Professional Documents
Culture Documents
MANAGEMENT,
SECOND CYCLE, 30 CREDITS
STOCKHOLM, SWEDEN 2020
MALIN KARLBOM
LOVISA HALLMAN
www.kth.se
Geotechnical reinforcement work
for foundation of extending an
existing residential building
We would like to give our supervisor Stefan Larsson, professor at the Royal Institute of
Technology, KTH, a big and genuine thank you for all your help and encouragement. Your
mentorship and knowledge have been valuable to us.
We would also like to thank our supervisors Joakim Berg and Daniel Beyer at Skanska’s
department of foundation and housing, respectively. Thank you for your valuable insights and for
sharing your experiences within the subject. Finally, we would like to thank Ricardo Öjring
Garcia at Skanska, for the interesting discussions and for all the time you spent helping us.
Thank you, Skanska, for the opportunity and for making this collaboration possible.
Stockholm 2020–05–18
Malin Karlbom & Lovisa Hallman
NOMENCLATURE
Abbreviations
BBR Boverkets Byggregler [Boverket’s Building Regulations]
EKS Boverkets Konstruktionsregler [Boverkets’ Construction Regulations]
GEO Geotechnical Bearing Capacity
PBL Plan- och Bygglagen [Planning and Building Act]
SLS Serviceability Limit State
STR Structural Bearing Capacity
ULS Ultimate Limit State
Symbols
REFERENCES ...............................................................................................................................................65
APPENDIX A ..................................................................................................................................................73
APPENDIX B ..................................................................................................................................................85
APPENDIX C ..................................................................................................................................................87
APPENDIX E .................................................................................................................................................111
1. INTRODUCTION
1.1 Background
In the last hundred years, a land elevation has taken place in Stockholm and according to SMHI
(2011), the elevation is measured up to an increase of 0.38 cm per year (Appendix A, part 9). This
land elevation causes an increased distance between the ground surface level and the groundwater
level, which in turn can pose a danger to the stability of wooden piles. When wooden piles are
exposed to oxygen, rot fungus can occur which in turn leads to a decreased carrying capacity. In
the worst case, it loses its strength and affects the building by the occurrence of subsidence which
in turn can lead to a collapse. The land elevation causes therefore, a need of replacing the existing
wooden piles in Stockholm.
Another critical problem that exists in big cities today is that the demand for housing is
increasing with population growth. According to Statistiska Centralbyrån (2019), the average
population growth is estimated to approximately 36 300 persons per year between 2009s-2018s in
Stockholm County (Table 1.1.1). The supply needs to be increased to meet the demand, since the
statistical result indicates that the population continues to increase in the future within the region.
The potential development area for new housings in Stockholm County is limited and an
innovative solution may be to exploit existing buildings with a superstructure. Such an action may
require strengthening works in the foundation due to the increased load. Since the existing
wooden piles has a need of replacement, the opportunity to exploit an existing building with a
superstructure is analyzed to optimize the required geotechnical reinforcement work.
Table 1.1.1. The population growth within Stockholm County (Statistiska Centralbyrån, 2019).
Population growth in Stockholm County during 2009s-2018s
Year Q1 Q2 Q3 Q4 Total amount
2009 8 159 9 474 12 151 8 135 37 919
2010 6 569 8 729 11 623 8 240 35 161
2011 9 602 10 007 10 574 6 947 37 130
2012 8 146 9 583 10 558 7 246 35 533
2013 8 859 8 997 10 613 7 567 36 036
2014 8 417 9 859 11 115 5 611 35 002
2015 7 061 8 423 10 628 7 283 33 395
2016 7 778 9 261 12 317 8 265 37 621
2017 8 796 10 094 11 643 8 550 39 083
2018 7 469 10 051 10 741 7 720 35 981
Average population growth per year in number of people 36 286
1
INTRODUCTION
• How does the amount of work differ in the geotechnical reinforcement between
an existing building compared to one with an expanded superstructure?
• How does the cost differ in the geotechnical reinforcement work between an
existing building compared to one with an expanded superstructure?
To broaden the area of application for the thesis, the most common existing building built with
wooden piles in Stockholm is chosen to be analyzed, due to the housing shortage. In this thesis,
the city center of Stockholm is considered and consists of the following districts: Kungsholmen,
Vasastaden, Östermalm, Norrmalm, Södermalm and Gamla Stan. Existing buildings are assumed
to have confined basements, adjoining residential buildings on the transverse sides, municipal
owned street on one of the longitudinal sides and a courtyard on the other side. The confined
basements delimit the use of piling machine and in turn, the potential pile dimension. Potential
geotechnical reinforcement works consists of a transfer method and a foundation method, which
are chosen in accordance to the geological conditions where wooden piles were used and how the
building is constructed.
The superstructure is assumed to be built on top of the existing building, as it is only extended in
height. It contains the same design of the floor plan as the existing building, due to
simplifications and structural advantages. Other parameters that this thesis considers for both the
existing building and the superstructure are the following: the building material, the construction,
the geological conditions and the existing foundation. The analyzes that are considered in this
thesis are the vertical forces, the horizontal forces and a global analysis of the moments. To
delimit the thesis, the analyzes excludes the control of buckling in the building, shear forces, bow
imperfections and bending moments in beams. To simplify, the walls are assumed to be
homogenous, which gives that openings as windows and doors are not considered.
2
METHODS AND METHODOLOGY
Seven topics have been in focus during the literature study, to ensure relevant information for the
thesis. The literature study is presented in Chapter 3 and concludes with a discussion regarding
how valuable the collected information is. The topics are following:
• Theoretical background and review over what have been done within the subject
• The geological conditions
• The building and architectural history
• The structure of existing buildings
• Potential building material for a superstructure
• Potential methods for reinforcement work of foundation
• Legislated regulations and requirements
Several data bases have been used during the study, where DiVA and Google Scholar are the two
main ones. Authorities regulations and other laws has also been used to ensure that the design
regulations are fulfilled. Internal information within Skanska has been used together with
personal communication within the field, to increase the study’s possibilities of becoming as
reality based as possible. Different search terms in both Swedish and English, have been applied
during the search in the data bases and the choice of the term and combinations of them has
been dependent on the intended outcome. Table 2.1.1 summarizes the search terms used.
3
METHODS AND METHODOLOGY
• Geological conditions
• Existing construction of foundation
• Existing construction of framework
• Connection construction
• Superstructure construction
The geological conditions are determined in accordance to which conditions wooden piles were
used for the most difficult soil strata sequence present in Stockholm. The most common building
technology within the era when most of the buildings was built within the city center of
Stockholm was chosen. When a superstructure is built, a connection construction between the
existing and extended part is needed and determined based on the literature survey. The weight
of the superstructure comprises of the choice of material and the number of storeys, which is
4
METHODS AND METHODOLOGY
optimized in accordance to Swedish legislated regulations. Two cases in form of two models are
constructed as follows:
The first analysis is analytically calculations of vertical loads to obtain the load distribution
through the load-bearing structure to the foundation. The second analytical analysis regards the
horizontal forces which the building is exposed to in the second case, due to the increased height
of the building. This includes the earth pressure and the wind forces, which needs to be verified
regarding the stabilizing moment. This is followed by the third analytical analysis, where the
results from the two earlier analyzes are combined to obtain design loads.
When the design loads are obtained for each wall, the new foundation can be determined
numerically through a program produced by SSAB (2019), called RRPileCalc. This gives what
kind of foundation that is necessary to carry the design load. Afterwards different potential load
transferring methods are applied on the determined foundation to distribute the load from the
building to the foundation. For each method and each wall, the number of piles is determined
through analytical calculations. To ensure that the pile can carry the design load, it is tested
numerically in the provided program. If the load is too large, more piles are being added through
analytical calculations to minimize the axial load each pile carries. This gives that this is an
iterative process. When the sufficient number of piles is determined, it is tested analytically to
also consider the geometric requirements.
Each method is applied on each wall, since a combination of the methods can be done for the
different walls in each cross-section. The potential combinations of the cross-sections are
combined to several total combinations to obtain the total potential geotechnical work for all the
walls. This total process is repeated for different potential pile dimensions.
The obtained results for each pile dimension with the combinations are afterwards cost estimated
by the identified required activities for each method. The activities are priced according to costs
developed by Skanska and the costs for each total combination is determined. This is to obtain
the differences between the two cases in both the amount of geotechnical work and for its costs.
5
6
LITERATURE SURVEY
3. LITERATURE SURVEY
Nedrén and Rinaldo (2018) analyzed a three-multi-storey house made of concrete with a
foundation consisted of a slab on a stone bed, a typical reference building from the Million
Programme. Their purpose was to add a superstructure consisting of two storeys of CLT. They
show that the utilization of the framework was low for the existing building and only 80 % of the
capacity of the foundation is used when the superstructure is built.
A SBUF report provided by Lidgren and Widerberg (2010), has been developed where
superstructures are extended on top of existing buildings between the time internal of the years
1960 to 1970. The analyzed existing buildings in the study had flat roofs, which gives that an
easier construction on top of the building can be applied to enable an extension of storeys.
Interviews with both many people and companies within the subject was done, with the purpose
to do an inventory for the conditions for the construction of the houses from the Million
Programme. The conclusion was that one to two storeys could be built without the need of
reinforcing the foundation. They obtained a total production cost for each project they
investigated, which consisted by the extension of the buildings with one or two storeys. This cost
is an average value 27 900 SEK/m2 with inflation included. Most of these superstructures used
prefabricated volumes, of which half of the project's construction consisted of wood in form of
both walls and frames, and some of them consisted of steel structures.
A similar result has been found through another study provided by Friberg and Karlin (2015).
They also analyzed buildings from the same era with a framework structure made of concrete.
Using a reference object, it could be possible to see how great the utilization was of the
framework. The capacity of the existing construction made of load bearing walls was only utilized
to 20 %. This enabled a superstructure to be applied thanks to the large capacity of the structure
without the need for reinforcement work.
There have been several existing buildings that has been extended with a superstructure
consisting of cross-laminated timber. There are many advantages with using wood in a
superstructure according to Martinsons (2019). They describe the low weight of wood as the key
to success, since wood is five times lighter than concrete, which minimizes the load of the
superstructure. Other advantages are that CLT retains its shape when exposed to moisture due to
its contexture and that its structural capacity is as great as concrete.
The Tricot Factory originally built in 1928. has been extended by a superstructure consisting of
wood (Martinsons, 2019). The project is in Hammarby Sjöstad, Stockholm. The project manager
describe wood as the ultimate material for this kind of work and the project has been
environment certified, which demonstrates the environmental advantages of this building
technology. This project consisted of an extended superstructure with a total new area of 8 800
m2. The superstructure can be built without expensive and time-consuming geotechnical
reinforcement works of foundation due to its light weight.
7
LITERATURE SURVEY
A study comparing a superstructure consisting of wood with another of concrete has been
provided by Bchar and Youssef (2018). The study shows that wood is the most efficient and
profitable building material to use, because concrete entails greater loads due to its heaviness,
which also affects the stability of the ground. When using a heavier material, as concrete, the
foundation needs to be strengthened. Which also is costly, which gives that wood is the
advantageous building material for extension works.
A study comparing one storey superstructure consisting of wood with another of steel has been
made (Oscarsson and Eklund, 2010). This superstructure was intended to be built on a two
storey building from 1968 with a flat roof and a framework of concrete. The study shows that the
existing framework can carry the superstructure in both wood and steel with good margins. The
margins are so large that a framework with few load-bearing walls, as the reference building in the
thesis has, can still carry the extension without any need of reinforcement work. However, the
thesis does not concern how the ground act and therefore, ensures that both the geological
conditions and the carrying capacity of the foundation should be analyzed and considered for a
real project. The study also contains a comparison between the advantages and disadvantages for
wood and steel. Steel is stronger and lighter than wood, nonetheless, steel is 15 % more
expensive to build with.
Karlsson and Rosin (2018) has performed a study with the purpose to analyze three residential
buildings made of masonry from the years between 1880s-1920s and their capability of storeys
extensions for superstructures. The buildings are located on Södermalm, Östermalm and
Blasieholmen. The focus was on the older masonry structures strength properties for the
construction to be able to carry a superstructure. They determined a procedure to calculate the
load that passes through a building through a vault, where the stresses that arise must not exceed
the compressive strength of the masonry wall. Masonry walls consists of both mortar and bricks
and are characterized by a good ability to absorb compressive stresses. Unfortunately, bricks and
mortar have a relatively poor ability to absorb shear and tensile stresses. Therefore, the turn of
the century enables further densification of large cities centers in Sweden, since the solid frame
allows high loads. Due to its poor ability to absorb shear and tensile stresses, it is hard to
determine the static system with the reason that the construction system is statistically
indeterminate. With the two different materials of the framework, mortar and bricks, they have
two different properties, but interact during load distribution. The angles and shape of the
masonry walls can be variated, which gives that the relationship between stress and strain is
direction dependent and therefore, nonlinear. However, it is important that the system must be in
equilibrium to prevent the structure from cracking or breaking. It can be controlled by analytical,
numerical or graphical methods how the load distribution and forces act in their direction
regarding the equilibrium conditions. This is important to ensure that the additional load would
not affect the equilibrium of the simplified static system. Their conclusion was based on their
recommendations of testing the compressive strength and their theoretical assumptions of the
construction. They conclude that there are good opportunities to build on top of an older
masonry building due to its good ability of compression. The study show that all the three
buildings are dimensioned and designed to be able to carry more load than what they are exposed
to. However, there are many parameters that needs to be considered in the design of a project
that is extended with a superstructure, as all building are different. This can for instance be the
static system, the variation of pressure over vaults, the attachment of any additional beams, the
equilibrium system and the interaction between the materials of the old and new buildings. The
superstructure must be performed in a certain way based on the conditions of the existing
building, since there is a large variation between the buildings. However, this requires further
studies, since the analysis only regards the compressive strength properties of a framework,
which is not sufficient to be able to draw a conclusion regarding the possibilities of building a
8
LITERATURE SURVEY
superstructure. An example is the need to study the strength in both bending and tension,
together with how both the foundation- and geological conditions are for the existing buildings.
This study enables an assurance that it is not the construction itself that gives way regarding the
compressive strength, when additional loads is added.
The geological conditions vary widely within the area of Stockholm. The geological conditions in
the central districts of the city are determined by using Sweden’s Geological Survey’s 3D-viewer
(SGU, 2017). SGU (2017. Figure 3.2.1) visualizes the city map of Stockholm, where an overall
division of the city has been made to clarify the location of the districts.
The most common soil strata sequences in the district are obtained from the 3D-viewer and are
presented for each district. The dominant geological conditions present in the district according
to SGU (2017), are presented in Table 3.2.1 to Table 3.2.6 for Kungsholmen, Södermalm, Gamla
stan, Norrmalm, Östermalm and Vasastaden.
The characteristic value of the undrained shear strength of the postglacial clay should, according
to the Swedish Geotechnical Institute (2008), be routinely determined with a fall cone test when
the clay is investigated. According to Sadek Baker (Personal communication, February 17th,
2020), the postglacial clay in Stockholm has a varying characteristic value for the undrained shear
strength between 4 – 12 kPa, where normally the value is 8 kPa.
9
LITERATURE SURVEY
Table 3.2.1. The dominant soil strata sequences in the district Kungsholmen (Summarized from SGU,2017).
Kungsholmen
Overlying soil Fill Fill Moraine -
Underlying soil Postglacial clay - - -
Gabbroid-dioritoid,
Rock Wacke Wacke Wacke or granite
wacke or granite
Soil depth 1-5 m 0-3 m 0-1 m 0-1 m
Table 3.2.2. The dominant soil strata sequences in the district Södermalm (Summarized from SGU, 2017).
Södermalm
Overlying soil Fill Fill Moraine Fill -
Underlying soil Postglacial clay - - Glacier sediment -
Rock Granite Granite Wacke or granite Granite Granite
Soil depth 1-20 m 3-10 m 0-1 m 0-20 m 0-1 m
Table 3.2.3. The dominant soil strata sequences in the district Gamla stan (Summarized from SGU, 2017).
Gamla stan
Overlying soil Fill Fill Fill Fill
Underlying soil Glacier sediment Postglacial clay Postglacial sand -
Rock Wacke Wacke Wacke Wacke
Soil depth 20-50 m 10-30 m 10-30 m 0-1 m
Table 3.2.4. The dominant soil strata sequences in the district Norrmalm (Summarized from SGU, 2017).
Norrmalm
Overlying soil Fill Fill Fill Fill Moraine
Glacier
Underlying soil Postglacial sand Postglacial clay - -
sediment
Wacke or
Rock Wacke Wacke Wacke Wacke
granite
10-20
Soil depth 10-20 m 3-5 m 5-20 m 0-1 m
m
Table 3.2.5. The dominant soil strata sequences in the district Östermalm (Summarized from SGU, 2017).
Östermalm
Overlying soil Moraine Moraine Filling - Filling
Underlying soil - - Postglacial clay - Sandy moraine
Rock Wacke Granite Wacke Wacke Granite
Soil depth 0-1 m 0-1 m 0-20 m 0-1 m 5-10 m
Table 3.2.6. The dominant soil strata sequences in the district Vasastaden (Summarized from SGU, 2017).
Vasastaden
Glacier
Overlying soil Moraine Fill - Fill Fill
sediment
Postglacial Glacier Postglaci
Underlying soil - - -
clay sediment al sand
Gabbroid-
Wacke or
Rock Wacke Wacke dioritoid or Wacke Wacke
granite
wacke
Soil depth 0-1 m 3-10 m 0-1 m 5-20 m 10-20 m 5-30 m
10
LITERATURE SURVEY
The housing construction almost stopped during the First World War (1914s-1918s) and the
intended demolitions of housings where postponed due to the current housing shortage
(Claesson, 1987; Bjerking, 1974). The housing shortage during these periods was further
exacerbated when all private construction activities were crippled. The construction costs rose
sharply due to material shortages and the rationing that went on during the war.
According to Christopher Vainesworth (Personal communication, January 20th, 2020), the area of
Östermalm was built during the 1880s-1890s and the majority of the areas Vasastaden,
Kungsholmen and Södermalm built between the 1900s-1940s. The city center was later built
between 1950s-1960s and consists of more office buildings than residential ones. According to
Riksantikvarieämbetet (n.d), the majority of residential buildings were built between 1880s-1920s
within the city center of Stockholm. The districts Vasastaden, Östermalm, Kungsholmen,
Norrmalm and Södermalm are to, a large extent, built during this era. The newly built buildings
in Stockholm Municipality are presented with a distribution between the decades when it was
built (Table 3.3.1). (Riksantikvarieämbetet, n.d.)
Table 3.3.1. Distribution of residential buildings built in Stockholm over time (Riksantikvarieämbetet (n.d).
Buildings Areas with the majority of Areas with the minority of
Decade
built buildings built buildings built
Single buildings on Östermalm
1700s-1860s 86 Gamla Stan, Norrmalm
and Södermalm
Smaller parts on Östermalm and Single buildings on Södermalm
1860s-1870s 23
Vasastaden and Gamla Stan
Smaller parts on Östermalm and
1870s-1880s 21 Single buildings on Södermalm
Norrmalm
Östermalm, Vasastaden, smaller parts
1880s-1890s 204 Single buildings on Norrmalm
on Kungsholmen & Södermalm
Southern Östermalm. A part in Single buildings on Södermalm
1890s-1900s 174
Vasastaden and Kungsholmen
Vasastaden, Östermalm, smaller parts Single buildings on Norrmalm
1900s-1910s 261
on Kungsholmen and Södermalm.
Few ones on Östermalm and
1910s-1920s 175 Vasastaden, Norrmalm, Södermalm
Kungsholmen
Great spread in Municipality, Smaller parts on Kungsholmen,
1920s-1930s 161
Södermalm, Vasastaden Östermalm and Norrmalm
Outside the city center,
Smaller parts of Norrmalm,
1930s-1940s 168 Kungsholmen, Northern part of
Södermalm and Vasastaden
Östermalm
Outside the city center and in the
1940s-1950s 116 Few ones within the city center
suburbs to Stockholm
11
LITERATURE SURVEY
Framework construction
Most of the buildings within Stockholm city center was built between 1880s-1920s, according to
Chapter 3.3. The construction material during this era was masonry and the framework in
housing buildings often consisted of load-bearing outer walls and centrally placed walls, called
heart walls (Bjerking, 1974). The buildings have one basement and 5 – 6 storeys in the bigger
cities. The indoor height was between 2.8 – 3.3 m, whereas the height in the basement was
between 2.4 – 2.7 m. These buildings have one elevator installed. The depth of the building could
be 11 – 12 m, a width could be 20 m and a total height around 24 – 27 m. A common type
example of construction is visualized in Figure 3.4.1.
Figure 3.4.1. The framework of a building built between 1890s-1910s with a height of 26.84m (Bjerking, 1974).
12
LITERATURE SURVEY
For a, thorough review of each construction component in a building with the building technique
used during 1880s-1920s, the typically building that was built between these years are presented
as follows:
Roof construction: The construction consisted of Swedish roof chairs that are attached to
longitudinal straps. It is covered with tongue and groove wood together with folded metal roof.
This type of roof construction is called saddle roof. (Bjerking, 1974)
Attic floor construction: It consists of wooden beams with dimensions 6” x 10” and a center
distance of 60 cm and is mounted on the load-bearing walls and partition walls (Bjerking, 1974).
The beams are often made of pinewood according to Klintberg and Åkehag (2017). The beams
are attached to a frame of 4” x 4” laid on the masonry wall where the floor consisted of 1 ½”
tongue and groove wood without fire bottom. There is a space between the beams for filling with
heavy materials such as lime gravel, which is laid on top of another thinner layer of filling and
blinds which could consist of newspaper, shavings or sawdust. The ceiling consists of a panel that
is plastered (Bjerking, 1974). According to Klintberg and Åkehag (2017), it could also be
common that the filling consists of clay and after the filling, a layer of uncut and edge-cut boards
is spiked diagonally on a plank frame. According to Bjerking, (1974), the total height of the
system of attic floor joist is 43 cm (Figure 3.4.1).
Floor construction: The system of floor joists in the building consists of the same parts as the
attic construction, except that these floors have a fire bottom of masonry tiles (Bjerking, 1974).
This is a layer of bricks to create a fire cell separating function (Björk, et al., 2013). The total
height of this type of construction is 36.8 cm (Figure 3.4.1) (Bjerking, 1974).
Ground floor construction: The construction could be made of unreinforced concrete cast
between steel beams that was put along the facade on the transverse partition walls. The floor
consists of 1 1/4” tongue and groove wood that lies on wedged rails on the concrete. The steel
beam in the outer wall carries the window openings, where the windows are divided by transverse
inwardly coupled arches. The total height of the ground floor is 50.8 cm (Figure 3.4.1). (Bjerking,
1974)
Outer wall construction: The outer wall is constructed of brick stones and has an exterior
plastered wall with lime plaster. The walls are constructed with 1 ½ brick stones for the first 4
floors, 2 brick stones for the floors beneath. The walls at the ground floor consists of 2 ½ brick
stones, regarding the space that must be given to large windows and façade cladding. (Bjerking,
1974)
Heart wall construction: The heart walls consists of 2 brick stones in the basement, 1 ½ brick
stones in the ground floor and 1 brick stone for the remaining floors, and each side is smooth
plastered. (Bjerking, 1974)
Basement construction: With the building technique during this era, a traditional type of
basement wall is placed on the foundation (Björk, et al., 2013). The basement wall is made of 3
brick stones for the upper part of the wall, where the lower part often consists of a dry-stone
wall, which is stones put together (Bjerking, 1974). The basement floor construction often
consists of concrete, with a varied thickness between 0.2 – 0.4 m, according to Joakim Berg
(Personal communication, March 11th, 2020).
13
LITERATURE SURVEY
Foundation construction
The design of the foundation has been varying over time, depending on the different building
technology that prevailed. The techniques were depending on the geological conditions, which
according to Björk, et al. (2013) are divided into four different groups, which are solid ground,
solid-semi-solid ground, soft soil and very soft soil. If the geological conditions consist of very
soft soil, as clay, the load must be transferred to a firmer soil layer with either plinths or wooden
piles. The decades when most of the buildings was built within Stockholm are around the turn of
the century, 1880s-1920s. During this era, wooden piles was installed with a piling crane,
anchored to a rust bed. The rust bed was a wooden construction placed underneath the dry-stone
walls to distribute the load evenly and is placed underneath the groundwater level. The piles were
driven down until it reached resistance, or they could be hanging in the soil through friction.
After 1920s, reinforced concrete piles began to be used. According to Björk, et al. (2013), the
most common building techniques for foundation in very soft soil conditions are two types of
wooden piles (Figure 3.4.2), described as follows:
Stone wall on wooden piles type 1: Between the 1880s-1910s, 4 – 7 m long wooden piles are placed in
3 – 5 rows under the foundation walls where the piles are cut off below the groundwater surface.
On top of the pile top, a beam rust bed out of logs was placed crosswire in two layers, that was
embedded with clay.
Stone wall on wooden piles type 2: Between the 1885s-1925s, 12 m long wooden piles are placed in 2 –
4 rows under the load-bearing walls. Where these piles also had a beam rust bed, but with planks
on top of it. Prior to the layer of planks, there was a layer of gravel, packed with a spit between
the piles and beams.
a) b)
Figure 3.4.2. Stone wall on wooden piles, a) with shorter lengths and b) longer lengths (Björk, et al. 2013).
