigates the prestress loss caused by section area and stress of steel reinforcements in the compression
strand corrosion and does not consider corrosion in steel reinforce- zones, respectively.
ments. Fig. 4 shows the strain distribution in the beam cross The mechanical behavior of concrete in tension can be modeled by
section. Based on the plane section assumption for the beam, a linear elastic constitutive law suggested by Vu et al. (2010). The non-
the strains of steel reinforcements in the tension and compression linear constitutive law of concrete proposed by Collins and Mitchell
0 , respectively, are
zones, εs;i and εs;i (1991) is used to describe the mechanical behavior of concrete in
hx − as compression. The stress–strain curves of concrete are expressed as
εs;i ¼ ε ð20aÞ     2 
hx − ap cp;i  ε ε
0
fc 2 c − c in compression
fc ¼ ε0 ε0 ð23Þ
0 h − hx − as0 E c εc in tension
εs;i ¼ ε ð20bÞ
hx − ap cp;i
where fc and εc = stress and strain of concrete, respectively; f c0 =
where h = height of beam; hx , ap , and as = distances from the cen- concrete compressive strength; and ε0 = concrete strain corresponding
ters of gravity of beam, strand and tensile reinforcements to the to the compressive strength, and is set to 0.002.

© ASCE 04020013-4 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


The total force of concrete Ci can be written as thickness of concrete cover, concrete strength, structural details,
Z and mechanical property of steel. The thickness of concrete cover,
Ci ¼ fc dAc ð24Þ concrete strength, structural details, and mechanical property of
Ac steel can be obtained from the design drawing and by practical
engineering measurement.
where Ac = cross-sectional area of damaged concrete. The corrosion loss of strand can be measured with nondestruc-
For corroded pretensioned concrete structures, the forces of pre- tive testing techniques such as half-cell potential, linear polariza-
stressing strand, concrete, and steel reinforcements should satisfy tion resistance, and acoustic emission methods (Mangual et al.
the following equilibrium equation: 2013). Additionally, strand corrosion in different regions can be
evaluated by crack widths on the concrete surface. Some models
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

0
Ci þ Fs;i − T p;i − Fs;i ¼ 0 ð25Þ have been proposed to predict corrosion loss with crack width
(Li and Yang 2011; Khan et al. 2014; Wang et al. 2019). Once
As mentioned above, a novel model, incorporating the coupling the aforementioned parameters have been obtained, the proposed
effects of concrete cracking and bond degradation, is proposed model can be employed to predict the prestress loss in corroded
to evaluate corrosion-induced prestress loss. The calculation pretensioned concrete structures in practical engineering.
process of prestress loss can be performed as follows. First, the
corrosion-induced cracking and bond degradation are estimated
by Eqs. (1)–(14). Subsequently, the stress variation in corroded Evaluation of Effective Prestress
strand at each segment is calculated by Eq. (16). Based on the
step-by-step accumulation, the strand stress increment is obtained In this section, eight concrete beams under various stress levels
by Eq. (15). The accumulation process is terminated when the were designed to evaluate the effect of strand corrosion on the ef-
stresses of prestressing strand, concrete, and steel reinforcements fective prestress. Electrochemically accelerated corrosion was used
in the beam section satisfy the strain compatibility and force equi- to obtain the different corrosion levels of strand in pretensioned
librium equations. Then, the effective prestress in the corroded strand concrete beams. The effective prestress in corroded pretensioned
is evaluated by Eq. (17). The effective prestress in uncorroded strand concrete beams was evaluated by the four-point flexural test.
can be obtained by setting the strand corrosion loss to zero in the
above procedure. The prestress loss is equal to the effective prestress Specimen Details
in uncorroded strand minus that in corroded strand. The calculation
flow chart of prestress loss is shown in Fig. 5. Eight concrete beams were designed with a rectangular section
For real-world prestress loss prediction, the following param- of 130 × 150 mm (5.12 × 5.91 in:) and a length of 2,000 mm
eters should be input into the model: strand corrosion loss, (78.74 in.). The beams were reinforced with a 15.2-mm (0.60 in.)
diameter seven-wire steel strand. Two 6-mm (0.24 in.) deformed
bars were arranged at the bottom of each beam, two 8-mm
(0.31 in.) deformed bars were employed at the top, and 6-mm
(0.24 in.) stirrups with 100-mm (3.94 in.) spacing were used in
the beams.
The mechanical properties of steel were measured by testing two
standard samples (General Administration of Quality Supervision,
Inspection and Quarantine of the People’s Republic of China
2010). The length of the standard samples was 500 mm (19.69 in.).
The yield and ultimate strengths of the strand were 1,830 MPa
(265.35 Ksi) and 1,910 MPa (276.95 Ksi), respectively. The yield
and ultimate strengths of the deformed bars were 400 MPa
(58.00 Ksi) and 540 MPa (78.30 Ksi), respectively. The covers
of the deformed bars and the strand were 30 mm (1.18 in.) and
42.4 mm (1.67 in.), respectively. The specimen details are shown
in Fig. 6.
The testing parameters of the specimens are presented in Table 1.
According to corrosion time, the specimens were divided into two
groups: Group A and Group B, each containing four specimens.
The corrosion times in Group A and Group B were 15 and 20 days,
respectively. To investigate the prestress losses under various stress
levels, each group was designed with four stress levels: 0, 0.25f p ,
0.5fp , and 0.75fp , respectively, where f p was 1,860 MPa
(269.70 Ksi).
Type 32.5 portland cement was used in the concrete. The con-
crete mix contained 417 kg=m3 (702.88 lb=yd3 ) cement,
1,026 kg=m3 (1,729.38 lb=yd3 ) coarse aggregates, and 676 kg=m3
(1,139.44 lb=yd3 ) fine aggregates. The water–cement ratio of the
concrete was 0.44. Sodium chloride (NaCl) with a 5% mass fraction
of cement was used in the concrete to catalyze the corrosion
process.
The 28-day uniaxial compressive strength of the concrete was
obtained by testing three cubes measuring 150 × 150 × 150 mm
Fig. 5. Calculation flowchart of prestress loss.
(5.91 × 5.91 × 5.91 in:) (Ministry of Housing and Urban-Rural

