PGA MIRI Mechanical Electrical Defects and Outstanding Works List

Location Service(s) Date Action By Remark(s)


Batalion Electrical 18.03.10 ATHSB All lighting fittings are to be installed with wire to prevent sagging of the ceiling boards that have been installed
Batalion Electrical 18.03.10 ATHSB Power Point not provided for Bain Marie
Batalion Electrical 18.03.10 ATHSB Switches and ppts are to be adjusted to be the same level as wall tiling (shift up)
Batalion Electrical 18.03.10 ATHSB Trunking in ceiling void not earthed
Batalion Electrical 18.03.10 ATHSB Trunking through wall opening not properly sealed
Batalion Electrical 18.03.10 ATHSB Earthing not installed (MDF ROOM)
Batalion Electrical 18.03.10 ATHSB Cable tray to PABX room not installed. Cable Tray to start from Manhole in MDF room through to PABX Room
Batalion Telephone 18.03.10 ATHSB Internal Cabling not installed (MDF ROOM)
Batalion Electrical 18.03.10 ATHSB Trunking tee off from main trunking not earthed
Batalion Electrical 18.03.10 ATHSB Trunking through walls/beams openings not sealed
Batalion ICT 18.03.10 GTSB Trunking tee off from main trunking not earthed
Batalion ICT 18.03.10 GTSB Trunking through walls/beams openings not sealed
Batalion ELV 18.03.10 ATHSB PA Speakers not installed (Generally)

SS5 Electrical 18.03.10 ATHSB Genset and AMF Board not installed
SS5 Ext Electrical 18.03.10 CEES Trenches not cleaned up
SS5 Ext Electrical 18.03.10 CEES Trenches not filled with sand
SS5 Ext Electrical 18.03.10 CEES Checker Plate cover not installed at trenches

Water Tower Lightning 18.03.10 ATHSB Lightning Protection (Non Conventional) at Water Tower not installed
Water Tower Electrical 18.03.10 Builder Conduits from Water Tower Pump room are not installed with G.I., instead with PVC

Trafik Electrical 18.03.10 ATHSB All lighting fittings are to be installed with wire to prevent sagging of the ceiling boards that have been installed
Trafik Electrical 18.03.10 ATHSB Trunking tee off from main trunking not earthed
Trafik Electrical 18.03.10 ATHSB Trunking through walls/beams openings not sealed
Trafik ICT 18.03.10 GTSB Trunking tee off from main trunking not earthed
Trafik ICT 18.03.10 GTSB Trunking through walls/beams openings not sealed
Trafik Ext Electrical 18.03.10 CEES Trenches not cleaned up
Trafik Ext Electrical 18.03.10 CEES Trenches not filled with sand
Trafik Ext Electrical 18.03.10 CEES Checker Plate cover not installed at trenches
Trafik Electrical 18.03.10 ATHSB Earthing not connected to Switchboard (SSB/POL)
Trafik Builder 18.03.10 Builder Louver installed at Server Room (Airconditioned Room)
Trafik Builder 18.03.10 Builder Ceiling suspended from M&E Services
Trafik Electrical 18.03.10 ATHSB 13A ppt not installed at Main entrance for Sliding door
Trafik Electrical 18.03.10 ATHSB 13A Metal Clad ppt not installed at Black Maria Entrance (for Roller Shutter)
Trafik Electrical 18.03.10 ATHSB Switch level incorrect at Lockup
Trafik Electrical 18.03.10 ATHSB Trunking tee off from main trunking not earthed
Trafik Electrical 18.03.10 ATHSB Trunking through walls/beams openings not sealed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Trafik ICT 18.03.10 GTSB Trunking tee off from main trunking not earthed
Trafik ICT 18.03.10 GTSB Trunking through walls/beams openings not sealed

SSTrafik Electrical 18.03.10 ATHSB Supporting Bracket at MSB not installed (Trench)
SSTrafik Ext Electrical 18.03.10 CEES Trenches not cleaned up
SSTrafik Ext Electrical 18.03.10 CEES Trenches not filled with sand
SSTrafik Ext Electrical 18.03.10 CEES Checker Plate cover not installed at trenches

Dewan Makan Electrical 18.03.10 ATHSB Switches and ppts not the same level
Dewan Makan Electrical 18.03.10 ATHSB All lighting fittings are to be installed with wire to prevent sagging

