BANGLADESH BANK

Khuna Office
Engineering Department

Estimate (as per present market price)


Date: 21/10/2020

Repairing & painting wall, ceiling of bathroom, kitchen & dinning of flat kha/32 of bldg. no 03,
Baniakhamar staff quarter, BB, Khulna.

Item no. Description of item Unit Quantity Rate (Tk.) Amount(Tk.)


A. Plaster = 100 sft (approx.)
1 Cement bag 1.00 400.00 400.00
2 Sand bag 5.00 40.00 200.00
3 Mason each 1.00 700.00 700.00
4 Helper each 1.00 500.00 500.00
S/Total 1800.00
B. Distemper = 400 sft (approx.)
1 Distemper gallon 1.00 350.00 350.00
2 Chalk powder kg. 2.00 35.00 70.00
3 4" brush each 1.00 150.00 150.00
4 Iron paper each 2.00 20.00 40.00
5 Painter each 1.00 600.00 600.00
6 Helper (paint) each 1.00 500.00 500.00
7 Material carrying charges L. S. 1.00 100.00 100.00
S/Total 1810.00
Total 3610.00
Say 3600.00
In word: Taka three thousand six hundred only.

(Ujjwal Mondol)
AD(Engg.-Civil)-2

DD(Engg.-Civil)

DGM(Engg.)