© ASCE 04020013-5 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


Fig. 6. Details of specimen (unit: millimeters; 1 mm ¼ 0.039 in:).
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

Table 1. Testing parameters the cathode. Direct current was impressed on the strand using a
Groups Beam number Prestress (MPa) Corrosion time (days) potentiostat. The corrosion current in the entire process was 0.1 A.
After the accelerated corrosion, the crack width in 10-cm
Group A PA0 0 15
(3.94 in.) intervals on the concrete surface was measured by a port-
PA1 0.25f p 15
PA2 0.5fp 15
able microscope with a resolution of 0.01 mm (0.0004 in.). The
PA3 0.75f p 15 average mass loss of the strand in the longitudinal direction was
Group B PB0 0 20 measured to reflect the corrosion level of strand in the global re-
PB1 0.25f p 20 gion. The average mass loss of strand in 10-cm (3.94 in.) intervals
PB2 0.5fp 20 was measured to reflect the variation of the corrosion degree in dif-
PB3 0.75f p 20 ferent regions.
Note: 1 MPa ¼ 0.145 Ksi. The measurement of mass loss of the strand was performed
after load testing, and the program was as follows. First, the con-
crete cover was removed by a destructive method, and the corroded
strand was taken out. Then, the corroded strand was cleaned with a
Development of the People’s Republic of China 2002). The con- 12% hydrochloric acid solution and neutralized with alkali (ASTM
crete compressive strength is given in Table 2. The average value 2011). Subsequently, the average mass loss of the entire strand was
and standard deviation of concrete compressive strength were measured, and is given in Table 3. Following this, the strand was
44.1 MPa (6.39 Ksi) and 1.68, respectively. The concrete tensile cut into segments with a length of 10 cm (3.94 in.), and the mass
strength ft can be related to the compressive strength of concrete loss of the segmental strand was measured.
pffiffiffiffiffi
f c as ft ¼ 0.56 f c based on ACI 318M (ACI 2011).
Crack Width and Corrosion Loss
Accelerated Corrosion and Data Measurement To reflect the corrosion degrees of the strand in the longitudinal
The differences between steel corrosion induced by the impressed direction, the corrosion morphology of the strand at 1=2 of PB3
current technique and natural environment have been investigated (the maximum corrosion loss of specimen in the experiment)
(El Maaddawy and Soudki 2003; Yuan et al. 2007). Accelerated was provided, as shown in Fig. 8.
corrosion, compared with natural corrosion, is more likely to cause Fig. 8 shows that there are few corrosion pits on the strand sur-
pitting corrosion in steel owing to the high current density (El face in the longitudinal direction. The depth and width of these
Maaddawy and Soudki 2003). Although the characteristics of ac- corrosion pits were small. The visual observation of the corroded
celerated corrosion are different from those of natural corrosion, the strand further indicates that using the uniform corrosion model to
accelerated corrosion is still widely used so that tests can be com- predict prestress loss is reasonable in the present study. Crack
pleted within a reasonable amount of time. widths and mass losses in 10-cm (3.94 in.) intervals are presented
In the present tests, the electrochemical method was employed to reflect the variation of the corrosion loss and crack width in the
to accelerate strand corrosion. To clarify the effect of strand corro- longitudinal direction, as shown in Fig. 9.
sion on prestress loss alone, the steel reinforcements were protected
with epoxy resin to prevent corrosion. Fig. 7 shows the accelerated
corrosion device. It consisted of a direct-current potentiostat and
a stainless steel plate. The strand was linked to the anode; the
'LUHFWFXUUHQW
stainless steel plate dipped in the 10% NaCl solution acted as