QF19A Electrical 18.03.10 ATHSB Lighting not installed at Plant Room

QF19A Telephone 18.03.10 ATHSB Trunking from SDF Room to Telephone Riser not installed at Ground Floor

External Ext Lighting 18.03.10 CEES Verticality of street lighting poles are not adjusted
External Ext Telephone 18.03.10 CEES JC9C at Pengangkutan Drop off porch not level to road level

SSTrafik Electrical 24.03.10 ATHSB Supporting Bracket at MSB not installed (Trench)
SSTrafik Ext Electrical 24.03.10 CEES Trenches not cleaned up
SSTrafik Ext Electrical 24.03.10 CEES Trenches not filled with sand
SSTrafik Ext Electrical 24.03.10 CEES Checker Plate cover not installed at trenches
SSTrafik Electrical 24.03.10 ATHSB Lighting not installed
SSTrafik Electrical 24.03.10 ATHSB MCB at DB not installed
SSTrafik Electrical 24.03.10 ATHSB Switches and PPT not installed
SSTrafik Electrical 24.03.10 ATHSB Genset and AMF Board not installed

SS5 Electrical 24.03.10 ATHSB Genset and AMF Board not installed
SS5 Ext Electrical 24.03.10 CEES Trenches not cleaned up and dewatered
SS5 Ext Electrical 24.03.10 CEES Trenches not filled with sand
SS5 Ext Electrical 24.03.10 CEES Checker Plate cover not installed at trenches
SS5 Electrical 24.03.10 ATHSB MCB at DB not installed

Kenderaan Electrical 24.03.10 ATHSB Trunking improperly installed (Staircase)


Kenderaan Electrical 24.03.10 ATHSB Openings not sealed (Staircase)
Kenderaan Electrical 24.03.10 ATHSB Ceiling points not properly sealed (Staircase)
Kenderaan Electrical 24.03.10 ATHSB Switches not patched up well (Staircase)
Kenderaan Electrical 24.03.10 ATHSB Isolator not patched up (Car Bays)
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Komunikasi Electrical 24.03.10 ATHSB Improper jointing of conduit/flexible pipe

PMP Builder 24.03.10 Builder No space to install light fitting due to omission of ceiling boards (2 no.s of 2x2Recessed light fittings outside of Pejabat)

Pengangkutan Builder 24.03.10 Builder Shift of Ceiling grid caused lighting to be off centered (Entrance)

Serbaguna Builder 24.03.10 Builder Change of Mineral Fiber Board to UAC Ceiling caused lighting to be installed on the surface (perimeter Prismatic lighting)
Serbaguna Electrical 24.03.10 ATHSB Middle row of Medium Bay lighting to be shifted up one space (All)

External Ext Electrical 24.03.10 CEES Verticality of Street Lighting not rectified