14
LITERATURE SURVEY
The European Union transition to functional standards in the members’ construction legislation
have increased the development regarding wood construction and makes it possible to build
bigger buildings and constructions in wood (Svenskt trä, n.d.a). Wood is the only current material
that is renewable and versatile raw. By increasing the amount of wood as building material, it
lowers the environmental impact, since the non-renewable materials, as concrete or steel, gives a
higher amount of carbon dioxide emissions. If wood replaces other building materials, the
average replacement factor 1.6 tons’ carbon dioxide per cubic meter wood material, which makes
a great difference in emissions. The transports are reduced during construction time, due to its
light weight (Svenskt trä, n.d.b). The large access of wood in Sweden enables the production of
the material at near distance, which also minimizes the transports and therefore, the emissions.
CLT is a material that consists of glued massive wood boards, that in turn consists of planed
wood where the boards are glued with every other layer crossed to increase the shape stability
and high resistance despite its low weight (Martinsons, 2019). CLT is the most common wood
product used as construction material due to its properties, stiffness and strength, as well as its
flexibility in varied geometry (Trä Guiden, 2017a). The material can be used in both walls and
beam systems, as well as system of joists (Trä Guiden, 2017b, 2017c). This type of wood
constitutes good protection properties in the event of fire, thanks to its large homogenous cross-
section, according to Martinsons (n.d).
15
LITERATURE SURVEY
The steel beams are placed on a casted heel, to adjust the wanted height. After the steel beams
are placed, they are fixed with bolts and then a layer of concrete is cast. Härlanda Byggteknik
Konstruktion AB (2017) also presents this method as a connection solution. However, an
additional 300 mm thick concrete layer is added and cast on the old floor to obtain a flat surface
for the new steel beams.
Steel as a connection construction material between an extended superstructure and the existing
building, has several advantages (Jernkontoret, 2018). The higher the strength of the steel, the less
amount of material is required, and the design and products can be made lighter and thinner but
still as durable as desired. Steel offers designs of varying length and quantity to make it possible
to create gaps for installations or elevators for instance. Steel is one of the most common
structural materials due to its mechanical properties as tensile-, dynamic- and fatigue strength.
Even though Jernkontoret (2019) tries to persuade the people of how good steel is with its wide
use and recycling ability, it unfortunately has great disadvantages. The largest carbon dioxide
emissions are produced in Sweden during the process of producing steel. According to Sveriges
Natur (2019), the steel producing company SSAB accounts for the majority of the largest carbon
dioxide emissions. This corresponds to almost 12 % of the total carbon dioxide emissions in
Sweden with 4.9 million tons’ carbon dioxides during 2018.
There are great opportunities to use CLT as the load bearing structure in both outer and heart
walls and system of floor joists (Trä Guiden, 2017c).
16
LITERATURE SURVEY
softened by too much water. The soils can be put into a scale from the weakest soil to the
strongest one in the following order: mud, clay, silt, sand and gravel, moraine, rock.
The need of strengthen a foundation could also be dependent on the existing conditions. If
existing wooden piles has been exposed to air, the bearing capacity can be weakened and the
function of the foundation ceases. All existing foundations are designed a certain lifespan, where
the maximum lifespan for a steel pile foundation usually is 100 years, according to SSAB (2019).
An old foundation is usually not designed for a cooperating interaction with a new foundation,
since it is not common to be able to verify the existing foundation. Skanska (2018) has
investigated the possibility of reusing existing pile foundations by proposing recommended
investigations, which are the followings:
• Assessment of the function of the existing foundation, for example measuring the height
of the floor to obtain any differences in the level. If large differences in level are
measured, the foundation probably does not work as originally intended, which means
that existing foundation should not be used, and new piles should be installed for the
building.
• Checking the condition of the existing piles, to check if the piles are damaged. The piles
are controlled through a Pile Integrity Test (PIT). The method is only applicable once the
pile top has been exposed or decoupled from the bottom plate.
17
LITERATURE SURVEY
According to Ricardo Öjring Garcia (Personal communication, May 13th, 2020), the ability to
install drilled piles with a Källarmus and threaded pipes, the capacity is 2.5 m/hours. In very
favorable conditions, the capacity can reach up to 5.0 m/hours, however, it requires an
experienced driller, a good machine as well as free pile positions.
The piles serve as a load bearing structure that transmit horizontal and vertical loads, as both
tensile and compressive forces, to the bearing soil or rock (Hamando, 2016). The piles can be
made of steel, wood or concrete and are divided into three groups: support, friction and
cohesion. Concrete piles are commonly used in new constructions of housing buildings and to
stabilize soil banks. Steel piles are used for larger bridges and buildings, or where there is poorly
bearing soil. Hundred years ago, it was common to use wooden piles as a foundation for
buildings in very soft soils. Wooden piles are still used to a small extent as starting piles, where
cohesion piling is used at great soil depths. However, the wooden piles are being extinct due to
competent people with great experience who have gradually retired, according to Joakim Berg
(Personal communication, May 6th, 2020).
Support piles, also called end-bearing piles, transfer the load via their tip down to the underlying
rock or other solid bearing soil, but can also transfer a little part of the load via friction
(Hamando, 2016). The most common pile is the tip-borne pile where the loads are transferred
directly to the rock and can therefore, obtain the greatest bearing capacity. These piles are often
examined for both technical and economical point of view before being used. The piles can be
installed together differently out of several one-meter pipes. A cheaper method is to weld pipes
together, whereas another faster method for these short pipes is to use threaded joints, but this
needs to be tightened and is more expensive (Skanska, 2014). Piles cannot be inspected or
18
LITERATURE SURVEY
repaired afterwards, which gives the importance of being careful with both planning and
execution of the installations. The piles can be executed in different ways like driven, drilled or
shafted (Hamando, 2016).
One common method is to install a RD-pile (Figure 3.6.1b), which is a drilled steel pile which can
be performed in two steps (Skanska, 2014). Where the first step is to drill the pile into rock and
the second step, inject the pile by filling it with cement. When filling the pile with cement, it can
work as a protection against corrosion, which is preferable when piles are in contact with water,
or as an injection pile with interaction between the steel pipe and the cement. The drilled method
is common to use for reinforcement work of foundation, since this method gives less vibrations
and less subsidence than other methods. The method of drilled steel piles is a good alternative
for confined workspaces, as there are small machines that enables this. Dependent on the
conditions, it is required to drill the pile a certain distance into the rock. Another drilled support
pile is the steel core. The steel core is performed in four steps, where the first step is to drill a
RD-pile as a casing, secondly, 3 – 6 m into rock. The third step is to manufacture the steel core,
which is to cast the pipe and then, fourthly, immediately lower the steel core into the hole, meter
by meter. The advantage of steel cores is that it carries higher compressive and tensile loads,
which gives that this method is popular used by geotechnical designers. If there is no risk of
major subsidence in the building, driven steel piles can be used. These piles are driven down to
rock or to a predetermined stop criterion. This method can install RR-piles, which is a driven
steel pile. The advantage of this method is the fast execution, whereas a disadvantage is that it can
lead to large subsidence. Another disadvantage is the large difficulty of hitting obstacles in the
ground, which gives the risk to obtain an early stop, i.e. above the rock, if you hit larger blocks or
existing foundation.
Another drilled method is to perform jet grouting. Keller Grundläggning (2020) describes the
installation process as first drill the jet columns to a wanted depth where the drill rod has a nozzle
that cuts the ground at high pressure. Afterwards, the eroded soil is mixed with water and cement
in the created cavity. This method has an accessibility to be performed in confined spaces, as the
machine that perform this has a height of 2 m. According to Svelander and Åkerlind (2015), the
best results of this method is obtained in friction soils but works in other soil types. LTH (2019)
describes that the method is not suitable in silt or clay soils but can work if an upper soil layer
consists of soft soil, where the method works as a composite construction.
a) b)
Figure 3.6.1. The drilling machine Källarmus drilling a) RD-piles and b) through an obstacle. (Skanska, 2014).
19
LITERATURE SURVEY
The size of a full niche depends on the wanted pile dimension and the method of splicing, since
the accessibility is important, according to Ricardo Öjring Garcia (Personal communication,
January 23rd, 2020). The method with full niches executed in dry-stone walls requires large
volumes of sawing to create the full niche, which is very expensive according to Ricardo Öjring
Garcia (Personal communication, January 23rd, 2020). The dimensions of a full niche can vary
around 2 m in height and 1 m for both width and depth, but some of the smaller machines can
fit in a niche with a width of 0.8 m. The height of the full niche is usually with one of the two
meters below the existing floor, due to the usual excavation of the floor. After drilling a pile, the
full niche is covered again through casting. The next full niche is created with large intermediate
steps so that no openings affect the load distribution too much during full niche opening and
installation of the piles, according to Ricardo Öjring Garcia (Personal communication, January
23rd, 2020).
Depending on both the material and the quality of the wall, the minimum and maximum center
distance vary between the niche openings and therefore, also the piles (Skanska, 2014). This is to
ensure that the bearing capacity is sufficient and that the opening does not collapse, when the
next full niche is opened, even though the first full niche has got its bearing capacity back after
being reinforced with bars, filled and cast. Figure 3.6.3a and Figure 3.6.3b visualizes a full niche
while both drilling and before casting, respectively. For masonry buildings, it is grateful to work
with full niches, as mortar has a relatively low elastic modulus and distributes the load gratefully,
which makes full niches practical. However, buildings from the turn of the century that have a
dry-stone wall can be in poor condition. It can, therefore, be necessary to inject the wall initially
by grouting it with concrete to tie the stones together to obtain a homogenous wall. This can also
be done after a hole opening to stabilize the wall. Centrally placed piles with full niches are
visualized in Figure 3.6.4.
Figure 3.6.2. The prospective full niche in a dry-stone wall (Skanska, 2014).
20
LITERATURE SURVEY
a) b)
Figure 3.6.3. The full niche a) with pile installation and b) filled with reinforcement, soon to be cast (Skanska, 2014).
Figure 3.6.4. The full niche designed in a wall where the pile is centrally installed (Skanska, 2020).
21
LITERATURE SURVEY
a) b)
Figure 3.6.5. The console cantilever a) with a plate (Skanska, 2014) and b) solution with a beam (Skanska, 2020).
According to Ricardo Öjring Garcia (Personal communication, January 23rd, 2020), the ground
beam consists of an incredible amount of reinforcement laid on top of the installed piles in the
excavated area. These are later cast into a new beam, which makes it possible to distribute the loads
further down to the foundation (Figure 3.6.6). However, this method is also an eccentric method
which creates a torque and gives that the load cannot be that large.
Figure 3.6.6. The ground beam solution consisting of reinforcement and concrete (Skanska, 2020).
22
LITERATURE SURVEY
Yoke beam
If there is access to both sides of a wall, a good solution is to install a yoke beam (Figure 3.6.7),
which is a method consisting of several steps (Skanska, 2014). Firstly, you drill through the wall
where the intended yoke beam is placed. Then you excavate next to the wall on both sides, where
the two opposite placed piles are installed. Afterwards, the beam is placed through the wall and
placed on top of the head of the piles. This construction is later, cast into the wall and floor. This
method is preferable for transverse walls, due to the accessibility of both sides of a wall and makes
the distribution of the load easier to the foundation through this method due to the opposite placed
piles on each side of the wall. If there are several piles in a group or in a row, a beam can be placed
longitudinal along the wall on the piles (Figure 3.6.8). Otherwise the yoke must be tightened with
a jack after installation to ensure that the load from the wall is distributed further down to the
piles.
a) b)
Figure 3.6.8. The yoke beam with one beam through the wall and the other beam longitudinal along the wall, presented in a) one cross-section
and b) the other cross-section. (Skanska, 2020)
23
LITERATURE SURVEY
Conical hole
A method that can be used for concrete structures is a conical hole where the load is distributed
through a slab to the prospective foundation (Skanska, 2014). Inclined holes are drilled through
the concrete with a conical geometry, where the pile is installed through the hole which later is
cast to create a plug that transfers the load into the pile (Figure 3.6.9a). This method is not
preferable if there are line loads that are distributed to a slab.
Cross pile
If there is an existing foundation that can be sensitive and there is an accessibility of both sides of
a wall, the cross-pile method is preferable, but is quite exceptional (Skanska, 2014). The
advantage is that you do not have to tear down a wall or create a niche in the wall. The cross piles
of steel are installed directly into the existing wall or foundation by drilling two inclined towards
each other on each side of the wall and is later cast by injection (Figure 3.6.9b). The method
requires a qualitative material on the wall, which means that it is not suitable for masonry walls
but works well with concrete or dry-stone wall.
a) b)
Figure 3.6.9. The reinforcement method with a) conical hole and b) cross piles (Skanska, 2014).
24
LITERATURE SURVEY
• Pile: The activities required for the pile. It includes the material of the pile itself with a
factor of material waste of 10 %, together with a thread, cutting, top plate, welding the
top plate, welding the ring bit, rent of pilot, hammer and the staff that executes the work.
• Drilling: The activities required for drilling the pile with a capacity on 2.5 m/hours
including drilling aggregate, high pressure water pump, operation, fuel and staff.
• Beams and welding: The activities required to constructing and place beams. It includes
the material for the beam itself together with staff for welding.
• Casting piles: The activities required for filling the pile with concrete. It includes pump
and costs for establishment, transport, flushing of piles, unloading of returned concrete,
concrete, aggregate, waiting time and staff.
• Casting: The activities required for restoring the floor and casting full niches, ground
beams, half niches, holes in the heart walls, yoke beams and longitudinal beams and
more. It includes formwork, reinforcement, concrete, pump, costs for establishment of
pump and staff.
• Controls: The activities required for checking the pile. It includes stop-driving of piles,
straightness measurement, ultrasonic testing of welding and staff.
• Cost for project organization: Includes a tractor, workers, production manager, project
engineer, operating costs for establishment, planning and preparation.
A mark-up of 12 %, corresponding to other general costs, should be considered on the total cost.
25
LITERATURE SURVEY
According to Sten Nilsson (Personal communication, March 12th, 2020), the material of a load
bearing wall is another parameter that needs to be taken into account, since the wall can crack or
in worst case, collapse, entirely dependent on the material. If a load bearing wall consists of
masonry, the maximum spacing between the piles should be between 1.5 – 2 m. If the load
bearing wall consists of concrete, the maximum spacing should be between 3 – 5 m. If the load
bearing wall consists of a dry-stone wall, the maximum spacing should be between 2 – 3 m.
According to Aron Lindgren (Personal communication, February 20th, 2020), full niches in a dry-
stone wall shall have a minimum distance between the openings of 0.5 – 1.0 m. According to
SSAB (2019), the minimum spacing between 220 mm piles is set to a distance of 0.8 m and 170
mm piles to a minimum distance to 0.6 m. After they are installed, they are tested with a
measurement called pile driving analyzer, PDA. This is to check the magnitude of the load that
the pile carries, to ensure that the load is carried by the prospective pile, regardless of the degree
of utilization. The more piles tested, the more accurate result can be obtained and a higher
carrying capacity of the pile can be assumed.
Another parameter to consider when a building is reinforced, is the large investment in this. This
includes taking the opportunity to make premises in basements more attractive and better. As an
example, with lowering the floor and creating a better working environment. For instance,
companies can rent basements, which in turn pays off the investment costs over time, or it could
be possible to sell the area to pay off the investment. Mäklarstatistik (2020) provides a sales price
in Stockholm City with an average price of 90 900 SEK/m2 for the last 12 months.
Boverket is the Swedish National Board of Housing, Building and Planning. In their construction
and building regulations, there are both regulations and general recommendations stated.
Regulations are rules that should be followed while the general recommendation is a proposal to
fulfill a decided rule, as a regulation. (Boverket, 2018b, 2019c)
26
LITERATURE SURVEY
The construction regulations, EKS, from Boverket are together with the Eurocodes enforcement
regulations to the requirements regarding durability and resistance (Boverket, 2019a). EKS
comprises Sweden’s national choices regarding the Eurocodes. These choices make the
Eurocodes incorporated to the Swedish regulations and through this, national requirements are
stated on the Swedish structures. The Eurocodes regarding design and actions on a building
along with geotechnical work is the Eurocode 0, EN 1990, the Eurocode 1, EN 1991, and the
Eurocode 7, EN 1997. The Eurocode 0 regulates the basis of structural design, the first
Eurocode regulates actions on structures and the seventh Eurocode regulates geotechnical
design.
A building should be designed and executed in a way so the highest probability of impacting the
construction, does not lead to following consequences presented below (Boverket, 2019a). This
applies both when the construction is built and when it is used.
The partial coefficient method is the basis for the verification of the building in accordance to
EKS (SFS 2011:10). Regulations regarding the verification of an existing building and a
superstructure are presented from both the EKS (SFS 2011:10) and the Eurocodes, given in a
shorter version to only include the relevant parts.
Reliability class should be determined for both a building and a geotechnical structure, which is a
classification regarding safety. For a building, A Ch. 13 § EKS (SFS 2011:10) says:
A Ch. 13 §
“Given the extent of the personal injuries that are likely to result from a failure of a
structural member, the member is assigned to one of the following reliability classes
a) Reliability class 1 (low), minor risk of serious personal injury
b) Reliability class 2 (normal), some risk of serious personal injury, or
c) Reliability class 3 (high), major risk of serious personal injury. (BFS 2015:6)”
Regarding the reliability class for geotechnical structure, A Ch. 13 § (SFS 2011:10) says that a
geotechnical construction should also be classified regarding safety as mentioned above.
27
LITERATURE SURVEY
It depends on the construction above the geotechnical one. IEG (2010) describes that a
foundation consisting of piles should belong to reliability class 1. This is when large deformations
cannot cause collapse and the structure above cannot be used as intended or only when people
staying near the structure for exceptional cases. Foundation consisting of piles should belong to
reliability class 3 when large deformations can cause collapse of the structure above. In addition
to class 3. a large group of people is staying in or near the structure. Foundation consisting of
piles which not belongs to neither the reliability class 1 nor 3. belongs to reliability class 2.
Snow load on the roof construction should be considered when the building is verified,
according to Boverket (2019f) and EN 1991-1-3. Wind load should also be included, according to
Boverket (2019e) and EN 1991-1-4.
Global analysis of the analyzed building is a requirement according to A Ch. 6 § EKS (SFS
2011:10):
A Ch. 6 §
“Structures and structural members shall with sufficient reliability have a mechanical
resistance equal to or greater than the effect of action during construction and design
working life. The construction works shall also have static equilibrium such that the effect
of stabilizing actions is equal to or greater than the effect of destabilizing actions. (BFS
2015:6)”
Combination of loads should be applied, according to EKS (SFS 2011:10), with equation 6.10 a)
and 6.10 b) in EN 1990 when designing structural bearing capacity (STR) and geotechnical
bearing capacity (GEO) in ultimate limit state.
Designing of piles is regulated in EN 1997-1 Ch. 6. Following limit states shall be considered
when end-bearing piles are designed:
28
LITERATURE SURVEY
BBR
The building regulations, BBR, from Boverket contains rules regarding the requirements in PBL,
the Planning and Building Act. It contains all technical requirements except durability and
resistance (Boverket, 2018c). According to Boverket (2018a), requirements regarding following
aspects for both material and building technology needs to be taken into account: fire protection,
light in buildings, thermal climate, moisture security, protection against vermin, acoustics
requirements and energy conservation.
One of the two main categories that regulates the allowed total height of a building is the
requirement regarding the fire safety given in BBR. To enable a safe evacuation in occurrence of
a fire, the total height of a building needs to be determined according to the regulations presented
below. The other main category that affects the total height of a building is the allowed minimum
room height. When a superstructure is built, the height of each storey must therefore, be adjusted
to the requirements, which in turn, affects the total height of the building.
There are several requirements that could be considered, however, the regulations regarding fire
safety and the allowed minimum room height in BBR (Boverket [BBR], SFS 2011:6) are
presented in a shorter version to only include relevant parts. They are presented in numerical
order from BBR (SFS 2011:6).
General recommendation
“The distance between the rescue vehicles’ hard standing and the building’s
attack point should be less than 50 meters. If evacuation is assumed to take
place using turntable ladders or hydraulic lift platforms, the distance from
the street, rescue road or hard standing to the building wall should be a
maximum of 9 meters.”
29
LITERATURE SURVEY
“Buildings shall be designed with the type of fire protection that ensures that fire safety is
satisfactory. The design of the fire protection shall assume that a fire could occur. Fire
protection shall be designed with adequate robustness to ensure all or large parts of the fire
protection is not knocked out by individual events or stresses. Buildings shall, following
the alteration, comply with the fire protection requirements in Sections 5:1-5:7. However,
the requirements may be satisfied in a way other than that specified where the
corresponding safety level is still achieved. Deviations from the safety level may be made it
there are exceptional reasons relating to the scope of the alteration and the buildings’
conditions. Rules on allowable deviations are contained in Section 1:22 and in Sections
5:81-5:87. However, deviations must never result in unacceptable risk to human safety.”
Sweden’s membership in EU, the European Union, entails that the country is within the global
agreement regarding the climate and is obligated to consider the environmental objectives
regarding a decrease of the global warming. This regards actions like decreasing the emissions,
decreasing the use of energy, increasing the part of renewable energy and increasing the biofuel
for transports. (Svenskt trä, n.d.a)
The construction industry contributes to a large part of carbon dioxide emissions in Sweden, the
production phase is the most critical one in the construction process today. Which gives that the
choice of building material has a large influence on the environmental impact and therefore,
needs to be considered. (Boverket, 2020b)
Another study by Friberg and Karlin (2015), shows that the existing load bearing walls in a
residential building only was utilized to 20 %, which gives that the load bearing structure is
oversized and have capacity for higher loads. However, these studies from the Million
Programme were not relevant due to the year of construction and its methods used for the
foundation, material and construction of the buildings. Nonetheless, several studies have been
done regarding the capacity of the existing framework to be able to carry an additional load,
which would be relevant if an analyzed reference building consisted of concrete. The studies do
not provide any information regarding the foundation when an extended part is added on top of
the existing building and has not been analyzed in the same origin as the capacity of the
construction.
30
LITERATURE SURVEY
During the time 1880s-1920s, most residential buildings in the central part of Stockholm was
built (Riksantikvarieämbetet, n.d). This regards all parts within the city center, except the part of
Gamla Stan, since there was a minor part of the buildings built during these years. A geological
survey has been carried out within the city center of Stockholm, where this part should be carried
out by several soil investigations on site to obtain reliability of the soil strata sequence. EN 1997
gives that initially sampling of soil in a project is required before any reinforcement work of a
foundation is started. The sampling of soil gives the soil strata sequence, that is the basis for the
design of the intended foundation. However, the geological survey by using the 3D program
provided by SGU (2017), several soil strata sequences were obtained. The chosen soil strata
sequence is the one when wooden piles was used as the foundation. There were several
sequences for when this type of foundation could be used. The deepest soil layer of clay was
chosen with the argument of, the deeper layer, the more difficult it is, from a geotechnical point
of view.
The existing wooden piles for a building built during the era, are probably a hundred years old
and could be hard to verify. The piles are in a confined space with low accessibility and therefore,
requires great efforts to be able to check the conditions of them. According to Skanska (2018),
the existing piles needs to be investigated with several extensive surveys to determine the carrying
capacity. Many investigations require the existing pile to be exposed and free laid. Therefore, this
requires that the tested pile does not carry any load during the investigation, which is a difficulty
to perform when the existing building is not demolished. The differences in heights can be
measured easily, and the groundwater can be investigated. However, with certainty, this is not
enough to ensure the carrying capacity of a pile. Therefore, the carrying capacity of the existing
piles cannot be verified. This gives, for this thesis, that the existing wooden piles are assumed to
not carry any loads.
The wooden piles are intended to be installed to the bedrock, whereas, the new piles should be
anchored into the rock. With the geological conditions of a deep layer of clay, the new piles are
end-bearing piles. In confined basements, the maximum dimension of installing a pile with a
small machine that can fit into the basement was 220 mm, as well as the recommended minimum
31
LITERATURE SURVEY
dimension of pile was 220 mm according to SSAB (2019). However, one of the most common
pile dimensions was the 170/10 pile. Therefore, these two dimensions are tested for this type of
work.
The different transfer methods are applicable on different walls in a building, dependent on
accessibility and the material of the wall. For the full niche, it can be done for both outer and
transverse placed walls. It requires a center distance with at least one-half meter between the
openings of the full niches, which needs to be considered. The ground beam with half a niche is a
method that can be done for both outer and transverse placed walls. However, this method is
limited to only being possible in one cross-section, due to the assumption that it is preferable to
create a slab instead of using ground beams in two cross-sections, since the excavation is too
detailed and requires more finishing touches than a slab. The yoke beam on the other hand, is
only possible for the transverse heart walls, since it requires accessibility both sides of a wall. The
slab with half a niche is a method which has similar properties as the method with the ground
beam with half a niche. This method is only applicable if it is used on all the walls in the two
cross-sections at once, and can, therefore, not be combined to any other method. The method of
cross piles is a method that also requires an access on both sides of a wall, which gives that it is
only possible for transverse walls. However, it is only possible to perform on dry-stone wall and
therefore, it gives that this method is not be tested in this thesis, since the transverse walls
consists of masonry. The method with the console cantilever beam and its half a niche gives large
moments. Therefore, it requires an extremely large dimension of cantilever beam or that the
beam is connected with an installed strut that takes tension forces, that in turn, requires a great
need of accessibility. Hence, this method is not tested in this thesis. The method with piles in a
conical hole has an advantage of installing piles with no space limitation. Nevertheless, the
method requires that the existing floor consists of concrete and it is not suitable when loads are
distributed to the foundation through walls as line loads, since it creates extreme eccentricities.
