PROJECT : S.R.

To Colour work for the Existing College building, Existing Boys Hostel building and
Development Work in Entrance Gate (Civil & Electrical work) in Shree Somnath Sanskrit University Campus,
Veraval (Gir-Somnath)

CLIENT : SHREE SOMNATH SANSKRIT UNIVERSITY, SOMNATH - VERAVAL(Gir-Somnath)

CONSULTANTS : BENCHMARK CONSULTANTS, AHMEDABAD


RECAPITULATION SHEET
Sr. No Description Amount

1.0 Work - 01 (S.R. To Colour work for the Existing College building.) 904772.36

Work 02 - (S.R. To Colour work for the Existing Boys Hostel


2.0 788420.93
building)

3.0 Work 03 - (Compound Wall at Entrance Gate ) 759715.82

3.1 Electrical work (Compound Wall at Entrance Gate ) 65584.55

* COST OF PROJECT 2518493.66

* TOTAL COST OF PROJECT 2518494.00

In Words Rupees TwentyFive Lakh Eighteen Thousand Four Hundred NinetyFour Only

I/we am/are/ willing to carry out the work at ………………….% below / Above …………………
………………….percent below / Above
(should be written in figures and words)
Tendered amount mentioned above amount of my / our tender works out as under
Tendered amount Rs.25,18,494.00 /-

Deduct………. % below Rs……………………. Add…………% Above Rs……


Net Amount Rs………………………………. Net Amount Rs……………
Net Amount in words in Rs…………………………………………………………………………………
Special Note :-
Contractor Shall give only rebate in tendered amount mentioned above and contractor shall
state " NIL" Percentage, if no reduction is offered.

The Registrar
Shree Somnath Sanskrit University The Bidder / Contractor
Veraval
PROJECT : S.R. To Colour work for the Existing College building, Existing Boys Hostel building and Development Work in Entrance Gate
(Civil & Electrical work) in Shree Somnath Sanskrit University Campus, Veraval (Gir-Somnath)

CLIENT : SHREE SOMNATH SANSKRIT UNIVERSITY, SOMNATH - VERAVAL(Gir-Somnath)

ARCHITECT : M/s. BENCHMARK CONSULTANTS, AHMEDABAD

SHEDULED - B
Total
Sr.No Unit Description Total rate In Words Amount in Rs.
Quantity
Work - 01 (S.R. To Colour work for the Existing College building.)
Applying Two Coats of Birla (white cement based) or Asian Acrylic
Lappy (Putty) and two coats of primer of approved brand and
manufacture on New Wall Surface to give an even shade including
Rupees FourtySeven
thoroughly brushing the surface free from mortar dropping and other
1.0 8124.00 Sq.mt 47.87 Paise EightySeven 388928.38
foreign matter and sand papered smooth. As per instruction & approval
Only
by Engineer -in-charge / Comsultant etc. Complete As per architectural
Drawing For All Floor and Level.

Painting (two Coats) with plastic emulsion paint of approved brand and
manufacture on undecorated wall surface to give an even shade
including throughly brushing the surface free from mortar droppings
and other foreign matter and sand papered smooth.[A] Wall Surface Rupees Fifty Paise
2.0 8124.00 Sq.mt 50.10 406979.90
As per instruction & approval by Engineer -in-charge / Comsultant etc. Ten Only
Complete As per architectural Drawing For All Floor and Level.

Providing 15mm thick cement plaster in single coat on Rough (Similar)


side of single or half brick walls for interior plastering upto floor two
level and finished even and smooth in (i) Cement mortar 1:3 (1- Rupees One
cement:3-sand)and finishing with a floating coat of neat cement slurry. Hundred Eighteen
3.0 50.00 Sq.mt 118.17 5908.50
(including all tools plants and machinary) As per instruction & approval Paise Seventeen
by Engineer -in-charge / Comsultant etc. Complete As per architectural Only
Drawing For All Floor and Level.