Table 2. Compressive strengths of concrete


Beam number (prestress) Compressive strength (MPa)
PA0 (0) 42.8
PA1 (0.25fp ) 43.5
PA2 (0.5fp ) 44.8
PA3 (0.75fp ) 43.9
PB0 (0) 41.6
PB1 (0.25f p ) 45.9
PB2 (0.5f p ) 43.4
PB3 (0.75f p ) 46.8
Fig. 7. Accelerated corrosion device.
Note: 1 MPa ¼ 0.145 Ksi.

© ASCE 04020013-6 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


Table 3. Summary of experimental results
Beam number (prestress) ρc (%) Fc (kN) Fu (kN) Fe;t (kN) fe;t (MPa) Normalized prestress loss (%)
PA0 (0) 7.05 5.0 38.0 0.0 0.0 0.0
PA1 (0.25fp ) 7.47 8.5 42.0 52.6 409.0 12.0
PA2 (0.5fp ) 8.35 11.5 45.5 89.7 704.1 24.3
PA3 (0.75fp ) 9.41 14.0 48.0 120.7 958.5 31.3
PB0 (0) 10.45 4.5 28.3 0.0 0.0 0.0
PB1 (0.25f p ) 11.52 7.0 31.0 37.5 304.9 34.4
PB2 (0.5f p ) 12.48 9.5 33.5 56.4 463.6 50.2
PB3 (0.75f p ) 14.69 11.5 36.7 74.0 624.0 55.3
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

Note: ρc = mass loss; Fc = cracking load; Fu = ultimate load; Fe;t = prestressing force; f e;t = effective prestress; 1 kN ¼ 0.225 kip; and 1 MPa ¼ 0.145 Ksi.

Fig. 8. Corrosion morphology of strand (unit: centimeters; 1 cm ¼ 0.0039 in:).

It can be seen that crack width relates to the prestress and cor- By varying the stress level of the strand from 0 to 75%fp , the aver-
rosion degree. Crack propagates as corrosion loss increases, and age increase in the mass loss rate is 37.0%.
prestress can accelerate the corrosion-induced cracking process.
Some studies indicate that the mass loss of steel associates well
with corrosion-induced crack width on the concrete surface (Khan Effective Prestress Evaluation under Various Stress
et al. 2014). This implies that the mass loss of the strand can be Levels
evaluated with crack width. Several experimental techniques have been proposed to evaluate
Comparison of the experimental data in Table 3 shows that the effective prestress in PC structures (Caro et al. 2013): (1) meas-
prestress can accelerate the mass loss of the strand. The mass losses uring longitudinal concrete strains over time at the center of gravity
of PA0 and PA3 were 7.05% and 9.41%, respectively. The mass of prestressing strand; (2) determining the cracking load based on
losses of PB0 and PB3 were 10.45% and 14.69%, respectively. load testing; (3) monitoring strain variation in the strand by cutting

2.4 Corrosion loss 0.20 2.4 0.20 2.4 0.20 2.4 Corrosion loss 0.20
Corrosion loss Corrosion loss
Crack width Crack width
Crack width /mm

Crack width /mm


Crack width /mm

2 Crack width
Crack width /mm

2 0.16 2 Crack width 0.16 2 0.16


0.16

Corrosion loss
Corrosion loss
Corrosion loss
Corrosion loss

PA0, 0 PA1, 0.25fp PA2, 0.5fp PA3, 0.75fp


1.6 1.6 1.6 1.6
0.12 0.12 0.12 0.12
1.2 1.2 1.2 1.2
0.08 0.08 0.08 0.08
0.8 0.8 0.8 0.8
0.04 0.4 0.04 0.4 0.04 0.04
0.4 0.4

0 0.00 0 0.00 0 0.00 0 0.00


0 40 80 120 160 200 0 40 80 120 160 200 0 40 80 120 160 200 0 40 80 120 160 200
(a) Beam length /cm (b) Beam length /cm (c) Beam length /cm (d) Beam length /cm

2.4 0.20 2.4 Corrosion loss 0.20


2.4 0.20 2.4 Corrosion loss 0.20 Corrosion loss
Corrosion loss Crack width
2 2 Crack width
Crack width /mm