Hence, this method is not tested in this thesis. Another important part before executing the
reinforcement work, the loads in the walls can be relieved with building props as a temporary
support that can unload the walls when executing the installment of reinforcement work.
32
LITERATURE SURVEY
laminated timber have, thanks to their large homogenous cross-sections, good protection
properties in the event of a fire (Martinsons, n.d). Cross-laminated timber is one of the most
common wood materials in load-carrying structures and has been used in previous projects
regarding exploiting superstructures (Martinsons, 2019). Therefore, no other material is
investigated. Previous studies show that wood is five times lighter than concrete. Foundation
reinforcement is expensive and the need of it can be minimized when using a lighter material, as
wood in a superstructure compared to a heavier material, as concrete. The scope of the
reinforcement work increases with heavier loads, which in turn can cause instability problems in
the ground, which is why wood is preferable for these kinds of structures.
The comparison between wood and steel show that steel is lighter and stronger than wood as a
building material (Oscarsson and Eklund, 2010). On the other hand, they also show that wood is
considerably cheaper. Svenskt trä (n.d.b) show that a large amount of carbon dioxide emissions
can be reduced when using wood instead of steel. The same applies for both costs and carbon
dioxide emissions to the comparison between concrete and wood as well (Bchar and Youssef,
2018). The advantages of using wood as a building material are superior. Along with Sweden’s
involvement in environmental objectives, wood becomes the chosen building material for the
superstructure (Svenskt trä, n.d.a).
33
34
THE CONSTRUCTED MODELS
a) b)
Figure 4.1.1. The assumed soil strata sequence in a) cross-section A and b) cross-section B.
35
THE CONSTRUCTED MODELS
Several investigations are required to determine and ensure the carrying capacity of an existing
foundation. In addition, if piles have a greater risk of being exposed by rot fungus, it is even
more important to be able to check the carrying capacity of the pile. Since the investigations
require the pile to be exposed and free laid, it is difficult to perform these in a confined
basement. Hence, the pile is assumed to not be controllable and therefore, cannot expect it to
carry any loads.
The literature survey shows that the major of the residential buildings within the city center of
Stockholm were built between 1880s-1920s. These buildings were constructed of masonry and
the model consists of 6 storeys with a basement, one stairwell and one elevator. The assumed
design of floor plan only considers the load-bearing elements and is simplified with continuous
transverse walls. Adjoining residences are assumed to enclose the building on its short ends, a
municipal owned street along its long side and a courtyard on the other side. It has a width of 20
m and a depth of 11.6 m (Figure 4.3.1). The building height is 26.8 m and is defined as the height
from the ground level to the existing roof ridge (Figure 4.3.2).
The room height in the housing is assumed to a height of 3.2 m, whereas the basement height is
determined to 2.4 m and is located 1.9 m below the ground surface. All the walls consist of
masonry and their thicknesses are assumed according to the literature survey. In the basement,
the outer walls are constructed with masonry laid on top of a dry-stone wall which has a width of
1.1 m (Figure 4.3.2). The floor in the basement is assumed to consist of a concrete slab with a
thickness of 0.2 m.
36
THE CONSTRUCTED MODELS
a) b)
4.3.2. The existing building in a) cross-section A and b) cross-section B.
To connect a superstructure with the existing building, it is assumed that the roof and the attic
floor is teared down. Since the façade of the existing buildings from this era often consist of
beautiful architecture details, the façade is wanted to be preserved. This gives that the heel
between the roof and the outer wall is extant. A new strengthen attic floor is constructed with
steel beams placed on top of the load-bearing walls to ensure that the loads are directly
distributed to the existing building. The attic floor construction has a final thickness of 73 cm and
is assumed to be adjusted with concrete heels, fixed with bolts and then a concrete slab (Figure
4.4.1).
a) b)
Figure 4.4.1. The connection construction in a) cross-section A and b) cross-section B.
37
THE CONSTRUCTED MODELS
From a sustainable and financial perspective, the superstructure is determined to consist of cross-
laminated timber. With the regulations, the maximum number of storeys is four, due to safety
aspects. To optimize the living space, the maximum allowable number of storeys is, therefore,
chosen. The height of the superstructure is calculated to 12.5 m with the chosen room height as
2.4 m. The existing building has a height of 22.5 m after the roof is teared down. The design of
floor plan is assumed to be the same as for the existing building to simplify calculations. Each
element in the superstructure and its dimension is determined according to the literature survey
(Figure 4.5.1). All calculations are given in Appendix B.
a) b)
38
THE CONSTRUCTED MODELS
The floor plan is the same for both models and is visualized in Figure 4.3.1. The first model is
visualized in Figure 4.3.2 and has a height of 26.8 m. Whereas, the second model has a height of
35 m (Figure 4.6.3). The calculations are presented in Appendix B.
a) b)
Figure 4.6.1. The walls location in a) cross-section A and b) cross-section B.
a) b)
Figure 4.6.2. The design of floor plan with the walls in a) cross-section A and b) cross-section B.
39
THE CONSTRUCTED MODELS
a) b)
40
ANALYSIS OF VERTICAL FORCES
ACTING ON THE BUILDING
The permanent loads correspond to the self-weight of the building for the two cases. This
includes exterior roof, roof trusses, attic floor, floor joists, reinforcing joists between the
superstructure and the existing building, non-load bearing walls and load-bearing walls. Whereas
the variable loads consist of snow- and residential loads.
The calculations are done for each part in the building, with its specific heaviness, thickness or
area that it acts on. The loads are distributed in its load path towards the load bearing walls that
in turn, distributes the load through a line load (Figure 4.3.1). All the loads are calculated with a
depth of 1 m into each cross-section and is therefore, presented in kN/m. All the calculations are
based on EN 1991 with EKS as guidelines and presented in Appendix C. These characteristic
values are used further on to obtain design loads for the ultimate limit state in each load-bearing
component by being differently combined according to the Eurocode. This gives that the
characteristic loads are presented separately for the permanent and the variable loads, for each
case, respectively.
Table 5.2.1. Obtained characteristic loads for cross-section A and outer wall.
Wall A1 Case 1 Case 2 Unit
Permanent load 357 391 kN/m
Variable residential load 35 58 kN/m
Variable snow load 5 5 kN/m
Long-term load 90 86 %
41
ANALYSIS OF VERTICAL FORCES
ACTING ON THE BUILDING
Table 5.2.2. Obtained characteristic loads for cross-section A and heart wall.
Wall A2 Case 1 Case 2 Unit
Permanent load 446 499 kN/m
Variable residential load 70 116 kN/m
Variable snow load 9 9 kN/m
Long-term load 85 80 %
Table 5.2.3. Obtained characteristic loads for cross-section B and outer wall.
Wall B1 Case 1 Case 2 Unit
Permanent load 442 487 kN/m
Variable residential load 54 90 kN/m
Variable snow load 7 7 kN/m
Long-term load 88 83 %
Table 5.2.4. Obtained characteristic loads for cross-section B and heart wall.
Wall B2 Case 1 Case 2 Unit
Permanent load 430 481 kN/m
Variable residential load 66 110 kN/m
Variable snow load 9 9 kN/m
Long-term load 85 80 %
42
ANALYSIS OF HORIZONTAL FORCES
ACTING ON THE BUILDING
Wind load
The wind load is calculated as a variable load that acts perpendicular towards the wall and the
roof. The load creates a moment in the foundation that is assumed to be a static moment, which
needs to be verified so it is stabilized through its self-weight. The wind load is calculated
according to EN 1991 and EKS (SFS 2011:10), and the calculations are done in an Excel spread.
Each component is calculated from the top of the superstructure down to the top of the
foundation. The heart walls in cross-section B are tested for torque created from the wind load,
since they are exposed to the force. According to EN 1991. a load set to obtain the design load
of the wind is checked and tested in the ultimate limit state. When the building is in static
equilibrium in the ultimate limit state, the wind load is the dimensioning one, namely adverse.
This gives that both the self-weight and other variable loads, as snow and residential loads, are
favorable for this case. The wind load acts on each of the four walls in cross-section B. The self-
weight and the variable load are calculated to only carry a few meters of each wall due to the
piecemeal wooden floor joists according to Aron Lindgren (Personal communication, February
20th, 2020). When the building is in static equilibrium, the wind load is acting on each floor joist.
The torque is calculated with each height of each acting wind force along with the weight of the
building that acts with an eccentricity.
Earth pressure
When the wind force is acting on one side of the building, the earth pressure is acting passively
on the opposite side, which requires it to be designed as a passive pressure. To be able to
determine if further actions is required in the geotechnical reinforcement work, a horizontal
equilibrium is analyzed for the earth pressure resultant and the total wind force. When
movements in a wall can occur due to actions, the magnitude of earth pressure and direction of
resultant forces shall be calculated, according to EN 1997. Where the resultant force is calculated
with the Rankine method, according to Das (2007). The passive earth pressure acts triangular
with a resultant force acting on a third of the total height of where the pressure acts.
43
ANALYSIS OF HORIZONTAL FORCES
ACTING ON THE BUILDING
The stabilizing moment is greater than the overturning moment for both the outer walls and for
the heart walls, which gives that no further actions is necessary. Each wall in cross-section B has
a wind load acting perpendicular to the wall on each floor joist, where these loads are summed to
a total wind load for each wall. The total wind load, including the wind load acting on the roof, is
summed up to 198 kN for the outer walls and 242 kN for the heart walls (Figure 6.2.1a). To
obtain the entire wind force for the building, each force on each wall is summed up to 879 kN.
The resulting distributed load from the passive earth pressure is calculated to 138 kN/m and is
acting per unit length of the wall (Figure 6.2.1b). The total passive resultant acts on a height of
0.6 m and is calculated to 2759 kN, which is larger than the total wind force acting on the
building (Figure 6.2.2). This gives that no further actions are required.
a) b)
Figure 6.2.1. The horizontal a) wind force on each wall and b) passive earth pressure.
44
DESIGN LOADS
7. DESIGN LOADS
For the dimensioning part, the equations 6.10a and 6.10b given in EN 1990 section 6.4.3.2, are
used for combining the loads for the structural bearing capacity. Where the equation 6.10a
includes both the permanent and the variable load as adverse. Whereas, equation 6.10b divides
the variable loads into two parts due to reduction, one non-cooperating load and one cooperating
load, where all loads are adverse. For the geotechnical bearing capacity, the alternation equation
6.10 is used. These equations and its components are explained and calculated in Appendix E.
The value of the two ultimate limit states of structural or geotechnical capacity in both case 1 and
case 2. respectively, that receives the highest value is the chosen design load, which subsequently
is checked in the numerical calculations for the foundation. All calculations are given in
Appendix E.
Table 7.2.1. Obtained design loads for case 1 in each cross-section and wall.
Load-case A: ULS for STR B: ULS for GEO C: SLS for STR & GEO Unit
Wall A1 523 445 384 kN/m
Wall A2 683 596 500 kN/m
Wall B1 660 568 484 kN/m
Wall B2 658 573 481 kN/m
45
DESIGN LOADS
Table 7.2.2. Obtained design loads for case 2 in each cross-section and wall.
Load-case A: ULS for STR B: ULS for GEO C: SLS for STR & GEO Unit
Wall A1 593 515 435 kN/m
Wall A2 804 719 586 kN/m
Wall B1 758 667 554 kN/m
Wall B2 773 691 563 kN/m
The largest value of these three load-cases in each cross-section and for each wall for the two
different cases, respectively, is the chosen value as the design load. The resulting loads are given
in the unit kN/m, which is a line load into the depth of the cross-section and are visualized in
Figure 7.2.1 and Figure 7.2.2.
a) b)
Figure 7.2.1. Obtained design loads for case 1 for a) cross-section A and b) cross-section B.
a) b)
Figure 7.2.2. Obtained design loads for case 2 for a) cross-section A and b) cross-section B.
46
ANALYSIS OF GEOTECHNICAL
REINFORCEMENT
8. ANALYSIS OF GEOTECHNICAL
REINFORCEMENT
• Pile 1: RD220/12.5
• Pile 2: RD170/10.0
In Table 8.1.1. the transfer methods are presented for which wall they can be applied to. The
capacity and resistance of the foundation are analyzed with numerical calculations, whereas the
transfer methods are analyzed with analytical calculations. These two calculations are together
done iterative. All calculations are given in Appendix F.
In the program, it is possible to obtain through numerical calculations the capacity of a certain
steel pile depending on several different input variables. It is of great importance that the
background variables are correctly entered in the program, as it influences the carrying capacity.
The program generates values of the carrying capacity for each tested pile dimension and are two
different ones for the ultimate limit state and for the serviceability limit state. The pile is tested in
structural and geotechnical bearing capacity for both states, respectively. The lowest value in
ultimate limit state is the obtained designed carrying capacity. To ensure that the new foundation
carries the load which the pile is subjected to, the certain pile is tested numerically. The used
numerical software, based on the finite element method, called RRPileCalc, is provided by SSAB.
47
ANALYSIS OF GEOTECHNICAL
REINFORCEMENT
The program makes it possible to choose between drilled or driven piles, how the piles are
supported to the building and the ground together with the surrounding geological conditions.
The program provides national regulation designing rules, as buckling resistance in the pile shaft,
which is not covered by the Eurocodes. The program has a function called “Advanced FEM”
which performs an analysis of the behavior of the designed pile with the first and second order
moments calculated, including how the ground behavior is acting around the pile. The use of the
program and interpretation of the results requires that the user has sufficient expertise within the
subject. (SSAB, 2020)
The parts that need to be considered in the design of piles are, according to IEG (2010), the
following ones divided into two parts. Where the first part is considered in the numerical
program, whereas the second part is not considered in the numerical program according to Antti
Perälä (Personal communication, March 3rd, 2020).
The program takes the following parts to into consideration during numerical calculations:
• Bearing resistance failure of the pile foundation with end bearing piles, the program
assumes that the resistance is verified by following end-of-driving criteria or by making
load tests.
• Failure in the ground due to transverse loading of the pile foundation with the
function called Advanced FEM, which calculates the resistance for horizontally loaded
piles. This also considers the resistance of the soil. The calculation is done for single piles,
which is little different than for pile groups.
• Structural failure of the pile in compression and buckling, as well as shear strength and
bending in Advanced FEM.
• Combined failure in the ground and in the pile foundation with Advanced FEM.
The failure can be either in pile or soil or both, if the resistances are close to each other.
The following parts that the program doesn’t cover are considered as follows:
• Combined failure in the ground and in the structure, it is not considered in the
program since it only considers piles and not the structure above it. Failure of the
construction is not be considered, as it is assumed to have a sufficiently bearing capacity.
• Excessive subsidence and excessive heave are not considered to be a problem due to
the end bearing pile that is drilled into the rock.
• Unacceptable vibrations are not considered to be a problem since the piles are drilled
which minimizes the vibrations and the effect on the surrounding.
According to Pålkommissionen (2014), the carrying capacity of a pile must be checked for
normal compressive force and bending torque in two different break modes to ensure it can
48
ANALYSIS OF GEOTECHNICAL
REINFORCEMENT
withstand the force and torque. One mode called material breakage, where the cross-sectional
capacity is checked, and the other mode is instability or buckling. The lowest value of either the
pile’s cross-sectional capacity or the buckling capacity is the result of the pile’s carrying capacity
for the compressive load.
There are several background variables that are entered in the program to obtain the carrying
capacity (SSAB, 2019). One variable is the steel grade, that is dependent on the pile dimension
provided by SSAB. Other variables are the lifespan of the pile, the corrosion thickness and
protection, the number of splices per buckling length and the design undrained shear strength.
The percentage of long-term load is considered in the program which affects the bed module and
the lateral resistance. The initial deflection of piles is considered by the buckling length divided by
a value depending on the soil. In the program, the geotechnical verification level is set to 3 since
it is dependent on the reliability class. This gives that it is necessary to measure 3 piles and at least
10 % of all piles with PDA according to Pålkommisionen (2014).
The design carrying capacity numerically obtained for each pile dimension needs to be larger than
the vertical load that the pile is exposed to. Each load transfer method has a given maximum
center distance for the piles, dependent on the material of the wall. This is the basis for the total
number of piles, which is analytically calculated as the width of each wall divided by the center
distance. These numbers of piles are rounded upwards to an integer. The design loads for each
wall, from Chapter 7. are analytically calculated to obtain an axial force that each pile carries that
afterwards, are compared to what it can carries at its maximum. It is necessary to add a pile until
that the axial force does not exceed the carrying capacity. To obtain the normal axial force, it is
calculated through multiplying the design load acting on each wall with the depth of the wall,
then divided by the number of piles. Since 100 % of the load from the wall is not transferred to
the pile, a safety parameter considers a certain degree of utilization. The chosen percentage of 75
% corresponds to the proportion of load that is transferred from the wall to the pile. This gives
that only 75 % of the carrying capacity are compared to the axial force. Piles are added iteratively
until the normal axial force is less than 75 % of the carrying capacity.
Each transfer method for each wall and each cross-section has geometric requirements which
affect how the piles should be placed, and therefore, the amount of piles. This requires for
instance, the number of piles to be an uneven or an even number to be placed correctly and
realistically. For cross-section A, the walls that the load is acting on is the longer walls and
therefore, the two transverse heart walls are needed to be considered in the geometry (Figure
4.6.2a). This gives that cross-section A requires an uneven number of piles, with one placed in
between the two transverse walls to make sure that the center distance does not exceed its limits.
For cross-section B, the shorter walls are the one that the load is acting on, which gives that one
transverse placed heart wall is needed to be considered in the geometry (Figure 4.6.2b). This gives
that cross-section B requires an even number of piles, to make sure that the piles are distributed
evenly on both sides of the heart wall. This gives that additional piles are added to the total
amount and therefore, requires an iteratively analytically calculation for the new axial normal
force. Each iterative calculation lowers the axial force, which lower the utilization each pile
carries.
These axial forces are inserted in the program, along with the geological conditions as the soil
strata sequence and the ground water level and numerically calculated with the function
Advanced FEM. The function exposes the pile to second order moment to obtain if the axial
force that is acting on the pile are carried by the carrying capacity and to ensure that the pile is
49
ANALYSIS OF GEOTECHNICAL
REINFORCEMENT
not exposed to buckling and cross-sectional material breakage. The length of the pile is also
entered in the function, where the average soil depth is assumed to 20 m and then one meter
drilled into rock to anchor the pile. The anchor gives that the support between the pile and the
rock is clamped, while the upper part of the pile is determined to prevent rotation and free
displacement.
This part is an iterative calculation, since if the calculated axial normal force is too large, the
cross-sectional material capacity is not enough, and the program stop proceeding with the
calculations. Then it is necessary to add a pile to the total number of piles and the axial normal
force is calculated once more, and this is repeated until the capacities are not exceeded. Each
normal axial force that each pile carries is tested for cross-sectional material capacity, instability
due to buckling capacity and the buckling length.
Table 8.3.1. The results of RD220/12.5 piles for each method for each wall and cross-section for case 1.
Type of wall Outer wall Heart wall
Type of method 1 2 4 1 2 3 4
Cross-section A 11 piles 10 piles 10 piles 11 piles 14 piles 14 piles 14 piles
Cross-section B 8 piles 8 piles 8 piles 8 piles 8 piles 8 piles 8 piles
Table 8.3.2. The results of RD170/10 piles for each method for each wall and cross-section for case 1.
Type of wall Outer wall Heart wall
Type of method 1 2 4 1 2 3 4
Cross-section A 15 piles 18 piles 18 piles 19 piles 22 piles 22 piles 22 piles
Cross-section B 12 piles 12 piles 12 piles 12 piles 12 piles 12 piles 12 piles
Table 8.3.3. The results of RD220/12.5 piles for each method for each wall and cross-section for case 2.
Type of wall Outer wall Heart wall
Type of method 1 2 4 1 2 3 4
Cross-section A 11 piles 10 piles 10 piles 13 piles 14 piles 14 piles 14 piles
Cross-section B 8 piles 8 piles 8 piles 8 piles 8 piles 8 piles 8 piles
Table 8.3.4. The results of RD170/10 piles for each method for each wall and cross-section for case 2.
Type of wall Outer wall Heart wall
Type of method 1 2 4 1 2 3 4
Cross-section A 17 piles 18 piles 18 piles 21 piles 22 piles 22 piles 22 piles
Cross-section B 12 piles 12 piles 12 piles 14 piles 16 piles 16 piles 16 piles
50
COST ESTIMATIONS FOR
GEOTECHNICAL WORK
The transfer methods are combined differently based on the ability to be combined for each wall
in each cross-section. Each cross-section has therefore, several combinations due to the
possibilities for the outer and the heart walls (Table 9.1.1). These combinations are valid for both
pile dimensions and both cases.
Table 9.1.1. The potential combinations of transfer methods for each cross-section.
Potential combinations
Wall A1: Method 1 Wall B1: Method 1
Combination 1 Combination 5
Wall A2: Method 1 Wall B2: Method 3
Wall A1: Method 1 Wall B1: Method 2
Combination 2 Combination 6
Wall A2: Method 3 Wall B2: Method 2
Wall A1: Method 2 Wall A1: Method 4
Combination 3 Combination 7
Wall A2: Method 2 Wall A2: Method 4
Wall B1: Method 1 Wall B1: Method 4
Combination 4 Combination 8
Wall B2: Method 1 Wall B2: Method 4
The combinations of transfer methods need to be combined of the two cross-sections to obtain a
final total combination. Nine total combinations are presented in Table 9.1.2.
Table 9.1.2. The potential total combinations of transfer methods for all walls.
Total combination TC 1 TC 2 TC 3 TC 4 TC 5 TC 6 TC 7 TC 8 TC 9
1 1 1 2 2 2 3 3 7
Combination
4 5 6 4 5 6 4 5 8
For each total combination, three different key performance indicators are obtained.
51
COST ESTIMATIONS FOR
GEOTECHNICAL WORK
The total cost, the number of piles and the number of installed meters for each total combination
and each case are presented in Table 9.2.1 to Table 9.2.4. The key performance indicators for
both cases and dimensions are presented in Table 9.2.5 to Table 9.2.8.
Table 9.2.1. The cost, the number of piles and installed meter for each total combination for RD220/12.5 for case 1.
Cross-section A & B Total cost Number of piles Installed meters
Total combination 1 15 272 963 SEK 65 Pcs 1365 m
Total combination 2 14 354 990 SEK 65 Pcs 1365 m
Total combination 3 13 532 087 SEK 65 Pcs 1365 m
Total combination 4 15 182 207 SEK 68 Pcs 1428 m
Total combination 5 14 264 234 SEK 68 Pcs 1428 m
Total combination 6 13 441 331 SEK 68 Pcs 1428 m
Total combination 7 13 448 090 SEK 66 Pcs 1386 m
Total combination 8 12 530 117 SEK 66 Pcs 1386 m
Total combination 9 12 724 577 SEK 66 Pcs 1386 m
Table 9.2.2. The cost, the number of piles and installed meter for each total combination for RD170/10 for case 1.
Cross-section A & B Total cost Number of piles Installed meters
Total combination 1 22 173 952 SEK 97 Pcs 2037 m
Total combination 2 20 714 556 SEK 97 Pcs 2037 m
Total combination 3 19 562 638 SEK 97 Pcs 2037 m
Total combination 4 21 503 183 SEK 100 Pcs 2100 m
Total combination 5 20 043 787 SEK 100 Pcs 2100 m
Total combination 6 18 891 870 SEK 100 Pcs 2100 m
Total combination 7 20 715 693 SEK 106 Pcs 2226 m
Total combination 8 19 256 296 SEK 106 Pcs 2226 m
Total combination 9 17 718 532 SEK 106 Pcs 2226 m
Table 9.2.3. The cost, the number of piles and installed meter for each total combination for RD220/12.5 for case 2.
Cross-section A & B Total cost Number of piles Installed meters
Total combination 1 15 721 386 SEK 67 Pcs 1407 m
Total combination 2 14 803 412 SEK 67 Pcs 1407 m
Total combination 3 13 980 510 SEK 67 Pcs 1407 m
Total combination 4 15 182 207 SEK 68 Pcs 1428 m
Total combination 5 14 264 234 SEK 68 Pcs 1428 m
Total combination 6 13 441 331 SEK 68 Pcs 1428 m
Total combination 7 13 448 090 SEK 66 Pcs 1386 m
Total combination 8 12 530 117 SEK 66 Pcs 1386 m
Total combination 9 12 724 577 SEK 66 Pcs 1386 m
52
COST ESTIMATIONS FOR
GEOTECHNICAL WORK
Table 9.2.4. The cost, the number of piles and installed meter for each total combination for RD170/10 for case 2.