Distempeing (One coats) with oil bound washable distemper of


approved brand and of required shade on wall surfaces to give an
even shade, after thorouhly brushing the surface clean of all grease
Rupees Seventeen
dirt, loose pieces of scales and alsoincluding distempering with oil
4.0 391.00 Sq.mt 17.27 Paise TwentySeven 6752.96
bound washable distemper of preparing the surface even and smooth.
Only
As per instruction & approval by Engineer -in-charge / Comsultant etc.
Complete As per architectural Drawing For All Floor and Level.

Applying two coats of oil paint in doors window and othet opening up to
two floor in building work as directed by EIC ( including all material and
Rupees SixtyEight
5.0 391.00 Sq.mt labour charge ) As per instruction & approval by Engineer -in-charge / 68.40 26743.31
Paise Fourty Only
Comsultant etc. Complete As per architectural Drawing For All Floor
and Level.
Removing and scraping of old deteriorated plaster of any thickness
from wall / R.C.C member including stacking of serviceable material
and disposal of unserviceable from site of work with all lead and lift. As Rupees Twelve
6.0 50.00 Sq.mt 12.02 600.95
per instruction & approval by Engineer -in-charge / Comsultant etc. Paise Two Only
Complete As per architectural Drawing For All Floor and Level.

Removing dry or oil bound distemper by a washing and scraping and


sand papering the wall surface smooth including necessary repairs to
Rupees Six Paise
7.0 8124.00 Sq.mt scratches complete. As per instruction & approval by Engineer -in- 6.97 56616.16
NinetySeven Only
charge / Comsultant etc. Complete As per architectural Drawing For All
Floor and Level.
Scraping oil paint from steel and other metal surface and making the
Rupees ThirtyOne
surface even (with Hand Scraping.) As per instruction & approval by
8.0 391.00 Sq.mt 31.31 Paise ThirtyOne 12242.21
Engineer -in-charge / Comsultant etc. Complete As per architectural
Only
Drawing For All Floor and Level.
* Total: Work 01 - S.R. To Colour work for the Existing College building 904772.36
Work 02 - (S.R. To Colour work for the Existing Boys Hostel building)
Applying two coats of Birla (white cement based) or Asian (acrylic lapy-
putty) or equivalent & two coats of primer of approved brand and
manufacture on new wall surface to give an even shade including
Rupees FourtySeven
thoroughly brushing the surface free from mortar dropping and other
1.0 6531.00 Sq.mt 47.87 Paise EightySeven 312665.09
foreign matter and sand papered smooth. As per instruction & approval
Only
by Engineer -in-charge / Comsultant etc. Complete As per architectural
Drawing For All Floor and Level.

Painting (two Coats) with plastic emulsion paint of approved brand and
manufacture on undecorated wall surface to give an even shade
including throughly brushing the surface free from mortar droppings
and other foreign matter and sand papered smooth.[A] Wall Surface Rupees Fifty Paise
2.0 6531.00 Sq.mt 50.10 327176.98
As per instruction & approval by Engineer -in-charge / Comsultant etc. Ten Only
Complete As per architectural Drawing For All Floor and Level.

Providing 15mm thick cement plaster in single coat on Rough


(Similar)side of single or half brick walls for interior plastering upto
floor two level and finished even and smooth in (i) Cement mortar 1:3 Rupees One
Hundred Eighteen
3.0 50.00 Sq.mt (1-cement:3-sand) and finishing with a floating coat of neat cement 118.17 5908.50
slurry. (including all tools plants and machinary) As per instruction & Paise Seventeen
approval by Engineer -in-charge / Comsultant etc. Complete As per Only
architectural Drawing For All Floor and Level.

BMC Shedule - B (Various work) 2


Distempeing (One coats) with oil bound washable distemper of
approved brand and of required shade on wall surfaces to give an
even shade, after thorouhly brushing the surface clean of all grease
Rupees Seventeen
dirt, loose pieces of scales and alsoincluding distempering with oil
4.0 779.00 Sq.mt 17.27 Paise TwentySeven 13454.11
bound washable distemper of preparing the surface even and smooth.
Only
As per instruction & approval by Engineer -in-charge / Comsultant etc.
Complete As per architectural Drawing For All Floor and Level.

