Professional Documents
Culture Documents
g
e
n
d
a
Economic impact
For new lines, accurate cross-belt analysis may avoid significant investments in pre-
homo system installation and minimize the size of homo-silos. Such an installation
costs about 0.5 million US$ (unit itself costs from 250,000 to 350,000$). Capital cost
savings for large projects can range in order of magnitude of $1 million to $10 million.
Operating cost implications in plants are on the order of magnitude of $1 million/year.
The realization of expected payback depends not only on the analytical and control
success of the planned application (does the project meet the control objectives?) but
also on realization of extended benefits from kiln-feed uniformity (i.e. the extent that kiln
operations capitalize on improved consistency to operate the pyro-process line more
efficiently). Continued control success over the long term requires adequate and well-
documented procedures for maintenance and calibration of the analyzer and software
system.
Future Directions
Going forward the cement industry has opportunities to manage increasing raw-material
and fuel complexity with further adaptations of PGNA technology. The industry can
expect several trends/ innovations likely to occur in this area:
Continued improvement in analyzer performance (e.g., detectors);
Increased sophistication of compensation methods (e.g., for layering);
Evolving computer platforms for analyzers;
Increasing numbers of plants with multiple PGNA and other on-line analyzers;
Further development and application of software solutions to reduce investment in
physical equipment;
Increasing variations of applications conceived by cement makers.
The ability of the analyzer manufacturers to continue to decrease the project costs in
constant dollars will favour the continued expansion of applications by progressive
cement makers. The continued evolution of the component technology should enable
this progression. Competitively priced analyzer systems, may prove applicable in down-
stream areas of the plant, such as kiln feed, clinker, fuels and even cement production.
Championship
Whether with development of new applications or a routine PGNAA application in a
plant, the single greatest determinant for success remains the quality of the project and
sustaining Champion.
For those new to the technology or planning on installing a system the sections relating
to the parts “A” would have the most relevance.
Those already having an analyzer can compare their status and procedures to parts
“B”.
Strong emphasis was put on the safe use of a CBA analyzer, in dealing with its
radioactive source.
Knowledge consolidation and data gathering for all types of CBA used make this study
a referential to any current or potential user of cross-belt analyzers.
1. Objectives
The aim of this study is to ensure the right selection, installation and use of cross-belt
analyzers for raw materials, and the accuracy and reliability of analysis.
2. Results
This report and its appendices include:
a) A brief description of the analyzers from different manufacturers, and assesses
their differences (operating principle, functionalities, and performance)
b) Review of status of current industrial applications (limestone, raw mix, clinker,
fuels etc…)
c) Review analyzer performance for different elements and characteristics of
material to analyze.
d) Installation guidelines to provide spectrometer stability and repeatability of
results
e) Procedures for calibration
f) Examples of incidents and recommended maintenance practices
g) A troubleshooting guide to ensure accurate results
The appendices include further details and examples in some of these areas.
3. Recommendations
a) Safety: In order to maintain a safe working environment,
plants should implement the following actions:
Each site must have a Radiation Safety Officer (RSO) certified from the nuclear
authority as able to handle the radiation sources and responsible to ensure
compliance with the jurisdiction’s regulations.
Each site shall have a Radiation Safety Program supervised by the RSO, including
annual audit procedures and emergency/ contingency plans.
The cross-belt analyzer (CBA) area should be considered restricted in terms of
access. As a minimum, clear signage and policy define the restriction, depending
The cement industry and Lafarge use analyzers in several different types of
applications, for example pile control and raw-mix control. New applications should
reference prior applications to benefit from the experience of others. A SIMIX study
should be obligatory for applications where a change in the existing control logic
(pile building or raw mill control) is proposed.
The basic choice between pile applications, raw-mix control (or both) depends on
the source of variations and control levers available to mitigate the variations. New
analyzer projects should identify these aspects and where possible reference pre-
existing analogous sites inside and/or outside Lafarge.
d) Analyzer Selection
Bid comparison
Each project should use a bid comparison table. Each Zone should share bid
comparison tables and develop a complete table template.
Guarantees
The project guarantees should include a static and dynamic method. The
project should ensure comparability by addressing the pertinent variables, for
example, specifying the time integration, belt loading, neutron source load /
flux.
The Zone experts should develop a common request document to formulate
the pertinent variables.
Service and support
At the time of purchase the negotiation should include the terms and cost of the
maintenance contract. The plant and Technical Centre should evaluate their local
context (examples: criticality of application, availability and proximity of service rep
and plant capability to perform maintenance and calibration) to determine the scope
of the required service contract. Scope examples: number of days available -- five
or seven per week, 24-hr service availability, calibration assistance. See
maintenance section for more details.
g) Maintenance
Maintenance applies to the analyzer and its electronics as well as related sub-
systems, such as communications, belt-load control, impact protection ploughs and
over-height sensors.
The maintenance planning schedule for the plant should include these systems. At
some sites the context would require a site maintenance champion with an
instrumentation background to be responsible for preventive and corrective
maintenance of all laboratory equipment including the CBA.
2. Safety ________________________________________________________ 18
2.1. SAFETY __________________________________________________________ 19
2.2. CROSS BELT ANALYZER RADIATION (ISOTOPE NEUTRON SOURCE)______________ 20
2.3. CBA RADIATION DOSE RATE MAP ______________________________________ 21
2.4. THE SAFE DISTANCE ________________________________________________ 23
2.4.1. Radiation Safety for Neutron-generator-type instruments ____________________ 24
2.4.2. Neutron Emitting Module handling______________________________________ 24
2.4.3. Electrical Hazard ___________________________________________________ 25
2.4.4. Source Leakage Test________________________________________________ 26
3. Applications ___________________________________________________ 27
3.1. INTRODUCTION ____________________________________________________ 28
3.2. DECISION TO INSTALL AN ANALYZER ____________________________________ 28
3.3. PGNAA VERSUS ALTERNATIVES _______________________________________ 30
3.4. QUARRY / NON-BLENDING STOCKPILE APPLICATIONS (A, B, C, J, K, L)___________ 34
3.5. BLENDING PILE APPLICATIONS _________________________________________ 34
3.6. RAW MILL AND DOWNSTREAM PROCESS CONTROL AND MONITORING ____________ 37
3.7. CHOICE OF CONTROL STRATEGY _______________________________________ 38
3.8. LAFARGE PLANTS - TECHNOLOGY EVOLUTION _____________________________ 39
3.9. STOCK PILE CONTROL _______________________________________________ 40
3.10. RAW MIX CONTROL _________________________________________________ 41
3.11. RAW MIX CONTROL – WET PROCESS ____________________________________ 41
3.12. APPLICATIONS OUTSIDE CEMENT _______________________________________ 43
7. Maintenance___________________________________________________ 93
7.1. INTRODUCTION ____________________________________________________ 94
7.2. VALUE OF PREVENTIVE MAINTENANCE ___________________________________ 94
7.3. PRESENTATION OF TA CBA MAINTENANCE APPENDIX _______________________ 96
7.4. CORRECTIVE MAINTENANCE FOR THERMO GAMMA METRICS (TROUBLESHOOTING GUIDE)
________________________________________________________________ 96
8. Appendix _____________________________________________________ 99
8.1. LAFARGE CBA TECHNICAL COMPARISON ________________________________ 100
8.2. LAFARGE CBA LIST 2012 ___________________________________________ 100
8.2.1. Printable A3 table mentioned in Chapter 3.8 _____________________________ 100
8.2.2. CBA Division dashboard 1: CBA Lafarge repartition per TC _________________ 100
8.2.3. CBA Division dashboard 2: CBA Lafarge repartition _______________________ 100
8.3. CBA INSTALLATION ________________________________________________ 100
8.4. CBA MAINTENANCE ________________________________________________ 100
8.5. RADIATION SAFETY MANUAL _________________________________________ 100
8.5.1. Controlled Neutron Analyzer, Sodern CAN – GEN III – Safety instructions (EADS
Sodern) _________________________________________________________ 100
Note: the mention of commercial products or trade processes; their source or vendor; or
their use in connection with material reported in this document should not be construed
as either an actual or implied endorsement of such products/services
The project-specific details and commercial aspects need to be discovered and defined
for each particular contract or something to that effect.
