F04(PRJ(SOL)-P-01)/12-1 PRE-COMMISSIONING TEST REPORT FOR


Revision No. 00 33kV HT CABLE
Date: 16.12.2020

PRE-COMMISSIONING TESTS FOR 33kV HT CABLE

I. GENERAL DETAILS
DETAILS
Project: 50 MW SOLAR PLANT, HASAPUR Sub-Station: ICR- 02

Feeder name: ICOG PANEL LOA/PO No.:

Make: TCL CABLE Type: HT CABLE,XLPE

Sr. No: NA AC Voltage Rating: 33 kV

Cable Size: 3C*185 sq mm Feeder From: IDT-02

Feeder To: HT PANEL ICOG(INCOMING) Year of Manufacture: 2022

Date of Completion of Erection: Date of Commissioning:

II. CHECK LISTS OF TESTS CARRIED OUT FOR 33kV HT CABLE


Performed Test Results
Sl. No. Name of Tests
(Yes/No) (Ok/Not Ok)
1 Physical Inspection YES OK
2 Insulation Resistance Measurement YES OK
3 Continuity for each core YES OK
4 Hi-Voltage Test (DC Voltage test) YES OK
5 Phase Marking Checks YES OK
6 Checks on End Termination Kit YES OK

III. PRE-COMMISSIONING CHECKS:


Sl. Status Remarks
Description
No YES NO Deficiencies, If any
1 Equipment is free from dirt/dust foreign materials etc. YES
2 Signed Cable Laying Check sheet reviewed. YES
3 Straight Through Joints (if open) inspected. YES
Termination inspection done. No sharp edges near to termination kit and YES
4
free from any physical damage.
5 Permanent leveling and identification is done. YES
Cable Laying completion certificate along with list of outstanding YES
6
activities reviewed.

Signature: Signature: Signature: Signature: Signature:

Name: Name: KASHYAP PATEL Name: Name: GOWTHAM Name: RATIKANT SAHOO
Designation: Erection
Designation: Testing Er. Designation: Erection Er. Designation: Testing Er. Designation: Quality Er.
Er.
Organization: Main
Organization: Main Bidder Organization: Renew Organization: Renew Organization: Renew
Bidder
Document No.
F04(PRJ(SOL)-P-01)/12-1 PRE-COMMISSIONING TEST REPORT FOR
Revision No. 00 33kV HT CABLE
Date: 16.12.2020

IV. IR TEST BEFORE HIPOT TEST:


INSULATION RESISTANCE MEASUREMENT

Make & Sl. No. of Testing Kit : FLUKE & 2560001


Date of Last Calibration of Kit : 16/07/2022
Ambient Temp in ºC : 320C
Date of Testing : 18/10/2022

SL. NO. BETWEEN MEGGER PERMISSIVE VALUE MEASURED VALUE


1 R-Phase & Earth 5000 V >1000 MΩ >1 TΩ
2 Y-Phase & Earth 5000 V >1000 MΩ >1 TΩ
3 B-Phase & Earth 5000 V >1000 MΩ >1 TΩ
4 R-Phase & Y-Phase 5000 V >1000 MΩ >1 TΩ
5 Y-Phase & B-Phase 5000 V >1000 MΩ >1 TΩ
6 B-Phase & R-Phase 5000 V >1000 MΩ >1 TΩ

V. CONTUINITY TEST
Make & Sl. No. of testing kit : FLUKE & 37911953WS
Date of last calibration of the kit : 18/07/2022
Ambient temp in ºC : 320C
Date of Testing : 18/10/2022
Sr. No. DESCRIPTION TYPE OF CHECKS CHECKED STATUS
1 R-Phase Electrical YES OK
2 Y-Phase Electrical YES OK
3 B-Phase Electrical YES OK

VI. HI-VOLTAGE TEST (DC VOLTAGE)


Make of testing kit : TELEMATRIX & 0612/01
Date of calibration : 19/07/2022
Ambient temperature : 320C
Date of Testing : 17/10//2022

Sr. INJECTED VOLTAGE HI-POT LEAKAGE


REFERENCE DURATION RESULTS
No. (DC) CURRENT (mA)
1 R +(Y+B+E) 53 KV 0.02 60 sec WITHSTOOD
2 Y+(R+B+E) 53 KV 0.02 60 sec WITHSTOOD
3 B+(R+Y+E) 53 KV 0.01 60 sec WITHSTOOD

Signature: Signature: Signature: Signature: Signature:

Name: Name: KASHYAP PATEL Name: Name: GOWTHAM Name: RATIKANT SAHOO
Designation: Erection
Designation: Testing Er. Designation: Erection Er. Designation: Testing Er. Designation: Quality Er.
Er.
Organization: Main
Organization: Main Bidder Organization: Renew Organization: Renew Organization: Renew
Bidder
Document No.
F04(PRJ(SOL)-P-01)/12-1 PRE-COMMISSIONING TEST REPORT FOR
Revision No. 00 33kV HT CABLE
Date: 16.12.2020

VII. IR TEST AFTER HIPOT TEST:


INSULATION RESISTANCE MEASUREMENT

Make & Sl. No. of Testing Kit : FLUKE & 2560001


Date of Last Calibration of Kit : 16/07/2022
Ambient Temp in ºC : 320C
Date of Testing : 17/10/2022

SL. NO. BETWEEN MEGGER PERMISSIVE VALUE MEASURED VALUE


1 R-Phase & Earth 5000 V >1000 MΩ >1 TΩ
2 Y-Phase & Earth 5000 V >1000 MΩ >1 TΩ
3 B-Phase & Earth 5000 V >1000 MΩ >1 TΩ
4 R-Phase & Y-Phase 5000 V >1000 MΩ >1 TΩ
5 Y-Phase & B-Phase 5000 V >1000 MΩ >1 TΩ
6 B-Phase & R-Phase 5000 V >1000 MΩ >1 TΩ

VIII. FINAL DOCUMENTATION REVIEW


i. Factory test results are available
YES NO

ii. Final documents of Pre- Commissioning checks reviewed and approved.


YES NO

Signature: Signature: Signature: Signature: Signature:

Name: Name: KASHYAP PATEL Name: Name: GOWTHAM Name: RATIKANT SAHOO
Designation: Erection
Designation: Testing Er. Designation: Erection Er. Designation: Testing Er. Designation: Quality Er.