Professional Documents
Culture Documents
IN
CONSTRUCTION CONTRACTS
What Is Variation?
• A Variation -sometimes referred to as
a Variation Instructions Or Variation
Order (VO) or Change Order , is an
Alteration to the Scope of Works in
a Construction Contract,. In the form of an
addition, substitution or omission from the
original Scope of Works.
1
8/15/2019
2
8/15/2019
• According to ICTAD/SBD/02
• Clause 13.1 –Variation may be initiated by the Engineer
at any time prior to issuing the Taking Over Certificate
for the Works, either by an instruction or by a request
for the Contractor to submit a proposal
• The Contractor shall execute and be bound by each
Variation , unless the Contractor promptly gives notice
to the Engineer stating with supporting documents
that the Contractor cannot readily obtain the materials
required for the Variation.
3
8/15/2019
4
8/15/2019
5
8/15/2019
Examples:
• 1).Willingdon Light Buff Facing Bricks in lieu of
Hildon Tuder Brown Facing Bricks. Tuder Brown
Facings was Rs. 21180. 00 per 1000, including
delivery, when contractor priced the bills, and the
price of Willingdon Light Buff Facings, delivered,
was Rs. 22,704.00 per 1000. The bill rates are Rs.
2,964.00 for 102.5 mm thick walls and Rs.
4,960.00 for 215 mm thick walls. The overhead
and profit was 20%. Calculate the new rates for
each wall thicknesses and prepare variation
account.
• 2). The roof slab to the flat increased from 125 mm thick
to 175 mm thick and the main reinforcement increased
from 12 mm to 16 mm Ø bars. The bill rate for 1 m³ Grade
C20 concrete is Rs. 14,400.00 and labour for placing is 12
hours per m³ for slab thickness ≤150 mm and 8 hours per
m³ for slab thickness >150 mm and ≤ 450 mm and the
labour rate is Rs. 640.00 per 8 hour day. The bill rate for 1
tonne steel bar is Rs. 118,000.00 and Bar Bender hours for
cut, bend and fix is 70 hours per tonne of 12 mm Ø bars
and 60 hours per tonne of 16 mm Ø bars. The binding wire
required is 15 kg. per tonne of 12 mm Ø bars and 10 kg. per
tonne of 16 mm Ø bars. A Bar Bender is paid Rs. 960.00 per
8 hour day and cost per kg. of binding wire is Rs. 150.00.
The overhead and profit was 20%. If the slab area is 12.0 m
X 5.0 m. calculate the additional cost of slab and
reinforcements, if the main bars are placed at 150 mm
centres.
6
8/15/2019