4.10 DESCRIPTION
a) Drawings: for Contractor produced drawings use the drawing number, revision
number and drawing title.
-1-
c) Samples, guarantees, manufacturer’s data, catalogue cuts, certificates, tests
and documents other than drawings: use the name or description of the item
submitted utilizing the same descriptive terms as the specification, BOQ or
contract drawings.
d) Contractor shall forward only one item per Submittal. This will facilitate the
review, expedite the return of the Submittal, make it easier to track revision
and cross reference with material delivery, inspection and installation. For
example, cement test certificates shall not appear on the same transmittal as
aggregate test certificates. In some cases, several documents may appear in
column.
4.11 TYPE
a) SD - Contractor produced coordinated shop drawing
b) SM - Sample
c) GT - Guarantee
d) OT - Other (e.g. For Information)
e) CT - Certificates
f) TT - Test
g) MS - Method Statements.
Manufacturer’s data, Catalogue cut, Brochure, Data Book,
h) MD -
Calculations, etc.
4.12 Quantity of Submittals
The number of copies of each document to be attached to the Submittal Form.
Each Shop drawing, bar bending schedule, test, sample or calculation submitted
initially for approval must be issued only cover sheet to CSI/RES and attachments to
HLW.
Catalogues, brochures and technical data,
manufacturer’s drawings, etc. 1 originals + 2 copies
-2-
4.13 Authorized Signature of the Contractor
The Signature shall be of a responsible person who in writing has been authorized to
sign on behalf of the Contractor and approved by the Employer.
4.15 Comments
Comments by the Lead Design Consultant or Project Manager or KBZF resulting from
the Submittal review.
c) Action “C” means that submittal does not comply with the Contract Documents
and that fabrication, manufacture, supply or construction shall not proceed.
Submittals stamped Action “C” are not permitted on the job site and are not to
be used. The Contractor shall make revision and resubmit.
d) Action “D” means that the submittal is issued solely for informational purpose
and that no further action is required on it.
4.19 Date
-3-
4.20 Copies received by the Lead Design Consultant’s Representative
As per requirements, the Contractor shall within a day of receipt, provide the Engineer
with 3 copies of the Submittals marked with the Lead Design Consultant’s
Representative’s comments. Copies for distribution shall be as stated on the Submittal
form.
For Action Codes ‘A’ and ‘B’, the Engineer’s Representatives shall receive the
Submittal Form with enclosures. For Code C, only the Submittal Form should be
returned. For material submittals catalogue copies, as required by the Lead Design
Consultant’s Representatives.