Applying two coats of oil paint in doors window and othet opening up to
two floor in building work as directed by EIC ( including all material and
Rupees SixtyEight
5.0 779.00 Sq.mt labour charge ) As per instruction & approval by Engineer -in-charge / 68.40 53281.42
Paise Fourty Only
Comsultant etc. Complete As per architectural Drawing For All Floor
and Level.
Removing and scraping of old deteriorated plaster of any thickness
from wall / R.C.C member including stacking of serviceable material
and disposal of unserviceable from site of work with all lead and lift. As Rupees Twelve
6.0 50.00 Sq.mt 12.02 600.95
per instruction & approval by Engineer -in-charge / Comsultant etc. Paise Two Only
Complete As per architectural Drawing For All Floor and Level.

Removing dry or oil bound distemper by a washing and scraping and


sand papering the wall surface smooth including necessary repairs to
Rupees Six Paise
7.0 7310.00 Sq.mt scratches complete. As per instruction & approval by Engineer -in- 6.97 50943.39
NinetySeven Only
charge / Comsultant etc. Complete As per architectural Drawing For All
Floor and Level.
Scraping oil paint from steel and other metal surface and making the
Rupees ThirtyOne
surface even (with Hand Scraping.) As per instruction & approval by
8.0 779.00 Sq.mt 31.31 Paise ThirtyOne 24390.49
Engineer -in-charge / Comsultant etc. Complete As per architectural
Only
Drawing For All Floor and Level.
* Total: Work 02 - (S.R. To Colour work for the Existing Boys Hostel building) 788420.93
Work 03 - (Compound Wall at Entrance Gate )

Excavation for foundation upto 1.5 m depth including sorting out and Rupees One
1.0 48.00 Cu.mt stacking of useful materials and disposing off the excavated stuff upto 152.51 Hundred FiftyTwo 7320.48
50 Meter lead.(D) Soft rock Paise FiftyOne Only

Excavation for foundation for depth from1.5 m to 3.0 m including Rupees One
2.0 16.00 Cu.mt sorting out and stacking of useful materials and disposing off the 165.64 Hundred SixtyFive 2650.24
excavated stuff upto 50 Meter lead. (D) Soft rock Paise SixtyFour Only

Filling available excavated earth (excluding rock) in trenches, plinth, Rupees


3.0 38.53 Cu.mt sides of foundations etc. in layers not exceeding 20 cm. in depth 77.27 SeventySeven Paise 2976.87
consolidation each deposited layer by ramming and watering. TwentySeven Only
Filling in foundation and plinth with murrum or selected soil in layers of Rupees Two
4.0 5.00 Cu.mt 20 cm. thickness including watering, ramming and consolidating etc. 252.50 Hundred FiftyTwo 1262.50
Complete. Paise Fifty Only
Applying general insecticide control treatment to floors, cupboards etc
including labour material etc. complete. Using Heptachloride 20 EC. As
Per 6113_pests Consentration Weight 0.50 percent is recommended Rupees
5.0 24.00 Sq.mt one litre chemical emulsion dillute with 39 liter of water will give. Total 23.63 TwentyThree Paise 567.22
dillute concrentration will be 40 litre inclusive of one litre chemical SixtyThree Only
emulsion appication 0.5 Litre chemical / Sq.mt of surface is
recommended as per I.S
Rupees Three
White Stone Bela mesonry block incourse in superstructure with stone Thousand One
6.0 41.47 Cu.mt of approved quality in Cement Mortar 1:5 (1-Cement :5- course sand) 3180.49 Hundred Eighty 131901.28
including packing the joints etc. complete. Paise FourtyNine
Only
Providing and laying controlled cement concrete M.200 for curing Rupees Three
complete including cost of formwork and excluding cost of Thousand Four
7.0 2.88 Cu.mt 3411.54 9825.23
reinforcement for reinforced concrete work in (C) Sill, Lintels, Chajjah, Hundred Eleven
Girders and Cantilever upto floor two level Paise FiftyFour Only
Rupees Four
Providing and laying controlled cement concrete M.200 and curing Thousand Five
8.0 2.16 Cu.mt complete including the cost of formwork and excluding cost of 4567.31 Hundred SixtySeven 9865.40
reinforcement for reinforced concrete work in (B) Plinth Beam Paise ThirtyOne
Only
Providing TMT Bar FE 500/500D reinforcement for R.C.C. work Rupees FourtyFive
9.0 745.20 Kg including bending, binding and placing in position complete upto floor 45.45 Paise FourtyFive 33869.34
two level Only
Rupees Three
Providing and applying anticorrosive treatment with polymer base
Thousand One
materials to the steel rainfarcement including descaling the dust and
10.0 0.70 MT 3187.56 Hundred 2237.67
applying the preventive coating of approved make (for the R.C.C.
EightySeven Paise
structures near coastal area only) etc complete.
FiftySix Only
Rupees Two
Providing and laying cement concrete 1:3:6 (1-Cement :3-coarse sand Thousand Two
11.0 5.51 Cu.mt :6-stone aggregates 40mm nominal size) and curing complete 2277.55 Hundred 12544.75
excluding cost of formwork in (A) Foundation and Plinth SeventySeven Paise
FiftyFive Only
20mm thick sand faced cement plaster on walls upto height 10 metres
Rupees Two
above ground level consisting of 12mm thick backing coat of C.M. 1:3
12.0 132.00 Sq.Mt 207.05 Hundred Seven 27330.60
(1-cement : 3- sand) and 8mm thick finishing coat of C.M. 1:1 (1-
Paise Five Only
cement : 1-sand) etc.complete.