Cross-section A & B Total cost Number of piles Installed meters
Total combination 1 24 830 619 SEK 109 Pcs 2289 m
Total combination 2 23 643 061 SEK 113 Pcs 2373 m
Total combination 3 22 509 877 SEK 113 Pcs 2373 m
Total combination 4 23 274 295 SEK 108 Pcs 2268 m
Total combination 5 22 086 737 SEK 112 Pcs 2352 m
Total combination 6 20 953 553 SEK 112 Pcs 2352 m
Total combination 7 21 601 248 SEK 110 Pcs 2310 m
Total combination 8 20 413 691 SEK 114 Pcs 2394 m
Total combination 9 18 731 670 SEK 114 Pcs 2394 m
Table 9.2.5. Key performance indicators for each total combination for RD220/12.5 for case 1.
Indicators Cost [SEK]/pile Cost [SEK]/m Cost [SEK]/10 m
Total combination 1 234 969 11 189 111 890
Total combination 2 220 846 10 516 105 165
Total combination 3 208 186 9 914 99 136
Total combination 4 223 268 10 632 106 318
Total combination 5 209 768 9 989 99 890
Total combination 6 197 667 9 413 94 127
Total combination 7 203 759 9 703 97 028
Total combination 8 189 850 9 040 90 405
Total combination 9 192 797 9 181 91 808
Table 9.2.6. Key performance indicators for each total combination for RD170/10 for case 1.
Indicators Cost [SEK]/pile Cost [SEK]/m Cost [SEK]/10 m
Total combination 1 228 597 10 886 108 856
Total combination 2 213 552 10 169 101 691
Total combination 3 201 677 9 604 96 037
Total combination 4 215 032 10 240 102 396
Total combination 5 200 438 9 545 95 447
Total combination 6 188 919 8 996 89 961
Total combination 7 195 431 9 306 93 062
Total combination 8 181 663 8 651 86 506
Total combination 9 167 156 7 960 79 598
Table 9.2.7. Key performance indicators for each total combination for RD220/12.5 for case 2.
Indicators Cost [SEK]/pile Cost [SEK]/m Cost [SEK]/10 m
Total combination 1 234 648 11 174 111 737
Total combination 2 220 946 10 521 105 213
Total combination 3 208 664 9 936 99 364
Total combination 4 223 268 10 632 106 318
Total combination 5 209 768 9 989 99 890
Total combination 6 197 667 9 413 94 127
Total combination 7 203 759 9 703 97 028
Total combination 8 189 850 9 040 90 405
Total combination 9 192 797 9 181 91 808
53
COST ESTIMATIONS FOR
GEOTECHNICAL WORK
Table 9.2.8. Key performance indicators for each total combination for RD170/10 for case 2.
Indicators Cost [SEK]/pile Cost [SEK]/m Cost [SEK]/10 m
Total combination 1 227 804 10 848 108 478
Total combination 2 209 231 9 963 99 634
Total combination 3 199 202 9 486 94 858
Total combination 4 215 503 10 262 102 620
Total combination 5 197 203 9 391 93 906
Total combination 6 187 085 8 909 89 088
Total combination 7 196 375 9 351 93 512
Total combination 8 179 067 8 527 85 270
Total combination 9 164 313 7 824 78 244
54
COST ASSESSMENT FOR
TOTAL CONSTRUCTION
The production cost for the superstructure is multiplied with the expanded housing area of the
four added storeys. The sales price is multiplied with the expanded housing area of the four
added storeys. For the second case, the cost for the geotechnical reinforcement work is summed
up with the production cost for the four storeys for each pile dimension. The differences in
revenues and costs are calculated for the two cases and pile dimensions to obtain the profitability.
All calculations are given in Appendix H.
Table 10.1. Results for the first case for any profitability.
Case 1 results for any profitability Magnitude Unit
Investment cost for RD220 12 530 117 SEK
Investment cost for RD170 17 718 532 SEK
Revenue for RD220 0 SEK
Revenue for RD170 0 SEK
Results for RD220 -12 530 117 SEK
Results for RD170 -17 718 532 SEK
Table 10.2. Results for the second case for any profitability.
Case 2 results for any profitability Magnitude Unit
Investment cost for RD220 32 086 717 SEK
Investment cost for RD170 38 288 270 SEK
Revenue for RD220 63 612 500 SEK
Revenue for RD170 63 612 500 SEK
Results for RD220 31 525 783 SEK
Results for RD170 25 324 230 SEK
55
56
DISCUSSION
11. DISCUSSION
11.1 Potential use of existing foundation
The existing wooden piles are assumed to not carry any load as an action of safety, due to the
difficulties to perform necessary investigations to ensure the carrying capacity of the existing
foundation. However, the existing wooden piles does carry the existing building as it is standing
today. This means that some of the existing piles does carry loads and therefore, enables reuse or
interaction with a new foundation. To perform such an action in the geotechnical reinforcement
work, the piles requires to be controllable for these investigations. If this kind of actions would
be possible in a real project, it could reduce the extent of the geotechnical reinforcement work.
Therefore, reduce both the costs and the environmental impact. If a geotechnical reinforcement
work is not performed when a building is extended, the existing foundation is overloaded since it
is not designed to carry additional load.
Several studies show that the capacity of the existing frameworks consisting of concrete has a
potential to carry more loads than what they do. Similar studies regarding masonry buildings has
been lacking, and is therefore, needed to be done for a real project. In this thesis, no control over
the stability of the structure and its ability to carry a superstructure without collapsing has been
made. This could have an effect and requires to be considered in a real project.
57
DISCUSSION
In a real project, where geotechnical reinforcement work is needed, the walls should be examined
to be able to withstand additional loads. If there is a lot of cracks and subsidence in an old
building, the material of the walls can be poor and therefore, hard to ensure that they can
withhold the distributed loads. Therefore, a recommendation is to use a smaller center distance
between the piles according to Sten Nilsson (Personal communication, March 12th, 2020).
The degree of the utilization regards the portion of load that is transferred from the walls to the
piles. This value depends, among other things, on the carrying capacity and the firmness of the
existing walls. As well as how well the interaction between the existing walls and the foundation
is designed, with the center distance considered. The degree of utilization provides a reality image
of what is reasonably conveyed to the foundation when the walls consists of the determined
material and is an important action of safety. This percentage can change based on changed
conditions or presumptions.
Since a hypothetical object is analyzed, any detailed development plans are not considered. This
can delimit the possibility of expanding a building or regulate the allowed number of storeys for a
building. The geotechnical reinforcement work can be affected by this and a different result can
be obtained. Therefore, this needs to be considered in a real project.
One parameter that has influenced this study is the assistance provided by the industry. Since
most of the knowledge is not provided through previous research in this subject, the knowledge
is acquired through reliable discussions with the knowledgeable industry's individuals. What is
mostly affected are the question marks that are wanted to be clarified through conversations
with, for example, knowledgeable individuals within construction for both building and
geotechnics. The problem that arose was that both parties referred to each other and that there
was no clear boundary between the parties. They gave different answers on the same questions
and it was clear that there exist weaknesses in the interaction between the parties.
58
DISCUSSION
mind that a minimum center distance between the openings of the full niches are of great
importance due to the risk of instability problems. At the same time, the distance must not be too
far in between, considering the material of the wall, as it must both withstand and distribute the
loads. Therefore, during construction, full niches should be performed in an order that cannot
cause these problems. This gives that they are often executed every third or fourth one, so the
full niches can regain its stability before opening of the next one. However, this minimum and
maximum distance is highly dependent on the material of the wall, which in turn comprises the
structure stability. Unfortunate, it is difficult to do samplings on whether the wall has a great
firmness or not, which gives the difficulty of obtaining plain guidelines for the range of center
distances. A dry-stone wall has higher solidity, firmness and greater strength than masonry walls
for instance, but lower ones comparing to concrete. Nonetheless, the stability is also affected by
the ground beam, the yoke beam and the slab, since the methods requires an excavation in the
walls, as well as in the floor and in the soil. The stability for these methods is mostly dependent
on the center distance, since it is a hole that is created through the wall. This gives that the
stability of the wall must be maintained, since the hole punching affects the overall stability of the
wall due to the center distance.
For the other transfer methods that are not analyzed in this thesis, this does not mean that they
are more expensive or less efficient than the analyzed methods. These methods are not possible
to test due to the selected hypothetical object, which makes it difficult to determine which of all
the methods is the most advantageous one. Since each object is unique, it is needed to review
each method to ensure the relevance for each specific project. This also includes the various
combinations that can be made when all methods are reviewed to obtain the cheapest alternative,
since the economical part is critical in a project to be able to be competitive in a tender process
for instance. Each unique object based on material selection, access and permits generates
different applicable methods and can therefore, give different cost results. All methods are,
therefore, not applicable to all projects which gives that these key figures and estimated costs
cannot be fully applied to another project.
59
DISCUSSION
addressed in this thesis, and the workable methods for this type of building have been analyzed.
The obtained key indicators can be used and applied on identical buildings to estimate the costs
for a geotechnical reinforcement work. These key ratios can be multiplied with a new amount of
piles in another project to be able to estimate the costs, since they depend on the numbers and
lengths of the piles. The key performance indicators can be a powerful tool when analyzing the
profitability of a certain superstructure project. However, if the building is not identical, as
deviations in the number of storeys or consists of another material, these key ratios cannot be
applicable.
The three key ratios presented in Chapter 9.2 are dependent on the number of piles, that in turn,
are dependent on the different combinations of load transfer methods. The indicators differ
between the two pile dimensions, but to a small extent. For the larger pile, the key ratios are
slightly larger than for the smaller dimension, since the larger pile dimension requires fewer
number of piles. The estimation shows that the smaller pile dimension requires a larger amount
of piles to carry the design load, which leads to an increased total cost. Between the two cases,
both the dimensions show that the key ratios are slightly larger for the first case than for the
second case. The second case has marginally lower key ratios, since it requires an increased
number of piles.
By combining these methods, the most cost-efficient geotechnical work is obtained. Where using
the larger pile, the cheapest combination consists of using ground beams, full niches and yoke
beams. Whereas, using the smaller pile, the cheapest combination is the slab. The results show
that the slab solution is the cheapest combination when the amount of piles is so great. The most
expensive combination for both pile dimension is the full niche used on all walls. All these results
apply for both cases. There is a significantly difference between the cheapest and the most
expensive total combination for both pile dimensions and both cases. This entails that it is
necessary to check, compare and combine the different load transfer methods, to determine the
cheapest geotechnical reinforcement work.
The cost estimation shows that the larger pile dimension gives a significantly cheaper final cost
compared to the smaller dimension. For the first case, the cost increased with an average value of
45 % when using the smaller pile compared to the larger pile. For the second case, the cost
increased with an average value of 57 % when using the smaller pile compared to the larger pile.
60
DISCUSSION
Hence, the most cost-effective solution is the large pile due to the large cost difference compared
to the smaller dimension. Therefore, one should try to minimize the number of piles, as it would
minimize the total cost of the project. However, the method that is the cheapest or the one that
gives the less amount of piles, does not necessarily need to be the production-friendliest one. If a
larger machine could be used, it could give an advantage in the capacity to execute the installation
of the piles. From the provided costs, the capacity of executing each activity in each method is
determined. A larger machine would reduce the necessary time for installation and therefore,
minimize the costs. However, the costs for the project organization depends on the project
duration. In a real project, the need of producing a detailed time schedule is necessary, as the
capacity of each activity affects the total duration. As an example, the waiting time should be
considered in the scheduling and by planning the work well it could be minimized. However, the
capacity for each activity could be difficult to determine in advance, which means that the costs
of the project organization, among others, can be significantly affected. When the project
organization costs are added, it is clearly that the amount of piles influences the final cost. Since
the final cost depends on the project duration, which in turn, depends on the number of piles.
The costs of the project organization constitute a large part of the total cost and entail greater
costs the longer the project proceeds. However, the total combination with the smallest amount
of piles does not necessarily give the cheapest total cost. This proves that the choice of transfer
method also affects the final total cost.
For the larger pile, the cost does not increase when a superstructure is built. However, for the
smaller pile, the cost increases with 6 % when the existing building is expanded with a
superstructure. Both the costs for the larger and the smaller pile dimensions corresponds to the
two cheapest combinations. Hence, the superstructure does not affect the total cost when using
the larger pile dimension. This gives that the intervention in the foundation is just as great for the
geotechnical reinforcement work for the existing building compared to extending it with a
superstructure.
11.10 Profitability
The cost for geotechnical work and the production cost for the superstructure is summed up and
is significantly lower than the sales price within the city center of Stockholm. However, the
geotechnical reinforcement work has not considered profits, risks or opportunities, such as
unforeseen costs. Neither does the production costs for the superstructure refer to what extent
that considers manufacturing or how they are allocated in the costs. The production costs do not
refer if costs for demolishing the existing roof or costs for reinforcing an existing framework are
considered, which are costs that must be considered in a real project. Which, of course, can affect
that the cost can change when these parameters are considered. However, the margin between
the revenue and the investment cost when applying a superstructure is sufficiently large, it
61
DISCUSSION
62
CONCLUSIONS
12. CONCLUSIONS
Within city center of Stockholm, most of the buildings was built during 1880s-1920s. These
buildings were founded on wooden piles where the geological conditions consisted of clay. These
piles are exposed to a risk of losing their carrying capacity due to the increasing land elevation.
The carrying capacity of the existing wooden piles must be ensured by several investigations,
which is difficult to perform in confined spaces. Therefore, a new foundation is required. With
the deep layer of clay in a densely populated area and the great risk of encounter obstacles in the
ground, the new foundation consists of drilled end-bearing steel piles, either of dimension
RD220/12.5 or RD170/10. A superstructure consisting of four storeys of wood are applied and
entails additional loads. The possible geotechnical reinforcement work that will transfer the loads
in this type of existing building are full niches, ground beam with half a niche, yoke beams and
slab with half a niche.
For the larger pile dimension in the existing building, the required amount is 65 – 68 piles
depending on how the transfer methods are combined. When the existing building is expanded
with a superstructure, the required amount is 66 – 68 piles. The superstructure entails no
substantially difference in the required amount of piles. Depending on how the transfer methods
are combined, the total cost for the geotechnical work in the existing building varies between
12.5 – 15.3 million SEK. When it is expanded with a superstructure, the total cost varies between
12.5 – 15.7 million SEK. For the cheapest possible geotechnical work, the superstructure entails
no difference in the cost. The investment cost for both the strengthening work and the
production of the superstructure is lower than the revenue, which gives a profit of 31.5 million
SEK. This gives that it is profitable to extend a building with a superstructure when the existing
foundation is strengthened with RD220/12.5 piles.
For the smaller pile dimension in the existing building, the required amount is 97 – 106 piles and
with an added superstructure, 108 – 114 piles. The superstructure entails a difference of
maximum 17 piles in the required amount. The total cost for the geotechnical work in the
existing building varies between 17.7 – 22.2 million SEK. When a superstructure is added, the
total cost varies between 18.7 – 24.8 million SEK. For the cheapest geotechnical work obtained,
the superstructure entails a difference in the cost of 1 million SEK. The investment cost for both
the strengthening work and the production of the superstructure is lower than the revenue,
which gives a profit of 25.3 million SEK. This gives that it is profitable to extend a building with
a superstructure when the existing foundation is strengthened with RD170/10 piles.
This study show that the larger pile provides the cheapest geotechnical reinforcement and no
differences in amount of piles and costs are obtained when a superstructure is applied on an
existing building in Stockholm. The revenue from a superstructure is so great, that the
profitability is a fact.
63
64
REFERENCES
REFERENCES
Bchar, P., Youssef, R. (2018). Bygga till ett våningsplan på befintligt flerbostadshus. Bachelor thesis, The
Royal Institute of Technology, Stockholm. Retrieved 2020-01-27 from: http://www.diva-
portal.org/smash/get/diva2:1229378/FULLTEXT01.pdf
Bjerking, S-E. (1974). Ombyggnad, Hur bostadshusen 1880–1940. (Statens institut för
byggnadsforskning). Stockholm: Svensk byggtjänst. Retrieved 2020-01-20 from:
http://www.byggnadsmaterial.lth.se/fileadmin/byggnadsmaterial/BFR-publ/BFR_1974-
R32.pdf
Björk, C., Kallstenius, P., Reppen, L. (2013). Så byggdes husen 1880–2000: arkitektur, konstruktion och
material i våra flerbostadshus under 120 år. Stockholm: AB Svensk Byggtjänst
Boverkets föreskrifter om ändring i Boverkets föreskrifter och allmänna råd (2011:10) om tillämpning av
europeiska konstruktionsstandarder (Eurokoder) (SFS 2011:10). Retrieved from Boverkets website:
https://rinfo.boverket.se/EKS/PDF/BFS2019-1-EKS-11.pdf
Boverket. (2018b). Föreskrifter och allmänna råd i Boverkets byggregler. Retrieved 2020-01-23 from:
https://www.boverket.se/sv/PBL-kunskapsbanken/regler-om-byggande/boverkets-
byggregler/om-bbr/foreskrifter-och-allmanna-rad/
Boverket. (2019b). Eurokoder och nationella val i EKS. Retrieved 2020-01-22 from
https://www.boverket.se/sv/PBL-kunskapsbanken/regler-om-byggande/boverkets-
konstruktionsregler/overgripande-bestammelser/nationella-val-i-eks/
Boverket. (2019c). Föreskrifter och allmänna råd i EKS. Retrieved 2020-01-22 from
https://www.boverket.se/sv/PBL-kunskapsbanken/regler-om-byggande/boverkets-
konstruktionsregler/om-eks/foreskrifter-och-allmanna-rad/
65
REFERENCES
Erlandsson, M. (2010). Miljödata för krossprodukter och naturgrus. Retrieved 2020-02-24 from:
https://www.ivl.se/download/18.343dc99d14e8bb0f58b76e6/1449742446674/C12.pdf
Eurocode 0: The basis of structural design. (EN 1990). Brussels: The European Union
Eurocode 1: Actions on structures - Part 1-1: General actions - Densities, self-weight, imposed loads for buildings
(EN 1991-1-1). Brussels: The European Union
Eurocode 1: Actions on structures - Part 1-3: General actions - Snow loads (EN 1991-1-3). Brussels: The
European Union
Eurocode 1: Actions on structures - Part 1-4: General actions - Wind actions (EN 1991-1-4). Brussels: The
European Union
Eurocode 7: Geotechnical design - Part 1: General rules (EN 1997-1). Brussels: The European Union
66
REFERENCES
Husgrunder (2015). Vad kostar det att förstärka sin grund. Retrieved 2020-01-22 from:
https://www.husgrunder.com/renovera-husgrund/kostnad-grundforstarkning/
Härlanda Byggteknik Konstruktion AB. (2017). Stomutredning för påbyggnad. Retrieved 2020-01-03
from: https://docplayer.se/110702180-Stomutredning-for-pabyggnad.html
Karlsson, J. (2017). Life cycle assessment of two multi-family houses - A comparative study between frame of
concrete and frame of CLT. Master thesis, Karlstads University, Karlstad. Retrieved from
http://www.diva-portal.org/smash/get/diva2:1116790/FULLTEXT01.pdf
Karlsson, V., Rosin, E. (2018). Analys av äldre murverkshus - Gällande befintliga byggnadens
förutsättningar för påbyggnad. Bachelor thesis, The Royal Institute of Technology, Stockholm.
Retrieved 2020-01-20 from: http://www.diva-
portal.org/smash/get/diva2:1229600/FULLTEXT01.pdf
Klintberg, A., Åkehag, Johnny. (2017). Träbjälklag med tung fyllning - Bjälklag framtaget med inspiration
av byggteknik från sekelskiftet 1800–1900. Bachelor thesis, The Royal Institute of Technology,
Stockholm. Retrieved 2020-02-05 from:
https://www.diva-portal.org/smash/get/diva2:1139336/FULLTEXT01.pdf
Lidgren, C. & Widerberg, C., (2010). SBUF Rapport, Våningspåbyggnad av hus från miljonprogrammet.
Retrieved 2020-01-21 from:
https://vpp.sbuf.se/Public/Documents/ProjectDocuments/650e245c-315d-4186-a9b3-
6246e0c03cf1/FinalReport/SBUF%2012194%20Slutrapport%20Våningspåbyggnad%20av%20h
us%20från%20miljonprogrammet.pdf
67
REFERENCES
Martinsons. (2019). Påbyggnader för bostäder och kontor. Retrieved 2020-01-23 from:
https://martinsons.se/wp-content/uploads/2019/11/martinsons_pabyggnader_low.pdf
Mäklarstatistik. (2020). Prisutveckling under 48 månader för bostadsrätter i centrala Stockholm. Retrieved
2020-01-21 from:
https://www.maklarstatistik.se/omrade/riket/stockholms-lan/stockholm/centrala-
stockholm/#/bostadsratter/48m
Nedrén, D., Rinaldo, G. (2018). Miljonprogrammet - Uppbyggnad och påbyggnad. Bachelor thesis,
Chalmers University of Technology, Gothenburg. Retrieved 2020-01-27 from:
https://odr.chalmers.se/bitstream/20.500.12380/255615/1/255615.pdf
Oscarsson, A., Eklund, J. (2010). Påbyggnad av våningsplan med lättkonstruktion - En jämförelse av stom
materialen trä och tunnplåt. Bachelor thesis, Uppsala University, Uppsala. Retrieved 2020-01-27
from: http://www.diva-portal.org/smash/get/diva2:661011/FULLTEXT01.pdf
Plan- och bygglagen (SFS 2010:900). Retrieved from Sweden’s parliaments website:
https://www.riksdagen.se/sv/dokument-lagar/dokument/svensk-forfattningssamling/plan--
och-bygglag-2010900_sfs-2010-900
Pålkommissionen. (2014). Verifiering av geoteknisk bärförmåga för pålar enligt Eurokod. Stockholm:
Svensk Byggtjänst. Retrieved 2020-02-25 from:
http://www.palkommissionen.org/getfile.ashx?cid=481683&cc=3&refid=1
Skanska. (2014). Grundläggning [Internal program regarding foundations, Adobe Flash]. Retrieved
2020-02-03.
Skanska. (2020). Foundation drawings and costs [Internal drawings and costs for activities within
reinforcement work and foundation]. Retrieved 2020-03-10.
68
REFERENCES
Statistiska centralbyrån. (2019). Befolkningen i Stockholms län 31 mars 2019. Retrieved 2019-11-26
from:
https://www.sll.se/globalassets/4.-regional-utveckling/publicerade-dokument/statistik-
befolkning-stockhoms-lan-q1-2019.pdf
Svenskt trä. (n.d.a). Trä är ett hållbart byggmaterial. Retrieved 2020-01-21 from
https://www.svenskttra.se/om-tra/att-valja-tra/tra-och-miljo/tra-ar-ett-hallbart-byggmaterial/
Sveriges Natur. (2019). De släppte ut mest koldioxid 2018. Retrieved 2020-01-24 from:
http://www.sverigesnatur.org/aktuellt/de-slappte-ut-mest-koldioxid-2018/
Swedish Geotechnical Institute. 2008. Information 1. Jords egenskaper. Retrieved 2020-02-19 from:
https://www.swedgeo.se/globalassets/publikationer/info/pdf/sgi-i1.pdf
69
REFERENCES
Trä Guiden. (2017d). Dimensionerande last för takbalkar och takstolar. Retrieved 2020-02-12 from:
https://www.traguiden.se/konstruktion/limtrakonstruktioner/fakta-om-
limtra/projektering/overslagsdimensionering/dimensionerande-last-for-takbalkar-och-takstolar/
Trä Guiden. (2019). Sadelbalkar av limträ i ett fack. Retrieved 2020-01-30 from:
https://www.traguiden.se/konstruktion/dimensionering/hjalpmedel---tabeller/tak/sadelbalkar-
av-limtra-i-ett-fack/?previousState=000100
Wahlgren, Carl-Henric., Schoning, Kristian., Tenne, Mats and Hansen M, Lars. (2018).
Stockholmsområdets berggrund, jordarter, geologiska utveckling och erfarenheter från infrastrukturprojekt.
Retreived 2020-01-12 from: https://resource.sgu.se/produkter/sgurapp/s1808-rapport.pdf
Åhs, M. (2012). SBUF Rapport, Fuktegenskaper för byggnadsmaterial. Retrieved 2020-02-24 from:
https://vpp.sbuf.se/Public/Documents/ProjectDocuments/db6a21fd-7e42-4db9-89d9-
346eac7cf117/FinalReport/SBUF%2012210%20Slutrapport%20Fuktegenskaper%20f%C3%B6r
%20byggnadsmaterial%20-%20en%20litteraturstudie.pdf
70
TABLE OF CONTENT FOR APPENDICES
71
72
APPENDIX A
APPENDIX A
This appendix consists of following parts with the use of EKS,
Eurocode & other references
Part 1. Existing building properties
Part 1a. Allowed distances according to BBR
The maximum allowed distance between the fire-fighting vehicle and the point of fire attack is 50
m. The maximum distance between the street, rescue path or installation site to the wall of the
house is not allowed to exceed 9 m. The allowed number of storeys are 10 when only having one
elevator. If the storeys exceed 10, a second elevator is required according to BBR (SFS 2011:6).