Crack width /mm

Crack width /mm

Crack width /mm

2 Crack width 2 Crack width 0.16 0.16


0.16 0.16
Corrosion loss

Corrosion loss
Corrosion loss

Corrosion loss

PB1, 0.25fp PB2, 0.5fp PB3, 0.75fp


1.6 PB0, 0 1.6 1.6 1.6
0.12 0.12 0.12 0.12
1.2 1.2 1.2 1.2
0.08 0.08 0.08 0.08
0.8 0.8 0.8 0.8
0.04 0.04 0.4 0.04 0.4 0.04
0.4 0.4
0 0.00 0 0.00 0 0.00 0 0.00
0 40 80 120 160 200 0 40 80 120 160 200 0 40 80 120 160 200 0 40 80 120 160 200
(e) Beam length /cm (f) Beam length/ cm (g) Beam length /cm (h) Beam length /cm

Fig. 9. Crack widths and corrosion losses: (a) PA0; (b) PA1; (c) PA2; (d) PA3; (e) PB0; (f) PB1; (g) PB2; and (h) PB3 (1 mm ¼ 0.039 in:).

© ASCE 04020013-7 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


Load cell

1 5
10 70 130 190

2 3 4

Fig. 10. Diagram of load testing (unit: centimeters; 1 cm ¼ 0.0039 in:).


Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

it into a representative exposed length; and (4) determining the side to beam’s weight; M c = cracking moment; and I c = inertia moment
pressure to close cracks in a small cylindrical hole. All these meth- of the gross section of damaged concrete.
ods require a reverse process from the testing results to calculate Based on cracking load and corrosion loss, the effective pre-
effective prestress using mechanical theory. Load testing is one of stress and prestress loss in corroded pretensioned concrete beams
the most commonly used techniques to evaluate effective prestress can be evaluated, and are given in Table 3. The normalized prestress
in the present testing. loss is defined as the ratio of the prestress loss in the corroded
A four-point flexural test was performed to obtain the load- strand to the effective prestress in the uncorroded strand. By com-
deflection curves of corroded specimens, as shown in Fig. 10. paring the prestress loss presented in Table 3, it is found that the
The specimens had a clear span of 1,800 mm (70.87 in.) and a high stress of strand can accelerate corrosion-induced prestress
bending span of 600 mm (23.62 in.). Loads were applied mono- loss. The normalized prestress losses of PA1 and PA3 are 12.0%
tonically and measured by a load cell. The load was applied at and 31.3%, respectively. The normalized prestress losses of PB1
a rate of 2 kN (0.45 kip) per step until beam failure. Subsequently, and PB3 are 34.4% and 55.3%, respectively. By varying the strand
the beam unloaded at a rate of 5 kN (1.12 kip) per step. The vertical stress level from 25%f p to 75%f p , the corrosion-induced prestress
deflections at the mid-span, supports, and loading points were mea- loss increases by 20.1%.
sured using electronic digital dial gauges. The displacements at the
mid-span were used to reflect the load-deflection curves of the
specimens and are shown in Fig. 11. It can be seen that beam de- Model Validation
flection increases as load increases to the maximum load. After
that, the concrete crushing in the compression zone results in a sud- The experimental results are used to verify the proposed model in
den decrease in the load, and leads to beam failure. The cracking this section. The relevant parameters are selected as follows. The
and ultimate loads are listed in Table 3. rust expansion ratio γ varies from 2 to 4 (Zhao and Jin 2006), and is
During load testing, the tensile stress at the bottom of the beam set to 3. The friction angle between corroded strand and concrete is
is affected by self-weight, effective prestress, and applied load. expressed as kc ¼ 0.37 − 0.26ðx − xc Þ (Coronelli 2002), where x =
Cracks may appear at the bottom of the beam once the tensile stress corrosion depth of the strand and xc = critical corrosion depth of the
exceeds the concrete tensile strength. The critical condition of con- strand at cover cracking. The coefficient of adhesion stress is given
crete cracking can be expressed as as fcoh ¼ 2 − 10ðx − xc Þ (Chen and Nepal 2016). The shape factor
constant Cr is set to 0.8 (Chen and Nepal 2016).
  For evaluating corrosion-induced prestress loss, the bond
1 ep M M
ft ¼ f p;η Ap ðηÞ þ yb − s yb − c yb ð26Þ strength of corroded strand is a key factor and should be clarified
Ac I c Ic Ic
first. Bond strengths under different corrosion losses are presented
in Fig. 12. The normalized bond strength in Fig. 12 is defined as the
where f p;η = effective prestress in the corroded strand; Ap ðηÞ = bond strength ratio of corroded strand to that of uncorroded strand.
residual cross-sectional area of the corroded strand; yb = distance As Fig. 12 shows, strand corrosion less than 6.6% can increase
from the neutral axis to the bottom of the beam; Ms = moment due bond strength, and further corrosion will lead to bond strength