The process of thermal neutron capture by a nucleus is shown in the Figure
A/D Converter
Digital
Signal Processor
2
5
2
Multi-
Multi-Channel 0
1
Analyzer 5
1
Cf-
Cf-252 Neutron Source x 30 x 15
0
5
BIOLOGICAL SHIELDING
0
0 1 2 3 4 5 6 7 8
Radiation Safety
The neutron sources (Cf-252 or tube) in the analyser emit neutron and gamma
radiation. Although the radiation levels in the vicinity of the system are comparable to
those emitted by naturally occurring sources, it is prudent to ensure that exposure to
personnel is minimized.
Radiation Fundamentals
Radiation is defined as the emission and propagation of energy through space or
through matter in the form of waves or particles. The process of emitting this energy is
called radioactivity. The emitted wave or particle is called radiation. There are five basic
types of radiation:
Alpha Radiation Beta Radiation
Legend: Neutrons Proton
Legend: Neutron Proton
Gamma Radiation X‐Ray Radiation
100 keV
High Speed
Electron
Heavy Atom like Tungsten
Legend: Neutron Proton
NaI
NaIDetector
Detector
Biological Material
Material
Biological
Shielding
Shielding
Gamma
GammaRayRay
Shield
Shield
Californium
Californium
Sources
Sources
The position of the Neutron tube for CNA analysers is in a similar position. Due to the
higher-energy 14-MeV neutron emissions, there is a lot more shielding material around
the instrument.
1.0 mR/hr
2.2 mR/hr
5.0 mR/hr*
7 ‐ 19 mR/hr
30 mR/hr*
1.2 mR/hr
0.5 mR/hr
2.8 mR/hr 2.0 mR/hr
6.0 mR/hr* 4.0 mR/hr*
* Belt Empty 1 meter from
The working scenarios are summarized below, calculated for four scenarios
Inspecting the CBA tunnel daily
Simply Passing by the CBA 5 times/day
Working overhead on the CBA electronics
Working on the Idler Assemblies
We can calculate the maximum time that a worker would be allowed to spend at the
Tunnel Opening of the Analyzer, where the dose rate is the highest, typically 5 to 31
mR/Hr. We will also assume the worker performs this hypothetical task 1 time per
month, or 12 times per year. The calculations are presented below, yielding an Allowed
Time per month of 13.5 Hours.
German Regulations: 50 000 mSv whole body
EBA Tunnel Opening Dose (Empty) = 283 mSv
Time Allowed = 50 000 / 283 = 176 Hours
Assume: 1 Period per Month
Time per Month = 176 / 12 = 14 Hours / Period
2 m = 24 mR/h
4 m = 6 mR/h
(2 sources 12 mR/h)
8 m = 1.5 mR/h
(2 sources 3 mR/h)
16 m = 0.37 mR/h
(2 sources =.75mR/h)
The attached table shows the radiation measurements at Lafarge Cement Emirates
plant far one meter from CBA, and it shows very low rate of dosing pre hour:
Up 0.1 mR/h
Down 0.1 mR/h
Right 0.8 mR/h
Left 0.8 mR/h
Front 0.40 mR/h
Back 0.40 mR/h
Recommendation
No matter how low the dose levels are, personnel are required to keep their received
doses to As Low As Reasonably Achievable (ALARA). The ALARA principle is
internationally recognized and consists of the following three guidelines:
Minimize time in the radiation area
Maximize the distance between yourself and the source of radiation
Utilize shielding whenever possible
Measure the radiation around one meter from the analyzer every six months.
Because the levels of emission from the Neutron Generator are higher (14MeV) there
are some particular details relevant to this type of instrument.
In International System of Units, the activity of a radioactive source is measured in
Becquerel
(symbol Bq), where one Becquerel is equal to one nuclear disintegration per second
(an older unit is the curie, 1 Bq=2.7 10-11 Ci).
The absorbed dose of ionizing radiation is measured in grays (symbol Gy) where one
gray is equal to one joule of energy being imparted to one kilogram of matter (the rad is
the previously used unit, 1 Gy=100 rad).
The dose equivalent, which is a measure of the effects of radiation on living organisms,
is the absorbed dose multiplied by a suitable factor that depends upon the type of
radiation. It is measured in sieverts (symbol Sv), where one sievert is a dose equivalent
of one joule per kilogram (an older unit is the rem, 1 Sv=100 rem).
Because the neutrons are produced by the NEM and not an Isotope source, there are
different and specific handling requirements.
In case of emergencies, the following instructions should be followed:
Turn off all power to the CNA and close and lock the CNA main switch
Rope off and restrict access to the area 15 meters around the Measuring
Module
Notify the Manufacturer and the appropriate authorities responsible for
emergency response activities.
During operation, the CNA uses several types of voltage according the electronic
module: typical values are 230V, 850V, 2kV and 100kV. These high voltage systems
are dangerous. All doors of the electronic cabinet should be closed except for
equipment maintenance or repair.
The CNA must always remain connected to earth.
The presence of an Uninterruptible Power Supply (UPS) in the electronic control
cabinet implies that the main switch must be OFF any time before servicing.