The material that the existing wall consists of is masonry bricks, which has the density of 1600
kg/m3 according to Åhs (2012). For each density, a heaviness can be obtained with multiplying it
with the gravity constant as following equation: " = ( ∙ 8. This gives that the heaviness for
masonry brick is 16 kN/m3. The thickness of the wall differs depending on which floor it is. One
masonry brick is 12”, where 1” is 25.4 mm thick and according to Bjerking (1974), is the number
of bricks and the heights of the walls distributed in Table A1.
The floor consists of several materials explained above, where the attic is the same, except adding
a layer of masonry bricks that has a thickness of 62 mm. The thickness of the other materials in
73
APPENDIX A
the floor is the following: plaster with 63.5 mm and wooden floor with 50.8 mm. The beams are
inside the layer of both filling and blind bottom. The layer of filling and beams is 177.8 mm thick
and the layer of beams and blind bottom is 76.2 mm. These layers have a distribution of 2.5 %
wooden beams of pine and 97.5 % fill, respectively blind bottom. (Bjerking, 1974)
The bottom floor is different from the other floors and consists of the following materials:
masonry bricks, wooden floor, filling and beams, steel beams. The thickness of the layers differs
from the other floors as well. The thickness that differs is the fill and beams with a thickness of
311 mm and the masonry bricks with 152 mm. This gives a percentage increase of 175 % for
filling and beams and 245 % for the masonry bricks. (Bjerking, 1974)
74
APPENDIX A
The beam is shaped like a saddle beam and has a slope of 3.7°. The dimensions are dependent on
the snow zone, which is 2 kN/m2 for Stockholm. Therefore, a beam is chosen where the lowest
height of the beam is 405 mm, whereas the largest height of the beam is 780 mm. The width of
the beam is 115 mm, the span for the beam can be used up to 12 m and be placed with a center
distance of 1.2 m. The load of the material on top of the beam, called the outer roof, is 0.85
kN/m2 with a thickness of 300 mm, consisting of insulation and a layer of protection against
moisture and wind. (Träguiden, 2019)
75
APPENDIX A
76
APPENDIX A
Table A2. Values for external pressure coefficients for Figure A3. Factors on each zone.
vertical walls of rectangular plan buildings.
Table A3. Values for external pressure coefficients for flat roofs.
77
APPENDIX A
78
APPENDIX A
79
APPENDIX A
Table A8. The values of corrosion due to lifecycle and target service life.
80
APPENDIX A
The bed module coefficient, A, due to short- or long-term loads is 50 for long-term and 150 for
short-term (SSAB, 2019). The coefficient of extreme value of lateral resistance, B, due to short- or
long-term loads is 6 for long-term and 9 for short-term. The values of A and B are interpolated in
the program dependent on the percentage of long-term load.
Initial deflection of piles is, according to SSAB (2019), a value of %1 = <-2 /400 for cohesive
soils and %1 = <-2 /300 for friction soils. The initial deflection may be affected by the number of
splices per buckling length. If more splices would be used, the structural bearing capacity in
service limit state changes, but not the capacity in the ultimate limit state. Since the layer of soil
consists of both friction soil and clay, the worst case is chosen, which gives %1 = <-2 /300. Since
the magnitude on the radius of curvature of the pile is significantly smaller in coarse-grained soil
layers, due to the lateral support than in cohesive soil layers.
81
APPENDIX A
Part 8. Costs
All costs in this chapter between Part 8a to Part 8f includes geotechnical reinforcement work and
are provided by Skanska (2020). The costs are given by a cost estimation in an internal program
regarding calculations and tenders. These costs include a factor of waste and a factor of capacity.
Whereas Part 8g includes costs involving the superstructure.
82
APPENDIX A
83
APPENDIX A
The land elevation in Stockholm is presented in Figure A4, according to SMHI (2011).
84
APPENDIX B
APPENDIX B
Analytical calculations of storeys extended
1. Input data
Table B1. Distance restrictions according to BBR (SFS 2011:6).
Allowed properties for safety Symbol Magnitude Unit Reference
Maximum distance between
ℎ0#2'82.-C63'0&-%( 50 m Appendix A, part 1a
fire truck and the point of fire
Maximum distance between
ℎ0#2'7(8=63'0&-%( 9 m Appendix A, part 1a
fire truck and the building
Maximum number of floors
that requires only one elevator ?)(E 10 Pcs Appendix A, part 1a
2. Calculations
When demolishing the existing roof (Figure B1), the total height of the building excluding the
attic is obtained by subtracting the height of the attic from the total existing height through
following equation:
85
APPENDIX B
Using Pythagorean theorem referred to the given requirements in BBR (2011:6), the maximum
allowed height of the building with the extension is calculated with following equation:
@ @
^ℎ0#2'82.-C63'0&-%( _ = (ℎ(""5;'% )@ + ^ℎ0#2'7(8=63'0&-%( _ → ℎ(""5;'% ≈ 49 R
The allowed vertical height of the building due to the fire safety is chosen to be 48 m, as an
action of safety. The maximum allowed height of the extension is determined by subtracting the
height of the existing building from the allowed height as follows:
The allowed number of storeys can therefore be calculated from the given data according to:
The maximum number of storeys are therefore, determined to 8, since it is rounded down.
According to the maximum number of storeys, due to the requirement regarding rescue
elevators, the maximum possible number of storeys are therefore, calculated as follows:
This gives a new total height of the extension through following equation:
The new total height of the building with both the existing and the extended part is obtained
through following equation:
The obtained total height is checked with the requirements of the maximum allowed building
height, according to the BBR (2011:6), as follows:
This gives that the requirement is fulfilled, which gives that the total number of storeys for the
existing building and the superstructure is calculated to 10 with a total height of 35 m, where the
extended building consists of 4 storeys.
86
APPENDIX C
APPENDIX C
Analytical calculations of load distribution
1. Input data
Table C1. Building properties of the total building
Total building properties Symbol Magnitude Unit Reference
Width of the building / 11.6 m Appendix A, part 1b
Depth of the building 2 20 m Appendix A, part 1b
No. of floors existing ?'E#&8#$1 6 Pcs Appendix A, part 1b
Indoor height of a floor ℎ0"552 2.4 m Appendix A, part 2a
No. of floors extended ?'E8'$%'% 4 Pcs Appendix B
Height the building ℎ!.#"%#$1 35 m Appendix B
87
APPENDIX C
Table C6. Properties of loads for both existing and the extended part.
Heaviness Symbol Magnitude Unit Reference
Load of residential load B2'&#%'$8#(" 2 kN/m2 Appendix A, part 2d
Non-bearing walls B$5$G!'(2#$1 0.2 kN/m2 Appendix A, part 2e
Bearing walls in extension B!'(2#$1 1.3 kN/m2 Appendix A, part 2e
88
APPENDIX C
2.1 Cross-section A
The first cross-section is visualized in Figure C1a for the total building and in Figure C1b for the
existing building. The distances that each wall carries are determined according to symmetry,
where the heart wall is placed in the half of the width. This gives that the two outer walls have
the same load distribution.
a) b)
Figure C1. Cross-section A for a) the total building and for b) the existing building.
The saddle beam (Figure C2) has two heights, h and H. The difference between these heights are
h’, which is the height visualized in Figure C3 and calculated as follows:
ℎS = 9 − ℎ = 0.375 R
89
APPENDIX C
Figure C3. Cross-section on the top of the saddle beam, showing where the walls are placed.
The load that is distributed from the roof towards the foundation through the whole building is
distributed between the two outer walls and the centrally placed heart wall. The width that the
outer walls takes is the width divided by 4, whereas the heart wall takes the width divided by 2
(Figure C3). The inclined length, L, according to Pythagorean theorem (Figure C3), is calculated
through following:
@
/
< = gℎS@ + h i = 5.81 R
2
The beams on the roof are placed with a center distance of 1200 mm, where the area that one
beam carries is calculated as follows:
2 ∙ < ∙ 2
-2550 = = 2 ∙ < ∙ 1.2 = 13.95 R@
2
1.2
9+ℎ
I!'() = K ∙ ∙ / = 0.79 RT
2
The heaviness from the roof truss is therefore:
I!'() ∙ "*+,
B25500$5'' = = 0.28 j>/R@
-2550
Another load that is acting on the roof is the snow load. It is calculated through following
equation:
The existing floor is consisting of several materials. To obtain the heaviness of the composite
parts in the floor, they are calculated with the distribution of a certain percentage as follows:
90
APPENDIX C
The attic is also consisting of several materials. To obtain the load, it is calculated as follows:
The bottom floor is also a composite floor, consisting of several materials. To obtain the load, it
is calculated as follows:
The loads of the walls depend on the number of bricks in each wall. To obtain the load of each
wall it is calculated with the amount of bricks as follows:
For the loads that acts and are distributed in the outer wall, the distance of the width
/ = 11.6 R is divided by 4.
/
825500$5'' C) = B25500$5'' ∙ = 0.82 j>/R
4
The self-weight of the outer roof is given by:
/
82550C) = B2550 ∙ = 2.47 j>/R
4
The self-weight of the floor joist is given by:
/
80"552C) = B0"552 ∙ ∙? = 16.82 j>/R
4 'E8'$%'%
91
APPENDIX C
/
8$5$G!'(2#$1(20 C) = B$5$G!'(2#$1 ∙ ∙? = 2.32 j>/R
4 'E8'$%'%
/
8&8''"LA = B&8''" ∙ = 2.9 j>/R
4
To obtain the self-weight for an existing floor, it is calculated as follows:
/
80"552(23'03-4 LA = B0"552(23'03-4 · ∙ ?'E#&8#$1 = 98.23 j>/R
4
The self-weight for the attic is calculated as follows:
/
8(88#-LA = B(88#- · = 19.25 j>/R
4
The self-weight for the bottom floor is calculated as follows:
/
80"552/#00#1 LA = B0"552/#00#1 · = 26.54 j>/R
4
8;(""LA = BA.V/$3%B · ℎ;(""*DE · ?'E#&8#$1 + B@/$3%B · ℎ;("") + BT/$3%B · ℎ;(""+ = 203.34 j>/R
/
8$5$G!'(2#$1(23 C) = B$5$G!'(2#$1 ∙ ∙? = 3.48 j>/R
4 'E#&8#$1
This is summarized without the roof on the existing building to:
8'E#&8#$1C) = 353.73 j>/R
92
APPENDIX C
Variable loads from both the extended and the existing part
The variable load of the snow that is acting on the outer wall is calculated to be the following:
<
B&$5;LA = B&$5; ∙ = 4.65 j>/R
2
The variable residential load that is acting on the outer walls are calculated to be the following:
/
B2'&#%'$8#("LA(23'03-4 = B2'&#%'$8#(" ∙ ∙ ?'E#&8#$1 = 34.8 j>/R
4
/
B2'&#%'$8#("LA(20(-6(6 = B2'&#%'$8#(" ∙ ∙ ?'E8'$%'% = 23.2 j>/R
4
Summary of variable loads from both the extended and the existing part
The variable load for the outer walls in section A is summarized into two parts, one for the
existing building and the second for the total building:
Summary of permanent loads from both the extended and the existing part
The self-weight for the outer walls in section A is summarized into two parts, one for the existing
building and the second for the total building:
For the load that acts and are distributed in the heart wall, the distance of the width / = 11.6 R
is divided by 2.
/
825500$5'' = B25500$5'' ∙ = 1.64 j>/R
C* 2
The self-weight of the outer roof is given by:
/
82550C* = B2550 ∙ = 4.94 j>/R
2
93
APPENDIX C
/
80"552C* = B0"552 ∙ ∙? = 33.6 j>/R
2 'E8'$%'%
The self-weight of the bearing walls is given by:
!
8$5$G!'(2#$1(20 C* = B$5$G!'(2#$1 ∙ @ ∙ ?'E8'$%'% = 4.64 j>/R
/
8&8''"L@ = B&8''" ∙ = 5.8 j>/R
2
To obtain the self-weight for an existing floor, it is calculated as follows:
/
80"552(23'03-4 L@ = B0"552(23'03-4 · ∙? = 196.45 j>/R
2 'E#&8#$1
/
8(88#-L@ = B(88#- · = 38.5 j>/R
2
The self-weight for the bottom floor is calculated as follows:
/
80"552/#00#1 L@ = B0"552/#00#1 · = 53.08 j>/R
2
The self-weight for the heart wall is calculated as follows:
8;(""L@ = BA/$3%B · ℎ;(""*DE · ?'E#&8#$1 + BA.V/$3%B · ℎ;("") + B@/$3%B · ℎ;(""+ = 138.46 j>/R
/
8$5$G!'(2#$1C* = B$5$G!'(2#$1 ∙ ∙? = 6.96 j>/R
2 'E#&8#$1
94
APPENDIX C
Variable loads from both the extended and the existing part
The variable load of the snow that is acting on the heart wall is calculated to be the following:
The variable residential load that is acting on the outer walls are calculated to be the following:
/
B2'&#%'$8#("L@(23'03-4 = B2'&#%'$8#(" ∙ ∙ ?'E#&8#$1 = 69.6 j>/R
2
/
B2'&#%'$8#("L@(20(-6(6 = B2'&#%'$8#(" ∙ ∙? = 46.4 j>/R
2 'E8'$%'%
Summary of variable loads from both the extended and the existing part
The variable load for the heart wall in section A is summarized into two parts, one for the
existing building and the second for the total building:
Summary of permanent loads from both the extended and the existing part
95
APPENDIX C
2.2 Cross-section B
The second cross-section is visualized in Figure C4a for the total building and in Figure C4b for
the existing building. The distances that each wall carries are determined according to symmetry,
where the two heart walls are placed centrally of the building. The load that acts on each wall is
distributed with half of the lengths that each wall takes. Due to symmetry, the outer walls have the
same loads as well for the heart walls.
a) b)
Figure C4. Cross-section B for a) the total building and for b) the existing building.
Figure C5 visualize the location of the walls in cross-section B. This gives that the loads from the
roof are distributed dependent on the distance between the two walls divided by two, which are
calculated as follows:
2 1
25 = h − 1i · = 4.5 R
2 2
2 1
2= = h + 1i · = 5.5 R
2 2
96
APPENDIX C
For the loads that acts and are distributed in the outer wall, the distance 25 = 4.5 R is used.
97
APPENDIX C
8;(""NA = BA.V/$3%B · ℎ;(""*DE · ?'E#&8#$1 + B@/$3%B · ℎ;("") + BT/$3%B · ℎ;(""+ = 203.34 j>/R
Variable loads from both the extended and the existing part
The variable load of the snow that is acting on the outer wall is calculated to be the following:
The variable residential load that is acting on the outer walls are calculated to be the following:
Summary of variable loads from both the extended and the existing part
The variable load for the outer walls in section B is summarized into two parts, one for the
existing building and the second for the total building:
Summary of permanent loads from both the extended and the existing part
98
APPENDIX C
For the loads that acts and are distributed in the outer wall, the distance 2= = 5.5 R is used.
The self-weight of the non-bearing walls for both extended and existing part is given by:
99
APPENDIX C
8;(""N@ = BA/$3%B · ℎ;(""*DE · ?'E#&8#$1 + BA.V/$3%B · ℎ;("") + B@/$3%B · ℎ;(""+ = 138.46 j>/R
Variable loads from both the extended and the existing part
The variable load of the snow that is acting on the heart wall is calculated to be the following:
The variable residential load that is acting on the outer walls are calculated to be the following:
Summary of variable loads from both the extended and the existing part
The variable load for the heart walls in section B is summarized into two parts, one for the
existing building and the second for the total building:
Summary of permanent loads from both the extended and the existing part
100
APPENDIX C
5% = 20 %
2.4 Summary of loads from all the cross-sections and walls for the two cases
A long-term load in percentage are calculated for each wall in each cross-section with
the following equation. The results of characteristic loads for each wall in each cross-
section are presented in Table C8 to Table C11 for the two cases:
Table C8. Obtained characteristic loads for cross-section A and outer wall.
Cross-section A outer wall Symbol Case 1 Case 2 Unit
Permanent load 7LA 357.03 391.21 kN/m
Variable residential load A2'&#%'$8#("LA 34.8 58 kN/m
Variable snow load A&$5;LA 4.65 4.65 kN/m
Long-term load 7LA% 90 86 %
Table C9. Obtained characteristic loads for cross-section A and heart wall.
Cross-section A heart wall Symbol Case 1 Case 2 Unit
Permanent load 7L@ 445.83 499.15 kN/m
Variable residential load A2'&#%'$8#("L@ 69.6 116 kN/m
Variable snow load A&$5;L@ 9.3 9.3 kN/m
Long-term load 7L@% 85 80 %
Table C10. Obtained characteristic loads for cross-section B and outer wall.
Cross-section B outer wall Symbol Case 1 Case 2 Unit
Permanent load 7NA 441.76 486.5 kN/m
Variable residential load A2'&#%'$8#("NA 54 90 kN/m
Variable snow load A&$5;NA 7.2 7.2 kN/m
Long-term load 7NA% 88 83 %
Table C11. Obtained characteristic loads for cross-section B and heart wall.
Cross-section B heart wall Symbol Case 1 Case 2 Unit
Permanent load 7N@ 429.86 481.2 kN/m
Variable residential load A2'&#%'$8#("N@ 66 110 kN/m
Variable snow load A&$5;N@ 8.8 8.8 kN/m
Long-term load 7N@% 85 80 %
101
102
APPENDIX D
APPENDIX D
Analytical calculations of wind and earth pressure
1. Input data
Table D1. Building properties of the total building.
Total building properties Symbol Magnitude Unit Reference
Width of the building / 11.6 m Appendix A, part 1b
Depth of the building 2 20 m Appendix A, part 1b
Height the building ℎ!.#"%#$1 35 m Appendix 2
Slope of the roof f 3.7 ° Appendix A, part 2b
103
APPENDIX D
The characteristic speed pressure is categorized in the Eurocode to three different shapes of profile
of velocity pressure according to these ones:
Case 1: ℎ!.#"%#$1 ≤ 2
Two separated characteristic speed pressures are needed for the two different heights,
ℎ!.#"%#$1 and 2 (Figure D1).
Figure D1. Wind pressure acting on the wall surface of the building.
The first part is to calculate how the wind load acts on the wall. The factor of form is calculated
to being able to calculate the acting wind load through adding the windward and the leeward
sides as following:
To obtain the design values of the wind loads acting on the wall, they are calculated as follows:
The second part is to calculate how the wind load acts on the roof, which is a saddle shaped roof.
The factor of form is calculated due to its shape, which is a flat roof (<5°) and for the windward
side, the factor and the wind load is calculated to:
2 1
L'$##! A (35) = B7 (35) · 07'$##!) · · = 4.03 j>/R@
10 cos (!)
104
APPENDIX D
2 1 2 1
L'$##! @ (35) = B7 (35) · 07'$##!* · h · − · i = 1.79 j>/R@
2 cos(!) 10 cos(!)
On the leeward side, the factor of form and the wind load is calculated to:
/ 1
L'$##! T (35) = B7 (35) · 07'$##!H · · = 0.78 j>/R@
2 cos (!)
This gives a summary of the wind load acting orthogonal on the roof to be the following:
The horizontal part of the wind load as a design load is therefore calculated as:
L'$##!
L'%$##! = "9 ( · #$07#
= 0.64 j>/R@
sin(!)
All the designed wind loads are calculated with each height that wind acts on, this gives that each
floor joist is carrying a wind force according to the following equation:
5'% = L'% · ∆ℎ
The wind forces are summarized in Table D5, where the existing floor 0 is the ground surface,
which gives a small height that the wind acts on for the first-floor joist:
To obtain a moment, each wind force is multiplied with the height it is acting on and then
summarized to a total moment (Table D6). The outer walls have the same values due to
symmetry, as well for the both heart walls, since it has the same width that the wind is acting on.
=I%# = 5'% · 25 · E
=I%7 = 5'% · 2= · E
105
APPENDIX D
The permanent weight that creates a moment that counteracts the moment of the wind, has a
width of 2 m due to wooden beams in the existing building. These beams can only carry 1 m per
side of a wall for the distributed area that acts on each part in the building.
The middle-placed walls only take 2 m of distributed characteristic self-weight, whereas the outer
walls only take 1 m. With the values obtained from Appendix C, the following permanent
characteristic loads are determined:
To obtain the design load, where the self-weight was favorable, the following equations are used:
These design loads of self-weight are calculated to a stabilizing moment with the dimension of
the building as its depth seen from the side where the wind force is acting and the distance b/6
due to the allowed eccentricity for a stabilizing moment, calculated in the following equations:
/
=&8(!#"#J#$1#50($8&"" = 75.8'2;("" · / · = 5611 j>R
6
106
APPENDIX D
/
=&8(!#"#J#$17(&$08&"" = 7='(28;("" · / · = 5504 j>R
6
The created overturned moment for wind, that is summarized in Table D6, is checked for
overturn:
The overturn can be created if the vertical resultant is not within the distance b/6 from the
center, which is why the eccentricity is calculated as follows:
/ =53'28.2$ /
3 < → 3 = <
6 7;("" 6
/ 11.6
= = 1.93 R
6 6
The values for the eccentricity are calculated to:
=53'28.2$#50($
35.8'2 = = 1.3 R < 1.93 R → d;!
75.8'2;(""
=53'28.2$7(&$0
3='(28 = = 1.5 R < 1.93 R → d;!
7='(28;(""
The stabilizing moment should, therefore, be bigger than the overturned moment where the ratio
shall exceed 1, as follows:
=&8(!#"#J#$1
> 1
=53'28.2$
=&8(!#"#J#$1#50($8&""
= 1.6 > 1 → d;
=53'28.2$#50($
=&8(!#"#J#$17(&$08&""
= 1.3 > 1 → d;
=53'28.2$7(&$0
This gives that the moment that the wind creates does not exceed the stabilizing moment.
Therefore, the wind force does not have to be considered when designing the foundation with
for instance, inclined piles.
107
APPENDIX D
3. Earth pressure
The given soil strata sequence is presented in Figure D2 and Figure D3 for both cross-section A
and cross-section B. The soil strata sequence is the one that is used when the earth pressure is
analyzed for passive pressure. The soil surrounding the wall consists of packed gravel and the
height of the wall beneath the ground level is 1.9 m.
a) b)
The dry-stone wall is exposed to a triangular passive earth pressure from the surrounding soil.
The equation is valid for granular soil with effective cohesion equal to zero. The coefficient of
passive earth pressure ;7 is calculated as:
1 + GÇ?É′
;7 = = 4.0
1 − GÇ?É′
To find the passive resultant force in horizontal direction, following equation is used with a
triangular load considered:
1 @
@K = ∙ "12(3'" ∙ 9S ∙ ;7 = 138.0 j>/R
2
The force is acting per unit length of the wall. To get the total passive resultant acting on the
wall, the depth of the building in cross-section A is multiplied with @7 .
A check is done to analyze the possibility of the earth pressure to counteract the wind force. The
check is done by horizontal equilibrium through:
Ñ @=52#J5$8(" = 0
108
APPENDIX D
The wind loads acting on each wall are summarized in Table D7. The total wind load is
summarized to @;#$% = 879 j>.
Table D7. The total wind force acting on the walls in the building.
Horizontal wind loads Magnitude Unit
Outer wall 198 kN
Heart wall 242 kN
Heart wall 242 kN
Outer wall 198 kN
All walls summarized 879 kN
@858(",7 − @;#$% = 2759 − 879 = 1880 j> → @858(",7 > @;#$% → d;!
The resultant of the earth pressure is larger than the total wind force, no further actions are
necessary.
109
110
APPENDIX E
APPENDIX E
Analytical calculations of design load
1. Input data
Table E1. Design parameters.
Parameters Symbol Magnitude Unit Reference
Residential reduce factor ,< #)75&'% 0.7 - Appendix A, part 5a
Snow reduce factor ,< &$5; 0.6 - Appendix A, part 5a
Partial coefficient STR "4 ( 1.35 - Appendix A, part 5c
permanent adverse =>?
Design values is determined in limit states according to EKS with Eurocode and the IEG (2010).
The characteristic values are dimensioned with partial coefficient and calculated with the three
equations, named Eq. 6.10a, Eq. 6.10b and Eq. 6.10.
For structural bearing capacity, the Eq. 6.10a is with the permanent load as the main load and
therefore, put adverse. Whereas the Eq. 6.10b is with the variable load as the main load and
therefore, put adverse.
Eq. 6.10b 4% = "/ · Ö' · "4 ( · ∑ 7#,F + "9 ( · AA.F + "9 ( · ∑ ,<.C · A#,F Ü
=>? =>? =>?
For geotechnical bearing capacity, the Eq. 6.10 is used with both the permanent and variable
loads as adverse.
Eq. 6.10 4% = "/ · Ö"4 ( · ∑ 7#,F + "9 ( · A#,F + "9 ( · ∑ ,<.C · A#,F Ü
@:A @:A @:A
For the serviceability limit state, for both structural and geotechnical bearing capacity, the
equation 6.10 is used without a safety class factor and the partial coefficients put equal to one.
Two cases are calculated, where case 1 is for the existing building and case 2 is for the total
building, which includes the existing and the extended superstructure.
111
APPENDIX E
2. Cross-section A
Table E2. Obtained characteristic loads for this cross-section and wall.