50 50
PA3, 0.75fp PB3, 0.75fp
PA2, 0.5fp PB2, 0.5fp
PA1, 0.25fp PB1, 0.25fp
40 PA0, 0 40 PB0, 0

30
Load /kN

30
Load /kN

20 20

10 10

0 0
0 5 10 15 20 25 30 0 5 10 15 20 25 30
(a) Deflection /mm (b) Deflection /mm

Fig. 11. Load-deflection curves: (a) Group A; and (b) Group B (1 kN ¼ 0.225 kip; 1 mm ¼ 0.039 in:).

© ASCE 04020013-8 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


1.6 1.2
Bond model proposed by the present study
1.4 Bond model proposed by Wang et al. (2016)

Normalized prestress loss


1
Normalized bond strength
1.2
0.8
1
0.2
0.6
0.8 0.15

0.6 0.4 0.1 6.0% 6.6%

0.4 0.05
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

0.2
0
0.2 0 0.02 0.04 0.06 0.08 0.1
0
0 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 Corrosion loss
Corrosion loss
Fig. 14. Prestress loss and corrosion loss.
Fig. 12. Bond strengths under different corrosion losses.

degradation. For slight corrosion less than 6.6%, the accumulation Wang et al. (2016) are employed to predict corrosion-induced pre-
of corrosion products can increase the roughness of the strand sur- stress loss, as shown in Fig. 14. Wang et al. (2016) designed 10
face and improve the friction and gear forces at the strand–concrete pull-out beams with various corrosion levels to investigate the bond
interface. Thus, slight strand corrosion can increase bond strength. degradation of corroded strand. Based on the experimental data, an
If corrosion loss exceeds 6.6%, severe concrete cracking can result, empirical model is proposed to predict bond strength as follows:
and the confinement of surrounding concrete may be reduced, lead- 
ing to bond strength degradation. 1.0; η ≤ 6.0%
Rη ¼ −11.8η
ð27Þ
For the effective prestress prediction, the bond strength in the 2.03e ; η > 6.0%
present model is selected as follows. Slightly corroded strand (cor-
rosion loss less than 6.6%) is considered to have bond strength sim- where Rη = bond strength ratio of corroded strand to that of uncor-
ilar to that of uncorroded strand for safety reserve reasons. When roded strand.
corrosion loss exceeds 6.6%, the bond strength model proposed in As Fig. 14 shows, the prestress loss depends on the corrosion
the present study is used to predict effective prestress. Fig. 13 degree. When corrosion loss is less than the critical value, strand
shows the predicted effective prestress and experimental results. corrosion may lead to slight concrete cracking but may not degrade
The normalized prestress in Fig. 13 is defined as the ratio of the bond strength and effective prestress. The critical corrosion loss
effective prestress in corroded strand to 75%f p . values for the present model and Wang et al. (2016) are 6.6%
The average error and standard deviation of the prediction re- and 6.0%, respectively. Exceeding the critical corrosion loss, strand
sults are 4.8% and 0.02, respectively. The prediction error in the corrosion can induce severe concrete cracking, which may reduce
jP −P j bond strength and effective prestress. The curve obtained from
present study is defined as t Pt p , where Pt and Pp are tested and the present model shows that the effective prestress would decrease
predicted effective prestress, respectively. The error may be as- to zero when the corrosion loss is greater than 34.0%. The variation
cribed to some simplifications of the analytical model; another rea- tendencies of prestress loss in Fig. 14 are similar for both models.
son for the error is the measurement uncertainty of the experimental This indicates that the proposed model can be employed to pre-
data. Considering the complexity of the corrosion process, the pre- dict the corrosion-induced prestress loss in pretensioned concrete
diction error can be accepted. This indicates that the proposed structures.
model can provide accurate prediction for the effective prestress in The objective of the present study is to propose an analytical
corroded pretensioned concrete structures. model to predict corrosion-induced prestress loss. The variability
To further clarify the applicability of the proposed model, of material parameters has not been considered, which can be ad-
the bond strength models proposed in the present study and in dressed by probabilistic analysis. Further studies on the variability

0.7 Prediction (PA3, 0.75fp) 0.7 Prediction (PB3, 0.75fp)


Prediction (PA2, 0.5fp) Prediction (PB2, 0.5fp)
0.6 0.6
Normalized prestress

Prediction (PA1, 0.25fp) Prediction (PB1, 0.25fp)


Normalized prestress

Testing (PA3, 0.75fp) Testing (PB3, 0.75fp)


0.5 0.5
Testing (PA2, 0.5fp) Testing (PB2, 0.5fp)
Testing (PA1, 0.25fp) 0.4 Testing (PB1, 0.25fp)
0.4
0.3 0.3

0.2 0.2

0.1 0.1

0 0
0 25 50 75 100 125 150 175 200 0 25 50 75 100 125 150 175 200
(a) Beam length (cm) (b) Beam length (cm)

Fig. 13. Experimental and predicted prestress: (a) Group A; and (b) Group B (1 cm ¼ 0.0039 in:).

