Professional Documents
Culture Documents
TOWN OF CALEDON
SEPTEMBER 2016
DISTRIBUTION
TABLE OF CONTENTS
TABLES
DIAGRAM
ENCLOSURES
1.0 INTRODUCTION
The purpose of the investigation was to reveal the subsurface conditions and to
determine the engineering properties of the disclosed soils for the design and
construction of the proposed project.
The investigation area is situated on Halton-Peel till plain, where the drift dominates
the soil stratigraphy. In places, lacustrine sand, silt, clay and drift which have been
reworked by the water action of Peel Ponding (glacial lake) have modified the drift
stratigraphy.
The subject site is located on an internal road crossing Centreville Creek in the
Albion Hills Conservation Area, located at 16500 Regional Road 50 in the Town of
Caledon.
The field work, consisting of 2 boreholes to depths of 12.6 m and 21.8 m, was
performed on April 22, 2016, at the locations shown on the Borehole Location Plan,
Drawing No. 1.
The field work was supervised and the findings recorded by a Geotechnical
Technician.
The elevation at each of the borehole locations was determined using hand-held
Global Navigation Satellite System surveying equipment (Trimble Geoexplorer XH
6000) which has a maximum accuracy of 10 cm.
Reference No. 1603-S116 4
This investigation has revealed that beneath the existing earth fill dam, the site is
underlain by strata of sandy silt and silty fine sand.
The boreholes are located within the existing earth dam. These boreholes revealed
that the earth fill of the dam extends to a depth of 6.1± m and consists of silty clay.
The original topsoil or alluvial deposits were not detected beneath the earth fill, but
may have been obscured by the augering.
The water content of the samples was found to range from 20% to 26%, indicating
that the fill is in a wet condition.
The obtained ‘N’ values are 4 and 5 blows per 30 cm of penetration showing that the
fill was placed with nominal compaction. Due to its unknown history and low ‘N’
values, the fill is not suitable for supporting any structures.
A grain size analysis was performed on 1 representative sample; the result is plotted
on Figure 3.
Reference No. 1603-S116 5
The fill is amorphous in structure; it will ravel and is susceptible to collapse in steep
cuts. Otherwise, where it is free of deleterious materials, its engineering properties
are generally similar to those of its constituent materials.
One must be aware that the samples retrieved from boreholes 10 cm in diameter may
not be truly representative of the geotechnical and environmental quality of the fill,
and do not indicate whether the topsoil beneath the earth fill was completely stripped.
This should be further assessed by laboratory testing and/or test pits.
One must also be aware that in cuts in the clay fill, the sides are prone to sudden
collapse, particularly if the fill is in a wet condition.
4.2 Sandy Silt (Both Boreholes) and Silty Fine Sand (Boreholes 2)
The sandy silt was found beneath the earth fill. It extends to the investigated depth of
12.6 m in Borehole 1. In Borehole 2, a silty fine sand was found underlying the silt at
a depth of 7.0± m, extending to the investigated depth of 21.8 m.
Sample examinations show that the silt and sand are non-cohesive. They are in a wet
condition and become highly dilatant when shaken by hand. The sand and silt are
water bearing.
The obtained ‘N’ values range from 7 to 39, with a median of 13 blows per 30 cm
penetration, from which the relative density is inferred to be loose to dense, being
generally compact. The loose to marginally compact condition extends to a depth of
9.0± to 12.0± m below the existing ground surface.
Reference No. 1603-S116 6
The natural water content of all the samples was determined and the results are
plotted on the Borehole Logs. The values range from 14% to 23%, with a median of
17%, indicating wet conditions. The wet soils are water bearing.
Grain size analyses were performed on 2 representative samples of the sandy silt and
1 representative sample of the silty fine sand. The results are plotted on Figures 4
and 5, respectively.
Based on the above findings, the following engineering properties are deduced:
The obtainable degree of compaction is primarily dependent on the soil moisture and,
to a lesser extent, on the type of compactor used and the effort applied.
As a general guide, the typical water content values of the revealed soils for Standard
Proctor compaction are presented in Table 1.
Based on the above findings, the in situ soils are generally too wet for 95% Standard
Proctor compaction and will require aeration prior to structural compaction. The
soils can be aerated by spreading them thinly on the ground in dry, warm weather.
