You are on page 1of 28

PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR

Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

LV PANEL TESTING AND COMMISSIONING PROCEDURE

1. GENERAL INSPECTION
2. EARTH CONTINUITY TEST
3. CONTACT RESISTANCE MEASUREMENT (CRM)
4. INSULATION RESISTANCE TEST (BEFORE HV TEST)
5. HIGH VOLTAGE (HI-POT) TEST
6. INSULATION RESISTANCE TEST (AFTER HV TEST)
7. AMMETER CALIBRATION TEST REPORT
8. VOLTMETER CALIBRATION TEST REPORT
9. UNDER VOLTAGE (UV)/OVERVOLTAGE (OV) RELAY TEST
10. CURRENT TRANSFORMER TEST
11. VOLTAGE TRANSFORMER TEST
12. ENERGY METER (MULTIFUNCTION METER) TEST
13. BREAKER TEST REPORT (INCOMER & OUTGOING)
14. RELAY TEST (SBEF, REF RELAY)
15. FUNCTIONAL TEST
16. ENERGIZE PROCEDURE

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

1. VISUAL INSPECTION AND GENERAL CHECKS:


The Inspection of the LVAC Panels has been carried out as per the Erection Control Form
S. NO DETAILS OBSERVATION / RESULT
1. Dimensions Check
2. Paint Finish (Internal/External) & Thickness
3. Size of Main horizontal Busbar.
4. Availability of Earth bar or earth Strip
5. Bus bar R, Y, B Phase Identification
6. Check Firmness of connection- in Torque Wrench method
7. Door Handles, locks, keys & Hinges
8. Mimic diagram, Nameplates, labels, stickers etc.
9. Earthing of doors
10. Make, Rating and Type of Components
11. Identification of Components
12. Manual Operation of ACB / MCCB
13. Check the Proper Tightness of Busbar (Torque Wrench)
14. Cable Terminations
15. Arrangement as per the SLD
Document No:

2. EARTH CONTINUITY TEST:

S.NO DESCRIPTION STATUS


1 Ensure that the Panel / circuit under test is isolated from supply.
Using a Multi Meter check the continuity of all Earth points with
2
Earth bar.

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

3. INSULATION RESISTANCE TEST (Before HV Test):


As per IEC 60439-1 The-insulation resistance test shall be conducted on a power circuit with a 1000V
Megger Instrument. The insulation resistance value (Megger value) is recorded.
Description Applied Voltage (DC) Withstand Time IR value Remarks
R- (Y+B+N+E) * 1 kV 60 Sec
Busbar
Y- (R+B+N+E) 1 kV 60 Sec
Healthy
B- (Y+R+N+E) 1 kV 60 Sec
Found is Ok.
N- (R+Y+B+E) 1 kV 60 Sec

4. HIGH VOLTAGE TEST FOR 415V LVAC BOARD


*Applied voltage: 2.0 kV (80 % FAT Value i.e. 2.5 kV)
Description Applied Voltage (AC) With Stand Time Leakage Current(mA) Remarks
R- (Y+B+N+E) 2 kV 60 Sec
Busbar
Y- (R+B+N+E) 2 kV 60 Sec
Healthy
B- (Y+R+N+E) 2 kV 60 Sec Found is Ok.
N- (R+Y+B+E) 2 kV 60 Sec

5. INSULATION RESISTANCE TEST (After HV Test):


Description Applied Voltage (DC) Withstand Time IR value Remarks
R- (Y+B+N+E) 1 kV 60 Sec
Busbar
Y- (R+B+N+E) 1 kV 60 Sec
Healthy
B- (Y+R+N+E) 1 kV 60 Sec Found is Ok.
N- (R+Y+B+E) 1 kV 60 Sec

Note: **When applying HV voltage to Rϕ, short and ground the other Phases and Neutral. Also, similarly
vice versa for other Phases as mentioned in the above table.

Insulation Resistance Acceptance Criteria:


Test & Acceptance as per IEEE C57.152 Clause# 7.2.13
1MΩ/kV system voltage is acceptable.