© ASCE 04020013-9 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


of prestress loss prediction are required; however, they are outside Mater. 40 (Mar): 650–658. https://doi.org/10.1016/j.conbuildmat
the scope of the present study. .2012.11.064.
Caro, L. A., J. R. Martí-Vargas, and P. Serna. 2013. “Prestress losses evalu-
ation in prestressed concrete prismatic specimens.” Eng. Struct.
Conclusions 48 (Mar): 704–715. https://doi.org/10.1016/j.engstruct.2012.11.038.
Castel, A., D. Coronelli, N. A. Vu, and R. François. 2011. “Structural
A novel model was proposed to predict the prestress loss in pre- response of corroded, unbonded posttensioned beams.” J. Struct.
Eng. 137 (7): 761–771. https://doi.org/10.1061/(ASCE)ST.1943
tensioned concrete structures caused by corrosive cracking. The
-541X.0000315.
effective prestress in eight corroded pretensioned concrete beams
Cavell, D. G., and P. Waldron. 2001. “A residual strength model for deterio-
under various stress levels was explored by the four-point flexural rating post-tensioned concrete bridges.” Comput. Struct. 79 (4):
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

test. The experimental results were used to validate the proposed 361–373. https://doi.org/10.1016/S0045-7949(00)00150-4.
model. The following conclusions can be drawn: CEB-FIP (Comité Euro-International du Béton-Fédération International de
• The proposed model can be used to accurately predict la Précontrainte). 2010. “Model code 2010: Final draft.” In Model code
corrosion-induced prestress loss. The superiority of the model prepared by special activity group 5. Lausanne, Switzerland: CEB-FIP.
is that it can consider the coupling effects of concrete cracking Chen, H. P., and J. Nepal. 2016. “Analytical model for residual bond
and bond degradation. strength of corroded reinforcement in concrete structures.” J. Eng.
• Prestress loss depends on the corrosion degree. Theoretical Mech. 142 (2): 04015079. https://doi.org/10.1061/(ASCE)EM.1943
analysis indicates that corrosion-induced concrete cracking may -7889.0000997.
not degrade the bond strength and effective prestress unless the Collins, M., and D. Mitchell. 1991. Prestressed concrete structure.
Englewood Cliffs, NJ: Prentice Hall.
corrosion loss exceeds 6.6%. As corrosion progresses, the bond
Coronelli, D. 2002. “Corrosion cracking and bond strength modeling for
strength and effective prestress decrease monotonically and then corroded bars in reinforced concrete.” ACI Struct. J. 99 (3): 267–276.
reduce to zero when the corrosion loss reaches 34.0%. Dai, L., L. Wang, J. Zhang, and X. Zhang. 2016. “A global model for
• High strand stress can accelerate corrosion-induced prestress corrosion-induced cracking in prestressed concrete structures.” Eng.
loss. By varying the strand stress level from 25% to 75% Fail. Anal. 62 (Apr): 263–275. https://doi.org/10.1016/j.engfailanal
of the strand tensile strength, corrosion-induced prestress loss .2016.01.013.
increases by 20.1%. Dang, C. N., R. W. Floyd, G. S. Prinz, and W. M. Hale. 2016. “Determi-
It should be mentioned that the specimens used in the present nation of bond stress distribution coefficient by maximum likelihood
study were subjected to electrochemically accelerated corrosion. method.” J. Struct. Eng. 142 (5): 04016003. https://doi.org/10.1061
Additionally, the uniform corrosion model was used to describe /(ASCE)ST.1943-541X.0001460.
strand corrosion. Strand corrosion in practical engineering may EI Maaddawy, T., and K. Soudki. 2003. “Effectiveness of impressed current
be more complex due to size effects and complex corrosion mecha- technique to simulate corrosion of steel reinforcement in concrete.”