The earth fill should be compacted using a heavy-weight, kneading-type roller. The
silt and sand can be compacted by a smooth roller with or without vibration,
depending on the water content of the soils being compacted. The lifts for
compaction should be limited to 20 cm, or to a suitable thickness as assessed by test
strips performed by the equipment which will be used at the time of construction.
One should be aware that with considerable effort a 90%± Standard Proctor
compaction of the wet silt and silty fine sand is achievable. Further densification is
prevented by the pore pressure induced by the compactive effort; however, large
random voids will have been expelled, and with time the pore pressure will dissipate
Reference No. 1603-S116 8
and the percentage of compaction will increase. There are many cases on record
where after a few months rest, the density of the compacted mantle has increased to
over 95% of its maximum Standard Proctor dry density.
If the compaction of the soils is carried out with the water content within the range
for 95% Standard Proctor dry density but on the wet side of the optimum, the surface
of the compacted soil mantle will roll under the dynamic compactive load. This is
unsuitable for pavement construction since each component of the pavement structure
is to be placed under dynamic conditions which will induce the rolling action of the
subgrade surface and cause structural failure of the new pavement. The foundations
for structures will be placed on a subgrade which will not be subjected to impact
loads. Therefore, the structurally compacted soil mantle with the water content on
the wet side or dry side of the optimum will provide an adequate subgrade for the
construction.
Reference No. 1603-S116 9
The water level in the boreholes could not be determined after drilling since water
was being used throughout the drilling process.
The soil colour changed from brown to grey at depths of 6.1± m and 7.0± m below
the prevailing ground surface. The brown colour indicates that the soils have
oxidized and may represent the transition of the groundwater level. The groundwater
level, however, will fluctuate with the seasons and will be affected by the water level
in the water course. The groundwater level is estimated to be close to the water level
in the existing watercourse.
In excavation, the groundwater yield from the water-bearing sandy silt and silty fine
sand will be appreciable and persistent. Groundwater control is necessary for
excavation into the saturated strata.
Reference No. 1603-S116 10
This investigation has revealed that beneath the existing earth fill dam, the site is
underlain by a strata of loose to dense, generally compact sandy silt and silty fine
sand.
The water level in the boreholes could not be determined because water was being
used throughout the drilling process. The groundwater level is estimated to be close
to the water level in the watercourse and will fluctuate with the seasons. It will be
affected by the water level in the watercourse. The groundwater yield from the sandy
silt and silty fine sand will be appreciable and persistent. Groundwater control is
necessary for excavation into the saturated strata.
The geotechnical findings which warrant special consideration are presented below:
The recommendations appropriate for the project described in Section 2.0 are
presented herein. One must be aware that the subsurface conditions may vary
Reference No. 1603-S116 11
The recommended soil pressures for the design of footings are listed below:
The suitable founding level for the above recommended bearing pressures lies at
El. 254.0± m.
The recommended soil pressures incorporate a safety factor of 3. The total and
differential settlements of the footings are estimated to be 25 mm and 15 mm,
respectively.
stratum. For preliminary design purpose, the carrying capacity of Helical Pilers of
200 mm diameter, extending to a depth of 20 m +, is approximately 500 kN (SLS)
and 800 kN (ULS). The capacity can be determined based on the type of pile being
used and should be confirmed by performing in situ static load tests on the working
piles. The founding elevations and design capacity of the Helical Piles should be
determined by the prospective Helical Pile Foundation Systems contractor. The cost
impact and the feasibility of the development based on the type of foundation used
should be carefully considered.
The foundations should have at least 1.2 m of earth cover for protection against frost
action, or should extend to below the anticipated scouring depth, whichever is
greater.
The footings must meet the requirements specified in the latest Ontario Building
Code. As a guide, the structure should be designed to resist an earthquake force
using Site Classification ‘D’ (stiff soil).
The backfill against the wing walls must consist of free-draining material with
subdrains or weepholes to drain the accumulated water behind the walls. This
measure is to prevent a build-up of ice pressure behind the wall which would impact
its structural integrity. Rip-rap should be placed along the wet perimeter to prevent
toe erosion, and the side slopes of the embankment should be sodded to protect
against rainwash erosion.
