PERIMETER FENCE
TALOTO, TAGBILARAN CITY, BOHOL
2
ITEM NO DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
CONCRETE
WORKS
1. Footing:
Cement 50 bags 230.00 11,500.00
Sand 10 cu.m. 1,100.00 11,000.00
I Gravel 20 cu.m. 1,100.00 22,000.00
2. Column
Cement 70 bags 230.00 16,100.00
Sand 15 cu.m. 1,100.00 16,500.00
Gravel 30 cu.m. 1,100.00 33,000.00
SUB-TOTAL 110,100.00
STEEL REINFORCEMENT
1. Column (DSB)
1.1. 12 mm Φ x 6.0m 96 pcs. 210.00 20,160.00
1.2. 10 mm Φ x 6.0m 45 pcs. 180.00 8,100.00
II 1.3. Tie Wire Gage#16 20 kls. 90.00 1,800.00
2. Footing
2.1 12 mm Φ x
6.0m 65 pcs. 210.00 13,650.00
2.2. Tie Wire Gage#16 15 kls. 90.00 1,350.00
SUB-TOTAL 45,060.00
FORMWORKS & SCAFFOLDINGS
1. Plywood
1.) 1/4" x 4' x 8' 43 sheets 500.00 21,500.00
2. Coco lumber
III 2.1. 2" x 2" x 10' 1300.00 bd.ft. 20.00 26,000.00
3. Common Wire Nails
3.1. # 4" CWN 2 box 1,200.00 2,400.00
3.2. # 1 1/2" CWN 2 box 1,200.00 2,400.00
SUB-TOTAL 52,300.00
BARD WIRE
IV
bard wire 1 lot 80,000.00 80,000.00
1
SUB-TOTAL 80,000.00
PPE
V 1.) Safety and Health Program 1 lot 15,000.00 15,000.00
SUB-TOTAL 15,000.00
GATE
VI Gate 1 lot 35,000.00 35,000.00
SUB-TOTAL 35,000.00
PAINTING
1.) Sand Paper 10 pcs 30.00 300.00
2.) 4" paint brush 5 pcs 70.00 350.00
3.) skim coat 5 bags 300.00 1,500.00
VII 4.) body filler 1 gal. 500.00 500.00
5.) semi-gloss paint 15 gal. 600.00 9,000.00
6.) red lead 15 gal. 550.00 8,250.00
7.) used cotton 5 kgs 50.00 250.00
SUB-TOTAL 20,150.00
TOTAL COST OF MATERIALS 357,610.00
LABOR COST (40% Total Cost of Materials) 94,400.00
CONTINGENCY COST (5% Total Cost of Materials) 17,880.50
GRAND TOTAL COST 469,890.50