Bungalow Demonstration

Your Name:_______________________

1
Page _____ 4
of _____
Div. 7 Thermal and Moisture Protection

Checklist: Asphalt Shingle Roof

Item: Units:

1. Eave Protection S.F.


2. Underlayment (one layer - 15 lb building paper*) S.F.
3. Metal Drip Edge Flashing @ Rakes L.F.
4. Metal Drip Edge flashing @ Eaves L.F.
5. Valley Protection (26 ga. X 24" wide gal. sheet metal) L.F.
6. Starter Strip @ Eaves L.F.
7. Asphalt Shingles on Plywood Sheathing (210lb**) S.Q.***
8. Cut/Fill Openings @ Collars, Vents & Fans Ea.
9. Cutting @ Hips, Valleys and Ridges Ea.
10. Step Flashings Ea.
11. Vertical Upstand Flashings L.F.
12. Hip and Ridge Caps S.Q.
13. Warranty (5year) S.Q.
14. Delivery S.Q.

* - … more properly referred to as No.15 non-perforated asphalt-saturated felt.


** - Most Manufacturers no longer quote mass, but rather as ten-year type, fifteen-year … thirty-year type.
*** - Round up to nearest 1/3 square, where applicable.
QUANTITY SHEET

PROJECT: Bungalow ESTIMATOR: Demonstration


LOCATION: EXTENSIONS: SHEET NO. 2 OF 4
DESIGNER: CHECKED: DATE:
DIV.NO. 7 DIV. TITLE Thermal and Moisture Protection DIV.SECTION Asphalt Roofing
Estimated
Description No. Dimensions Quantity Unit

ASPHALT ROOFING 36"x12" shingles; 29 shingles per bundle; one bundle covers 1/3 SQ

ROOF SLOPE = 5:12 NOTE:


38'-10"
dimensions to
1.083 outside (o/s)
0.417 face of walls

1 39'-0"

47'-9"
1.474
8'-4"
6'-9"

15'-6"
12'-0" 16" O.H.
P1 = 2(L + W + ΣR)
18'-6"

Eave Protection (3' wide self-adhering membrane)


L = 2(38.83+47.75+6.75)
horizontal adjustment calculation
L = 186.67 (o/s face of wall)
L = 186.67+(4x2x1.33) = 197.33
DDT gable 1: -
12.00+2(1.33) = (14.67)
DDT gable 2: - Two laps each at two corners
18.50+2(1.33) = (21.17)
161.50 161.50 3.00 - 484.50 SF
ADD @ inner corners for laps 2x2 3.00 3.00 - 36.00
520.50 SF 520 SF

Underlayment/ Felt Paper (one layer - 15lb building paper)


Overall Area:
L = 38.83 + 2(1.33) = 41.50 50.42 - 2092.29 SF
W = 47.75 + 2(1.33) = - - - -
DDT - SW Corner: 12.00+8.33= 20.33 8.75 - (177.92)
15.50-6.75= - - - -
DDT recess: W = 8.33 - 2(1.33)= 5.67 6.75 - (38.25)
1876.13 SF
Common Rafter Slope Factor ∗ 1.083
2031.84 SF
DDT - Eave Prot. (from abv.) (484.5 m2) - (484.50)
1547.34 SF
ADD - for Top Laps (2"/36"=6%) ∗ 1.060
1640.18 SF 1640 SF
QUANTITY SHEET

PROJECT: Bungalow ESTIMATOR: Demonstration


LOCATION: EXTENSIONS: SHEET NO. 3 OF 4
DESIGNER: CHECKED: DATE:
DIV.NO. 7 DIV. TITLE Thermal and Moisture Protection DIV.SECTION Asphalt Roofing
Estimated
Description No. Dimensions Quantity Unit

ASPHALT ROOFING CONT'D

Metal Drip-Edge Flashing @ Rakes


L1 gable 1 from above: 12+2(1.33) 14.67 - - 14.67 LF
L2 gable 2 from above: 18.5+2(1.33) 21.17 - - 21.17
35.83 LF
Common Rafter Slope Factor ∗ 1.083
38.81 LF 39 LF

Metal Drip-Edge Flashing @ Eaves


from Eave Protection: 161.50 - - 161.50 LF 161 LF

Valley Protection (26 ga. X 24" wide galv. sheet metal)


L1 = from abv 14.67/2 = 7.33 - - 7.33 LF
L2 = from abv 21.17/2 = 10.58 - - 10.58
17.92 LF
Hip Rafter Slope Factor ∗ 1.474
26.41 LF 26 LF

Starter Strip @ Eaves


from Eave Protection: 161.50 - - 161.50 LF 161 LF
1 2/3 SQ

Asphalt Shingles (210lb; 5/12 slope; allow 6% waste)


from Underlayment: (2031.84 SF) - 2031.84 SF 2032 SF
20 1/3 SQ

Cut/Fit Roof Openings


Plumbing Stacks 3 - - - 3 No.
Attic Vent 2 - - - 2
5 No. 5 No.
QUANTITY SHEET

PROJECT: Bungalow ESTIMATOR: Demonstration


LOCATION: EXTENSIONS: SHEET NO. 4 OF 4
DESIGNER: CHECKED: DATE:
DIV.NO. 7 DIV. TITLE Thermal and Moisture Protection DIV.SECTION Asphalt Roofing
Estimated
Description No. Dimensions Quantity Unit

ASPHALT ROOFING CONT'D

Cutting @ Hips, Valleys, Ridges


CRRun=(47.75+2(1.33)-15.50)/2 =
Common RafterRun = 17.46 LF
House Main Ridge:
38.83+2(1.33)-2(17.46) = 6.58 6.58 - - 6.58 LF
Hips and Valleys: - - - -
17.46 x1.474 = 4 25.73 - - 102.93
House Lower Ridge: - - - -
6.75+(12.00+2(1.33))/2 = 14.08 14.08 - - 14.08
Ridge above Garage: - - - -
15.50+(18.5+2(1.33))/2 = 26.08 26.08 - - 26.08
149.68 LF 150 LF
* two cuts per 3-tab shingle * 0.67 OR
=2 cuts per 3ft per shingle =0.67/ft 99.79 EA 100 EA

Hip and Ridge Caps (made of cut shingles - 1 shingle covers 1.25')
from Cutting abv: L= 149.68 LF (149.68LF) - 149.68 LF
DDT Valleys (26.41)
123.27 LF 123 LF
1 1/3 SQ

Warranty (5 year)
from Shingles (2031.84 SF) - 2031.84 SF (convert to SQ) 20 1/3 SQ

Delivery (include RoofTop Shingle Off-Loading)


from Shingles (20.33 SQ) - 20.33 SQ
add 6% waste - - - 1.22
from Capping (1.33 SQ) - 1.33
from Starter Strip @ Eaves (1.67 SQ) 1.67
24.55 SQ 25 SQ
OR 74 Bdl