Because of the presence of an Uninterruptible Power Supply (UPS) in the electronic
control cabinet, turning off the main supply outside the cabinet does not guarantee that
the power is off. Always turn the main switch off!
The following table provides some more detail on the factors for this decision:
Simix study showing C3S variance with 40<C3S variance C3S variance Sampling protocol,
need of better control 120m minutes with 120m with 120m Understanding of Raw
average <40 minutes average minutes average Materials variability
< 100 > 100
In any event the project requires a business case, particularly to elaborate and justify
the aspect of operational efficiencies.
The realization of expected payback depends not only on the analytical and control
success of the planned application (does the project meet the control objectives?) but
also on realization of extended benefits from kiln-feed uniformity (i.e. the extent that kiln
operations capitalize on improved consistency to operate the pyro-process line more
efficiently). Continued control success over the long term requires adequate and well
documented procedures for maintenance and calibration of the analyzer and software
system.
Since the mid 1990’s the use of PGNA analysis has grown steadily from less than 100
units installed in 1997 to probably over 700 units operating now and from perhaps three
units installed on raw mills to likely over 200 used for raw-mill control. The use of
PGNA analysis technology has evolved from a rarity in cement plants to become for the
most part a common retrofit and nearly a standard for new plants.
The earliest use of PGNA occurred in the solid fuels industry and this use has
continued steady growth. In addition it has also seen increased applications in the
mining and metals industries, for example for copper, scrap, iron ore, magnesite, and
During the past 10+ years the cost of PGNA equipment has fallen by more than half
and the project cost, mechanical, electrical, automation, commissioning – all in, often
today amounts to less than $US 500k. During the past several years several instances
have occurred where a plant has tried EDXRF and subsequently replaced the system
with a cross-belt-type PGNA system. Some examples of this: Port-la-Nouvelle, Kujawy,
Harleyville and Theodore (Holcim).
The bulk of PGNA applications fall into two classes, quarry (pile control and sorting)
and raw mill (raw-mix control). Several other uncommon and potential applications
exist.
B Quarry Monitoring Crushed rock CBA Uncommon Alpena Soley used to give feedback
to quarry (ex. To update
quarry model) without
changing number of
truckloads, etc.
C Quarry Sorting Crushed rock CBA Common Roberta Also Rillito, Clarkdale (major
(MGO, SiO2) Oxds alkalis etc)
D Pile Truck proportioning Crushed rock CBA Very Buderus Significant feedback to quarry
Common operations
E Pile Loader Proportioning Crushed rock CBA Very Several Works well if monitored by
into pre-blend pile Common Cimpor plants crusher operator, who directs
the loader
F Pile 2 Feeder (partial) Crushed rock CBA Very Exshaw Increases the automation
dosage into batch pile Common
G Pile 3 0r more Feeder Crushed rock CBA Common Oro Grande Old plant, before new pre-
Dosage into batch pile blending system installed.
Dosed to target, no RM
correction. Works well
provided pile-end segregation
not a problem
H Pile Truck/Loader/Feeder Crushed rock CBA Common Lucerne Dual control continuous and
Dosage into Valley batch -- Davenport IA doses
continuous pile additives as well
I Pile Feeder Dosage into Crushed rock CBA Common Egypt Possible to build raw mix in
continuous pile ± pile the pile and have little or
additives correction at RM
J Pile Barge loading Crushed rock CBA Uncommon Cave-in-Rock Can build barge load to a
target (QC) and/or certify the
load is on spec (QA)
K Pile Feeder Dosage into Crushed rock CBA Uncommon Alpena Keep limestone in bin on
mill feed bin spec while drawing from 2 or
more conic secondary piles
Q Raw Feedback on RM Powder "chute" Uncommon Alpena In continuous use since 1991.
mix product style But manufacturers have no
modern system available for
powder
R Process Kiln Feed Powder "chute" Hypothetical Would be possible if a PGNA
style powder system is available.
ATC has an EDXRF used for
this
S Process Clinker Partially "chute" R&D Technology works, but needs
cooled clinker style or undefined, tested at Exshaw.
CBA
T Process Fuels CBA Hypothetical Not known if implemented
thus far, but equipment
available and widely used in
mines and powerplants
Note that while fuel applications are as of now hypothetical in cement, the fuels industry
has made wide application of the PGNA technology.
The location of the installed analyzer in the plant flow sheet and the number and nature
of levers available to act on the analyses defines each category (A to S).
Batch piles may contain a variety of materials either solely from the limestone quarry or
other quarry or the limestone plus other additives. Some common features of batch
piles include:
The averaging effect of the batch permits a lesser analyzer-repeatability
performance (thus analyzers in these applications generally have a lower rate of
neutron consumption).
The layout footprint requires a relatively large area in cases of linear piles.
The analyzer location after a crusher likely has large belt-load variation unless the
project includes specific measures to control the variations (including a VFD).
The material size on the belt will consist of that fed to the pile and thus normally the
size fed to the raw mill.
Operational calibration adjustments have no straightforward reference to adjust
analyzer accuracy, unless the operation has a pre-existing sampling tower on the
same line.
Circular continuous piles serve similar purposes to batch piles. In terms of analyzer
applications they have the following distinctions:
Smaller practical batch blending volume of perhaps 20% of the pile capacity
High-frequency analyzer-based control fits well with this characteristic
Analyzers used for demanding continuous-control applications likely have a higher
rate of neutron consumption than those used for batch-blending piles
Less flexibility to manage the quarry or add other materials in multi-hour campaigns
In both cases the distinction between applications, as outlined in the table and
schematic, lies with the number and nature of the control levers and degree of possible
automation. Defined in this sense, the typical blending-pile applications include:
Truck-load proportioning to batch-blending pile – “D”
Loader (+ trucks) proportioning/dosage to batch-blending pile – “E”
Feeder/Loader/Truck proportioning/dosage of mainly limestone to batch-blending
pile – “F”
Three or more feeder dosage of limestone and additives to batch pile – “G”
Feeder/Loader/Truck proportioning/dosage of mainly limestone to continuous-
blending (chevcon) pile, example at Lucerne Valley [11] – “H”
Feeder dosage of limestone and additives to continuous-blending (chevcon) pile –
“I”
See below the examples of batch and continuous control with piles and at the raw mill.