Batalion Builder 31.03.10 Builder Ceiling orientation at Bilik Am Latihan changed, Lighting layout affected
Batalion Builder 31.03.10 Builder Ceiling suspended from M&E Services (Bilik Server)
Batalion Telephone 31.03.10 ATHSB Telephone Trunking turns/bends not earthed
Batalion Telephone 31.03.10 ATHSB Telephone DP not installed
Batalion Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Batalion Electrical 31.03.10 ATHSB Plant room lighting not installed, inclusive of two smaller rooms at corners
Batalion Electrical 31.03.10 ATHSB Light motor room lighting not installed
Batalion Electrical 31.03.10 ATHSB Trunking turns/bends not earthed
Batalion Electrical 31.03.10 ATHSB UPVC Conduits in Corridor not supported with bracket in ceiling void
Batalion Electrical 31.03.10 ATHSB No proper jointing between flexible GI pipe and UPVC conduit
Batalion Electrical 31.03.10 ATHSB Lighting unable to be installed due to aircon ducting (Bilik Gerakan)
Batalion Electrical 31.03.10 ATHSB Lighting not symmetrically installed at Office rooms (Bilik Ketua Pentadbiran, Bilik Pegawai Komunikasi)
Batalion Electrical 31.03.10 ATHSB Incorrect Mounting Height of ppts at Bilik Amhasnet
Batalion Electrical 31.03.10 ATHSB All Wiring at ceiling void of Bilik amhasnet without conduiting
Batalion Electrical 31.03.10 ATHSB Trunkings do not contain 30% spare space
Batalion Electrical 31.03.10 ATHSB Trunking openings through wall not patched up
Batalion Electrical 31.03.10 ATHSB Lighting at Bilik Pejabat Am not installed
Batalion Electrical 31.03.10 ATHSB Trunking and Tray at Bilik MDF not installed
Batalion Electrical 31.03.10 ATHSB Lighting at Bilik MDF Not installed
Batalion Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Batalion Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Batalion ELV 31.03.10 ATHSB Siren System Not installed (Façade of Building)
Batalion ELV 31.03.10 ATHSB PA Speakers not alligned (corridor, Bilik Pejabat Am, 2nd FLoor)
Batalion ELV 31.03.10 ATHSB Pa Speakers not alligned with lighting at ceiling of 2nd floor (next to void)
Batalion ELV 31.03.10 ATHSB Conference system not installed
Batalion ELV 31.03.10 ATHSB Card access system not installed
Batalion ELV 31.03.10 ATHSB Audio visual system not installed
Batalion ELV 31.03.10 ATHSB CCTV system not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Batalion ELV 31.03.10 ATHSB PA Rack not installed
Batalion ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Batalion ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Batalion ICT 31.03.10 GTSB Core Switches not installed
Batalion ICT 31.03.10 GTSB Patch Panels not installed
Batalion ICT 31.03.10 GTSB UPS not installed
Batalion ICT 31.03.10 GTSB Access Switch not installed
Batalion ICT 31.03.10 GTSB Trunking and Tray at Bilik Server not earthed at bends
Batalion ICT 31.03.10 GTSB Trunking and Tray through wall opening not patched up (Bilik Server)
Batalion ICT 31.03.10 GTSB ICT Trunking turns/bends not earthed
Batalion Lightning 31.03.10 ATHSB Lightning Protection system not installed

SS5 Electrical 31.03.10 ATHSB Perimeter Lighting of SS5 not installed, Substation is energised already
SS5 Lightning 31.03.10 ATHSB Lightning Protection system not installed

External Ext Electrical 31.03.10 CEES Existing Street Lighting next to Bengkel Kenderaan Not removed
External Ext Electrical 31.03.10 CEES Street Lighting Verticality not rectified
External Ext Telephone 31.03.10 CEES JC9C manhole installed with string prior to testing
External Ext Lighting 31.03.10 CEES Compound Lighting not installed
External Ext Electrical 31.03.10 CEES Gate column Lights not installed
External ELV 31.03.10 ATHSB External ELV CCTV (Stor Peluru) not installed

Kenderaan Electrical 31.03.10 ATHSB Switch at Sink of Bengkel Kenderaan intalled at tile area
Kenderaan Electrical 31.03.10 ATHSB Wall Points not patched up
Kenderaan Electrical 31.03.10 ATHSB Bengkel Kenderaan Perimeter Lighting not installed
Kenderaan Telephone 31.03.10 ATHSB Telephone DP not installed
Kenderaan Lightning 31.03.10 ATHSB Lightning Protection system not installed

Stor Peluru Electrical 31.03.10 ATHSB Lighting Not installed


Stor Peluru Telephone 31.03.10 ATHSB Telephone Point at Stor senjata installed inside of room instead of outside
Stor Peluru Electrical 31.03.10 ATHSB Lightning copper tape improperly installed at roof of Stor Senjata

Stor Senjata Electrical 31.03.10 ATHSB Stor Senjata Lighting at Drop off Porch not installed
Stor Senjata Electrical 31.03.10 ATHSB Stor Senjata ICT Rack without power point
Stor Senjata Electrical 31.03.10 ATHSB ACMV CP Trunking opening not patched up
Stor Senjata Electrical 31.03.10 ATHSB ACMC CP Trunking turns/bends not earthed
Stor Senjata Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Stor Senjata Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Stor Senjata Telephone 31.03.10 ATHSB Telephone DP not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Stor Senjata ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Stor Senjata ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Stor Senjata ICT 31.03.10 GTSB UPS not installed
Stor Senjata ICT 31.03.10 GTSB Access Switch not installed
Stor Senjata Lightning 31.03.10 ATHSB Lightning Protection system not installed