Cross-section A outer wall Symbol Case 1 Case 2 Unit
Permanent load 7LA 357.03 391.21 kN/m
Variable residential load B2'&#%'$8#("LA 34.8 58 kN/m
Variable snow load B&$5;LA 4.65 4.65 kN/m
From the first and the second equation, the highest value is the structural capacity in ULS. This
gives for the first equation, 6.10a, in ULS that following equation is used:
1) 4% = "/ · Ö"4 ( · 7LA + "9 ( · ,< #)75&'% · B2'&#%'$8#("LA + "9 ( · ,< &$5; ·
=>? =>? =>?
B&$5;LA Ü
This gives for the second equation, 6.10b, the following equation in ULS is used:
2) 4% = "/ · Ö' · "4 ( · 7LA + "9 ( · B2'&#%'$8#("LA + "9 ( · ,< &$5; · B&$5;LA Ü
=>? =>? =>?
The geotechnical capacity with equation, 6.10 in ULS gives the following equation is used:
For the service limit state with Eq. 6.10. the following equation is used:
4% = ":+: · 7LA + ":+: · ,< #)75&'% · B2'&#%'$8#("LA + ":+: · ,< &$5; · B&$5;LA
The results of the equations above for the two cases are summarized in Table E3.
Table E3. Obtained design loads for this cross-section and wall for the two cases.
Cross-section A outer wall ULS – STR ULS – GEO SLS Unit
Design load for case 1 6.10a) 523 445 384 kN/m
6.10b) 485
Design load for case 2 6.10a) 593 515 435 kN/m
6.10b) 561
The largest value is the chosen design load, which for the outer wall in section A is 523 kN/m
for case 1 and 593 kN/m for case 2.
112
APPENDIX E
Table E4. Obtained characteristic loads for this cross-section and wall.
Cross-section A heart wall Symbol Case 1 Case 2 Unit
Permanent load 7L@ 445.83 499.15 kN/m
Variable residential load B2'&#%'$8#("L@ 69.6 116 kN/m
Variable snow load B&$5;L@ 9.3 9.3 kN/m
From the first and the second equation, the highest value is the structural capacity in ULS. This
gives for the first equation, 6.10a, in ULS that the following equation is used:
(1) 4% = "/ · Ö"4 ( · 7L@ + "9 ( · ,< #)75&'% · B2'&#%'$8#("L@ + "9 ( · ,< &$5; ·
=>? =>? =>?
B&$5;L@ Ü
This gives for the second equation, 6.10b, the following equation in ULS is used:
(2) 4% = "/ · Ö' · "4 ( · 7L@ + "9 ( · B2'&#%'$8#("L@ + "9 ( · ,< &$5; · B&$5;L@ Ü
=>? =>? =>?
The geotechnical capacity with equation, 6.10 in ULS gives the following equation is used:
For the service limit state with Eq. 6.10. the following equation is used:
4% = ":+: · 7L@ + ":+: · ,< #)75&'% · B2'&#%'$8#("L@ + ":+: · ,< &$5; · B&$5;L@
The results of the equations above for the two cases are summarized in Table E5.
Table E5. Obtained design loads for this cross-section and wall for the two cases.
Cross-section A heart wall ULS – STR ULS – GEO SLS Unit
6.10a) 683
Design load for case 1 596 500 kN/m
6.10b) 648
6.10a) 804
Design load for case 2 719 586 kN/m
6.10b) 782
The largest value is the chosen design load, which for the heart wall in section A is 683 kN/m for
case 1 and 804 kN/m for case 2.
113
APPENDIX E
3. Cross-section B
3.1 Calculations for the design load in the outer wall
The characteristic values obtained from Appendix C for each cross-section and wall is
summarized in Table E6.
Table E6. Obtained characteristic loads for this cross-section and wall.
Cross-section B outer wall Symbol Case 1 Case 2 Unit
Permanent load 7NA 441.76 486.5 kN/m
Variable residential load B2'&#%'$8#("NA 54 90 kN/m
Variable snow load B&$5;NA 7.2 7.2 kN/m
From the first and the second equation, the highest value is the structural capacity in ULS. This
gives for the first equation, 6.10a, in ULS that following equation is used:
(1) 4% = "/ · Ö"4 ( · 7NA + "9 ( · ,< #)75&'% · B2'&#%'$8#("NA + "9 ( · ,< &$5; ·
=>? =>? =>?
B&$5;NA Ü
This gives for the second equation, 6.10b, the following equation in ULS is used:
(2) 4% = "/ · Ö' · "4 ( · 7NA + "9 ( · B2'&#%'$8#("NA + "9 ( · ,< &$5; · B&$5;NA Ü
=>? =>? =>?
The geotechnical capacity with equation, 6.10 in ULS gives the following equation is used:
For the service limit state with Eq. 6.10. the following equation is used:
4% = ":+: · 7NA + ":+: · ,< #)75&'% · B2'&#%'$8#("NA + ":+: · ,< &$5; · B&$5;NA
The results of the equations above for the two cases are summarized in Table E7.
Table E7. Obtained design loads for this cross-section and wall for the two cases.
Cross-section B outer wall ULS – STR ULS – GEO SLS Unit
6.10a) 660
Design load for case 1 568 484 kN/m
6.10b) 618
6.10a) 758
Design load for case 2 667 554 kN/m
6.10b) 726
The largest value is the chosen design load, which for the outer wall in section B is 660 kN/m for
case 1 and 758 kN/m for case 2.
114
APPENDIX E
Table E8. Obtained characteristic loads for this cross-section and wall.
Cross-section B heart wall Symbol Case 1 Case 2 Unit
Permanent load 7N@ 429.86 481.2 kN/m
Variable residential load B2'&#%'$8#("N@ 66 110 kN/m
Variable snow load B&$5;N@ 8.8 8.8 kN/m
From the first and the second equation, the highest value is the structural capacity in ULS. This
gives for the first equation, 6.10a, in ULS that the following equation is used:
(1) 4% = "/ · Ö"4 ( · 7N@ + "9 ( · ,< #)75&'% · B2'&#%'$8#("N@ + "9 ( · ,< &$5; ·
=>? =>? =>?
B&$5;N@ Ü
This gives for the second equation, 6.10b, the following equation in ULS is used:
(2) 4% = "/ · Ö' · "4 ( · 7N@ + "9 ( · B2'&#%'$8#("N@ + "9 ( · ,< &$5; · B&$5;N@ Ü
=>? =>? =>?
The geotechnical capacity with equation, 6.10 in ULS gives the following equation is used:
For the service limit state with Eq. 6.10. the following equation is used:
4% = ":+: · 7N@ + ":+: · ,< #)75&'% · B2'&#%'$8#("N@ + ":+: · ,< &$5; · B&$5;N@
The results of the equations above for the two cases are summarized in Table E9.
Table E9. Obtained design loads for this cross-section and wall for the two cases.
Cross-section B heart wall ULS – STR ULS – GEO SLS Unit
6.10a) 658
Design load for case 1 573 481 kN/m
6.10b) 623
6.10a) 773
Design load for case 2 691 563 kN/m
6.10b) 751
The largest value is the chosen design load, which for the outer wall in section B is 658 kN/m for
case 1 and 773 kN/m for case 2.
115
APPENDIX E
Table E10. Summarized table for obtained design loads for case 1 for each wall.
ULS ULS SLS
Wall Unit
Structural Geotechnical Structural & Geotechnical
A1 523 445 384 kN/m
A2 683 596 500 kN/m
B1 660 568 484 kN/m
B2 658 573 481 kN/m
Table E11. Summarized table for obtained design loads for case 2 for each wall.
ULS ULS SLS
Wall Unit
Structural Geotechnical Structural & Geotechnical
A1 593 515 435 kN/m
A2 804 719 586 kN/m
B1 758 667 554 kN/m
B2 773 691 563 kN/m
116
APPENDIX F
APPENDIX F
Calculations of geotechnical reinforcement methods
1. Input data
Table F1. Input data and properties in the foundation program provided by SSAB.
Properties Symbol Magnitude Unit Reference
Pile dimension outer 25.8'2 219.1 or 169.3 mm Appendix A, part 7a
Pile dimension thickness 28=#-C$'&& 12.5 or 10 mm Appendix A, part 7a
Steel grade of pile 66% 440 MPa Appendix A, part 7a
Corrosion thickness 2-5225$ 2.2 mm Appendix A, part 7b
Class of concrete filling 0 C30/37 - Appendix A, part 7b
Creep coefficient + 2 - Appendix A, part 7b
Undrained shear
strength 1.C 10 kPa Appendix A, part 7c
Partial factor for
undrained shear strength "-. 1.4 - Appendix A, part 7c
Coefficient of modulus of
subgrade reaction - 58.8 - Appendix A, part 7c
Coefficient of extreme
value of lateral resistance . 6.6 - Appendix A, part 7c
A software provided by SSAB are used for numerical calculations. This program takes short or
long-term into consideration, along with the design value for the undrained shear strength and the
actual thickness of the pile due to corrosion. From the Table F1, the given data are used as input
in the program RRCalcPile that SSAB provided. With initial deflection of a pile set to the worst
case, the program calculates the structural bearing capacity that a pile can have for both ultimate
limit state and service limit state, along with the geotechnical bearing capacity. The value that is the
lowest of the two in the ultimate limit state is the dimensioned bearing capacity that the pile has.
Two different graphs are provided, one with the capacity as a function of deflection (Figure F1a)
and one with the buckling length visualized (Figure F1b).
117
APPENDIX F
a) b)
Figure F1. One tested pile with a) the capacity as a function of deflection and b) buckling length SSAB (2019).
The program has a function called Advanced FEM, where the finite element method is testing
the pile divided into small parts dependent on its total installed length. This is to ensure that it
can carry the load with the second order moment taken into consideration along with the
inserted soil strata sequence. This gives sinus curve thus, where the axial load is tested in the
program due to buckling. The horizontal load can also be tested in this function if the pile would
be exposed to one.
Four different transfer methods are provided from Chapter 8. These methods are tested for each
cross-section to obtain how many piles that are required dependent on the method with the
design loads from Chapter 7 (Table F2) and the obtained bearing capacities provided by the
program.
The analytical calculations are checked to ensure that the design load, 4% , for each pile is less
than the bearing capacity of each pile, á% . It is verified with the equation: 4% ≤ á%
Each pile has a certain bearing capacity that is carried out in the program depending on the
dimension of it. The different bearing capacities obtained from the program for the two tested
dimensions RD220/12.5 and RD170/10 are presented in Table F3.
Table F3. Bearing capacities obtained in RRPileCalc for two different dimensions.
Bearing capacity RD220/12.5 RD170/10 Unit
ULS – structural bearing capacity 1689 980 kN
ULS – geotechnical bearing capacity 2053 1258 kN
SLS – STR and GEO bearing capacity 1581 918 kN
Buckling length due to the dimension 5.8 4.4 m
These bearing capacities for the two dimensions are checked towards the axial force that the pile
carries with a determined degree of utilization to 75 %. The axial force is calculated with an
118
APPENDIX F
iterative calculation to ensure that the normal force that is distributed to the pile is lower than the
value with 75 % of the bearing capacity. Therefore, these values need to be less than 1267 kN for
RD220/12.5 and 735 kN for RD170/10. To determine the normal axial force, the spacing
between the piles is required. These maximum distances depend on the material of the wall
(Table F4).
Table F4. Maximum and minimum spacing for walls with different materials and openings.
Center distances Maximum Minimum
Dry stone wall with full niche 2–3 m 0.5 - 1 m
0.8 for RD220
Dry stone wall with half a niche 2–3 m m
0.6 for RD170
0.8 for RD220
Masonry wall 1.5 – 2 m m
0.6 for RD170
The amount of piles is determined with the depth of the wall that the load is acting on divided by
the maximum center distance, as follows:
!
Cross-section A: ?7#"'& = --
%
Cross-section B: ?7#"'& = --
The amount of piles is rounded upwards to an integer. The design load for each wall is multiplied
with the width or depth of the wall where the load is acting and then divided by the amount of
piles, to obtain the axial force acting in one pile for each specific wall.
I · !
Cross-section A: > = $ 6
93"('
I6 · %
Cross-section B: > =
$93"('
This axial force is then inserted in the program and run with the function called Advanced FEM,
to expose the pile to second order moment to obtain if the force is small enough. The pile is
tested for the cross-sectional material capacity and the instability due to buckling capacity.
If the cross-sectional material capacity is not enough, the program does not proceed with the
calculations. This part is therefore, iteratively calculated. If the axial normal force is too large, one
pile is added to each case and a new axial normal force is calculated. This is tested in the program
and if the program continues to run without interruption, the force is small enough to be carried
by the pile.
Another parameter which needs to be considered is the geometric requirement. The different
transfer methods have different geometric requirements for each cross-section and each wall.
The amount of piles is necessary to be an uneven or an even number to place them correctly and
realistically (Table F5 to Table F8). Which may give an added pile before running the program.
Table F5. Geometric amount due to the method used on wall A1.
Wall: A1 Method 1 Method 2 & 4
No. of distribution points required Uneven amount Uneven amount
No. of piles required Uneven amount Even amount
119
APPENDIX F
Table F6. Geometric amount due to the method used on wall A2.
Wall: A2 Method 1 Method 2 & 4 Method 3
No. of distribution points required Uneven amount Uneven amount Uneven amount
No. of piles required Uneven amount Even amount Even amount
Table F7. Geometric amount due to the method used on wall B1.
Wall: B1 Method 1 Method 2 & 4
No. of distribution points required Even amount Even amount
No. of piles required Even amount Even amount
Table F8. Geometric amount due to the method used on wall B2.
Wall: B2 Method 1 Method 2 & 4 Method 3
No. of distribution points required Even amount Even amount Even amount
No. of piles required Even amount Even amount Even amount
To exemplify the even and uneven amount of piles and distribution points, the Figure F3 and
Figure F4 can illustrate the different locations of the walls. Where the walls with its depth in
cross-section B, due to geometric reasons needs to have an even distribution of points for both
sides, due to a heart wall placed in the middle. The walls with its depth in cross-section A need
uneven amount of piles, due to the two transverse heart walls, where one pile is needed to be
placed between them.
a) b)
120
APPENDIX F
Table F9. Results of calculations for RD220/12.5 for methods subjected on wall A1.
Case 1 - A1 for RD220/12.5 Method 1 Method 2 & 4 Unit
Design load 523 523 kN/m
75 % of bearing capacity 1267 1267 kN
No. of piles rounded up 10 7 Pcs
Normal force 1045 1493 kN
Is the normal force less than Yes No → add pile -
maximum bearing capacity?
Adding extra piles - 7+1=8 Pcs
New normal force - 1307 kN
Meet geometric requirements? No → add pile No → add pile -
Adding extra piles 10 + 1 = 11 8 + 2 = 10 Pcs
New normal force 950 1045 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 11 10 Pcs
Chosen calculated normal force 950 1045 kN
Calculated average center distance 1.82 2.00 m
Chosen calculated installed meters 231 210 m
For the first cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F10).
Table F10. Results of calculations for RD220/12.5 for methods subjected on wall A2.
Case 1 - A2 for RD220/12.5 Method 1 Method 2 & 4 Method 3 Unit
Design load 683 683 683 kN/m
75 % of bearing capacity 1267 1267 1267 kN
No. of piles rounded up 10 10 10 Pcs
Normal force 1367 1367 1367 kN
Is the normal force less than No → add No → add pile No → add pile -
maximum bearing capacity? pile
Adding extra piles 10 + 1 = 11 10 + 1 = 11 10 + 1 = 11 Pcs
New normal force 1242 1242 1242 kN
Meet geometric requirements? Yes No → add pile No → add pile -
Adding extra piles - 11 + 3 = 14 11 + 3 = 14 Pcs
New normal force - 976 976 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 11 14 14 Pcs
Chosen calculated normal force 1242 976 976 kN
Calculated average center distance 1.82 1.43 1.43 m
Chosen calculated installed meters 231 294 294 m
121
APPENDIX F
Table F11. Results of calculations for RD220/12.5 for methods subjected on wall B1.
Case 1 - B1 for RD220/12.5 Method 1 Method 2 & 4 Unit
Design load 660 660 kN/m
75 % of bearing capacity 1267 1267 kN
No. of piles rounded up 6 4 Pcs
Normal force 1275 1913 kN
Is the normal force less than No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6+1=7 4+3=7 Pcs
New normal force 1093 1093 kN
Meet geometric requirements? No → add pile No → add pile -
Adding extra piles 7+1=8 7+1=8 Pcs
New normal force 956 956 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 8 8 Pcs
Chosen calculated normal force 956 956 kN
Calculated average center distance 1.45 1.45 m
Chosen calculated installed meters 168 168 m
For the second cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F12).
Table F12. Results of calculations for RD220/12.5 for methods subjected on wall B2.
Case 1 - B2 for RD220/12.5 Method 1 Method 2 & 4 Method 3 Unit
Design load 658 658 658 kN/m
75 % of bearing capacity 1267 1267 1267 kN
No. of piles rounded up 6 6 6 Pcs
Normal force 1271 1271 1271 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6+1=7 6+1=7 6+1=7 Pcs
New normal force 1090 1090 1090 kN
Meet geometric requirements? No → add pile No → add pile No → add pile -
Adding extra piles 7+1=8 7+1=8 7+1=8 Pcs
New normal force 953 953 953 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 8 8 8 Pcs
Chosen calculated normal force 953 953 953 kN
Calculated average center distance 1.45 1.45 1.45 m
Chosen calculated installed meters 168 168 168 m
122
APPENDIX F
Table F13. Results of calculations for RD170/10 for methods subjected on wall A1.
Case 1 - A1 for RD170/10 Method 1 Method 2 & 4 Unit
Design load 523 523 kN/m
75 % of bearing capacity 735 735 kN
No. of piles rounded up 10 7 Pcs
Normal force 1045 1493 kN
Is the normal force less than No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 10 + 5 = 15 7 + 8 = 15 Pcs
New normal force 697 697 kN
Meet geometric requirements? Yes No → add pile -
Adding extra piles - 15 + 3 = 18 Pcs
New normal force - 581 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 15 18 Pcs
Chosen calculated normal force 697 581 kN
Calculated average center distance 1.33 1.11 m
Chosen calculated installed meters 315 378 m
For the first cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F14).
Table F14. Results of calculations for RD170/10 for methods subjected on wall A2.
Case 1 - A2 for RD170/10 Method 1 Method 2 & 4 Method 3 Unit
Design load 683 683 683 kN/m
75 % of bearing capacity 735 735 735 kN
No. of piles rounded up 10 10 10 Pcs
Normal force 1367 1367 1367 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 10 + 9 = 19 10 + 9 = 19 10 + 9 = 19 Pcs
New normal force 719 719 719 kN
Meet geometric requirements? Yes No → add pile No → add pile -
Adding extra piles - 19 + 3 = 22 19 + 3 = 22 Pcs
New normal force - 621 621 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 19 22 22 Pcs
Chosen calculated normal force 719 621 621 kN
Calculated average center distance 1.05 0.91 0.91 m
Chosen calculated installed meters 399 462 462 m
123
APPENDIX F
Table F15. Results of calculations for RD170/10 for methods subjected on wall B1.
Case 1 - B1 for RD170/10 Method 1 Method 2 & 4 Unit
Design load 660 660 kN/m
75 % of bearing capacity 735 735 kN
No. of piles rounded up 6 4 Pcs
Normal force 1275 1913 kN
Is the normal force less than No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6 + 5 = 11 4 + 7 = 11 Pcs
New normal force 696 696 kN
Meet geometric requirements? No → add pile No → add pile -
Adding extra piles 11 + 1 = 12 11 + 1 = 12 Pcs
New normal force 638 638 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 12 12 Pcs
Chosen calculated normal force 638 638 kN
Calculated average center distance 0.97 0.97 m
Chosen calculated installed meters 252 252 m
For the second cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F16).
Table F16. Results of calculations for RD170/10 for methods subjected on wall B2.
Case 1 - B2 for RD170/10 Method 1 Method 2 & 4 Method 3 Unit
Design load 658 658 658 kN/m
75 % of bearing capacity 735 735 735 kN
No. of piles rounded up 6 6 6 Pcs
Normal force 1271 1271 1271 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6 + 5 = 11 6 + 5 = 11 6 + 5 = 11 Pcs
New normal force 693 693 693 kN
Meet geometric requirements? No → add pile No → add pile No → add pile -
Adding extra piles 11 + 1 = 12 11 + 1 = 12 11 + 1 = 12 Pcs
New normal force 636 636 636 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 12 12 12 Pcs
Chosen calculated normal force 636 636 636 kN
Calculated average center distance 0.97 0.97 0.97 m
Chosen calculated installed meters 252 252 252 m
124
APPENDIX F
Table F17. Results of calculations for RD220/12.5 for methods subjected on wall A1.
Case 2 - A1 for RD220/12.5 Method 1 Method 2 & 4 Unit
Design load 593 593 kN/m
75 % of bearing capacity 1267 1267 kN
No. of piles rounded up 10 7 Pcs
Normal force 1186 1695 kN
Is the normal force less than Yes No → add pile -
maximum bearing capacity?
Adding extra piles - 7 + 3 = 10 Pcs
New normal force - 1186 kN
Meet geometric requirements? No → add pile Yes -
Adding extra piles 10 + 1 = 11 - Pcs
New normal force 1079 - kN
Meet all requirements? Yes Yes -
Chosen amount of piles 11 10 Pcs
Chosen calculated normal force 1079 1186 kN
Calculated average center distance 1.82 2.00 m
Chosen calculated installed meters 231 210 m
For the first cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F18).
Table F18. Results of calculations for RD220/12.5 for methods subjected on wall A2.
Case 2 - A2 for RD220/12.5 Method 1 Method 2 & 4 Method 3 Unit
Design load 804 804 804 kN/m
75 % of bearing capacity 1267 1267 1267 kN
No. of piles rounded up 10 10 10 Pcs
Normal force 1608 1608 1608 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 10 + 3 = 13 10 + 3 = 13 10 + 3 = 13 Pcs
New normal force 1237 1237 1237 kN
Meet geometric requirements? Yes No → add pile No → add pile -
Adding extra piles - 13 + 1 = 14 13 + 1 = 14 Pcs
New normal force - 1149 1149 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 13 14 14 Pcs
Chosen calculated normal force 1237 1149 1149 kN
Calculated average center distance 1.54 1.43 1.43 m
Chosen calculated installed meters 273 294 294 m
125
APPENDIX F
Table F19. Results of calculations for RD220/12.5 for methods subjected on wall B1.
Case 2 - B1 for RD220/12.5 Method 1 Method 2 & 4 Unit
Design load 758 758 kN/m
75 % of bearing capacity 1267 1267 kN
No. of piles rounded up 6 4 Pcs
Normal force 1465 2197 kN
Is the normal force less than maximum No → add pile No → add pile -
bearing capacity?
Adding extra piles 6+1=7 4+3=7 Pcs
New normal force 1256 1256 kN
Meet geometric requirements? No → add pile No → add pile -
Adding extra piles 7+1=8 7+1=8 Pcs
New normal force 1099 1099 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 8 8 Pcs
Chosen calculated normal force 1099 1099 kN
Calculated average center distance 1.45 1.45 m
Chosen calculated installed meters 168 168 m
For the second cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F20).
Table F20. Results of calculations for RD220/12.5 for methods subjected on wall B2.
Case 2 - B2 for RD220/12.5 Method 1 Method 2 & 4 Method 3 Unit
Design load 773 773 773 kN/m
75 % of bearing capacity 1267 1267 1267 kN
No. of piles rounded up 6 6 6 Pcs
Normal force 1495 1495 1495 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6+2=8 6+2=8 6+2=8 Pcs
New normal force 1121 1121 1121 kN
Meet geometric requirements? Yes Yes Yes -
Adding extra piles - - - Pcs
New normal force - - - kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 8 8 8 Pcs
Chosen calculated normal force 1121 1121 1121 kN
Calculated average center distance 1.45 1.45 1.45 m
Chosen calculated installed meters 168 168 168 m
126
APPENDIX F
For the first cross-section and outer walls, the following parts are obtained through the
calculations explained above (Table F21).
Table F21. Results of calculations for RD170/10 for methods subjected on wall A1.
Case 2 - A1 for RD170/10 Method 1 Method 2 & 4 Unit
Design load 593 593 kN/m
75 % of bearing capacity 735 735 kN
No. of piles rounded up 10 7 Pcs
Normal force 1186 1695 kN
Is the normal force less than No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 10 + 7 = 17 7 + 9 = 17 Pcs
New normal force 698 698 kN
Meet geometric requirements? Yes No → add pile -
Adding extra piles - 17 + 1 = 18 Pcs
New normal force - 659 kN
Meet all requirements? Yes Yes -
Chosen amount of piles 17 18 Pcs
Chosen calculated normal force 698 659 kN
Calculated average center distance 1.18 1.11 m
Chosen calculated installed meters 357 378 m
For the first cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F22).
Table F22. Results of calculations for RD170/10 for methods subjected on wall A2.