The analyzer, mounted on the collection belt, determines the raw-mix chemistry each
minute and software processes the data to determine new feeder settings, working in
continuous closed-loop feedback control. Since the control can enact many more
control actions in a given time, compared to the classic method of basing control on
samples taken of the ground raw mix after the mill, it can compensate more readily for
chemical variations in raw materials. Since this high-frequency control results in higher
frequency residual variations, it enhances the effectiveness of blending silos located
between the mill and kiln feed. With these advantages, numerous plants have
experienced notable success with this application. However to achieve success, the
application has prerequisites, for example:
Adequate feed system to deliver the materials without interruptions;
Adequate weigh feeders able to deliver to proportional set points issued
automatically by software;
A strategy for determining and maintaining the analyzer dynamic calibration;
Normally the system using an analyzer for raw-mix control will include a VFD to
maintain constant mass loading (expressed as kg/m) on the belt passing through
the analyzer;
Close to 100% analyzer reliability -- normally attainable with this technology;
Strategy to anticipate, detect and resolve problems with any of the above and a
have backup plan to control raw mix;
Mastery of the effect of dust flows, particularly for PH/PC plants.
Concerning the dynamic calibration and the stability of it, the equipment layout has a
particular role. The Performance and Installation sections 4 and 5 have more
discussion on this.
The raw-mill application demands relatively good analyzer repeatability performance
and thus higher neutron consumption compared to purely batch pile-monitoring
systems.
The table and schematic show the following potential raw-mix-control and downstream
applications:
Feed-forward on pile output (analyzing one or more materials individually) – “M”
Feedback control on complete raw-mill feed (analyzer located on collection belt
ahead of mill)
Feedback control on partial raw-mill feed (some material added after the analysis
point) example, Lehigh/Heidelberg Union Bridge Maryland USA – “N”
Feedback control on raw-mill product (analysis of powder1,2) –“Q”
Feedback control on raw-mill product (analysis of slurry) –“P”
Kiln-feed (analysis of powder: to compensate for dust flows, mill down periods,
material added after mill) – “R”
Clinker (to compensate for the above + kiln additions) – “S”
Fuels (to blend multiple fuels to ash or sulphur target) – “T”
Notes:
1 Alpena plant is an example of a growing number of plants with two or more
PGNA systems (they have four).
2 Currently PGNA has little application for dynamic powder analysis (Alpena
being an exception) and the available means for higher frequency control
after the mill consists of autolabs and near-line EDXRF. However the
relatively low cost of PGNA and robustness with respect to particle size
and mineralogy imply a possible renaissance in the application of it.
The following summarizes the evolution of the technology in the Lafarge context:
System Thermo- ASYS Sabia Appx yrs Thermo ASYS, Sodern
Gamma example Sabia
Chute style "1812" "1812" 1987-1994 Alpena
etc
Analogue cross belt CBA 1994-1998 Saint-Pierre-la-Cour
Lafarge + Holcim participated with 1st CBA; SP le Cour 2nd unit installed
Sabia introduced XL in 2005, 1st light-frame cross belt
Omni developed by ASYS then melded with Thermo technology after Thermo
acquired ASYS
Sodern (tube source) started around 1998 marketed as Polysius (example Kujawy
pile analyzer) and revamped the line around 2005
Thermo also now markets an Omni-flex which can accept either an isotope or tube
source.
The CBA is distributed and applied among Lafarge plants to control and optimize the
prehomo stock pile and/or the total raw-mix composition feed to the raw mill, and it is
also used for controlling and sorting the limestone. The table below shows the total
distribution of CBA and its application in all Lafarge plants; in summary there are 43
different instruments in 36 plants; there is one or more plant in progress to install the
CBA.
The most common applications for cross-belt analyzers in Lafarge occur with stockpile
control representing 57% with 35% used for raw mix control and 9 % for limestone
control.
9%
35%
57%
Table 1 shows the distribution of CBA per each model and technical centre
Slurry
Inlet
Lafarge Ravena
L F Hi
G Alumin Mag.
H
G
H
G Rod
Rod
Informatio Discharge
Processin
Modul SL- Basin
Analyze
Plant Primar
Smar
Sample
Materi
Controlle
CBA
To Blending Tanks
Sampled coal PGNAA analyzer that can analyze 2-25 Small Sample PGNAA Analyzer that analyzes 3-5Kg of coal
TPH on a dedicated belt. or rock in plastic buckets using minimal skilled labour
Sample stream PGNAA slurry analyzer that analyzes fertilizer and mineral slurries. Multiplexed slurries flow through
the analyzer from 75mm sample lines into a urethane flow cell.
Install location
Before After
[1] Foster, S.; Bond, J. April 2006. “The history and future of nuclear elemental
analyzers for product optimization in the cement industry” in: Cement Industry
Technical Conference, 2006. Conference Record. IEEE, 9-14 April 2006 Location:
Phoenix, AZ
[2] Worrell, Ernst; Galitsky, Christina; March 2008. “Energy Efficiency Improvement and
Cost Saving Opportunities for Cement Making. An ENERGY STAR Guide for Energy
and Plant Managers.” Energy Analysis Department, Environmental Energy
Technologies Division, Ernest Orlando Lawrence Berkeley National Laboratory,
University of California, Berkeley, California
[3] Foster, Steve. September 2007. “Limiting Variability.” International Cement Review
[6] Lanz, Victor. May 2002. “Raw Material Management.” International Cement Review
[7] ICR Research. June 2004. “Analyzers Line Up.” International Cement Review
[9] Bourgon, J., Woodward R., Ackermann R. May 1995. “Cementos Apasco Succeeds
with New On-line Elemental Analyzer.” World Cement.
[11] Leetham, Darrell. January 2008. “Online Stockpile Analysis”. World Cement
[12] Foster, Steve; Graham, Jonathon. February 2009. “Lafarge, Whitehall Opts for
PGNA Analyzer.” World Cement.
[14] Jacobs, Richard; Regis, Steven. March/April 2006. “Automated Cement Plant
Quality Control” IEEE Industry Applications Magazine
4.1. Performance
4.1.1. Introduction
The MLR (Multiple Linear Regression) is used to calculate the entire shape of all the
elemental peaks. Most commonly, vendors use a full-spectrum analysis such as Library
Least Squares that utilizes the instrument response to pure elements used as a library
Step 2: The regression software calculates the amount of each library response that will
most nearly approximate the shape of the signal spectra when added together
PGNAA library
spectra
PGNAA library
spectra
One minute
Elemental Spectra for
One minute
Elemental Spectra
The MLR results have been applied to the Elemental Response Library and shown here
graphically juxtaposed with the original Sample Gamma Spectra.
Typical analysis steps (details vary between manufacturers):
The MLR produces a basic elemental analysis (in mass terms, raw coefficients)
Stoichiometric conversion to oxides
4.1.3.1. Sensitivity
Sensitivity is the capability of CBA to detect the elements. The stronger elements are
those with the higher cross sections thus stronger gamma-ray production and with
distinct emission energies.
The table below shows the theoretical range of sensitivity for each of the elements in
the periodic table for a PGNA instrument, from which guarantees are derived.