PMP Electrical 31.03.10 ATHSB PMP internal lighting not installed


PMP Electrical 31.03.10 ATHSB PMP medium Bay not installed
PMP Electrical 31.03.10 ATHSB PMP perimeter lighting not installed
PMP Electrical 31.03.10 ATHSB UPVC Conduits in Ceiling space not supported with bracket
PMP Telephone 31.03.10 ATHSB Telephone DP not installed
PMP ICT 31.03.10 GTSB UPS not installed
PMP ICT 31.03.10 GTSB Access Switch not installed
PMP Lightning 31.03.10 ATHSB Lightning Protection system not installed

Komandan Electrical 31.03.10 ATHSB Kem Komandan Interior Lighting not installed
Komandan Electrical 31.03.10 ATHSB Kem Komandan Perimeter Lighting not installed
Komandan Electrical 31.03.10 ATHSB Kem Komandan Drop off Porch Lighting not installed
Komandan Electrical 31.03.10 ATHSB Kem Komandan ICT Rack witout Power Point
Komandan Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Komandan Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Komandan Telephone 31.03.10 ATHSB Telephone DP not installed
Komandan ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Komandan ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Komandan ICT 31.03.10 GTSB Trunking and Tray not earthed at bends
Komandan ICT 31.03.10 GTSB UPS not installed
Komandan ICT 31.03.10 GTSB Access Switch not installed
Komandan Lightning 31.03.10 ATHSB Lightning Protection system not installed

Komunikasi Electrical 31.03.10 ATHSB Kem Komandan ICT Rack witout Power Point
Komunikasi Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Komunikasi Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Komunikasi Electrical 31.03.10 ATHSB Improper jointing of conduit/flexible pipe
Komunikasi Telephone 31.03.10 ATHSB Telephone DP not installed
Komunikasi ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Komunikasi ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Komunikasi ICT 31.03.10 GTSB Trunking and Tray not earthed at bends
Komunikasi ICT 31.03.10 GTSB UPS not installed
Komunikasi ICT 31.03.10 GTSB Access Switch not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Komunikasi Lightning 31.03.10 ATHSB Lightning Protection system not installed

Bekalan Electrical 31.03.10 ATHSB Stor Bekalan ICT Rack without Power Point
Bekalan Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Bekalan Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Bekalan Telephone 31.03.10 ATHSB Telephone DP not installed
Bekalan ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Bekalan ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Bekalan ICT 31.03.10 GTSB Trunking and Tray not earthed at bends
Bekalan ICT 31.03.10 GTSB UPS not installed
Bekalan ICT 31.03.10 GTSB Access Switch not installed
Bekalan Lightning 31.03.10 ATHSB Lightning Protection system not installed

SS4 Electrical 31.03.10 ATHSB SS4 (PGA 3) Lighting not installed


SS4 Ext Electrical 31.03.10 CEES SS4 (PGA 3) Trench not dewatered and cleaned
SS4 Ext Electrical 31.03.10 CEES SS4 (PGA 3) Trench not sand filled
SS4 Lightning 31.03.10 ATHSB Lightning Protection system not installed

Tadika Electrical 31.03.10 ATHSB Internal Lighting not installed


Tadika Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Tadika Electrical 31.03.10 ATHSB SSB not installed
Tadika Telephone 31.03.10 ATHSB Telephone DP not installed
Tadika Lightning 31.03.10 ATHSB Lightning Protection system not installed

Kafa Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Kafa Electrical 31.03.10 ATHSB Internal ppt not installed
Kafa Telephone 31.03.10 ATHSB Telephone DP not installed
Kafa Lightning 31.03.10 ATHSB Lightning Protection system not installed

Surau Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Surau Electrical 31.03.10 ATHSB Internal Lighting not installed
Surau Electrical 31.03.10 ATHSB Wall Fans not installed
Surau Electrical 31.03.10 ATHSB Flood Light not installed
Surau Electrical 31.03.10 ATHSB Switches and ppts not installed
Surau Electrical 31.03.10 ATHSB Trunking through wall (corridor) not patched up
Surau Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Surau Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Surau Telephone 31.03.10 ATHSB Telephone DP not installed
Surau Lightning 31.03.10 ATHSB Lightning Protection system not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List