Case 2 - A2 for RD170/10 Method 1 Method 2 & 4 Method 3 Unit
Design load 804 804 804 kN/m
75 % of bearing capacity 735 735 735 kN
No. of piles rounded up 10 10 10 Pcs
Normal force 1608 1608 1608 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 10 + 12 = 22 10 + 11 = 21 10 + 11 = 21 Pcs
New normal force 731 804 804 kN
Meet geometric requirements? No → add pile No → add pile No → add pile -
Adding extra piles 22 + 1 = 23 21 + 1 = 22 21 + 1 = 22 Pcs
New normal force 699 731 731 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 23 22 22 Pcs
Chosen calculated normal force 699 731 731 kN
Calculated average center distance 0.87 0.91 0.91 m
Chosen calculated installed meters 483 462 462 m
127
APPENDIX F
Table F23. Results of calculations for RD170/10 for methods subjected on wall B1.
Case 2 - B1 for RD170/10 Method 1 Method 2 & 4 Unit
Design load 758 758 kN/m
75 % of bearing capacity 735 735 kN
No. of piles rounded up 6 4 Pcs
Normal force 1465 2197 kN
Is the normal force less than No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6 + 6 = 12 4 + 8 = 12 Pcs
New normal force 732 732 kN
Meet geometric requirements? Yes Yes -
Adding extra piles - - Pcs
New normal force - - kN
Meet all requirements? Yes Yes -
Chosen amount of piles 12 12 Pcs
Chosen calculated normal force 732 732 kN
Calculated average center distance 0.97 0.97 m
Chosen calculated installed meters 252 252 m
For the second cross-section and heart walls, the following parts are obtained through the
calculations explained above (Table F24).
Table F24. Results of calculations for RD170/10 for methods subjected on wall B2.
Case 2 - B2 for RD170/10 Method 1 Method 2 & 4 Method 3 Unit
Design load 773 773 773 kN/m
75 % of bearing capacity 735 735 735 kN
No. of piles rounded up 6 6 6 Pcs
Normal force 1495 1495 1495 kN
Is the normal force less than No → add pile No → add pile No → add pile -
maximum bearing capacity?
Adding extra piles 6 + 7 = 13 6 + 7 = 13 6 + 7 = 13 Pcs
New normal force 690 690 690 kN
Meet geometric requirements? No → add pile No → add pile No → add pile -
Adding extra piles 13 + 1 = 14 13 + 3 = 16 13 + 3 = 16 Pcs
New normal force 641 560 560 kN
Meet all requirements? Yes Yes Yes -
Chosen amount of piles 14 16 16 Pcs
Chosen calculated normal force 641 560 560 kN
Calculated average center distance 0.83 0.73 0.73 m
Chosen calculated installed meters 294 336 336 m
128
APPENDIX F
Table F26. Amount of piles and installed meters for RD170/10 piles for case 1.
Wall Outer Heart
Method 1 2 4 1 2 3 4
15 piles 18 piles 18 piles 19 piles 22 piles 22 piles 22 piles
697 kN 581 kN 581 kN 719 kN 621 kN 621 kN 621 kN
CS A
1.33 m 1.11 m 1.11 m 1.05 m 0.91 m 0.91 m 0.91 m
315 m 378 m 378 m 399 m 462 m 462 m 462 m
12 piles 12 piles 12 piles 12 piles 12 piles 12 piles 12 piles
638 kN 638 kN 638 kN 636 kN 636 kN 636 kN 636 kN
CS B
0.97 m 0.97 m 0.97 m 0.97 m 0.97 m 0.97 m 0.97 m
252 m 252 m 252 m 252 m 252 m 252 m 252 m
Table F27. Amount of piles and installed meters for RD220/12.5 piles for case 2.
Wall Outer Heart
Method 1 2 4 1 2 3 4
11 piles 10 piles 10 piles 13 piles 14 piles 14 piles 14 piles
1079 kN 1186 kN 1186 kN 1237 kN 1149 kN 1149 kN 1149 kN
CS A
1.82 m 2.00 m 2.00 m 1.54 m 1.43 m 1.43 m 1.43 m
231 m 210 m 210 m 273 m 294 m 294 m 294 m
8 piles 8 piles 8 piles 8 piles 8 piles 8 piles 8 piles
1099 kN 1099 kN 1099 kN 1121 kN 1121 kN 1121 kN 1121 kN
CS B
1.45 m 1.45 m 1.45 m 1.45 m 1.45 m 1.45 m 1.45 m
168 m 168 m 168 m 168 m 168 m 168 m 168 m
Table F28. Amount of piles and installed meters for RD170/10 piles for case 2.
Wall Outer Heart
Method 1 2 4 1 2 3 4
17 piles 18 piles 18 piles 23 piles 22 piles 22 piles 22 piles
698 kN 659 kN 659 kN 699 kN 731 kN 731 kN 731 kN
CS A
1.18 m 1.11 m 1.11 m 0.87 m 0.91 m 0.91 m 0.91 m
357 m 378 m 378 m 483 m 462 m 462 m 462 m
12 piles 12 piles 12 piles 14 piles 16 piles 16 piles 16 piles
732 kN 732 kN 732 kN 641 kN 560 kN 560 kN 560 kN
CS B
0.97 m 0.97 m 0.97 m 0.83 m 0.73 m 0.73 m 0.73 m
252 m 252 m 252 m 294 m 336 m 336 m 336 m
129
130
APPENDIX F
APPENDIX G
Cost calculations for geotechnical reinforcement methods
The number of piles and the installed pile lengths for each wall and each pile are given in Chapter
8 (Table G2) (Table G3). The dimensions of one full niche (Table G4).
Table G2. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A1 11 22 Pcs 231 462 m
Wall A2 11 11 Pcs 231 231 m
Wall B1 8 16 Pcs 168 336 m
Wall B2 8 16 Pcs 168 336 m
Table G3. The number of piles and the installed pile length for each wall for RD170/10.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A1 15 30 Pcs 315 630 m
Wall A2 19 19 Pcs 399 399 m
Wall B1 12 24 Pcs 252 504 m
Wall B2 12 24 Pcs 252 504 m
Wall A1
The volume for sawing and demolishing the niches is calculated as:
The number of penetrations through rust bed and planks is equal to the total amount of piles.
131
APPENDIX F
The welding work of the top plate and ring bit together with the top plate itself have a cost per
pile. The quantity is therefore, set to the total amount of piles for each activity. The cost for the
RD-pile is set to the total installed pile meter, which is 462 m for RD220/12.5 and 630 m for
RD170/10. The same quantity is set for the rent of the pilot. The activity of cutting micro piles
occurs two times per pile. The rent of the hammer is given as a cost per day, where the duration
is the required amount of time with four added days to consider preparation and decommission.
The process of drilling and filling the piles with concrete is set to the total installed pile meter.
The total quantity of piles which needs to be controlled is set to the total amount of piles. The
casting of the niches is set to the total volume of niches, which was calculated above to 38.72 m3
for RD220/12.5 and to 52.80 m3 for RD170/10. The costs for establishment include
establishment, decommission and transport. These activities are only done once. The activities
are assumed to last during two working days, which requires staff for 16 hours.
The same process is used when the quantities for the rest of the walls are calculated. The number
of piles and the total installed pile length are changed in accordance to Table G2 and Table G3.
Wall A2
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 19.36 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ V$#-=' = 33.44 RT
Wall B1
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 28.16 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 42.24 RT
Wall B2
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 28.16 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 42.24 RT
Total quantities
The quantities are summarized in Table G5 and Table G6 for each wall and each pile dimension.
132
APPENDIX F
Controls
Stop-driving 22 11 16 16 Pcs
Staff for stop-driving: Machine operator 22 11 16 16 Hour
Straightness measuring 22 11 16 16 Pcs
Staff for straightness measuring: Machine operator 22 11 16 16 Hour
Ultrasonic testing of weld 22 11 16 16 Pcs
Casting
Casting of full niche 38.72 19.36 28.16 28.16 m3
Establishment
High pressure water pump 1 1 1 1 Occasion
Transport, establishment, decommission: Pile trailer 1 1 1 1 Occasion
Transport, establishment, decommission: Low loader 1 1 1 1 Occasion
Staff: Machine operator 16 16 16 16 Hour
Total cost
To find the total cost of each activity, the cost per piece is multiplied with the total quantity for
each activity. The total cost for each activity is summed up and a total cost for each wall,
respectively, is obtained for RD220/125 (Table G7) and for RD170/10 (Table G8).
133
APPENDIX F
Table G7. Total cost for each wall when using RD220/12.5 and method 1.
Wall Total cost
Wall A1 3 704 504 SEK
Wall A2 1 867 981 SEK
Wall B1 2 702 764 SEK
Wall B2 2 702 764 SEK
Table G8. Total cost for each wall when using RD170/10 and method 1.
Wall Total cost
Wall A1 4 964 558 SEK
Wall A2 3 155 754 SEK
Wall B1 3 977 938 SEK
Wall B2 3 977 938 SEK
Table G9. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles per Total piles per Installed meter Total installed meter
Wall Unit Unit
wall cross-section per wall per cross-section
Wall A1 10 20 Pcs 210 420 m
Wall A2 14 14 Pcs 294 294 m
Wall B1 8 16 Pcs 168 336 m
Wall B2 8 16 Pcs 168 336 m
Table G10. The number of piles and the installed pile length for each wall for RD170/10.
Total piles per Installed meter Total installed meter
Wall Piles per wall Unit Unit
cross-section per wall per cross-section
Wall A1 18 36 Pcs 378 756 m
Wall A2 22 22 Pcs 462 462 m
Wall B1 12 24 Pcs 252 504 m
Wall B2 12 24 Pcs 252 504 m
The dimensions for the ground beams, the half a niche in the outer walls and the required hole in
the heart walls and are valid for both pile dimension (Table G11). The inner distance between the
walls is used to determine the length of the ground beams (Figure G1).
a) b)
Figure G1. The distance between the walls in a) cross-section A and in b) cross-section B.
134
APPENDIX F
Table G11. Dimensions of the ground beams, one half a niche and one hole.
Height [m] Width [m] Length [m] Volume [m3]
Ground beam: Wall A1 0.8 0.8 2.325 1.49
Ground beam: Wall A2 0.8 0.8 4.650 2.98
Ground beam: Wall B1 0.8 0.8 3.925 2.51
Ground beam: Wall B2 0.8 0.8 4.625 2.96
Half a niche 0.8 0.8 0.733 0.47
Hole 0.8 0.8 0.600 0.38
Wall A1
The total quantity for demolishing the 0.2 m thick existing concrete floor are calculated as the
total amount of half a niche times the cross-section area of the ground beam:
The demolition of dry-stone wall is equal to the total amount of piles multiplied with the volume
of one half a niche. The total volume is calculated as:
Since the ground beam requires a height of 0.8 m and only 0.2 m existing concrete floor has been
excavated, an excavation of 0.6 m thick soil is required. The volume is calculated as:
Regarding the casting of the ground beams and the half niches, the cost is given in m3. This
corresponds to the total volume, which is determined by the sum of the total volume for the
ground beam and the total volume for the half a niche, which is calculated to:
The same process is used when the quantities for the rest of the walls are calculated. The number
of piles and the total installed pile meter are changed in accordance to Table G9 and Table G10.
Wall A2
The number of holes in the heart wall is set to 7 for RD220/12.5 and 11 for RD170/10, which is
equal to the number of beams and in turn, equal to the total amount of piles divided by two.
135
APPENDIX F
Wall B1
The number of half a niche in the outer walls is equal to the number of piles for both
RD220/12.5 and RD170/10, respectively.
Wall B2
The number of holes in the heart walls is set to 8 for RD220/12.5 and to 12 for RD170/10.
Total quantities
The quantities for each wall are summarized in Table G12 and Table G13 for each wall and pile.
136
APPENDIX F
137
APPENDIX F
Total cost
The cost for each wall is calculated with the same method as for the full niche, for both
RD220/12.5 (Table G14) and RD170/10 (Table G15).
Table G14. Total cost for each wall when using RD220/12.5 and method 2.
Wall Total cost
Wall A1 2 469 146 SEK
Wall A2 1 440 756 SEK
Wall B1 2 210 882 SEK
Wall B2 1 640 293 SEK
Table G15. Total cost for each wall when using RD170/10 and method 2.
Wall Total cost
Wall A1 4 328 577 SEK
Wall A2 2 190 629 SEK
Wall B1 3 240 115 SEK
Wall B2 2 384 231 SEK
The number of piles and the installed pile lengths for each wall and each pile are given by
Chapter 8 (Table G16 and Table G17).
Table G16. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A2 14 14 Pcs 294 294 m
Wall B2 8 16 Pcs 168 336 m
Table G17. The number of piles and the installed pile length for each wall for RD170/10.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A2 22 22 Pcs 462 462 m
Wall B2 12 24 Pcs 252 504 m
138
APPENDIX F
This method requires holes in the heart walls to make space for the yoke beams. It also requires
an excavation of the existing floor and soil to make space for both the yoke beams and the beams
longitudinal with the wall. The beams consist of steel and needs to be casted in with concrete.
The dimensions of the hole in the heart wall (Table G18) and the dimensions for the concrete
beams longitudinal with the wall (Table G19 and Table G20) are presented below.
àÇ!R3H3å=5"' @ @
-=5"' = h i ∙ ç = 0.132 R@
2
I=5"' = 93Ç8ℎH=5"' ∙ LÇ2Hℎ=5"' ∙ <3?8Hℎ=5"' = 0.079 RT
Table G19. Dimensions of the longitudinal concrete beams for pile RD220/12.5.
Wall Height Unit Width Unit Length Unit Volume Unit
Wall A2 0.68 m 0.50 m 5.72 m 1.95 m3
Wall B2 0.68 m 0.50 m 2.90 m 0.99 m3
Table G20. Dimensions of the longitudinal concrete beams for pile RD170/10.
Wall Height Unit Width Unit Length Unit Volume Unit
Wall A2 0.68 m 0.50 m 7.28 m 2.48 m3
Wall B2 0.68 m 0.50 m 3.88 m 1.32 m3
The lengths of the longitudinal beams are determined through the determined average center
distance between the piles, given in Chapter 8. The center distance regards the spacing between
the total amount of piles, which needs to be multiplied with 2, since half the total amount of piles
is located on each side of the wall. For wall A2 and pile RD220/12.5, the center distance is
determined to 1.43 m in Chapter 8 and the final distance to 2.86 m. Since wall A2 requires 14
piles in total, one yoke beam needs to connect 2 piles between the walls B2, and 6 yoke beams
needs to connect 12 piles at the rest of the wall. Due to symmetry, 3 yokes beams connect 6 piles
at each sides of the walls B2, which in turn, requires 4 longitudinal beams of length 5.72 m. The
number of yoke beams and the numbers of holes in the heart wall is therefore, set to 7.
For wall A2 and pile RD170/10, the center distance is determined to 0.91 m and the final
distance to 1.82 m. Due to this, 4 longitudinal beams with length 7.28 m are required. The
number of yoke beams and the numbers of holes in the heart walls is set to 11.
The center distance is determined to 1.45 m for wall B2 and pile RD220/12.5 and the final
distance to 2.90 m. The required number of total piles is set to 16. This leads to a need of 8 yoke
beams that connects 16 piles in total, 2 yoke beams and 4 piles on respective wall B2 and on
respective side of wall A2. In turn, this gives 8 longitudinal beams with length 2.90 m.
For wall B2 and pile RD170/10, the center distance is set to 0.97 m and the final one to 1.94 m.
The required number of piles is set to 24, which gives 12 yoke beams. This in turn, gives 8
139
APPENDIX F
longitudinal beams with a length of 3.88 m. The longitudinal beams consist of HEB220 and the
yoke beams consist of HEB260. The data is summarized in Table G21 and Table G22.
Wall A2
The total quantity for demolition of the 0.2 m thick existing concrete floor are calculated as:
The total volume of demolition of masonry to make space for the yoke beam through the heart
wall is calculated as:
Since the excavation requires a height of 0.68 m and only 0.2 m existing concrete floor has been
excavated, an excavation of 0.48 m thick soil is required. The volume of the excavation is
calculated as:
The costs for the steel beams are given per meter and the quantity for each steel beam are
calculated by multiplication of the length of the beam with the numbers of beams. 2 welders are
required and needs 2 hours each per beam, which gives the total time of 4 hours per beam. The
total time is therefore, multiplied with the numbers of beams.
Regarding the casting, the cost is given in m3 and the volume corresponds to the space where the
beams are located. The volume is determined by the sum of the volume for the longitudinal
beams and of the volume for the holes, which is calculated to:
The same process is used when the quantities for the rest of the walls are calculated. The number
of piles and the total installed pile meter are changed in accordance to Table G16 and Table G17.
140
APPENDIX F
Wall B2
RD220/12.5: -858(",0"552 = ?858(",MIN@@< ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 11.60 R@
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 0.63 RT
RD220/12.5: I858(",&5#" = ?858(",MIN@@< ∙ 0.48 ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 5.57 RT
RD220/12.5: I858(" = ?858(",MIN@@< ∙ I"5$1#8.%#$(" !'(),L@ + I858(",=5"'& = 8.52 RT
Total quantities
The quantities for each wall are summarized in Table G23 and Table G24 for each wall and pile.
141
APPENDIX F
Total cost
The cost for each wall is calculated with the same methodology as for the first and the second
method and are summarized for RD220/12.5 (Table G25) and for RD170/10 (Table G26).
Table G25. Total cost for each wall when using RD220/12.5 in method 3.
Wall Total cost
Wall A2 1 687 253 SEK
Wall B2 1 883 145 SEK
Table G26. Total costs for respectively wall when using RD170/10 in method 3.
Wall Total cost
Wall A2 2 457 158 SEK
Wall B2 2 674 905 SEK
142
APPENDIX F
The number of piles and the installed pile lengths for each wall and each pile are given by
Chapter 8 (Table G27 and Table G28).
Table G27. The number of piles and the installed pile length for RD220/12.5.
Wall Total piles Unit Total installed meter Unit
Wall A1 & Wall B1 36 Pcs 756 m
Wall A2 & Wall B2 30 Pcs 630 m
All walls 66 Pcs 1 386 m
Table G28. The number of piles and the installed pile length for RD170/10.
Wall Total piles Unit Total installed meter Unit
Wall A1 & Wall B1 60 Pcs 1 260 m
Wall A2 & Wall B2 46 Pcs 966 m
All walls 106 Pcs 2 226 m
This method requires holes in the heart walls and a longitudinal half a niche along the outer walls.
The existing concrete floor needs to be removed along with the underlying soil to make space for
the slab. The dimensions of one hole in the heart wall and the inner dimensions for the slab
(Figure G1) is presented in Table G29 and Table G30.
The longitudinal half a niche required in the outer walls has a width of 2/3 times the dry-stone
wall thickness, which is equal to 0.73 m. The height is set to the same height as the slab. The
length of the half a niche is determined to 9.9 m in cross-section A and to 18.3 m in cross-section
B (Figure G2). The dimensions of the longitudinal half’s niches are presented in Table G31.
143
APPENDIX F
a) b)
Figure G2. The distance between the walls in a) cross-section A and in b) cross-section B.
Table G31. Dimensions of the longitudinal half’s niches.
Width [m] Height [m] Length [m] Total area [m2]
Cross-section A 0.73 0.8 9.9 14.52
Cross-section B 0.73 0.8 18.3 26.84
The total volume of the longitudinal half a niche is summed to: -"5$1,$#-=',858 = 41.36 R@
All walls
The total quantity for demolition of the 0.2 m thick existing concrete floor are equal to the area
for the inner slab:
The total volume of demolition of masonry to make space for the slab through the heart walls is
calculated as:
Since the slab needs to have a height of 0.8 m and only 0.2 m existing concrete floor has been
excavated, an excavation of 0.6 m thick soil is required. The volume of the excavation is
calculated as:
Regarding the casting, the cost is given in m3. The volume is determined by the sum of the total
volume of the inner slab, the total volume of the longitudinal half a niche and the total volume of
the holes in the heart walls.
144
APPENDIX F
The same process is used when the quantities for the rest of the walls are calculated. The number
of piles and the total installed pile meter are changed in accordance to Table G27 and Table G28.
Total quantities
The quantities are summarized in Table G32 and Table G33 for all walls and each pile.
Table G32. Total quantities for all walls and for RD220/12.5.
Activity All walls Unit
Sawing and demolition
Demolition of 0.2 m thick existing concrete floor on ground 159.03 m2
Demolition of masonry wall 5.76 m3
Demolition of dry-stone wall 33.09 m3
Excavation of soil 95.42 m3
Pile
RD-pile 219.1 x 12.5 mm 1386 m
Cutting of micro pile 220/12.5 mm 132 Pcs
Welding of top plate 220/12.5 mm 66 Pcs
Welding of ring bit 220/12.5 mm 66 Pcs
Top plate 66 Pcs
Rent of pilot 220/12.5 mm 1386 m
Rent of hammer 70 Day
Drilling
Drilling of pile 220/12.5 mm 1386 m
Filling of pile
Filling of pile 220/12.5 mm with concrete 1386 m
Controls
Stop-driving 66 Pcs
Staff for stop-driving: Machine operator 66 Hour
Straightness measuring 66 Pcs
Staff for straightness measuring: Machine operator 66 Hour
Ultrasonic testing of weld 66 Pcs
Casting
Casting of slab 166.07 m3
Reinforcement including staff 166.07 m3
Establishment
High pressure water pump 1 Occasion
Transport, establishment, decommission: Pile trailer 1 Occasion
Transport, establishment, decommission: Low loader 1 Occasion
Staff: Machine operator 16 Hour
145
APPENDIX F
Pile
RD-pile 168.3 x 10 mm 2226 m
Cutting of micro pile 170/10 mm 212 Pcs
Welding of top plate 170/10 mm 106 Pcs
Welding of ring bit 170/10 mm 106 Pcs
Top plate 106 Pcs
Rent of pilot 170/10 mm 2226 m
Rent of hammer 110 Day
Drilling
Drilling of pile 170/10 mm 2226 m
Filling of pile
Filling of pile 170/10 mm with concrete 2226 m
Controls
Stop-driving 106 Pcs
Staff for stop-driving: Machine operator 106 Hour
Straightness measuring 106 Pcs
Staff for straightness measuring: Machine operator 106 Hour
Ultrasonic testing of weld 106 Pcs
Casting
Casting of slab 169.14 m3
Reinforcement including staff 169.14 m3
Establishment
High pressure water pump 1 Occasion
Transport, establishment, decommission: Pile trailer 1 Occasion
Transport, establishment, decommission: Low loader 1 Occasion
Staff: Machine operator 16 Hour
Total cost
The total cost for all walls is presented in Table G34 and Table G35 for both pile dimensions.
Table G34. Total cost for all walls when using RD220/12.5 in method 4.
RD220/12.5 Total cost
All walls 8 669 438 SEK
Table G35. Total costs for all walls when using RD170/10 in method 4.
RD220/12.5 Total cost
All walls 11 799 046 SEK
The combinations of the methods and their costs are presented in Table G36 and Table G37 for
each pile dimension. The slab method can only be combined with itself, therefore, the method is
calculated for all walls in both cross-sections. This gives that it is not possible to divide the cost
per each cross-section or wall. Combination 7 and combination 8, which includes the slab
method on all walls in both cross-sections, is therefore, presented as a total cost for the total
combination below.
146
APPENDIX F
Table G36. The cost, the number of piles and the number of installed meter for each combination and for RD220/12.5.
Number Installed
Combination Type of wall Cost per method Total cost
of piles meters
Wall A1: Method 1 3 704 504 SEK
Combination 1 5 572 485 SEK 33 Pcs 693 m
Wall A2: Method 1 1 867 981 SEK
Wall A1: Method 1 3 704 504 SEK
Combination 2 5 391 757 SEK 36 Pcs 756 m
Wall A2: Method 3 1 687 253 SEK
Wall A1: Method 2 2 469 146 SEK
Combination 3 3 909 902 SEK 34 Pcs 714 m
Wall A2: Method 2 1 440 756 SEK
Wall B1: Method 1 2 702 764 SEK
Combination 4 5 405 529 SEK 32 Pcs 672 m
Wall B2: Method 1 2 702 764 SEK
Wall B1: Method 1 2 702 764 SEK
Combination 5 4 585 910 SEK 32 Pcs 672 m
Wall B2: Method 3 1 883 145 SEK
Wall B1: Method 2 2 210 882 SEK
Combination 6 3 851 175 SEK 32 Pcs 672 m
Wall B2: Method 2 1 640 293 SEK
Table G37. The cost, the number of piles and the number of installed meter for each combination and for RD170/10.
Number Installed
Combination Type of wall Cost per method Total cost
of piles meters
Wall A1: Method 1 4 964 558 SEK
Combination 1 8 120 312 SEK 49 Pcs 1029 m
Wall A2: Method 1 3 155 754 SEK
Wall A1: Method 1 4 964 558 SEK
Combination 2 7 421 716 SEK 52 Pcs 1092 m
Wall A2: Method 3 2 457 158 SEK
Wall A1: Method 2 4 328 577 SEK
Combination 3 6 519 207 SEK 58 Pcs 1218 m
Wall A2: Method 2 2 190 629 SEK
Wall B1: Method 1 3 977 938 SEK
Combination 4 7 955 875 SEK 48 Pcs 1008 m
Wall B2: Method 1 3 977 938 SEK
Wall B1: Method 1 3 977 938 SEK
Combination 5 6 652 843 SEK 48 Pcs 1008 m
Wall B2: Method 3 2 674 905 SEK
Wall B1: Method 2 3 240 115 SEK
Combination 6 5 624 345 SEK 48 Pcs 1008 m
Wall B2: Method 2 2 384 231 SEK
147
APPENDIX F
The combinations are combined once again, to a total combination. The total combinations and
their costs are presented for RD220/12.5 in Table G38 and for RD170/10 in Table G39.