The performance of PGNAA in detection the elements differs from one element to
another depending on neutron cross section and spectrum resolution.
In cement manufacturing the following tables shows typical results for oxides commonly
reported in both raw-mix control and stock-pile control.
The higher the inverse ratio with the Coefficient of Variation2 (relative standard
deviation) the more apt the system, analyzer+ control software, to have good control.
2
Coefficient of Variation (COV) = relative standard deviation = Average / Stdev
Typical Typical
Typical Raw- 10-min Average
10-min mix Oxide stdev stockpile 1/VOC
Oxide stdev average 1/COV SiO2 0.13 12.69 97
SiO2 0.2 14 70 Al2O3 0.17 3.41 20
Al2O3 0.2 3.3 17 Fe2O3 0.02 1.89 84
Fe2O3 0.05 2.1 42 CaO 0.23 41.73 180
CaO 0.25 44 176 K2O 0.03 0.62 21
MgO 0.25 3 12 SO3 0.07 0.16 2
SO3 0.1 0.4 4 MgO 0.26 2.68 10
K2O 0.05 0.4 8
Na2O 0.1 0.1 1
TiO2 0.02 0.2 10
P2O5 0.5 0.5 1
MnO2 0.02 0.05 3
Cl 0.005 0.015 3
The relative control capability is best with the major oxides of Ca, Si and Fe while for Al
is relatively lower due to it is strongly influenced by Fe, and analyzer designers should
improve the resolution of spectral capture.
While for minor elements, the relative control capability is very low however it can be
increased with longer integration times.
Below shows the neutron cross section (3in barns) of each element in comparison with
Gamma rays per 100 neutrons.
N-Gamma G-Rays per Barns X G´s Rel. Signal
Atomic No. Element Cross Section 100 per 100 strength
in Barns neutrons neutrons raw mix*
100
33.2
10
2.1 2.5
1
0.4 0.23 0.43 0.512
K Cl Na Al Fe Ca Mg S Si
0.16
0.1
0.063
N-Gamma Cross Section in Barns
0.01
Mg has a much smaller neutron cross section and therefore delivers performance which
may prove challenging to an operation with an MgO control issue due to the gamma
rays emitted per neutrons are normally depressed by the influence of some elements
like Si and Al, therefore the vendor’s guarantees must fit with the intended application.
Cl has relatively high neutron cross section and acts as a mild neutron poison, therefore
it can affect performance for the other oxides. The vendor can guarantee the detection
of very low Cl, around 0.005%, but if it is high (> 1%) Cl % in the materials it can
compromise results for the other elements. Also note that this character explains the
needs for low-Cl belt material.
K and Na despite of the very smaller neutron cross section, but the performance is very
low due to it has inherently weak signals that are interfered with by the stronger
elements.
As described above CBA by using PGNAA is a powerful technique for obtaining and
testing on-line elemental analysis of stream flow of bulk materials either it is wet of dry,
but it also has some issues or shortcomings that must be considered in the evaluation
of the performance on an existing system. In some cases the end user can do things to
minimize the effects of some of these issues.
Density Effects
If the density of the material being analyzed changes significantly it can have an effect
on the neutronics, affecting the number and/or distribution of available neutrons that get
captured by the elements in the sample as well as the number of gamma rays that are
able to make it to the detector for analysis.
For example, different sources of iron ore, magnetite, pyrite, etc. or large moisture
variations could affect the density. To a large extent, the normalization routine in the
analysis software should compensate for density variations. In some analyzers,
(notably Sabia) tracking and review of the total-counts data can help to determine if
density variations occur.
Source
Age Repeatability Guaranteed at 80Kg/meter
(Month)
SiO2 Fe2O3 Al2O3 CaO MgO K2O Na2O SO3 Cl
0 0.15 0.04 0.17 0.27 0.27 0.03 0.17 0.07 0.17
3 0.155 0.045 0.18 0.28 0.281 0.034 0.176 0.047 0.176
6 0.16 0.045 0.185 0.289 0.288 0.034 0.183 0.075 0.183
9 0.174 0.045 0.146 0.299 0.299 0.034 0.189 0.075 0.189
12 0.179 0.045 0.194 0.309 0.31 0.034 0.195 0.047 0.195
15 0.184 0.05 0.204 0.318 0.317 0.038 0.201 0.079 0.201
18 0.189 0.05 0.146 0.328 0.328 0.038 0.208 0.084 0.208
21 0.194 0.05 0.214 0.342 0.338 0.038 0.214 0.084 0.214
24 0.203 0.055 0.194 0.352 0.349 0.041 0.22 0.047 0.22
27 0.208 0.055 0.194 0.362 0.364 0.041 0.227 0.089 0.227
30 0.213 0.055 0.238 0.376 0.374 0.041 0.233 0.093 0.233
33 0.218 0.06 0.248 0.386 0.385 0.045 0.246 0.098 0.246
36 0.223 0.06 0.253 0.4 0.4 0.045 0.252 0.098 0.252
Table1
Thermo has also provided predicted CBA performance in terms of 10min static
repeatability test against the belt load (Kg/m) and the source life time as shown from
the below graph for CaO.
The following graphs show the 10-minute repeatability versus the belt load (Kg/meter),
and versus the source age at 80 Kg/meter for all elements.
0.70
0.60
10 min repeatability
0.50
source age
conveyor load
0.40
0.30
0.20
0 3 6 9 12 15 18 21 24 27 30 33
months
130 120 110 100 90 80 70 60 50 40 30 20
Kg per meter
Belt-load Geometry
The analytical environment varies according to the geometry of the belt load as
expressed as follows:
Layered
Transfer point (90 deg)
Actively mixed
A fully mixed belt load is least likely to cause analytical drifts (for the reason discussed
earlier), however many layered and transfer-point (not mixed) plant environments
successfully use analyzers. The specifics of the material chemistry and moisture
contents determine the likelihood of problems with this issue. In some problematic
cases, compensations have successfully mitigated layering issues (Whitehall).
An example of the layering effect occurred in MANNERSDORF plant (referenced in Les
Cas/ Plant Experience) and indicates the LSF standard deviation and KFUI improved
by decreasing the layering effect as shown below from the attached illustration.
Mix
on the belt
Conveyor
Type of mix / date Deviation LSF (FX / GM) St Dev LSF raw mix
Regular mix no. 1 1998 4.24 3.00
Regular mix no. 2 1998 3.33 3.46
Mix for 0 C3A 1998 4.27 3.18
March 1999 1.98 6.00
April 1999 2.57 2.48
May 1999 2.79 2.03
Plant KFUI:
Year KFUI Comments
1997 16.2 Start up GM and homo shut down
1998 22.4 Continuous operation with GM without homo
03/1999 19.3 First optimization step with GM without homo
04/1999 13.2 Further optimization steps
05/1999 9.5 System optimized
Weak Elements
Elements like Al, Mg, Na, and K have inherently weak signals with which the stronger
elements interfere. The performance of these elements can be enhanced with a high
precision detector, higher levels of source strength, and optimized detector response
sets.