Serbaguna Builder 31.03.10 Builder Lighting unable to be installed at Control room, no space
Serbaguna Builder 31.03.10 Builder Lighting unable to be installed at Corridor due to ceiling layout
Serbaguna Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Serbaguna Electrical 31.03.10 ATHSB Perimeter lightning not installed
Serbaguna Electrical 31.03.10 ATHSB Medium bay court lighting not installed
Serbaguna Electrical 31.03.10 ATHSB UPVC Conduits not supported with bracket in ceiling void
Serbaguna Electrical 31.03.10 ATHSB Trunking turns/bends not earthed
Serbaguna Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Serbaguna Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Serbaguna ELV 31.03.10 ATHSB Stage lighting not installed
Serbaguna ELV 31.03.10 ATHSB Stage curtain not installed
Serbaguna ELV 31.03.10 ATHSB Sound reinforcement not installed
Serbaguna Lightning 31.03.10 ATHSB Lightning Protection system not installed

Trafik Builder 31.03.10 Builder Louver at Bilik Server not Sealed up


Trafik Electrical 31.03.10 ATHSB Trunkings do not contain 30% spare space
Trafik Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Trafik Electrical 31.03.10 ATHSB Trunking turns/bends not earthed
Trafik Electrical 31.03.10 ATHSB UPVC Conduits in Corridor not supported with bracket in ceiling void
Trafik Electrical 31.03.10 ATHSB No proper jointing between flexible GI pipe and UPVC conduit
Trafik Electrical 31.03.10 ATHSB Trunking and Tray at Bilik MDF not installed
Trafik Electrical 31.03.10 ATHSB Lighting at Bilik MDF Not installed
Trafik Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Trafik Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Trafik ELV 31.03.10 ATHSB Siren System Not installed (Façade of Building)
Trafik ELV 31.03.10 ATHSB Telephone Trunking turns/bends not earthed
Trafik ELV 31.03.10 ATHSB Pa Speakers not alligned with lighting at Ground Floor Corridor
Trafik ELV 31.03.10 ATHSB Conference system not installed
Trafik ELV 31.03.10 ATHSB Card access system not installed
Trafik ELV 31.03.10 ATHSB Audio visual system not installed
Trafik ELV 31.03.10 ATHSB CCTV system not installed
Trafik ELV 31.03.10 ATHSB PA Rack not installed
Trafik Telephone 31.03.10 ATHSB Telephone DP not installed
Trafik ICT 31.03.10 GTSB Trunking tee off from main trunking not earthed
Trafik ICT 31.03.10 GTSB Trunking through walls/beams openings not sealed
Trafik ICT 31.03.10 GTSB Core Switches not installed
Trafik ICT 31.03.10 GTSB Patch Panels not installed
Trafik ICT 31.03.10 GTSB UPS not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Trafik ICT 31.03.10 GTSB Access Switch not installed
Trafik ICT 31.03.10 GTSB ICT Trunking turns/bends not earthed
Trafik Lightning 31.03.10 ATHSB Lightning Protection system not installed

Pengangkutan Builder 31.03.10 Builder Shift of Ceiling grid caused lighting to be off centered (Entrance)
Pengangkutan Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
Pengangkutan Electrical 31.03.10 ATHSB UPVC Conduits not supported with bracket in ceiling void
Pengangkutan Electrical 31.03.10 ATHSB Trunking turns/bends not earthed
Pengangkutan Electrical 31.03.10 ATHSB Trunking tee off from main trunking not earthed
Pengangkutan Electrical 31.03.10 ATHSB Trunking through walls/beams openings not sealed
Pengangkutan Electrical 31.03.10 ATHSB ICT Rack witout Power Point
Pengangkutan ICT 31.03.10 GTSB Patch Panels not installed
Pengangkutan ICT 31.03.10 GTSB UPS not installed
Pengangkutan ICT 31.03.10 GTSB Access Switch not installed
Pengangkutan ICT 31.03.10 GTSB ICT Trunking turns/bends not earthed
Pengangkutan Lightning 31.03.10 ATHSB Lightning Protection system not installed

QFTrafik Electrical 31.03.10 ATHSB Drop Off Porch Lighting not installed
QFTrafik Lightning 31.03.10 ATHSB Lightning Protection system not installed

Chapel Builder 07.04.10 Builder Telephone Manhole not built


Chapel Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Chapel Electrical 07.04.10 ATHSB Internal ppt and switches not installed
Chapel Electrical 07.04.10 ATHSB Telephone DP not installed
Chapel Electrical 07.04.10 ATHSB Internal lighting not installed
Chapel Electrical 07.04.10 ATHSB DB not installed
Chapel ELV 07.04.10 ATHSB PA system not installed
Chapel Lightning 07.04.10 ATHSB Lightning Protection system not installed

