Egyptian Maintenance Company

GPC - Ras Ghareb District


WO.PARENT:
For Rigs Project
PM

Work Order No. : GPC-3147883 PM For PULLING WELL RIG COOPER # 4 LTO-250 (Onshore). Start date: 1/21/2022

Comp. Date: 1/28/2022


Work Type : PM Status: WAPPR
Next Due Date

Permit number W/O Priority: 3 Need Shutdown: YES NO

Equipment : RIG000002972 PULLING WELL RIG COOPER # 4 LTO-250 (Onshore).

Location : WORK0000000SHOP WORKSHOP EMC SITE

Job Plan : JP-ON-RIG-2M Job Plan for RIG Two Month (ONSHORE).

GL Account: : Originating W/O:

Operations DESCRIPTION Observation Est. Duration DONE (Y/N)


10.00 --------------------------- Engine------------------------------- 0.00
20.00 Change Lube Oil. 0.00
30.00 Replace Oil Filter. 0.00
40.00 Clean Engine Breather. 0.00
50.00 Add Coolant If Required. 0.00
60.00 Inspect All V-Belts Adjust Change If Necessary. 0.00
70.00 Clean Dust Collectors. 0.00
80.00 Clean & Lubricate Governer Linkages. 0.00
90.00 Change Fuel Filter. 0.00
100.00 Clean Air Filter. 0.00
110.00 Clean and Check Battery Electrolyte Level Add Distilled Water If Necessary. 0.00
120.00 Grease For Bearings. 0.00
130.00 Clean Radiator From Outside. 0.00
140.00 Inspect Hoses And Clamps. 0.00
150.00 Clean Primary Fuel Strainer. 0.00
160.00 Check Emergency Shut-Down Controls. 0.00
170.00 Inspect Turbocharger For Proper Operation. 0.00
180.00 Inspect Crankshaft Vibration Damper. 0.00
190.00 Inspect Air Compressor. 0.00
200.00 Inspect Water Pump. 0.00
210.00 Check Alternator. 0.00
220.00 Check Starting Motor. 0.00
230.00 ---------------------- Transmission -------------------------- 0.00
240.00 Check Transmission Oil Level And Color. 0.00

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 1 of 6
Egyptian Maintenance Company
GPC - Ras Ghareb District
WO.PARENT:
For Rigs Project
PM

250.00 Check All Forward and Reverse Speed Are Functioning Well. 0.00
260.00 Check Main Pressure Reading. 0.00
270.00 --------------------------- Carrier ----------------------------- 0.00
280.00 Check Right Angle Gearbox Oil Level / Add If Necessary. 0.00
290.00 Check Propeller Shaft Condition. 0.00
300.00 Grease Propeller Shaft Universal Joint. 0.00
310.00 Grease Main Drum Bearing. 0.00
320.00 Check Main Drum Clutch For Proper Engagement. 0.00
330.00 Grease Main Drum Idler Wheel Bearing. 0.00
340.00 Check Main Drum Chain Case Oil Level / Add If Necessary. 0.00
350.00 Check Main Drum Chain Links. 0.00
360.00 Check Main Drum Brake System For Proper Operation. 0.00
370.00 Check Main Drum Wire Rope Condition. 0.00
380.00 Grease Sand line Bearing. 0.00
390.00 Check Sand line Chain Links. 0.00
400.00 Check Sand line Chain Case Oil Level Add If Necessary. 0.00
410.00 Check Sand line Brake System For Proper Operation. 0.00
420.00 Check Sand line Wire Rope Condition. 0.00
430.00 Check Sand line Cathead Condition / Perform Any Required Repair. 0.00
440.00 Grease Cathead Bearing. 0.00
450.00 Check Raising Cylinder Pin. 0.00
460.00 Check Raising Cylinder Pin Holes. 0.00
470.00 Check Screw Jack Bolt. 0.00
480.00 Check Screw Jack Nut. 0.00
490.00 Check Telescoping Cylinder Pin. 0.00
500.00 Check Telescoping Cylinder Hole. 0.00
510.00 Check Cathead Condition. 0.00
520.00 Grease Cathead Bearing. 0.00
530.00 Check Cathead Chain. 0.00
540.00 Check Cathead Chain Oil Level. 0.00
550.00 Check Hydraulic Oil Tank Level. 0.00
560.00 Clean Hydraulic Filter. 0.00
570.00 Check Hydraulic Pump Pressure. 0.00
580.00 Check Hydraulic Pump Clutch For Proper Operation. 0.00
590.00 Check Hydraulic Piping / Hoses. 0.00