See Appendix 8-6: Element detection with CBA
Detector
Detector
Subtended
Angle
Duration of Measurement
The longer the system can integrate the captured impulses; the better will be the
repeatability.
The shortest integration is for the one-minute analyses.
Performance guarantee for repeatability is based on an integration of 10 minutes.
The repeatability in standard-deviation terms improves by the square root of the
multiplication factor for the integration time up to one-hour integration.
Contamination
Depending on the analyzer design, belt spillages make result in residual extraneous
material inside the zone of analysis. If this potential exists, the plant should ensure that
analysis zone remains free of extraneous material.
A key initial decision point relates to the source of neutrons. The decision of either tube
or Cf isotope limits the choice to two vendors either way. As a practical matter normally
a project will request quotes from all three vendors in order to explore pricing.
Some aspects of Cf isotope versus tube:
The appendices have a technical comparison; the following page presents this
comparison.
See Appendix 8-1 Lafarge CBA technical comparison
Shield Material Mixture of high hydrogen wax Bismuth, lead, high hydrogen wax Polyethelyn & Parofin wax - hydrogrn
Radiation level from 1 meter 2 micro sivert 2 micro sivert Standard 25 micro sivert / Medium 7.5 micro sivert
Neutron Source Californum source - CF 252 Californum source - CF 252 NEM - Neutrom Emmiting Module
Source life time 2.6 year 2.6 year 12000 to 14000 hours and guranteed 6000 hours
40 40 30
Detector operation Temperature
Cooling for detector = No Cooling for detector = No Cooling for detector = Yes
Software Compatible with QMC, QCX, Polab, ….. QMC, QCX, Polab, ….. QMC, QCX, Polab, …..
Signal Interface OPC Server, ModBus, ProfiBus,4 --20 ma OPC Server, ModBus, ProfiBus,4 --20 ma OPC Server, ModBus, ProfiBus,4 --20 ma
Maintenance Contract / year Cost = 42,000 USD Cost = 30,000 USD Cost = 10,000 Euro = 14000 USD
Recommednded spare parts package 47,000 without detector 70,000 including new detector 71,300 including new detector
Detector Price New detector Price = 70,000 Euro New detector Price = 40,000 Euro
20 micro grams = 27,500 USD / 30 months 20 micro grams = 14,500 USD / 30 months
Neutron Emitting Module = 35000 / Year Euro (without
Neuton source price
maintenance contract
30 micro grams = 33,750 USD
40 micro grams = 29,000 USD
40 micro grams = 41,000 USD
Control Panel
Detectors
The price comparison is given for 2010. Updated prices can be found in appendix and
in the frame agreement.
Typically each manufacturer upgrades their own models; however Sabia has
proven competent and lower cost to provide upgrades for various Thermo and
ASYS models.
5.1.3. Layering
Transfer points can lead to improved mixing of the belt load; however the resultant
mixture must maintain a consistent belt-load position and geometry. To avoid layering
problems some projects have expressly chosen an analyzer location to take advantage
of the mixing afforded by a transfer point. In some cases this has led to a successful
project. However, some of the most difficult cases to resolve have arisen from this
strategy.
In the case of Retznei, the plant has their analyzer installed after a 90-degree transfer.
The plant has not reported insurmountable effects on the dynamic calibration. They did
however install a “ski-jump” plate on the iron feeder belt to avoid “splotches” of iron on
the belt. We do not know with any certainty to what extent the installation must mitigate
iron splotches, however Retznei seemed to improve their results by reducing this effect.
In the case of Richmond, the transfer point tends to deposit the coarse and fine
materials on one side of the belt after the transfer point. While in the past, the coarse
material reported to the viewer’s left-hand side of the conveyor, one can see in the
following pictures that coarse material now favours the right -hand side. The
concentration of the coarse material affects the analysis since, depending on the
material contents, the alumina, silica and iron may change their distribution according to
the distribution of the various particle sizes.
The minimum tunnel height without undue risk of material striking the housing favours
repeatability performance. Of course the arrangement must always include protection
devices to remove oversize material from the belt and over-height detection to stop the
belt in time to prevent a collision if the protection fails. A belt with controlled constant
load can operate with a lesser nominal tunnel clearance. Several plants have
experienced excessive material collisions against the housing due to over height/
oversize material on the conveyor and/or having an analyzer designed with a tight
tunnel.
In the case of Davenport, the analyzer had a very tight tunnel in order to favour
repeatability performance (continuous control into a circular pile). Collisions caused
housing damage (belt speed running around 2 m/s). Les Cas/ Plant Experience has
several case histories from this project, including an inexpensive way to monitor the risk
of material collisions. Eventually the vendor had to raise the tunnel height about 10 cm
as no solution worked to adequately regulate surges from the crusher.
Analyzer assembly
Depending on the manufacturer, the integration of the analyzer assembly will
require 1-2 days to a week to mechanically integrate. It may require or at least
benefit from crane access. At-height installations likely require structurally
reinforcement, depending on the model selected. In any event the project
members need to well plan and schedule the work.
Analyzer protection structure
Modern designs require minimal protection from weather; however a simple
sunroof is usually advisable. In some cases a more elaborate building with
locked access may be needed or at least advantageous to prevent
unauthorized access.
Slider Bed
Some designs still have a slider bed, others do not. In cases with slider beds
the wear rate will depend heavily on correct belt alignment. This will greatly
affect operating cost.
Radiation Sources and Source Cask
The project needs to consider the correct storage aspect and delivery time of
the sources (isotope or tube). If ordered too early the strength wastes; ordered
too late, commissioning delayed.
The appendices and other Lafarge documentation (see On-line Analyzer e-library in
EASI Plus!) has examples of SOP’s.
Normally the manufacturer supplies 5 Reference standards which have a specific range
for each oxide (e.g. SiO2 4%-24%). The ‘middle’ standard is usually on target with the
chemistry of the raw material passing through the analyzer.
The plant can prepare one or more plant-specific calibration standards, the mass of
these standards should be sufficient to obtain the targeted belt load and therefore used
for static testing of a matrix containing the same elements as the production material.
Most plants with Thermo analyzers might have one or two plant-specific samples to
complement the factory standards. Thermo supplies the factory standards prepared
from pure materials. An exception is Richmond which has the original Thermo “boats”
in addition to local material in tubes. Plants with Sabia analyzers have all the reference
standards prepared from plant materials using appropriate recipes. Some Sodern
analyzers also use local materials for the reference.