Tadika Electrical 07.04.10 ATHSB Internal Lighting not installed


Tadika Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Tadika Electrical 07.04.10 ATHSB SSB not installed
Tadika Electrical 07.04.10 ATHSB Internal Lighting, switches, DB not installed
Tadika Telephone 07.04.10 ATHSB Telephone DP not installed
Tadika Lightning 07.04.10 ATHSB Lightning Protection system not installed
Tadika Builder 07.04.10 Builder Window level at 800mm instead of 900mm causing power points to be blocked by table

Kafa Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Kafa Electrical 07.04.10 ATHSB Internal ppt not installed
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Kafa Electrical 07.04.10 ATHSB Internal Lighting, switches, DB not installed
Kafa Telephone 07.04.10 ATHSB Telephone DP not installed
Kafa Lightning 07.04.10 ATHSB Lightning Protection system not installed

Surau Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Surau Electrical 07.04.10 ATHSB Internal Lighting not installed
Surau Electrical 07.04.10 ATHSB Wall Fans not installed
Surau Electrical 07.04.10 ATHSB Flood Light not installed
Surau Electrical 07.04.10 ATHSB Trunking not earthed
Surau Electrical 07.04.10 ATHSB Switches and ppts not installed
Surau Electrical 07.04.10 ATHSB Trunking through wall (corridor) not patched up
Surau Electrical 07.04.10 ATHSB Trunking tee off from main trunking not earthed
Surau Electrical 07.04.10 ATHSB Trunking through walls/beams openings not sealed
Surau Electrical 07.04.10 ATHSB SSB to be shifted due to clash with door
Surau Telephone 07.04.10 ATHSB Telephone DP not installed
Surau Lightning 07.04.10 ATHSB Lightning Protection system not installed

Serbaguna Builder 07.04.10 Builder Lighting unable to be installed at Control room, no space
Serbaguna Builder 07.04.10 Builder Lighting unable to be installed at Corridor due to ceiling layout
Serbaguna Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Serbaguna Electrical 07.04.10 ATHSB Perimeter lightning not installed
Serbaguna Electrical 07.04.10 ATHSB Medium bay court lighting not installed
Serbaguna Electrical 07.04.10 ATHSB UPVC Conduits not supported with bracket in ceiling void
Serbaguna Electrical 07.04.10 ATHSB Trunking turns/bends not earthed
Serbaguna Electrical 07.04.10 ATHSB Trunking tee off from main trunking not earthed
Serbaguna Electrical 07.04.10 ATHSB Trunking through walls/beams openings not sealed
Serbaguna Electrical 07.04.10 ATHSB Keluar sign installed on opposite side of wall (rear entrance)
Serbaguna Electrical 07.04.10 ATHSB Switches at toilet too low (less than 1450mm)
Serbaguna ELV 07.04.10 ATHSB Stage lighting not installed
Serbaguna ELV 07.04.10 ATHSB Stage curtain not installed
Serbaguna ELV 07.04.10 ATHSB Sound reinforcement not installed
Serbaguna Lightning 07.04.10 ATHSB Lightning Protection system not installed

SS1/3 Electrical 07.04.10 ATHSB SS4 (PGA 3) Lighting not installed


SS1/3 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not dewatered and cleaned
SS1/3 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not sand filled
SS1/3 Lightning 07.04.10 ATHSB Lightning Protection system not installed
SS1/3 Builder 07.04.10 Builder Builder did not install grille/louver at Genset room
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
SS4 Electrical 07.04.10 ATHSB SS4 (PGA 3) Lighting not installed
SS4 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not dewatered and cleaned
SS4 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not sand filled
SS4 Lightning 07.04.10 ATHSB Lightning Protection system not installed
SS4 Builder 07.04.10 Builder Builder did not install grille/louver at Genset room

SS5 Electrical 07.04.10 ATHSB SS4 (PGA 3) Lighting not installed


SS5 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not dewatered and cleaned
SS5 Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not sand filled
SS5 Lightning 07.04.10 ATHSB Lightning Protection system not installed
SS5 Builder 07.04.10 Builder Builder did not install grille/louver at Genset room

SSTrafik Electrical 07.04.10 ATHSB SS4 (PGA 3) Lighting not installed


SSTrafik Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not dewatered and cleaned
SSTrafik Ext Electrical 07.04.10 CEES SS4 (PGA 3) Trench not sand filled
SSTrafik Lightning 07.04.10 ATHSB Lightning Protection system not installed
SSTrafik Builder 07.04.10 Builder Builder did not install grille/louver at Genset room