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

7. AMMETER CALIBRATION:

7.1 INCOMER -M1 R-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600/5 A
Type : D96LMC Range : 0-1600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.2 INCOMER -M1 Y-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600/5 A
Type : D96LMC Range : 0-1600 A
Injected Secondary Expected Meter Current Ammeter Reading
% Error
Current in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.3 INCOMER -M1 B-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600/ 5 A
Type : D96LMC Range : 0-1600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

7.4 INCOMER -M2 R-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600 /5 A
Type : D96LMC Range : 0-1600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.5 INCOMER -M2 Y-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600/5 A
Type : D96LMC Range : 0-1600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.6 INCOMER -M2 B-Phase Ammeter Calibration:


Make : HOBUT CT Ratio : 1600/5 A
Type : D96LMC Range : 0-1600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
400 400
800 800
1200 1200
1600 1600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

7.7 OUTGOING T3M5- Ammeter Calibration:


Make : HOBUT CT Ratio : 400/5 A
Type : D96LMC Range : 0-400 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R, Y, B) in Amps in Amps ( R, Y, B)
100 100
200 200
300 300
400 400
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.8 OUTGOING T3M6- Ammeter Calibration:


Make : HOBUT CT Ratio : 400/5 A
Type : D96LMC Range : 0-400 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R, Y, B) in Amps in Amps ( R, Y, B)
100 100
200 200
300 300
400 400
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.9 OUTGOING T4M5- Ammeter Calibration:


Make : HOBUT CT Ratio : 600/5 A
Type : D96LMC Range : 0-600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R, Y, B) in Amps in Amps ( R, Y, B)
100 100
200 200
300 300
400 400
500 500
600 600

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100


Ammeter Found Healthy : YES / NO

7.10 OUTGOING T4M6- Ammeter Calibration:


Make : HOBUT CT Ratio : 600/5 A
Type : D96LMC Range : 0-600 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps (R,Y,B) in Amps in Amps ( R,Y,B)
100 100
200 200
300 300
400 400
500 500
600 600
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.11 OUTGOING T6M3- Ammeter Calibration:


Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps (R,Y,B) in Amps in Amps (R,Y,B)
50 50
100 100
150 150
200 200
250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.12 OUTGOING T6M4- Ammeter Calibration:


Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps in Amps in Amps
50 50
100 100
150 150
200 200

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.13 OUTGOING T7M3- Ammeter Calibration:


Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R,Y,B) in Amps in Amps ( R,Y,B )
50 50
100 100
150 150
200 200
250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.14 OUTGOING T7M4- Ammeter Calibration:


Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R,Y,B) in Amps in Amps ( R,Y,B )
50 50
100 100
150 150
200 200
250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

7.15 OUTGOING T7M5- Ammeter Calibration:


Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R,Y,B) in Amps in Amps ( R,Y,B )
50 50
100 100
150 150

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

200 200
250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO
7.16 OUTGOING T6M5- Ammeter Calibration:
Make : HOBUT CT Ratio : 250/5 A
Type : D96LMC Range : 0-250 A
Injected Primary Current Expected Meter Current Ammeter Reading
% Error
in Amps ( R,Y,B) in Amps in Amps ( R,Y,B )
50 50
100 100
150 150
200 200
250 250
% of Error = (Actual Reading – Expected Reading) / (Full scale Reading) *100
Ammeter Found Healthy : YES / NO

8.VOLTMETER CALIBRATION:
8.1 INCOMER -M1 Voltmeter Calibration:
Make : HOBUT VT Ratio :-
Type : D96LMC Range : 0-500 V
Measured Voltage Frequency
Phase Injected Voltage Injected
U12 U23 U31 (HZ)
R-N 240
Y-N 240
B-N 240
R-Y-B-N 415
Voltmeter Found Healthy : YES / NO

8.2 INCOMER -M2 Voltmeter Calibration:


Make : HOBUT VT Ratio :-
Type : D96LMC Range : 0-500 V
Measured Voltage Frequency
Phase Injected Voltage Injected
U12 U23 U31 (HZ)
R-N 240
Y-N 240

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

B-N 240
R-Y-B-N 415
Voltmeter Found Healthy : YES / NO

9. BREAKER TEST REPORT

INCOMER ACB :

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag Incomer – M1
Rated Current (In) 1600A
In
IR
Overload
tr
(L)
Temp
L Trip time (Sec)
Isd
Selective
Isd * t = Flat
Short
tsd
Circuit (S)
S Trip Time (mSec)
Ig
Earth Fault I*t
( G) tg
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag Incomer – M2
Rated Current (In) 1600A
In
IR
Over load
tr
(L)
Temp
L Trip time (Sec)
Isd
Selective
Isd * t = Flat
Short
tsd
Circuit (S)
S Trip Time (mSec)
Ig
Earth Fault I*t
( G) tg
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M1
Rated Current (In) 63A
IR Range 0.63 -1.0
Long IR Setting 1.0
Time Current Injected (A) 315A
L Trip time (Sec)
Short Ii Range 6-12
Time Ii Setting 12
Current Injected (A) 800A