J. Mater. Civ. Eng. 15 (1): 41–47. https://doi.org/10.1061/(ASCE)0899
nism. More studies on corrosion-induced prestress loss in the natu-
-1561(2003)15:1(41).
ral environment are required. El-Tawil, S., C. Ogunc, A. Okeil, and M. Shahawy. 2001. “Static and
fatigue analyses of RC beams strengthened with CFRP laminates.”
J. Compos. Constr. 5 (4): 258–267. https://doi.org/10.1061/(ASCE)
Acknowledgments 1090-0268(2001)5:4(258).
General Administration of Quality Supervision, Inspection and Quarantine
This work was conducted with financial support from the State of the People’s Republic of China. 2010. Metallic materials—Tensile
Key Development Program for Basic Research of China (Grant testing—Part 1: Method of test at room temperature. [In Chinese.]
No. 2015CB057705), and the National Natural Science Foundation GB/T 228.1. Beijing: Certified Information Systems Auditor.
of China (Grant Nos. 51678069, 51708477). Their support is grate- Han, S. J., D. H. Lee, S. H. Cho, S. B. Ka, and K. S. Kim. 2016. “Esti-
fully acknowledged. mation of transfer lengths in precast pretensioned concrete members
based on a modified thick-walled cylinder model.” Struct. Concr.
17 (1): 52–62. https://doi.org/10.1002/suco.201500049.
References Han, W., J. Wu, C. S. Cai, and S. Chen. 2015. “Characteristics and dynamic
impact of overloaded extra heavy trucks on typical highway bridges.”
AASHTO. 2010. AASHTO-LRFD bridge design specifications. J. Bridge Eng. 20 (2): 05014011. https://doi.org/10.1061/(ASCE)BE
Washington, DC: AASHTO. .1943-5592.0000666.
Abdelatif, A. O., J. S. Owen, and M. F. M. Hussein. 2015. “Modelling the Khan, I., R. François, and A. Castel. 2014. “Prediction of reinforcement
prestress transfer in pre-tensioned concrete elements.” Finite Elem. corrosion using corrosion induced cracks width in corroded reinforced
Anal. Des. 94 (Feb): 47–63. https://doi.org/10.1016/j.finel.2014.09 concrete beams.” Cem. Concr. Res. 56 (Feb): 84–96. https://doi.org/10
.007. .1016/j.cemconres.2013.11.006.
ACI (American Concrete Institute). 2011. Building code requirements for Kottari, A. K., and P. B. Shing. 2014. “Estimation of long-term prestress
structural concrete and commentary. ACI 318M. Farmington Hills, losses in post-tensioned girders.” ACI Struct. J. 111 (5): 1091–1100.
MI: ACI. https://doi.org/10.14359/51686921.
ASTM. 2011. Standard practice for preparing, cleaning, and evaluating Li, C. Q., and S. T. Yang. 2011. “Prediction of concrete crack width under
corrosion test specimens. ASTM G1-03. West Conshohocken, PA: combined reinforcement corrosion and applied load.” J. Eng. Mech.
ASTM. 137 (11): 722–731. https://doi.org/10.1061/(ASCE)EM.1943-7889
Bhargava, K., A. K. Ghosh, Y. Mori, and S. Ramanujam. 2006. “Model for .0000289.
cover cracking due to rebar corrosion in RC structures.” Eng. Struct. Li, F., Y. Yuan, and C. Q. Li. 2011. “Corrosion propagation of prestressing
28 (8): 1093–1109. https://doi.org/10.1016/j.engstruct.2005.11.014. steel strands in concrete subject to chloride attack.” Constr. Build. Ma-
Biondini, F., and D. M. Frangopol. 2016. “Life-cycle performance of ter. 25 (10): 3878–3885. https://doi.org/10.1016/j.conbuildmat.2011.04
deteriorating structural systems under uncertainty: Review.” J. Struct. .011.
Eng. 142 (9): F4016001. https://doi.org/10.1061/(ASCE)ST.1943 Lim, S., M. Akiyama, and D. M. Frangopol. 2016. “Assessment of the
-541X.0001544. structural performance of corrosion-affected RC members based on ex-
Briere, V., K. A. Harries, J. Kasan, and C. Hager. 2013. “Dilation behavior perimental study and probabilistic modeling.” Eng. Struct. 127 (Nov):
of seven-wire prestressing strand—The Hoyer effect.” Constr. Build. 189–205. https://doi.org/10.1016/j.engstruct.2016.08.040.