Batalion Builder 07.04.10 Builder Ceiling orientation at Bilik Am Latihan changed, Lighting layout affected
Batalion Builder 07.04.10 Builder Ceiling suspended from M&E Services (Bilik Server)
Batalion Telephone 07.04.10 ATHSB Telephone Trunking turns/bends not earthed
Batalion Telephone 07.04.10 ATHSB Telephone DP not installed
Batalion Electrical 07.04.10 ATHSB Grd flr Trunking resting on ceiling board, not suspended
Batalion Electrical 07.04.10 ATHSB No earting and bracket support for trunking turning (both ends of GRD floor corridor)
Batalion Electrical 07.04.10 ATHSB Openings for trunkings are not sealed up
Batalion Electrical 07.04.10 ATHSB Miscellaneous switches, ppt, lighting not installed
Batalion Electrical 07.04.10 ATHSB Bilik Taklimat downlights are not installed
Batalion Electrical 07.04.10 ATHSB Trunking through wall opening not sealed up
Batalion Electrical 07.04.10 ATHSB Bain Marie power point not installed (Kantin)
Batalion Electrical 07.04.10 ATHSB Keluar sign not installed (general)
Batalion Electrical 07.04.10 ATHSB MDF room trunking/tray not installed (as per request by Telekom)
Batalion Electrical 07.04.10 ATHSB Earthing at MDF room not done
Batalion Electrical 07.04.10 ATHSB Flexible joints not securely installed
Batalion Electrical 07.04.10 ATHSB Drop Off Porch Lighting not installed
Batalion Electrical 07.04.10 ATHSB Plant room lighting not installed, inclusive of two smaller rooms at corners
Batalion Electrical 07.04.10 ATHSB Light motor room lighting not installed
Batalion Electrical 07.04.10 ATHSB Trunking turns/bends not earthed
Batalion Electrical 07.04.10 ATHSB UPVC Conduits in Corridor not supported with bracket in ceiling void
Batalion Electrical 07.04.10 ATHSB No proper jointing between flexible GI pipe and UPVC conduit
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Batalion Electrical 07.04.10 ATHSB Lighting unable to be installed due to aircon ducting (Bilik Gerakan)
Batalion Electrical 07.04.10 ATHSB Lighting not symmetrically installed at Office rooms (Bilik Ketua Pentadbiran, Bilik Pegawai Komunikasi)
Batalion Electrical 07.04.10 ATHSB Incorrect Mounting Height of ppts at Bilik Amhasnet
Batalion Electrical 07.04.10 ATHSB All Wiring at ceiling void of Bilik amhasnet without conduiting
Batalion Electrical 07.04.10 ATHSB Trunkings do not contain 30% spare space
Batalion Electrical 07.04.10 ATHSB Trunking openings through wall not patched up
Batalion Electrical 07.04.10 ATHSB Lighting at Bilik Pejabat Am not installed
Batalion Electrical 07.04.10 ATHSB Trunking and Tray at Bilik MDF not installed
Batalion Electrical 07.04.10 ATHSB Lighting at Bilik MDF Not installed
Batalion Electrical 07.04.10 ATHSB Trunking tee off from main trunking not earthed
Batalion Electrical 07.04.10 ATHSB Trunking through walls/beams openings not sealed
Batalion ELV 07.04.10 ATHSB Bilik Kebal Card access and EM Lock not installed
Batalion ELV 07.04.10 ATHSB Pejabat AM Tatatertib - Speaker Wrong Position
Batalion ELV 07.04.10 ATHSB Siren System Not installed (Façade of Building)
Batalion ELV 07.04.10 ATHSB PA Speakers not alligned (corridor, Bilik Pejabat Am, 2nd FLoor)
Batalion ELV 07.04.10 ATHSB Pa Speakers not alligned with lighting at ceiling of 2nd floor (next to void)
Batalion ELV 07.04.10 ATHSB Conference system not installed
Batalion ELV 07.04.10 ATHSB Card access system not installed
Batalion ELV 07.04.10 ATHSB Audio visual system not installed
Batalion ELV 07.04.10 ATHSB CCTV system not installed
Batalion ELV 07.04.10 ATHSB PA Rack not installed
Batalion ICT 07.04.10 GTSB PABX tray at PABX room not earthed
Batalion ICT 07.04.10 GTSB Pejabt AM IT - ICT tray resting directly on ACMV Ducting
Batalion ICT 07.04.10 GTSB Flexible joints not securely installed
Batalion ICT 07.04.10 GTSB Pejabat AM Tatatertib - ICT Points not level
Batalion ICT 07.04.10 GTSB Trunking tee off from main trunking not earthed
Batalion ICT 07.04.10 GTSB Trunking through walls/beams openings not sealed
Batalion ICT 07.04.10 GTSB Core Switches not installed
Batalion ICT 07.04.10 GTSB Patch Panels not installed
Batalion ICT 07.04.10 GTSB UPS not installed
Batalion ICT 07.04.10 GTSB Access Switch not installed
Batalion ICT 07.04.10 GTSB Trunking and Tray at Bilik Server not earthed at bends
Batalion ICT 07.04.10 GTSB Trunking and Tray through wall opening not patched up (Bilik Server)
Batalion ICT 07.04.10 GTSB ICT Trunking turns/bends not earthed
Batalion Lightning 07.04.10 ATHSB Lightning Protection system not installed

