You are on page 1of 2

DOC NO.

: D-2-01-03-01-04

PRE-COMMISSIONING FORMATS FOR WAVE TRAP

I. GENERAL DETAILS

DETAILS
Region: North East Sub-Station:400/132KV Yurembam SS
Feeder name: 410/ SILCHAR-2 Make: CGL
Phase: Y-Φ & B-Φ Voltage Rating :420 kV
Current Rating :3020A
Year of Manufacture:2017 Type:
Band Width: mH Rating:
Date of Erection Date Of Energisation:

II. Pre-Commissioning Checks


S.N Description Status TEST
(YES/NO) RESULTS (OK/
NOT OK)
1 Equipment is free from dirt/dust foreign materials etc Yes Ok
2 Equipment is free from all visible defects on Yes Ok
physical inspection
3 Support structures has been provided with double Yes Ok
earth
4 All nuts and bolts are tightened correctly as per Yes Ok
specified Torque
5 Permanent lavelling and identification is done Yes Ok
6 Leveling and alignment of structure and base frame Yes Ok
is checked
7 All insulators & line matching unit are free from Yes Ok
any physical defects
8 Tightness of nuts / bolts of terminal connectors are Yes Ok
checked
9 Erection completion certificate along with list of Yes Ok
outstanding Activities reviewed
10 Check that the tuning unit and arrestor are Yes Ok
properly tightened and free from any damage
11 Tuning unit connection as per PLCC frequency Yes Ok

III. INSULATION RESISTANCE MEASUREMENT :

EQUIPMENT USED: DIGITAL MULTIMETER Calibration date: 1.10.18


Make: MOTWANE Sl. No: w8248658

Permissive
Between value R-Φ Y-Φ B-Φ

Upper Terminal and Earth >1000 M.OHM - 4.44 GΩ 4.34 GΩ


LA of the Wave Trap >1 M.OHM -

Wave Trap Format No.: CF/WT/09/R-4 DATED 21/09/2018

Page 1 of 2
DOC NO.: D-2-01-03-01-04

IV. Contact Resistance Measurement :


Make of testing kit Scope
Date of calibration 09/04/2019

Contact Resistance Units R-Φ Y-Φ B-Φ


Across Terminal P1 µΩ NA 18.4 µΩ 17.4 µΩ
Across Terminal P2 µΩ NA 9.7 µΩ 9.8 µΩ

V. Final Documentation Review:


1. Final documents of Pre- Commissioning checks reviewed and approved

Yes No

2. Document regarding spares equipment, O&M manuals etc available at sit for O&M purpose
Yes No

3. After modification, if any, “As built Drawings” are available at site

Yes No

Signature: Signature: Signature: Signature:

Name: Name: Name: Name:

Desgn.: Desgn.: Desgn.: Desgn.:

Organization: (Erection Agency) (POWERGRID Site (POWERGRID


(Supplier I/C) Commg. Team)
Representative) Members:
(Wherever 1.
Applicable) 2.
3.

Wave Trap Format No.: CF/WT/09/R-4 DATED 21/09/2018

Page 2 of 2