© ASCE 04020013-10 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013


Mangual, J., M. ElBatanouny, P. Ziehl, and F. Matta. 2013. “Corrosion Vu, N. A., A. Castel, and R. François. 2010. “Response of post-tensioned
damage quantification of prestressing strands using acoustic emission.” concrete beams with unbonded tendons including serviceability and ul-
J. Mater. Civ. Eng. 25 (9): 1326–1334. https://doi.org/10.1061/(ASCE) timate state.” Eng. Struct. 32 (2): 556–569. https://doi.org/10.1016/j
MT.1943-5533.0000669. .engstruct.2009.11.001.
Ministry of Housing and Urban-Rural Development of the People’s Wang, L., L. Dai, H. Bian, Y. Ma, and J. Zhang. 2019. “Concrete cracking
Republic of China. 2002. Standard for test method of performance prediction under combined prestress and strand corrosion.” Struct. In-
on ordinary fresh concrete. [In Chinese.] GB/T 50081-2002. Beijing: frastruct. Eng. 15 (3): 285–295. https://doi.org/10.1080/15732479
Architecture and Building Press. .2018.1550519.
Osborn, G. P., P. J. Barr, D. A. Petty, M. W. Halling, and T. R. Brackus. Wang, L., X. Zhang, J. Zhang, J. Yi, and Y. Liu. 2016. “Simplified model
2012. “Residual prestress forces and shear capacity of salvaged pre- for corrosion-induced bond degradation between steel strand and con-
stressed concrete bridge girders.” J. Bridge Eng. 17 (2): 302–309. crete.” J. Mater. Civ. Eng. 29 (4): 04016257. https://doi.org/10.1061
Downloaded from ascelibrary.org by Changsha University of Science and Technology on 01/14/20. Copyright ASCE. For personal use only; all rights reserved.

https://doi.org/10.1061/(ASCE)BE.1943-5592.0000212. /(ASCE)MT.1943-5533.0001784.
Pantazopoulou, S. J., and K. D. Papoulia. 2001. “Modeling cover-cracking Wang, X., and X. Liu. 2006. “Bond strength modeling for corroded rein-
forcements.” Constr. Build. Mater. 20 (3): 177–186. https://doi.org/10
due to reinforcement corrosion in RC structures.” J. Eng. Mech.
.1016/j.conbuildmat.2005.01.015.
127 (4): 342–351. https://doi.org/10.1061/(ASCE)0733-9399(2001)
Ward, D. B., C. N. Dang, R. W. Floyd, and W. M. Hale. 2016. “Prestress
127:4(342).
losses of double-tee girders cast with lightweight self-consolidating
PCI (Precast/Prestressed Concrete Institute) and Industry Handbook Com-
concrete.” J. Build. Eng. 7 (Sep): 133–142. https://doi.org/10.1016/j
mittee. 2010. PCI design handbook—Precast/prestressed concrete.
.jobe.2016.06.004.
7th ed. Chicago: Prestressed Concrete Institute. Yuan, Y., Y. Ji, and S. P. Shah. 2007. “Comparison of two accelerated
Pillai, R. G., D. Trejo, P. Gardoni, M. B. D. Hueste, and K. Reinschmidt. corrosion techniques for concrete structures.” ACI Struct. J. 104 (3):
2014. “Time-variant flexural reliability of posttensioned, segmental con- 344–347. https://doi.org/10.14359/18624.
crete bridges exposed to corrosive environments.” J. Struct. Eng. 140 (8): Zhang, W., Z. Ye, X. Gu, X. Liu, and S. Li. 2017. “Assessment of fatigue
A4014018. https://doi.org/10.1061/(ASCE)ST.1943-541X.0000991. life for corroded reinforced concrete beams under uniaxial bending.”
Ramirez-Garcia, A. T., C. N. Dang, W. M. Hale, and J. R. Martí-Vargas. J. Struct. Eng. 143 (7): 04017048. https://doi.org/10.1061/(ASCE)ST
2017. “A higher-order equation for modeling strand bond in preten- .1943-541X.0001778.
sioned concrete beams.” Eng. Struct. 131 (Jan): 345–361. https://doi Zhang, W., and H. Yuan. 2014. “Corrosion fatigue effects on life estimation
.org/10.1016/j.engstruct.2016.10.050. of deteriorated bridges under vehicle impacts.” Eng. Struct. 71 (Jul):
Val, D. V., L. Chernin, and M. G. Stewart. 2009. “Experimental and 128–136. https://doi.org/10.1016/j.engstruct.2014.04.004.
numerical investigation of corrosion-induced cover cracking in rein- Zhao, Y., and W. Jin. 2006. “Modeling the amount of steel corrosion at the
forced concrete structures.” J. Struct. Eng. 135 (4): 376–385. https://doi cracking of concrete cover.” Adv. Struct. Eng. 9 (5): 687–696. https://
.org/10.1061/(ASCE)0733-9445(2009)135:4(376). doi.org/10.1260/136943306778827556.

© ASCE 04020013-11 J. Struct. Eng.

J. Struct. Eng., 2020, 146(3): 04020013

You might also like