Trafik Builder 07.04.10 Builder Switches blocked by Sliding Door


Trafik Electrical 07.04.10 ATHSB Trunking touching Flexible Ducting
Trafik ELV 07.04.10 ATHSB Speaker and Downlight not alligned
PGA MIRI Mechanical Electrical Defects and Outstanding Works List
Trafik Electrical 07.04.10 ATHSB MDF Room Trunking and Tray not done as per Telekom request
Trafik Electrical 07.04.10 ATHSB MDF Room Earthing not done as per Telekom request
Trafik Electrical 07.04.10 ATHSB PABX Room Trunking not done
Trafik Electrical 07.04.10 ATHSB All lighting fittings are to be installed with wire to prevent sagging of the ceiling boards that have been installed
Trafik Electrical 07.04.10 ATHSB Trunking tee off from main trunking not earthed
Trafik Electrical 07.04.10 ATHSB Trunking through walls/beams openings not sealed
Trafik ICT 07.04.10 GTSB Trunking tee off from main trunking not earthed
Trafik ICT 07.04.10 GTSB Trunking through walls/beams openings not sealed
Trafik Ext Electrical 07.04.10 CEES Trenches not cleaned up
Trafik Ext Electrical 07.04.10 CEES Trenches not filled with sand
Trafik Ext Electrical 07.04.10 CEES Checker Plate cover not installed at trenches
Trafik Electrical 07.04.10 ATHSB Earthing not connected to Switchboard (SSB/POL)
Trafik Builder 07.04.10 Builder Louver installed at Server Room (Airconditioned Room)
Trafik Builder 07.04.10 Builder Ceiling suspended from M&E Services
Trafik Electrical 07.04.10 ATHSB 13A ppt not installed at Main entrance for Sliding door
Trafik Electrical 07.04.10 ATHSB 13A Metal Clad ppt not installed at Black Maria Entrance (for Roller Shutter)
Trafik Electrical 07.04.10 ATHSB Switch level incorrect at Lockup
Trafik Electrical 07.04.10 ATHSB Trunking tee off from main trunking not earthed
Trafik Electrical 07.04.10 ATHSB Trunking through walls/beams openings not sealed
Trafik ICT 07.04.10 GTSB Trunking tee off from main trunking not earthed
Trafik ICT 07.04.10 GTSB Trunking through walls/beams openings not sealed

External Electrical 07.04.10 CEES Jointing of LT cables not done


External Electrical 07.04.10 CEES Jointing of HT cables not done
External Electrical 07.04.10 CEES Bollard Lighting lighting points at Landscape Area not installed
External Ext Electrical 07.04.10 CEES Existing Street Lighting next to Bengkel Kenderaan Not removed
External Ext Electrical 07.04.10 CEES Street Lighting Verticality not rectified
External Ext Telephone 07.04.10 CEES JC9C manhole installed with string prior to TELEKOM testing
External Ext Lighting 07.04.10 CEES Compound Lighting not installed
External Ext Electrical 07.04.10 CEES Gate column Lights not installed
External ELV 07.04.10 ATHSB External ELV CCTV (Stor Peluru) not installed