Table G38. The cost, the number of piles and the number of installed meter for each total combination for RD220/12.5.
Number Installed
Cross-section A & B Total cost
of piles meters
Combination 1
Total combination 1 10 978 014 SEK 65 Pcs 1365 m
Combination 4
Combination 1
Total combination 2 10 158 395 SEK 65 Pcs 1365 m
Combination 5
Combination 1
Total combination 3 9 423 661 SEK 65 Pcs 1365 m
Combination 6
Combination 2
Total combination 4 10 797 286 SEK 68 Pcs 1428 m
Combination 4
Combination 2
Total combination 5 9 977 667 SEK 68 Pcs 1428 m
Combination 5
Combination 2
Total combination 6 9 242 933 SEK 68 Pcs 1428 m
Combination 6
Combination 3
Total combination 7 9 315 431 SEK 66 Pcs 1386 m
Combination 4
Combination 3
Total combination 8 8 495 812 SEK 66 Pcs 1386 m
Combination 5
Combination 7
Total combination 9 8 669 438 SEK 66 Pcs 1386 m
Combination 8
Table G39. The cost, the number of piles and the number of installed meter for each total combination for RD170/10.
Number Installed
Cross-section A & B Total cost
of piles meters
Combination 1
Total combination 1 16 076 188 SEK 97 Pcs 2037 m
Combination 4
Combination 1
Total combination 2 14 773 155 SEK 97 Pcs 2037 m
Combination 5
Combination 1
Total combination 3 13 744 658 SEK 97 Pcs 2037 m
Combination 6
Combination 2
Total combination 4 15 377 591 SEK 100 Pcs 2100 m
Combination 4
Combination 2
Total combination 5 14 074 559 SEK 100 Pcs 2100 m
Combination 5
Combination 2
Total combination 6 13 046 061 SEK 100 Pcs 2100 m
Combination 6
Combination 3
Total combination 7 14 475 082 SEK 106 Pcs 2226 m
Combination 4
Combination 3
Total combination 8 13 172 050 SEK 106 Pcs 2226 m
Combination 5
Combination 7
Total combination 9 11 799 046 SEK 106 Pcs 2226 m
Combination 8
148
APPENDIX F
The cost regarding the project organization is given as a cost per day. Since the capacity is
installing one pile per day, the cost is multiplied with the total number of piles for the total
combination with 15 more added days to consider time for planning, preparation and
establishment. The project organization cost is then added to the total cost for the total
combination, where the sum is multiplied with 1.12 to consider the central general cost of a
mark-up of 12 %. This is done for each pile dimension (Table G40 and Table G41).
Table G40. The total cost for each total combination for RD220/12.5.
Total combination Total cost
Total combination 1 15 272 963 SEK
Table G41. The total cost for each total combination for RD170/10.
Total combination Total cost
Total combination 1 22 173 952 SEK
149
APPENDIX F
3 key performance indicators can be determined from the cost estimation (Table G42 and Table
G43). By dividing the total cost for the total combination with the total number of piles, the cost
per pile is obtained. By dividing the total cost with the total installed pile meter, the cost per
meter is determined and by multiply the same ratio with 10 the cost per 10-meter pile is obtained.
Table G42. Key performance indicators for each total combination for RD220/12.5.
Indicator 1: Indicator 2: Indicator 3:
Cross-section A & B Cost per pile Cost per meter Cost per 10 meters
[SEK/Pcs] [SEK/m] [SEK/10m]
Total combination 1 234 969 11 189 111 890
Total combination 2 220 846 10 516 105 165
Total combination 3 208 186 9 914 99 136
Total combination 4 223 268 10 632 106 318
Total combination 5 209 768 9 989 99 890
Total combination 6 197 667 9 413 94 127
Total combination 7 203 759 9 703 97 028
Total combination 8 189 850 9 040 90 405
Total combination 9 192 797 9 181 91 808
Table G43. Key performance indicators for each total combination for RD170/10.
Indicator 1: Indicator 2: Indicator 3:
Cross-section A & B Cost per pile Cost per meter Cost per 10 meters
[SEK/Pcs] [SEK/m] [SEK/10m]
Total combination 1 228 597 10 886 108 856
Total combination 2 213 552 10 169 101 691
Total combination 3 201 677 9 604 96 037
Total combination 4 215 032 10 240 102 396
Total combination 5 200 438 9 545 95 447
Total combination 6 188 919 8 996 89 961
Total combination 7 195 431 9 306 93 062
Total combination 8 181 663 8 651 86 506
Total combination 9 167 156 7 960 79 598
150
APPENDIX F
The number of piles and the installed pile length for each wall and each pile are given in Chapter
8 (Table G35) (Table G36).
Table G35. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A1 11 22 Pcs 231 462 m
Wall A2 13 13 Pcs 273 273 m
Wall B1 8 16 Pcs 168 336 m
Wall B2 8 16 Pcs 168 336 m
Table G36. The number of piles and the installed pile length for each wall for RD170/10.
Piles per Total piles per Installed Total installed meter
Wall Unit Unit
wall cross-section meter per wall per cross-section
Wall A1 17 34 Pcs 357 714 m
Wall A2 23 23 Pcs 483 483 m
Wall B1 12 24 Pcs 252 504 m
Wall B2 14 28 Pcs 294 588 m
Wall A1
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 38.72 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 59.84 RT
Wall A2
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 22.88 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 40.48 RT
Wall B1
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 28.16 RT
RD170/10: I858(",$#-='& = ?858(",W#"'& ∙ I$#-=' = 42.24 RT
Wall B2
RD220/12.5: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 28.16 RT
RD170/10: I858(",$#-='& = ?858(",7#"'& ∙ I$#-=' = 49.28 RT
Total quantities
The quantities are summarized in Table G37 and Table G38 for each wall and pile.
151
APPENDIX F
152
APPENDIX F
Total cost
The cost is presented in Table G39 and Table G40 for each wall and pile.
Table G39. Total cost for each wall when using RD220/12.5 in method 1.
Wall Total cost
Wall A1 3 704 504 SEK
Wall A2 2 201 894 SEK
Wall B1 2 702 764 SEK
Wall B2 2 702 764 SEK
Table G40. Total costs for respectively wall when using RD170/10 in method 1.
Wall Total cost
Wall A1 5 622 304 SEK
Wall A2 3 813 501 SEK
Wall B1 3 977 938 SEK
Wall B2 4 635 684 SEK
Table G41. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles Total piles per Installed meter Total installed meter
Wall Unit Unit
per wall cross-section per wall per cross-section
Wall A1 10 20 Pcs 210 420 m
Wall A2 14 14 Pcs 294 294 m
Wall B1 8 16 Pcs 168 336 m
Wall B2 8 16 Pcs 168 336 m
Table G42. The number of piles and the installed pile length for each wall for RD170/10.
Piles Total piles per Installed meter Total installed meter
Wall Unit Unit
per wall cross-section per wall per cross-section
Wall A1 18 36 Pcs 378 756 m
Wall A2 22 22 Pcs 462 462 m
Wall B1 12 24 Pcs 252 504 m
Wall B2 16 32 Pcs 336 672 m
153
APPENDIX F
Wall A1
RD220/12.5: -858(",0"552 = ?858(",7#"'& ∙ LÇ2HℎLA ∙ <3?8HℎLA = 37.20 R@
RD220/12.5: I858(",b`cdefgbh = ?858(",7#"'& ∙ I=("0$#-=' = 9.39 RT
RD220/12.5: I858(",&5#" = ?858(",7#"'& ∙ 0.6 ∙ LÇ2HℎLA ∙ <3?8HℎLA = 22.32 RT
RD220/12.5: I858(" = ?858(",7#"'& ∙ I125.$%!'(),LA + I858(",=("0$#-=' = 39.15 RT
Wall A2
RD220/12.5: -858(",0"552 = ?858(",=5"'& ∙ LÇ2HℎL@ ∙ <3?8HℎL@ = 26.04 R@
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 2.69 RT
RD220/12.5: I858(",&5#" = ?858(",=5"'& ∙ 0.6 ∙ LÇ2HℎL@ ∙ <3?8HℎL@ = 15.62 RT
RD220/12.5: I858(" = ?858(",=5"'& ∙ I125.$%!'(),L@ + I858(",=5"'& = 23.52 RT
Wall B1
RD220/12.5: -858(",0"552 = ?858(",7#"'& ∙ LÇ2HℎNA ∙ <3?8HℎNA = 50.24 R@
RD220/12.5: I858(",=("0$#-=' = ?858(",7#"'& ∙ I=("0$#-=' = 7.51 RT
RD220/12.5: I858(",&5#" = ?858(",7#"'& ∙ 0.6 ∙ Li2HℎNA ∙ <3?8HℎNA = 30.14 RT
RD220/12.5: I858(" = ?858(",7#"'& ∙ I125.$%!'(),NA + I858(",=("0$#-=' = 47.70 RT
Wall B2
RD220/12.5: -858(",0"5i2 = ?858(",=5"'& ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 29.60 R@
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 3.07 RT
RD220/12.5: I858(",&5#" = ?858(",=5"'& ∙ 0.6 ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 17.76 RT
RD220/12.5: I858(" = ?858(",=5"'& ∙ V125.$%!'(),N@ + I858(",=5"'& = 26.75 RT
154
APPENDIX F
Total quantities
The quantities are summarized in Table G43 and Table G44 for each wall and pile.
155
APPENDIX F
Total cost
The cost is presented in Table G45 and Table G46 for each wall and pile.
Table G45. Total cost for each wall when using RD220/12.5 in method 2.
Wall Total cost
Wall A1 2 469 146 SEK
Wall A2 1 440 756 SEK
Wall B1 2 210 882 SEK
Wall B2 1 640 293 SEK
Table G46. Total cost for each wall when using RD170/10 in method 2.
Wall Total cost
Wall A1 4 328 577 SEK
Wall A2 2 190 629 SEK
Wall B1 3 240 115 SEK
Wall B2 3 168 489 SEK
The number of piles and the installed pile length for each wall and each pile are given in Chapter
8 (Table G47) (Table G48).
Table G47. The number of piles and the installed pile length for each wall for RD220/12.5.
Piles per Total piles per Installed meter Total installed meter
Wall Unit Unit
wall cross-section per wall per cross-section
Wall A2 14 14 Pcs 294 294 m
Wall B2 8 16 Pcs 168 336 m
156
APPENDIX F
Table G48. The number of piles and the installed pile length for each wall for RD170/10.
Piles per Total piles per Installed meter Total installed meter
Wall Unit Unit
wall cross-section per wall per cross-section
Wall A2 22 22 Pcs 462 462 m
Wall B2 16 32 Pcs 336 672 m
The dimensions for the concrete beams longitudinal with the wall are shown in Table G49 and
Table G50 for each pile and wall.
For wall A2 and pile RD220/12.5, the average center distance is determined to 1.43 m and the
final one is set to 2.86 m. 4 longitudinal beams of length 5.72 m are required. The number of
yoke beams and the number of holes in the heart wall is set to 7.
For wall A2 and pile RD170/10, the average center distance is determined to 0.91 m and the final
one is set to 1.82 m. 4 longitudinal beams of length 7.28 m are required. The number of yoke
beams and the numbers of holes in the heart walls is set to 11.
For wall B2 and pile RD220/12.5, the average center distance is determined to 1.45 m and the
final one is set to 2.9 m. 8 longitudinal beams of length 2.90 m are required. The number of yoke
beams and the numbers of holes in the heart walls is set to 8.
For wall B2 and pile RD170/10, the average center distance is determined to 0.73 m and the final
one is set to 1.46 m. 8 longitudinal beams of length 4.38 m are required. The number of yoke
beams and the numbers of holes in the heart walls is set to 16.
The data is summarized for RD220/12.5 (Table G51) and for RD170/10 (Table G52).
157
APPENDIX F
Wall A2
RD220/12.5: -858(",0"552 = ?858(",MIN@@< ∙ LÇ2HℎL@ ∙ <3?8HℎL@ = 11.44 R@
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 0.55 RT
RD220/12.5: I858(",&5#" = ?858(",MIN@@< ∙ 0.48 ∙ LÇ2HℎL@ ∙ <3?8HℎL@ = 5.49 RT
RD220/12.5: I858(" = ?858(",MIN@@< ∙ I"5$1#8.%#$(" !'(),L@ + I858(",=5"'& = 8.33 RT
Wall B2
RD220/12.5: -858(",0"552 = ?858(",MIN@@< ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 11.60 R@
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 0.63 RT
RD220/12.5: I858(",&5#" = ?858(",MIN@@< ∙ 0.48 ∙ LÇ2HℎN@ ∙ <3?8HℎN@ = 5.57 RT
RD220/12.5: I858(" = ?858(",MIN@@< ∙ I"5$1#8.%#$(" !'(),L@ + I858(",=5"'& = 8.52 RT
Total quantities
The quantities for each wall are summarized in Table G53 and Table G54.
158
APPENDIX F
159
APPENDIX F
Casting
Casting of beam 10.77 13.18 m3
Establishment
High pressure water pump 1 1 Occasion
Transport, establishment, decommission: Pile trailer 1 1 Occasion
Transport, establishment, decommission: Low loader 1 1 Occasion
Staff: Machine operator 16 16 Hour
Total cost
The cost is summarized in Table G55 and Table G56 for each wall and pile.
Table G55. Total cost for each wall when using RD220/12.5 in method 3.
Wall Total cost
Wall A2 1 687 253 SEK
Wall B2 1 883 145 SEK
Table G56. Total cost for each wall when using RD170/10 in method 3.
Wall Total cost
Wall A2 2 457 158 SEK
Wall B2 3 442 437 SEK
Table G57. The number of piles and the installed pile length for RD220/12.5.
Wall Total piles Unit Total installed meter Unit
Wall A1 & Wall B1 36 Pcs 756 m
Wall A2 & Wall B2 30 Pcs 630 m
All walls 66 Pcs 1386 m
Table G58. The number of piles and the installed pile length for RD170/10.
Wall Total piles Unit Total installed meter Unit
Wall A1 & Wall B1 60 Pcs 1 260 m
Wall A2 & Wall B2 54 Pcs 1134 m
All walls 114 Pcs 2394 m
The required number of holes in the heart walls are set to 15 for RD220 and 27 for RD170.
All walls
RD220/12.5: I858(",=5"'& = ?858(",=5"'& ∙ I=5"' = 5.76 RT
RD220: I858(" = I858(",=("0$#-=' + I858(",=5"'& + -#$$'2,&"(! ∙ 93Ç8ℎH#$$'2,&"(! = 166.07 RT
The same process is used when the quantities for the rest of the walls are calculated. The number
of piles and the total installed pile meter are changed in accordance to Table G57 and Table G58.
160
APPENDIX F
Total quantities
The quantities are summarized in Table G59 and Table G60 for all walls and each pile.
Table G59. Total quantities for all walls and for RD220/12.5.
Activity All walls Unit
Sawing and demolition
Demolition of 0.2 m thick existing concrete floor on ground 159.03 m2
Demolition of masonry wall 5.76 m3
Demolition of dry-stone wall 33.09 m3
Excavation of soil 95.42 m3
Pile
RD-pile 219.1 x 12.5 mm 1386 m
Cutting of micro pile 220/12.5 mm 132 Pcs
Welding of top plate 220/12.5 mm 66 Pcs
Welding of ring bit 220/12.5 mm 66 Pcs
Top plate 66 Pcs
Rent of pilot 220/12.5 mm 1386 m
Rent of hammer 70 Day
Drilling
Drilling of pile 220/12.5 mm 1386 m
Filling of pile
Filling of pile 220/12.5 mm with concrete 1386 m
Controls
Stop-driving 66 Pcs
Staff for stop-driving: Machine operator 66 Hour
Straightness measuring 66 Pcs
Staff for straightness measuring: Machine operator 66 Hour
Ultrasonic testing of weld 66 Pcs
Casting
Casting of slab 166.07 m3
Reinforcement including staff 166.07 m3
Establishment
High pressure water pump 1 Occasion
Transport, establishment, decommission: Pile trailer 1 Occasion
Transport, establishment, decommission: Low loader 1 Occasion
Staff: Machine operator 16 Hour
161
APPENDIX F
Total cost
The total cost for all walls is presented in Table G61 and Table G62 for both pile dimensions.
Table G61. Total cost for all walls when using RD220/12.5 in method 4.
RD220/12.5 Total cost
All walls 8 669 438 SEK
Table G62. Total costs for all walls when using RD170/10 in method 4.
RD220/12.5 Total cost
All walls 12 437 777 SEK
Table G63. The cost, the number of piles and the number of installed meter for each combination for RD220/12.5.
Number Installed
Combination Type of wall Cost per method Total cost
of piles meters
Wall A1: Method 1 3 704 504 SEK
Combination 1 5 906 399 SEK 35 Pcs 735 m
Wall A2: Method 1 2 201 894 SEK
Wall A1: Method 1 3 704 504 SEK
Combination 2 5 391 757 SEK 36 Pcs 756 m
Wall A2: Method 3 1 687 253 SEK
Wall A1: Method 2 2 469 146 SEK
Combination 3 3 909 902 SEK 34 Pcs 714 m
Wall A2: Method 2 1 440 756 SEK
Wall B1: Method 1 2 702 764 SEK
Combination 4 5 405 529 SEK 32 Pcs 672 m
Wall B2: Method 1 2 702 764 SEK
162
APPENDIX F
Table G64. The cost, the number of piles and the number of installed meter for each combination for RD170/10.
Number Installed
Combination Type of wall Cost per method Total cost
of piles meters
Wall A1: Method 1 5 622 304 SEK
Combination 1 9 435 805 SEK 57 Pcs 1197 m
Wall A2: Method 1 3 813 501 SEK
Wall A1: Method 1 5 622 304 SEK
Combination 2 8 079 462 SEK 56 Pcs 1176 m
Wall A2: Method 3 2 457 158 SEK
Wall A1: Method 2 4 328 577 SEK
Combination 3 6 519 207 SEK 58 Pcs 1218 m
Wall A2: Method 2 2 190 629 SEK
Wall B1: Method 1 3 977 938 SEK
Combination 4 8 613 622 SEK 52 Pcs 1092 m
Wall B2: Method 1 4 635 684 SEK
Wall B1: Method 1 3 977 938 SEK
Combination 5 7 420 375 SEK 56 Pcs 1176 m
Wall B2: Method 3 3 442 437 SEK
Wall B1: Method 2 3 240 115 SEK
Combination 6 6 408 603 SEK 56 Pcs 1176 m
Wall B2: Method 2 3 168 489 SEK
The total combinations, each cost and each installed meter (Table G65 and Table G66).
Table G65. The cost, the number of piles and the number of installed meter for each total combination for RD220/12.5.
Number Installed
Cross-section A & B Total cost
of piles meters
Combination 1
Total combination 1 11 311 927 SEK 67 Pcs 1407 m
Combination 4
Combination 1
Total combination 2 10 492 308 SEK 67 Pcs 1407 m
Combination 5
Combination 1
Total combination 3 9 757 574 SEK 67 Pcs 1407 m
Combination 6
Combination 2
Total combination 4 10 797 286 SEK 68 Pcs 1428 m
Combination 4
Combination 2
Total combination 5 9 977 667 SEK 68 Pcs 1428 m
Combination 5
Combination 2
Total combination 6 9 242 933 SEK 68 Pcs 1428 m
Combination 6
Combination 3
Total combination 7 9 315 431 SEK 66 Pcs 1386 m
Combination 4
Combination 3
Total combination 8 8 495 812 SEK 66 Pcs 1386 m
Combination 5
Combination 7
Total combination 9 8 669 438 SEK 66 Pcs 1386 m
Combination 8
163
APPENDIX F
Table G66. The cost, the number of piles and the number of installed meter for each total combination for RD170/10.
Number Installed
Cross-section A & B Total cost
of piles meters
Combination 1
Total combination 1 18 049 428 SEK 109 Pcs 2289 m
Combination 4
Combination 1
Total combination 2 16 856 180 SEK 113 Pcs 2373 m
Combination 5
Combination 1
Total combination 3 15 844 409 SEK 113 Pcs 2373 m
Combination 6
Combination 2
Total combination 4 16 693 084 SEK 108 Pcs 2268 m
Combination 4
Combination 2
Total combination 5 15 499 837 SEK 112 Pcs 2352 m
Combination 5
Combination 2
Total combination 6 14 488 065 SEK 112 Pcs 2352 m
Combination 6
Combination 3
Total combination 7 15 132 829 SEK 110 Pcs 2310 m
Combination 4
Combination 3
Total combination 8 13 939 581 SEK 114 Pcs 2394 m
Combination 5
Combination 7
Total combination 9 12 437 777 SEK 114 Pcs 2394 m
Combination 8
When the project organization cost and the central general cost is considered, following total
costs for each pile type and each total combination is obtained (Table G67 and Table G68).
Table G67. The total cost for each total combination for RD220/12.5.
Total combination Total cost
Total combination 1 15 721 386 SEK
164
APPENDIX F
Table G68. The total cost for each total combination for RD170/10.
Total combination Total cost
Total combination 1 24 830 619 SEK
The key performance indicators from each total combination, for RD220/12.5 (Table G69) and
for RD170/10 (Table G70).
Table G69. Key performance indicators for each total combination for RD220/12.5.
Indicator 1: Indicator 2: Indicator 3:
Cross-section A & B Cost per pile Cost per meter Cost per 10 meters
[SEK/Pcs] [SEK/m] [SEK/10m]
Total combination 1 234 648 11 174 111 737
Total combination 2 220 946 10 521 105 213
Total combination 3 208 664 9 936 99 364
Total combination 4 223 268 10 632 106 318
Total combination 5 209 768 9 989 99 890
Total combination 6 197 667 9 413 94 127
Total combination 7 203 759 9 703 97 028
Total combination 8 189 850 9 040 90 405
Table G70. Key performance indicators for each total combination for RD170/10.
Cross-section A & B Indicator 1: Indicator 2: Indicator 3:
Cost per pile Cost per meter Cost per 10 meters
[SEK/Pcs] [SEK/m] [SEK/10m]
Total combination 1 227 804 10 848 108 478
Total combination 2 209 231 9 963 99 634
Total combination 3 199 202 9 486 94 858
Total combination 4 215 503 10 262 102 620
Total combination 5 197 203 9 391 93 906
Total combination 6 187 085 8 909 89 088
Total combination 7 196 375 9 351 93 512
Total combination 8 179 067 8 527 85 270
165
166
APPENDIX H
APPENDIX H
Cost calculations for the total construction
1. Input data
Table H1. Input data and properties of the total building.
Parameters Symbol Magnitude Unit Reference
Living space of one storey -(2'( 175 m2 Chapter 4, the model
No. of floors extended ?'E8'$%'% 4 Pcs Appendix B
Superstructure production costs 1725% 27 938 SEK/m2 Appendix A, part 8h
Sales price in Stockholm City 1&("'& 90 875 SEK/m2 Appendix A, part 8h
Costs for cheapest geotechnical
0?/@@<%&'() 12 530 117 SEK Appendix G
work for case 1 and RD220
Costs for cheapest geotechnical
0?/AB<%&'() 17 718 532 SEK Appendix G
work for case 1 and RD170
Costs for cheapest geotechnical
0?/@@<%&'(* 12 530 117 SEK Appendix G
work for case 2 and RD220
Costs for cheapest geotechnical
0?/AB<%&'(* 18 731 670 SEK Appendix G
work for case 2 and RD170
2. Calculations
The production cost for a superstructure is calculated with the living space of four added storeys
to a final cost for the second case to the following:
The total costs are summed up for the second case to the following for RD220:
The total costs are summed up for the second case to the following for RD170:
The revenue is obtained with the sales price for the 4 added storeys that could be sold to:
Through the differences in revenues and costs, the following result is obtained for the second
case for both RD220 and RD170, respectively:
167
APPENDIX H
3. Results
The results of the investment cost, revenue and profitability for the two cases for both RD220
and RD170 are presented in the two following tables:
Table H2. Results for the first case for any profitability.
Case 1 results for any profitability Magnitude Unit
Investment cost for case 1 and RD220 12 530 117 SEK
Investment cost for case 1 and RD170 17 718 532 SEK
Revenue for case 1 and RD220 0 SEK
Revenue for case 1 and RD170 0 SEK
Results for case 1 and RD220 -12 530 117 SEK
Results for case 1 and RD170 -17 718 532 SEK
Table H3. Results for the second case for any profitability.
Case 2 results for any profitability Magnitude Unit
Investment cost for case 2 and RD220 32 086 717 SEK
Investment cost for case 2 and RD170 38 288 270 SEK
Revenue for case 2 and RD220 63 612 500 SEK
Revenue for case 2 and RD170 63 612 500 SEK
Results for case 2 and RD220 31 525 783 SEK
Results for case 2 and RD170 25 324 230 SEK
168