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

S Trip Time (m Sec)


Manual Close/Trip from Push Button Found is ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M2
Rated Current (In) 63A
IR Range 0.63 -1.0
Long IR Setting 1.0
Time Current Injected (A) 315A
L Trip time (Sec)
Ii Range 6 - 12
Short Ii Setting 12
Time Current Injected (A) 800A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found is ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M3
Rated Current (In) 63A
IR Range 0.63 -1.0
Lo
IR Setting 1.0
ng
Current Injected (A)
Ti 315A
0.63*20*5=63 A
me
L Trip time (Sec)
Ii Range 6 - 12
Sh
Ii Setting 12
ort
Current Injected (A)
Ti 800A
(20*0.63)*6*3=567 A
me
S Trip Time (m Sec)
Manual Close/Trip from
Found is Ok
Push Button

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M4
Rated Current (In) 125A
IR Range 0.63 -1.0
Long IR Setting 0.63
Time Current Injected (A) 0.63*20*5=63 A 394A
L Trip time (Sec)
Ii Range 6-12
Ii Setting 10
Short
Current Injected (A) (20*0.63)*6*3=567
Time 1300
A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M5
Rated Current (In) 400A
In 1.0
IR 1.0
Over load tr 30.00
(L) Temp Cold
Injected Current (A) 1600A
L Trip time (Sec)
Isd 1.0 ( For Test Reference Setting)
Selective Isd * t = Flat FLAT
Short tsd 0.30
Circuit (S) Injected Current (A) 500
S Trip Time (mSec)

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Ig 0.2
I*t flat
Earth Fault
tg 0.2
( G)
Injected Current (A) 90A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found is ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T3-M6
Rated Current (In) 400A
In 1.0
IR 1.0
Overload tr 30.00
(L) Temp Cold
Injected Current (A) 1600A
L Trip time (Sec)
Isd 1.0 ( For Test Reference Setting)
Selective Isd * t = Flat FLAT
Short tsd 0.30
Circuit (S) Injected Current (A) 500 A
S Trip Time (mSec)
Ig 0.2
I*t flat
Earth Fault
tg 0.2
( G)
Injected Current in A 90A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found ok.

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M1

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Rated Current (In) 63A


IR Range 0.63 – 1.0
Long IR Setting 0.63
Time Current Injected (A) 199A
L Trip time (Sec)
Ii Range 6 – 12
Short Ii Setting 12
Time Current Injected (A) 800A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M2
Rated Current (In) 250A
IR Range 0.63 – 1.0
Long IR Setting 0.8
Time Current Injected (A) 1000 A
L Trip time (Sec)
SC Curve Range 1 -12
Short SC Curve Setting 5
Time Current Injected (A) 1300
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M3
Rated Current (In) 250A
IR Range 0.63 – 1.0
Long IR Setting 0.8
Time Current Injected (A) 1000 A
L Trip time (Sec)
Ii Range 1 -12
Short Ii Setting 5
Time Current Injected (A) 1300
S Trip Time (m Sec)

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M4
Rated Current (In) 50A
IR Range 0.63 – 1.0
Long IR Setting 0.8
Time Current Injected (A) 200A
L Trip time (Sec)
Ii Range 6 – 12
Short Ii Setting 12
Time Current Injected (A) 600
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M5
Rated Current (In) 630A
In 0.63 – 1.0
IR 0.63
Overload
Injected Current ( A) 1580 A
(L)
Temp Cold
L Trip time (Sec)
Selective SC.Curve Range 1 -12
Short SC Curve Charac. Setting 2 ( For Testing reduced Setting)
Circuit (S) Injected Current 1300

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

S Trip Time (mSec)


Manual Close/Trip from Push Button Found ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T4-M6
Rated Current (In) 630A
In 0.63 – 1.0
IR 0.63
Overload
Injected Current ( A) 1580 A
(L)
Temp Cold
L Trip time (Sec)
SC.Curve Range 1 -12
Selective
SC Curve Charac. Setting 2 ( For Testing reduced Setting)
Short
Injected Current 1300
Circuit (S)
S Trip Time (mSec)
Manual Close/Trip from Push Button Found ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M1
Rated Current (In) 63A
IR Range 0.63 – 1.0
Long IR Setting 0.63
Time Current Injected (A) 199 A
L Trip time (Sec)
Short Ii Range 6 - 12
Time Ii Setting 12
Current Injected (A) 800 A