The below picture shows a plant-specific standard sample comprised of 36 bags of 5 kg
each.
The static accuracy test was based on factory concentration measurements obtained
on the standard samples supplied by manufacture or local materials and compared with
the results obtained on site, for which each standard was measured for a period of 1 h.
The deviations are expressed as Root Means Square Deviation (RMSD), which can
also be expressed as 1 sigma.
n
x i y i 2
RMSD i1
n
Where: xi = factory value
yi = current value
n = number of standards
Note 1: Range of material composition in reference standards. Guarantees are a function of the range; a larger range will dictate a
larger guarantee. Conversely, a smaller range will dictate a smaller guarantee
Recommendation:
CBA performance should be verified as a minimum by static accuracy test
every 6 months by measuring one standard sample delivered by supplier or
by measuring a plant-specific standard. In cases of doubtful calibration
stability, the standards should be run each month or more often.
See Appendix 8-7: Static calibration
The other suppliers have similar procedures.
The static repeatability test is determined by measuring one standard sample for a
period of 5h = 300 minutes. The obtained 300 one-minute analyses are summarized in
blocks of ten-minute analyses, for every ten-minute block the average value for each
Conveyor Loading
The Tables below show typical guaranteed values of Static Repeatability from
ThermoFisher versus belt loading
Belt Guaranteed Ten-minute Repeatability by Oxide Note 1
Load
Kg/m
SiO2 Al2O3 Fe2O3 CaO MgO K2O Na2O
110 0,21 0,21 0,04 0,30 0,33 0,07 0,15
130 0,18 0,18 0,04 0,27 0,29 0,06 0,13
150 0,16 0,16 0,03 0,24 0,26 0,05 0,12
170 0,16 0,16 0,03 0,23 0,25 0,05 0,11
190 0,15 0,15 0,03 0,22 0,24 0,05 0,11
Note 1: The values apply for a nominal tunnel opening 313 mm and 38ug Cf source
Recommendation:
CBA performance verification should be conducted every six months by static
repeatability test
See Appendix 8-7: Static calibration
The other suppliers have similar procedures.
Dynamic calibration refers to comparison of analyzer data obtained while the belt runs
versus some independent sampling and analysis method. The samples may come
directly of the same material, but more often will come from another sampling point in
the process and may or possibly not represent precisely the same material and have
time delays between the analyzer data and reference samples.
Take care to manage bias in the reference methods -- the plant control plan needs
to have coherence between analytical systems and control targets.
Understand possible conditions affecting the dynamic calibration and reduce their
effects during the calibration tests.
If these conditions change at a later date, then run another dynamic calibration test
In general, CBA measures coarse materials; generally > 3-cm top size, often 10 cm
or even coarser, thus direct sampling from the belt would require increments with
masses of 25 kg – 250 kg or more.
The CBA integrates the chemistry for the entire time period defined and integration
time for each dynamic point of reference typically = 1 hour. The reference method
must thus obtain a composite sample to represent the entire comparison mass.
The ranges of calibration should be adjusted to fit the intended use of the analyzer.
Generally a larger range in the calibration adversely affects repeatability and
standard error. However in some cases, the manufacturer has the ability to
implement a multiple calibration (either with a manual or automatic trigger). This
can allow for a greater range without degrading the standard error.
The normal method to quantify the difference from reference to analyzer uses the
RMSD (root mean square deviation) = the average of the squared differences
between the reference and the analyzer; this average to the square root. A
“standard error” calculation can also be used.
The criteria for judging the results depends on experience in the particular plant
conditions; clearly however the original system guarantee can give some guidance
for the analyzer accuracy under dynamic conditions,
The on-line analyzer accuracy is verified by back calculating the composition of the
stockpiles using the raw meal composition and subtracting the proportion of the
correctives (Limestone and clay, sand …etc). The bias between the values given by the
CBA and the results obtained from the back-calculation will be established by analyzing
a certain quantity of stockpiles (in most cases 5 stockpiles), taking into consideration
that the dynamic accuracy based any given data point may have considerable error.
The performance of this comparison presents several challenges and should consider
the following factors:
1. Only one comparison can be made for each stockpile, thus requiring months of
data collection in order to achieve statistical significance.
2. The CBA and the raw meal sampler are not presented with the same material.
The raw meal sampler receives all the “correctives” from the raw mix
proportioning which did not pass through the CBA. The XRF results must be
corrected mathematically for the composition of the correctives.
3. This may require sampling each corrective stream several times per shift, for
several months.
4. The XRF analysis of the raw meal sample must properly account for the lot of
the raw material. Keep in mind that the analyser data consists of a continuous
integration of the material chemistry; the samples will always consist of
increments from this lot and the test protocol must ensure sufficient number of
increments to have adequate representation of the “lot”.
5. All of the other drawbacks associated with the raw-meal sampler mentioned
earlier still apply.
The RMSD of each oxide is computed and the analyzer adjusted, provided the data
shows a bias, by the supplier or locally if capable.
In some retrofit cases the plant may have a sampling tower available. In these cases
the dynamic calibration may use a direct comparison between the tower hourly
composite samples and hourly analyzer averages. Since in several ways this
resembles the method used for raw-mill-sample calibration, refer to that section for
more details.
Particular issues to consider include:
Take particular care with sample preparation and analysis (fused bead
recommended)
Review the sampling tower design and maintenance to ensure that it takes
accurate and repeatable samples.
In most cases we find that the tower has some bias issues (all the more likely if the
plant plans to replace it with a CBA); in these cases, the calibration sampling may
potentially use a special protocol designed to correct tower’s problem temporarily.
A validation may be possible by using another method to cross-check the dynamic
samples, e.g. that described in the above section or comparison with blast-hole
samples for the piles tested. The validation may be used for example, to detect a
bias for one or more oxides.
In the case where the plant can crash stop the belt and preserve the dynamic condition
of the material, then a complete sample of the material can provide the basis of a
reference analysis by XRF. Few plants have tried this method, as it requires
substantial effort; however a least one successful case occurred at Exshaw.
In this case the plant has a means to obtain samples from the moving belt; a transfer
point may provide this opportunity. Keeping in mind that each data point in the
calibration must represent 30-minutes to one-hour of material and with five to ten
increments required of at least 25-kg each (for 2cm stone), the scope of this procedure
becomes very large. For plants having 10-cm rock or greater on the belt the increment
size becomes extremely problematic (apprx. 200 kg).
Clearly the sample-collection and sample preparation methods need to respect
sampling rules (see L.O., Two Golden Rules of Sampling). In addition, each
circumstance requires a careful risk assessment and critical look at the means for
obtaining the sample increments from an operating conveyor system.
