Saudi Aramco Inspection Checklist: Concrete Fireproofing Final Inspection SAIC-B-1004 15-Nov-17 Civil
Saudi Aramco Inspection Checklist: Concrete Fireproofing Final Inspection SAIC-B-1004 15-Nov-17 Civil
00 30-Jun-16
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Prior to top coating, the surface shall be dry, free from defects and loose
SAES-B-006
A2 contaminants shall have been removed by brushing with a stiff bristle
Sec. 8.5.2
brush and vacuuming.
• Second top coat, Saudi Aramco Stock Number 1000194797 shall be SAES-B-006
A5
applied to dry-film thickness of 75 to 125 micrometers. Sec. 8.5.2
The minimum thickness of dense concrete is 50mm from reinforcing wire SASD
A6
mesh and the material complies with 09-SAMSS-097 and SAES-Q-001. AC-036711
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-B-006 -- Fireproofing for Plants, 20 November 2011
2- SASD-AD-036711 -- Concrete Fireproofing for Structural Members, 1 September 2000