BMC Shedule - B (Various work) 3


Providing and applying two coats of acrylic exterior weather paint on
out side of wall surface of approved quality paint like "APEX" ULTIMA
brand make & required shade after thoroughly brushing the surface
free from mortar & scrapping old white wash/snow sem or oil painted
Rupees One
surface inc. scaffolding, cleaning the wall & preparing the surface even
13.0 1282.00 Sq.mt 131.30 Hundred ThirtyOne 168326.60
& smooth, filling the cracks incl. applying one coat of white priming
Paise Thirty Only
coat of reputed brand as suggested by Dy. Engg. etc. comp.as
directed. As per instruction & approval by Engineer -in-charge /
Comsultant etc. Complete As per architectural Drawing For All Floor
and Level.
Providing & Fixing Approve Shade & Colour 16mm to 18mm thick
Rupees Two
Granite stone with Single side Mirror polished with all edges shall be
Thousand Four
moulded and polished for dedo and flooring including with base of
14.0 8.28 Sq.mt 2481.57 Hundred EightyOne 20547.40
Chemical mortar laid over and jointed with grey cement slurry mixed
Paise FiftySeven
with pigment to match the shade of slab including rubbing and
Only
polishing etc. complete.with groove all labour, tols, takel,etc complete.
Rupees Three
Demolition of Brick work and stone masonry including stacking of
Hundred Fourty
15.0 18.24 Cmt. serviceable materilas and disposal of unserviceable materials with all 340.37 6208.35
Paise ThirtySeven
lead and lift.(ii) In Cement Mortar.
Only
Providing, supplying and fixing logo of “SHREE SOMNATH SANSKRIT Rupees FiftyOne
UNIVERSITY” with arrangement of LED light with PVC frame of Thousand Four
16.0 2.00 Each 51420.11 102840.22
diameter 38” including arrangement of LED light, complete as per Hundred Twenty
selection of officer in change etc complete as per directed Paise Eleven Only

Providing and fixing stainless steel lette "SHREE SOMNATH


Rupees FiftyFive
SANSKRIUT UNIVERSITY ” of 12” on 3mm ACP background with 9”
Thousand One
17.0 2.00 Each frame of 3mm ACP sheet on three sides of letter also 6” frame on door 55148.02 110296.04
Hundred FourtyEight
and S.S letter as per selection of engineer in charge size of complete
Paise Two Only
outer frame with decorative light etc complete as per directed.