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 2 of 6
Egyptian Maintenance Company
GPC - Ras Ghareb District
WO.PARENT:
For Rigs Project
PM

600.00 Check Hydraulic Valves Functions. 0.00


610.00 Check Hydraulic Raising Cylinder Pressure. 0.00
620.00 Check Hydraulic Raising Cylinder For Leaks. 0.00
630.00 Check Hydraulic Telescoping Pressure. 0.00
640.00 Check Hydraulic Telescoping For Leaks. 0.00
650.00 Check Air Compressor Outlet Pressure / Perform Any Required Repair. 0.00
660.00 Clean Air Compressor Suction Filter. 0.00
670.00 Drain Air Tank. 0.00
680.00 Check Air Pressure Gauges. 0.00
690.00 Check Air Compressor Belts. 0.00
700.00 Clean Pneumatic System Filters /Lubricators. 0.00
710.00 Check Air Piping /Hoses For Leaks. 0.00
720.00 Check Air Control Valves. 0.00
730.00 Check Brakes for Proper Parking. 0.00
740.00 Check Steering Pump Outlet Pressure. 0.00
750.00 Check Steering Piping / Hoses. 0.00
760.00 Check Steering Cylinder for Leaks. 0.00
770.00 Check Steering Links. 0.00
780.00 Check Steering Tank Oil Level / Add If Necessary. 0.00
790.00 Check Differential Oil Level / Add If Necessary. 0.00
800.00 Check Reading Propeller Shaft. 0.00
810.00 Check Reading Propeller Shaft Universal Joint.. 0.00
820.00 Check Mast Second Stage Lock Pins / Cylinders. 0.00
830.00 Check Mast Pins / Replace If Necessary. 0.00
840.00 Check Mast Pins Holes / Repair If Necessary. 0.00
850.00 Check Racking Platform Pin. 0.00
860.00 Check Racking Platform Hole. 0.00
870.00 Check Racking Platform Fingers. 0.00
880.00 Check Racking Platform Board Walking. 0.00
890.00 Check Racking Platform Guys. 0.00
900.00 Check Racking Platform Shackles. 0.00
910.00 Grease Traveling Block Bearing. 0.00
920.00 Inspect Main Drum Rims. 0.00
930.00 Inspect Main Drum Idler Wheel. 0.00
940.00 Inspect Main Drum Sprocket Teeth. 0.00

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 3 of 6
Egyptian Maintenance Company
GPC - Ras Ghareb District
WO.PARENT:
For Rigs Project
PM

950.00 Inspect Sand line Idler Wheel. 0.00


960.00 Inspect Sand line Sprocket Teeth. 0.00
970.00 Inspect Sand line Drum Rims. 0.00
980.00 Visually Inspect Mast. 0.00

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 4 of 6
Egyptian Maintenance Company
GPC - Ras Ghareb District
WO.PARENT:
For Rigs Project
PM

Estimated Duration : 48.00 Actual EMC Duration: Total Actual Duration :

Remarks :
PM Status
Comp Cancel Hold

Technical Report :

Down time Signature


Date Action
EMC GPC EMC GPC

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 5 of 6
Egyptian Maintenance Company
GPC - Ras Ghareb District
WO.PARENT:
For Rigs Project
PM

GPC Oper. GPC Maint EMC Date Completed GPC Opearion GPC Maintenance GPC Approval
intiate Iniate

Page 6 of 6