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

S Trip Time (m Sec)


Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M2
Rated Current (In) 250A
IR Range 0.63 – 1.0
Overloa IR Setting 0.63
d (L) Current Injected (A) 790
L Trip time (Sec)
SC curve charc. Range 1 – 12
Short
SC Curve Setting 2 ( For Testing purpose reduced setting)
Circuit
Current Injected (A) 600 A
(S)
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M3
Rated Current (In) 250A
IR Range 0.63 – 1.0
Overloa IR Setting 0.63
d (L) Current Injected (A) 790
L Trip time (Sec)
SC curve charc. Range 1 – 12
Short
SC Curve Setting 2 ( For Testing purpose reduced setting)
Circuit
Current Injected (A) 600 A
(S)
S Trip Time (m Sec)

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M4
Rated Current (In) 250A
IR Range 0.63 – 1.0
Overloa IR Setting 0.63
d (L) Current Injected (A) 790
L Trip time (Sec)
SC curve charc. Range 1 – 12
Short
SC Curve Setting 2 ( For Testing purpose reduced setting)
Circuit
Current Injected (A) 600 A
(S)
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Breaker Tag T5-M5 (SPARE)


Rated Current (In) 63A
IR Range 0.63 – 1.0
Long IR Setting 0.63
Time Current Injected (A) 315A
L Trip time (Sec)
Ii Range 6 -12
Short Ii Setting 12
Time Current Injected (A) 800 A
S Trip Time (mSec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M6
Rated Current (In) 63A
IR Range 0.63 – 1.0
Long IR Setting 1.0
Time Current Injected (A) 315 A
L Trip time (Sec)
Ii Range 6- 12
Short Ii Setting 12
Time Current Injected (A) 800 A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Breaker Tag T5-M7


Rated Current (In) 125A
IR Range 0.63 – 1.0
Long IR Setting 1.0
Time Current Injected (A) 625 A
L Trip time (Sec)
Ii Range 6 – 12
Short Ii Setting 12
Time Current Injected (A) 1600 A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T5-M8
Rated Current (In) 250A
IR Range 0.63 -1.0
Long IR Setting 1.0
Time Current Injected (A) 1250 A
L Trip time (Sec)
Ii Range 0.63 -12
Short Ii Setting 12
Time Current Injected (A) 3000
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T6-M1
Rated Current (In) 125A

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

IR Range 0.63- 1.0


Long IR Setting 0.63
Time Current Injected (A) 394 A
L Trip time (Sec)
Ii Range 6 -12
Short
Ii Setting 10
Time
Current Injected (A) 1300
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T6-M2 ( SPARE)
Rated Current (In) 125A
IR Range 0.63 – 1.0
Long IR Setting 1.0
Time Current Injected (A) 625 A
L Trip time (Sec)
Ii Range 6 – 12
Short Ii Setting 12
Time Current Injected (A) 1500
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T6-M3 ( NB-LF-LVS-0001)
Rated Current (In) 400A
Overload In 0.63
(L) IR 1.0
tr 30 s
Temp Cold

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Injected Current (A) 1260A


L Trip time (Sec)
Isd 1.0 ( for Testing Purposes reduced Setting )
Selective Isd * t = Flat Flat
Short tsd 0.30
Circuit (S) Injected Current ( A) 500A
S Trip Time (mSec)
Ig 0.20
I*t Flat
Earth Fault
tg 0.20 S
( G)
Injected Current ( A) 90A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T6-M4 (NB-LF-LVS-0001-F2)
Rated Current (In) 400A
In 0.63
IR 1.0
Overload tr 30 s
(L) Temp Cold
Injected Current ( A) 1260A
L Trip time (Sec)
Isd 1.0 ( for Testing Purposes reduced Setting )
Selective Isd * t = Flat
Short tsd 0.30
Circuit (S) Injected Current ( A) 500A
S Trip Time (mSec)
Ig 0.20
I*t Flat
Earth Fault
tg 0.20 S
( G)
Injected Current ( A) 90A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found Ok