Reference No. 1603-S116 13
The backfill around the culvert structure must be conducted simultaneously on both
sides. The on-site inorganic soils are generally suitable for trench backfill; however,
they should be sorted free of any topsoil, deleterious materials and foreign matter
prior to the backfilling.
The backfill in the trenches should be compacted to at least 95% of its maximum
Standard Proctor dry density in the lower portion. In the zone within 1.0 m below the
road subgrade, the materials should be compacted with the water content 2% to 3%
drier than the optimum, and the compaction should be increased to at least 98% of the
respective maximum Standard Proctor dry density. This is to provide the required
stiffness for pavement construction. In the lower zone, the compaction should be
carried out on the wet side of the optimum; this allows a wider latitude of lift
thickness.
One must be aware of the possible consequences during trench backfilling and
exercise caution as described below:
Based on the borehole findings, the recommended pavement design for the reinstated
road is presented in Table 2.
In preparation of the subgrade, the ground surface must be proof-rolled. Any soft
organics, deleterious materials and foreign matter should be subexcavated and
replaced by properly compacted, organic-free earth fill. The final subgrade must
consist of uniform material with cross-falls towards the boundary, swales or
subdrains.
In the zone within 1.0 m below the pavement subgrade, the backfill should be
compacted to at least 98% of its maximum Standard Proctor dry density, with the
water content 2% to 3% drier than the optimum. In the lower zone, a 95% or +
Standard Proctor compaction is considered adequate.
All the granular bases should be compacted to their maximum Standard Proctor dry
density.
Reference No. 1603-S116 16
The recommended soil parameters for the project design are given in Table 3.
6.6 Excavation
The sides of the open cut should be flattened to 1 vertical:1.5 or + horizontal; where it
is extended into wet or saturated soils, the sides should be flattened to 1 vertical:
3 or + horizontal. Alternatively, the open cut should be stabilized by proper shoring.
In the areas where a vertical cut is necessary, it must be carried out in a trench box or
it must be properly shored. In the design of the trench box and/or shoring structure,
the recommended lateral earth pressure distribution for the revealed soils are given in
Diagram 1.
Reference No. 1603-S116 18
0.65 γ Ka H
γw h
In calculating the lateral earth pressure for the shoring structure, the soil parameters
are provided in Section 6.5. The soil above the trench box must be cut at
1 vertical:1.5 or + horizontal.
As previously discussed, the groundwater yield from the silt and silty fine sand will
be appreciable and persistent. An appropriate dewatering scheme and/or a temporary
channel diversion will be required for the duration of the project construction.
Undrained Shear
PENETRATION RESISTANCE Strength (ksf) ‘N’ (blows/ft) Consistency
90
80
70
60
50
40
30
20
Percent Passing
10
0
100 Grain Size in millimeters 10 1 0.1 0.01 0.001
Figure: 3
Elevation (m): 257.7 (cm./sec.) = 10-7
Classification of Sample [& Group Symbol]: SILTY CLAY, Fill
a tr. of sand
GRAIN SIZE DISTRIBUTION Reference No: 1603-S116
U.S. BUREAU OF SOILS CLASSIFICATION
GRAVEL SAND
SILT CLAY
COARSE FINE COARSE MEDIUM FINE V. FINE
90
BH.2/Sa.3
80
70
60
BH.1/Sa.5
50
40
30
20
Percent Passing
10
0
100 Grain Size in millimeters 10 1 0.1 0.01 0.001
Figure: 4
Elevation (m): 253.1 256.0 (cm./sec.) = 10-5 10-4
Classification of Sample [& Group Symbol]: SANDY SILT
a tr. of clay
Soil Engineers Ltd. GRAIN SIZE DISTRIBUTION Reference No: 1603-S116
U.S. BUREAU OF SOILS CLASSIFICATION
GRAVEL SAND
SILT CLAY
COARSE FINE COARSE MEDIUM FINE V. FINE
90
80
70
60
50
40
30
20
Percent Passing
10
0
100 Grain Size in millimeters 10 1 0.1 0.01 0.001
Figure: 5
Elevation (m): 240.7 (cm./sec.) = 10-3
Classification of Sample [& Group Symbol]: SILTY FINE SAND
a tr. of clay