Professional Documents
Culture Documents
Minutes of Meeting
Time: 10:00AM
Date: 09/08/2013
Action By
Target Date
CFO Certification: M/s.ANC asked M/s.ETA to arrange CFO inspection to obtain Fire NOC. M/s.ETA committed that application will be given to CFO on 12-Aug-13 and visti will be arranged on 16-Aug-13. And also confirmed that fire fighting system final commissioning will start on 12-Aug-13 CEI Certification: M/s/ANC asked M/s.ETA to submit final Chief Electrical Certification. M/s.ETA committed that application with documents will be submitted on 13-Aug-13 and visit will be arranged on 19-Aug-13 to obtain certification
CERTIFCATIONS REQUIRED
ETA
Application submission& FFTG commissioning 12-Aug-13 CFO visit to site 16-Aug-13 Application submission 13-Aug-13 CEIvisit to site 19-Aug-13
ETA
Cutoff lobby works at Ground floor double height area: M/s.ANC asked M/s.ETA to complete the rectification works at cutoff lobby. M/s.ETA confirmed that fire fighting related works will start after CFO visit ( 16-Aug-13). How ever HVAC related works will start on priority basis. M/s.ANC instructed ETA to complete the works on prority FHC installation:M/s.ANC raised serious concern regarding the installation of fire hose cabinets(internal & External) with all accessories. M/s.ETA confirmed that same will be done priro CFO visit
Fire Fighting
ETA ETA
15-Aug-13
PHE
Installation of CP grating/Floor trap:M/s.ANC asked ETA regarding the installation of CP grating. M/s.ETA committed that same will be done Roof Tank Connections:M/s.ANC asked M/s.ETA to complete the roof tank connections.M/s.ETA confimed that work is under progress and same will be completed
ETA ETA
13-Aug-13 12-Aug-13
HVAC
Plant room aluminium cladding :M/s.ANC asked ETA to do aluminium cladding at Ets room..ETA stated that same will be done at the earliest. M/s.ANC instructed ETA to start the works immediately and complete by 20-Aug-13. If the works are not started by 12Aug-13, M/s.ANC will get the job done at M/s.ETA's risk and cost Smoke Extract fan installation: M/s.ANC asked ETA to complete the installation of Smoke extract fans at basement.ETA cofirmed that same will be done FAHU ducting at Basement: M/s.ANC asked ETA to complete the FAHU ducting at basement. M/s.ETA confimed that same will be done AHU Drain & Bibcock installaton; M/s.ANC asked ETA to complete AHU drain and bibcock installations at AHU rooms. M/s.ETA stated that works are on hold due to confirmation of variation. M/s.ANC clearly instructed ETA to complete the works on priority without any furhter delay. Otherwise M/s.ANC will get the job done at M/s.ETA's risk and cost. Final testing & Commissioning:M/s.ANC asked ETA to do final testing & commissioing of HVAC system.ETA confirmed that testing will be done but prior to that normal water for flushing to be arranged by M/s.ANC for flushing the system. M/s.ANC agred that normal water will be provided
ETA
ON PRIORITY
ETA& ANC
10-Aug-13
Page 1 of 2
Sr. No.
Installation of UPS isolators: M/s.ANC asked ETA to complete the installation of Ups isolators.ETA cofirmed that same will be done Terminations of OFC cable: M/s.ANC asked ETA to complete the terminations of OFC cable in telephone DBs from Basement to Terrace. M/s.ETA confimed that same will be done Light fixtures installaton; M/s.ANC asked ETA to complete the installation of light fixtures from 26th to 28th floor. ETA confirmed that same will be done Shade of Aviation light:M/s.ANC asked ETA to raise the inspecton of aviation lights to confim that the shade for PMC approval. M/s.ETA confirmed that same will be done and also confimed that shade of aviation light is RED Charging of all DBS till roof: M/s.ANC asked ETA to charge all the DB's till roof.M/s.ETA stated that same will be done subject to handover of electrical room keys from 21st floor to 28th floor from ANC team. M/s.ANC committed that all the electrical room keys from 21st floor to 28th floor will be handed over to ETA. Rectifcation of 1000kVA Tranformer HT cable: M/s.ANC asked ETA to rectify the HT cable of 1000kVA transformer . M/s.ETA confimed that same will be done . Signages of all services: M/s.ANC asked ETA to complete the signages of all services. M/s.ETA confimed that all signages will be installed prior CFO inspection
ELECTRICAL
Items discussed
Action By
Target Date
Page 2 of 2