Saudi Aramco Inspection Checklist: Fireproofing Concrete Curing Inspection SAIC-B-1003 15-Nov-17 Civil
Saudi Aramco Inspection Checklist: Fireproofing Concrete Curing Inspection SAIC-B-1003 15-Nov-17 Civil
00 30-Jun-16
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Maximum total dissolved solids in water used for curing shall not exceed SAES-Q-001
A2
1000 parts per million. Sec. 7.25.2
Any formwork used shall be covered and kept continuously moist during
SAES-Q-001
A3 the early curing period before formwork is removed.
Sec. 7.25.6
(ACI 305R, Sec. 4.4.4)
Water curing shall be continuous until compressive strength has reached SAES-Q-001
A4
70% of the specified strength but not less than 7 days Sec. 7.25.3
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-B-006 -- Fireproofing for Plants, 20 November 2011
2- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 07 January 2016