supplying and laying decorative stone pebble for decoration of out side
Rupees Seven
18.0 120.00 Kg of gate devloptment including proper fixing in line & level as per 707.00 84840.00
Hundred Seven Only
suggested by engineer in charge etc. Complete as directed (MR)
Removing dry or oil bound distemper by a washing and scraping and
sand papering the wall surface smooth including necessary repairs to
Rupees Six Paise
19.0 1250.00 Sq.mt scratches complete. As per instruction & approval by Engineer -in- 6.97 8711.25
NinetySeven Only
charge / Comsultant etc. Complete As per architectural Drawing For All
Floor and Level.
Applying priming coat over priviously painted steel andother metel
surface after and includingpreparing the surface by throughlycleaning, Rupees TwentyTwo
20.0 200.00 Sq.mt oil,grease, dirt and other foreignmatter and scoured with brushes 22.22 Paise TwentyTwo 4444.00
finesteel wood, scrapers and sand paper withready mixed priming Only
paint brushing red lead sor 2015-16 it no 19001 pg no 184
Painting two coats (excluding primingcoat) on previously painted steel
Rupees FiftyFive
and other metal surface with enamel paint,brushing to give an even
21.0 200.00 Sq.mt 55.75 Paise SeventyFive 11150.40
shade includingcleaning the surface of all dirt, dust and other foreign
Only
matter.
* Total: Work 03 - (Compound Wall at Entrance Gate) 759715.82
Electrical work (Compound Wall at Entrance Gate )

Point wiring for Light / Bell with 2-1.5 sq.mm & earthwire of 1.5 sq.mm
(Green) both are of ISI marked 1.1 KV grade FRLS PVC insulated
multistrand copper wires, in following type of pipe to be erected
concealed in/ on surface on wall/ceiling complete with 6A Modular type
Rupees Four
switch / bell push & accessories and earth continuity of following type,
22.0 2.00 Pt 424.20 Hundred TwentyFour 848.40
erected on PVC / Metallic box, single mounting base frame covered
Paise Twenty Only
with textured / metallic front plate modules erected on / in wall / ceiling
as per pipe erected, with necessary Lamp holder/ceiling rose /
H.D.Connector as directed. (a) with medium class Rigid PVC pipe and
accessories Cat- III

Point wiring for Individual Plug with & earthwire of 1.5 sq.mm (Green)
both are of ISI marked 1.1 KV grade FRLS PVC insulated multistrand
copper wires, in following type of to be erected concealed in / on Rupees Four
surface of wall / ceiling complete with Modular type switch & 5 pin Plug Hundred FourtyNine
23.0 2.00 Pt 449.45 898.90
erected on PVC / Metallic box covered with appropriate front plate Paise FourtyFive
modules erected on / in wall / ceiling as per pipe erected with following Only
type of accessories. [I] For 6A Plug with 2-1.5 sq.mm Cu. Wire (a)
with medium class Rigid PVC pipe and accessories Cat- III

Point wiring for Individual Plug with & earthwire of 1.5 sq.mm (Green)
both are of ISI marked 1.1 KV grade FRLS PVC insulated multistrand
copper wires, in following type of to be erected concealed in / on Rupees Seven
surface of wall / ceiling complete with Modular type switch & 5 pin Plug Hundred
24.0 2.00 Pt 797.90 1595.80
erected on PVC / Metallic box covered with appropriate front plate NinetySeven Paise
modules erected on / in wall / ceiling as per pipe erected with following Ninety Only
type of accessories. [III] For 16A Plug with 2-4 sq.mm Cu. Wire (a)
with medium class Rigid PVC pipe and accessories Cat- III

Point wiring for Looped Plug with 6A Modular type switch & 5 pin
Rupees Two
socket erected on PVC / Metallic box, single mounting base frame
25.0 2.00 Pt 242.40 Hundred FourtyTwo 484.80
covered with textured / metallic front plate modules erected on / in
Paise Fourty Only
wall / ceiling with following type accessories Cat. III

Providing following type of Modular Type Accessories mounted with


pvc / metallic box, single mounting base frame covered with textured / Rupees Twenty
26.0 2.00 Ea 20.20 40.40
metallic front plate , modules erected with necessary connection. As Paise Twenty Only
desired by Engineer In charge (7) Blank Plate Single Cat III