The data treatment for this method resembles that used for a sampling-tower reference.
In the case of raw-mix proportioning control by CBA at mill inlet, we can generally use
the post-mill raw-mix sampler and analysis by XRF as the reference data. Particularly
in cases where certain factors may degrade the comparison, use of a calculated raw
mix as a second comparison can add value to the calibration project. In order to ensure
the correct range of calibration, the test method should include “feeder bumps”. This
means that the test will prescribe a variety of raw-material feed settings to obtain
various combinations of raw-mix chemistry.
In the case of raw-mix proportioning control by CBA at mill inlet, the following includes
some complicating factors:
The errors associated with the system of raw meal sampling, sample preparation
and XRF analysis
The time delay from the CBA to the raw-meal sampler may vary according to
material type and re-circulating load, making it challenging to adequately
synchronize the analyzer analysis time with the raw-meal sample time.
Intervening dust streams between the CBA and the raw-meal sampler reduce the
equivalence of the lot of material which the CBA and sampler each measure
With QMC controlling and stable feeder operation, begin sampling for one hour. The
average feed rate percentages, during this time, become the baseline. Stop raw-mix
software control. Manually step feeders, guided by table 1, to the percent increments
from baseline for sequence #1. Continue sampling throughout all sequences. Maintain
each sequence for one hour. Then step feeders to the setting for the next sequence #2.
Note, all settings are departures from baseline, they are not cumulative. Repeat
process though all nine sequences.
Sequences #3,#6, and #9 return to baseline percentages. After thirty minutes, check
the CBA analysis rolling average to judge, if the baseline is near criteria set points. If
acceptable, continue next round of deltas using same baseline. If not, then make
adjustment to baseline and apply deltas.
The dynamic relationship between the analyzer and reference may shift quickly or
slowly over time. The plant should have a method to monitor the calibration
relationship versus a production reference.
For raw-mix analyzers, a reference to clinker, if possible adjusted for other inputs, can
serve this purpose. A trend of hypothetical raw mix calculated from estimated material
chemistry can add insight as well.
For stockpile analyzers, the back-calculated pile chemistry can work as described in the
calibration section. The use of a spreadsheet polling data from IP21 or other historian
can provide the basis of this calculation on a semi-automatic basis.
The following simple example shows a graph from Exshaw. In this case they track the
MgO in kiln feed versus average pre-homo-pile MgO as a ratio. In their case MgO
plays an important role in pile control and the MgO content of materials added at the
mill does not vary too much. Changes in this ratio can indicate a drift of the calibration
if gradual or a particular incident in more abrupt cases.
The deviations of the ratio exhibit a “statistical” behaviour thus each site should develop
a “control chart” method based on for example SPC or Shift-away in order to detect
drifts requiring corrective action
1.20
1.15
1.10
1.05
1.00
0.95
0.90
0 5 10 15 20 25 30 35 40 45
Pile #
Recommendation:
It is recommended to have a means to continuously monitor the dynamic
calibration. In the case that the monitor shows an anomaly or other problems
occur, possibly caused by a drift of the dynamic calibration or a specific
condition occurs that could shift the dynamic calibration, then a calibration test
should take place, based on the above methods.
The core mission of this equipment in the plant’s control scheme typically leverages the
costs associated with downtime as the attendant increase in chemical variability tends
to increase the downtime and maintenance costs of major plant equipment, particularly
the kiln.
For the analyzer to function properly it depends on several subsystems, thus
maintenance applies to the analyzer and its electronics as well as related
communications, belt-load control, impact protection plows and over-height sensors.
Therefore the maintenance considerations must address these systems as well.
The maintenance planning schedule for the plant should include these systems. At
some sites the context would require a site maintenance champion with an
instrumentation background to be responsible for preventive and corrective
maintenance of all laboratory equipment including the CBA.
Recommendations Recap
Maintenance applies to the analyzer and its electronics as well as related sub-
systems, such as communications, belt-load control, impact protection ploughs and
over-height sensors.
The maintenance planning schedule for the plant should include these systems. At
some sites the context would require a site maintenance champion with an
instrumentation background to be responsible for preventive and corrective
maintenance of all laboratory equipment including the CBA.
All CBA systems must be covered with maintenance contract. Assign annual
budget for maintenance contract.
Potentially the contract covers, for example:
o Monthly remote system evaluation and report,
o Phone assistance (24/7 or 8/5),
o Parts replacement,
o On-site service calls if needed,
o Bi-annual site visits for PM and radiological requirements,
o Calibration assistance
o Vehicle for computer and software upgrades.
For a given plant, the optimum scope and terms of the contract should be
determined with the assistance of the Technical Centre Experts
Assign budget for source replenishment no less frequently than every 2.6 years (30
months) and start replenishment procedure as often as every 2 years if needed by
control requirements.
Tube-based systems shall have an effective contract in place and back-up tube
procedures if warranted to assure minimum interruption to neutron supply.
Develop an equipment sustainability plan to avoid obsolescence – upgrade
schedule based on negotiations and quotations from main suppliers.
Typically each manufacturer upgrades their own models; however Sabia has
proven competent and lower cost to provide upgrades for various Thermo and
ASYS models.
8.6.2. The history and future of nuclear elemental analyzers for product
optimization in the cement industry, S. Foster (SABIA), J. Bond
(CTS). Conference Record. IEEE, 9–14 April 2006
ON line control or raw mix case of Retznei manuscript CTEC technical B.Köck, G.Miklau
A003 Lafarge CTEC
meeting Retznei 1998 03.09.98
A007 KFUI Improvement via Cross Belt Analyzer Lafarge CTEC A. Ebenschweiger
A018 Example CBX Accuracy Test -Joppa Plant -Raw MIll2 Lafarge NA CTS
A028 GAMMAMETRICS ANALYZER – Plant Experience Les Cas 032-04 Lafarge CTS
NEUTRON ACTIVATION ANALYSIS OF THE RAW MATERIALS ON
A029 Lafarge SPLC
BELT -Les Cas 053-04
ACCURACY OF THE NEUTRON ACTIVATION ANALYSIS ON BELT
A030 – Plant Experience Les Cas 053-05 Lafarge SPLC
CLINKER SAMPLING FOR GAMMADENSITOMETRY - Les Cas 059- Lafarge Val
A031
13 d’Azergues
RAW MIX CONTROL LOGIC (GAMMAMETRICS vs. METOREX)-
A032 Plant Experience Les Cas 075-02 Lafarge PLN
A033 Performance Guarantees for Pre Blend - Limits Lafarge CTC
A034 Sodern - CBA Form for Manufacture Survey - Rev2Sodern Lafarge CTC
A035 System Administrator Guide ASYS