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T6-M5 (SPARE)
Rated Current (In) 400A
In 0.63
IR 1.0
Overload tr 30 s
(L) Temp Cold
Injected Current ( A) 1260A
L Trip time (Sec)
Isd 1.0 ( for Testing Purposes reduced Setting )
Selective Isd * t = Flat
Short tsd 0.30
Circuit (S) Injected Current ( A) 500A
S Trip Time (mSec)
Ig 0.20
Earth Fault
I*t Flat
( G)
tg 0.20 S
Injected Current ( A) 90A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T7-M1 (SPARE)
Rated Current (In) 63A
IR Range 0.63 – 1.0
Long IR Setting 1.0
Time Current Injected (A) 315 A
L Trip time (Sec)
Ii Range 6-12
Short Ii Setting 12
Time Current Injected (A) 800 A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T7-M2 ( SPARE)
Rated Current (In) 50A
IR Range 0.63 -1.0
Long IR Setting 1.0
Time Current Injected (A) 250 A
L Trip time (Sec)
Ii Range 6- 12
Short Ii Setting 12
Time Current Injected (A) 700A
S Trip Time (m Sec)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T7-M3 ( NB-PW-LVS-0001-F1)
Rated Current (In) 400A
In 0.50
IR 1.0
Overload tr 30.00
(L) Temp Cold
Injected Current ( A) 1000A
L Trip time (Sec)
Isd 1.0 ( For Testing Purposes reduced Setting )
Selective Isd * t Flat
Short tsd 0.30
Circuit (S) Injected Current ( A) 400A
S Trip Time (mSec)
Ig 0.20
I*t Flat
Earth Fault
tg 0.2
( G)
Injected Current (A) 50A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T7-M4 ( NB-PW-LVS-0001-F2)
Rated Current (In) 400A
In 0.50
IR 1.0
Overload tr 30.00
(L) Temp Cold
Injected Current ( A) 1000A
L Trip time (Sec)
Isd 1.0 ( For Testing Purposes reduced Setting )
Selective Isd * t Flat
Short tsd 0.30
Circuit (S) Injected Current ( A) 400A
S Trip Time (mSec)
Ig 0.20
Earth Fault
I*t Flat
( G)
tg 0.2
Injected Current (A) 50A
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button Found Ok

PHASE REFERENCE R Y B
Panel Tag NB-UTS-LVS-0002
Breaker Tag T7-M5 (NB-UTS-PFC-0002)
Rated Current (In) 400A
In
IR
Overload
tr
(L)
Temp
L Trip time (Sec)
Isd
Selective
Isd * t = Flat
Short
tsd
Circuit (S)
S Trip Time (mSec)
Earth Fault Ig
( G) I*t

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

tg
G Trip Time (mSec)
Instantaneo
I= Non NA
us (i)
Manual Close/Trip from Push Button

15.FUNCTIONAL TEST

15.1 FUNCTIONAL TEST (LOCAL/MANUAL/BREAKER SERVICE POSITION)

INCOMER M1 INCOMER M2
BREKAER
CLOSE

Breaker Close Possible :✔


Breaker Close Not Possible : ❌

16.ENERGIZATION PROCEDURE:
Ensure LVAC Incomer -1,2, Bus Coupler Breakers are in Open Position, then Energies Auxiliary
Transformer -1,2 by closing the respective HV Circuit Breakers.
1. Check supply connected at both incoming, Voltage level and phase sequence.
2. Check the presence of the mechanical protectors preventing any accidental contact with
Live Parts.
3. Open the outgoing circuit breakers.
4. Supply Distribution Board via the Auxiliary Transformers check for voltage and correct
phase sequence and Polarities.
5. Upstream of all circuit breakers indictors and protections.
6. Check the distribution board alarm information return up to the output terminal blocks.
PHASE SEQUENCE CHECK:
Phase Sequence Remarks
R–Y–B

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date
PROJECT TITLE: NEW NAVAL BASE PROJECT/NPP0050 Manufacturer: AL BIDDA SWITCHGEAR
Name of Substation/Panel : NB-UTS-LVS-0002 ( UTILITY BUILDING )

Y–B–R
B–R-Y
PLACING INTO SERVICE:
1. Energization of the LVAC board after closing of the main circuit-breaker.
2. Check that all necessary protective and signaling devices are in services.
3. Close all outgoing circuit-breaker, when necessary, after checking of the corresponding power
cable.
4. Phase out supplies with reference supply.

SUB CONTRACTOR : AYT CONTRACTOR: QBC PMC: REQ


Signatur Signatur Signatur
eName eName eName
Date Date Date