BMC Shedule - B (Various work) 4


Point wiring for secondary light point with 2-1.5 sq.mm & earthwire
of 1.5 sq.mm (green) both are of ISI marked 1.1 KV grade FRLS PVC
insulated multistrand copper wires, in following type of pipe to be
erected concealed in / flushed on wall/ceiling, complete with earth
continuity and necessary connection with primary light with Rupees One
27.0 10.00 Pt accessories erected on Metal / PVC box covered with 3 mm thick 121.20 Hundred TwentyOne 1212.00
PC(Polycarbonet) / Acrylic sheet for open / concealed wiring. with Paise Twenty Only
necessary Lamp holder / ceiling rose / H.D.Connector as directed.
Note:- Maximum up to 6 mtrs length, excess will be considered as
Mains for Secondary Point. (a) with medium class Rigid PVC pipe
and accessories

Providing and erecting ISI mark Medium class RIGID PVC PIPES of
following size complete to be erected on/in wall or ceiling erected with Rupees ThirtyTwo
28.0 100.00 Mtr necessary PVC fittings & Junction boxes fixed with adhesive solution & 32.32 Paise ThirtyTwo 3232.00
Clamps with following dia of pipes, in approved manner as directed Only
(b) 25 mm
Providing and erecting ISI mark Medium class RIGID PVC PIPES of
following size complete to be erected on/in wall or ceiling erected with Rupees FiftyThree
29.0 100.00 Mtr necessary PVC fittings & Junction boxes fixed with adhesive solution & 53.53 Paise FiftyThree 5353.00
Clamps with following dia of pipes, in approved manner as directed (c) Only
32 mm
Mains with 1.1 KV grade FRLS PVC insulated ISI marked stranded
Copper conductor wire in following type of pipe to be erected
concealed in /flushed on wall/ceiling, with 1.5 sq. mm copper Rupees Sixty Paise
30.0 150.00 Mtr 60.60 9090.00
conductor FRLS PVC insulated stranded wire of green colour for earth Sixty Only
continuity of following size (a) with medium class Rigid PVC pipe
and accessories (a) 2 wire 1.5 sq. mm
Mains with 1.1 KV grade FRLS PVC insulated ISI marked stranded
Copper conductor wire in following type of pipe to be erected
concealed in /flushed on wall/ceiling, with 1.5 sq. mm copper Rupees Eighty Paise
31.0 94.69 Mtr 80.80 7650.95
conductor FRLS PVC insulated stranded wire of green colour for earth Eighty Only
continuity of following size (a) with medium class Rigid PVC pipe
and accessories (b) 2 wire 2.5 sq. mm
Supplying and erecting LED indoor fittings with LEDs of wattage 0.2
Watt to 0.5 Watt assembled on single MCPCB, with housing used as
a heat sink shall be made of thick sheet Steel conforming to IS:
513/CRCA polyester powder coated and high U.V. & corrosion
Rupees Two
resistance with diffuser and/or Polycarbonate optics with company
Thousand Seven
32.0 10.00 Ea mark/name 120 to 300 V,Power Factor more than 0.9, THD < 10 %, 2727.00 27270.00
Hundred
CCT 4000 K to 6500K, Uniformity ratio >0.7, Luminaire efficiency> 85
TwentySeven Only
lumens/watt , LED driver efficiency > 85 % CREE / OSRAM / PHILIPS
Lumileds / NICHIA/SEOUL/Bridgelux(U.S.A.) make LED used for
luminaire. (Each fitting required LM-79 & LM-80 Certificates)(G) Spot
Light , 5W, 425 Lumens, Surge-2KV(b) 11 Watts
Approved make ELCBs / RCCBs conforming to IS: 12640 and having
sensitivity of 30 mA and Short Circuit withstand capacity of 6 KA and Rupees Two
suitable for operation on single phase 240 V. having characteristic of Thousand Six
33.0 3.00 Ea 2636.10 7908.30
quick action & tripping with all advance feature & do not incorporate Hundred ThirtySix
any electronic component. for following Max. rating erected as Paise Ten Only
directed (ii) 40Amps. DP Cat. III
* Total: Work 04 - Electrical work (Compound Wall at Entrance Gate ) 65584.55

BMC Shedule - B (Various work) 5