Kementerian ESDM Republik Indonesia
1. Indonesia Oil & Gas Balance
3
3
Kementerian ESDM Republik Indonesia
PROYEKSI PRODUKSI GAS BUMI 2015 – 2050
dalam MMSCFD
4
4
Kementerian ESDM Republik Indonesia
NERACA GAS BUMI INDONESIA 2015 – 2030
2019
MULAI IMPOR GAS
National Energy Agency Forecast: Gas demand in 2025 will make up to 20% of National Energy Mix (7,134 BOED), or 8,249 BBTUD
5
5
Kementerian ESDM Republik Indonesia
PEMANFAATAN GAS BUMI INDONESIA 2016
LPG Domestik
2.50% Realisasi Penyaluran Gas Pipa untuk Domestik
LNG Domestik Tahun 2016
5.91% 2,000
1,814.76
Kelistrikan 1,800
14.98%
1,600 1,510.91
1,400
BBTUD
LNG Ekspor 1,000 758.76
29.10%
800 718.09
600
321.05
Industri 400
22.10% 206.20
200 8.50
Ekspor Gas Pipa 3.51
3.13 3.78
11.80% -
Kelistrikan Pupuk Industri Lifting Minyak City Gas
Lifting
BBG Transportasi City Gas Minyak
0.06% 0.05% 3.02% Realisasi (BBTUD) Kontrak
6
6
Kementerian ESDM Republik Indonesia
NATIONAL OIL & GAS DEMAND & PRODUCTION
In mboepd 15 Years
AVE CAGR
In 2015 the gap between national supply and demand begins. OE Production
4%
5.500
5.000 5.315
4.550
4.500
+4% 3.950
4.000
3.500 3.270
3.000 2.600
2.500 2.270 2.230 2.195 2.190
2.000 2.190 1.810
2.025 2.065 2.120
1.500
1.435
1.000 1.085
785
500 535
0
2012 2013 2014 2015 2020 2025 2030 2040 2050
National Supply National Demand
7
source : ESDM, SKK Migas, Upstream Team Projection | 4 7
Kementerian ESDM Republik Indonesia
NATIONAL GAS DEMAND & PRODUCTION
In mmscfd
15 Years
In 2021 the gap between national supply and demand begins. CAGR Average
Industry (98,26%)
7%
Household (0,11%)
Gas
Consumption Commercial (1,34%)
Transportation (0,29%)
18.000 16.300
16.000
+7% 13.600
14.000
11.300
12.000
10.000 9.100
8.165 8.130 8.145 8.110
8.000 7.000
5.700
6.000 5.800
3.640 3.650 3.910 3.995
4.000 4.100
3.400
2.500
2.000
0
2012 2013 2014 2015 2020 2025 2030 2040 2050
National Supply National Demand 8
source : ESDM, SKK Migas, Upstream Team Projection | 8
Kementerian ESDM Republik Indonesia
2. Gas Infrastructure Development
9
9
Kementerian ESDM Republik Indonesia
Infrastruktur Gas Bumi Existing & Rencana
EXISTING
ROADMAP
2016 – 2030
KEBUTUHAN INVESTASI
(Miliar USD)
Liquefac SPBG +
Pipa tion CNG
12 25.6 1.93 TOTAL
Regasific
ation Jargas LPG
48.2
6.1 2.2 0.4 10
10
Kementerian ESDM Republik Indonesia
VIRTUAL PIPELINE CLUSTER CONCEPT
CLUSTER II (MALUKU) CLUSTER I (PAPUA)
• Pembangkit 130 MMSCFD [875MW]
• Pembangkit 138M MSCFD [630 MW]
• Smelter 100 MMSFD
• Industri 288 MMSCFD
• Industri 55 MMSCFD
• Rumah Tangga 1 MMSCFD
• Rumah Tangga 1 MMSCFD
CLUSTER II (MALUKU)
CLUSTER IV (NATUNA)
• Pembangkit 49 MMSCFD [495 MW]
11
11
Kementerian ESDM Republik Indonesia
CLUSTER I (PAPUA)
LNG Vessel : 8000 m3 LNG Vessel : 8000 m3 Primary Hub Jayapura
Frequency : 2 x 2 weeks Frequency : 2 x 2 weeks Total Pembangkit : 11 (250 MW)
Primary Hub Travel : 700 km Gas Demand : 50 MMSCFD
Travel : 1,600 km
Sorong Isotank : 90 Iso/ 2 weeks
Primary Hub
Jayapura
Primary Hub
LNG Vessel : 8000 m3
Frequency : 1 x 2 weeks Timika
Travel : 1,000 km
FSU FSRU
Pembangkit 31 Lokasi Rencana Pembangkit 630 MW Liquefaction Plant PLTGU/MGU
FSRU/FSU/FRU 3 Lokasi PLTG/MG
Secondary Hub/Land based Storage
Land Based Regas 8 Lokasi Kebutuhan Gas 138 MMSCFD
Smelter MPP
12
Iso Tank Regas System 8 Lokasi Land based Regas Terminal Small Vessel Route
12
Kementerian ESDM Republik Indonesia LNG Iso tank Regas System Isotank Barge Route
CLUSTER II (MALUKU)
Primary Hub
Maba
FSRU
Pembangkit 24 Location Rencana Pembangkit 875 MW
Liquefaction Plant PLTGU/MGU
FSRU/FSU/FRU 3 Location PLTG/MG
Land Based Regas 5 Location Kebutuhan Gas 130 MMSCFD Secondary Hub/Land based Storage
Smelter MPP
13
Iso Tank Regas System 10 Location Kebutuhan Gas Smelter 100 MMSCFD Land based Regas Terminal Small Vessel Route
13
Kementerian ESDM Republik Indonesia LNG Iso tank Regas System Isotank Barge Route
CLUSTER III (NUSA TENGGARA)
Primary Hub
Makassar
Primary Hub Pomala
Pembangkit : 8 (145 MW)
Gas Demand : 34 MMSCFD
Smelter : 1 Plant (100 MMSCFD)
Isotank : 126 Iso/ 2 weeks
Primary Hub
Lombok
FSRU
Pembangkit 30 Location Rencana Pembangkit 1,750 MW Liquefaction Plant PLTGU/MGU
FSRU/FSU/FRU 4 Location PLTG/MG
Kebutuhan Gas 183 MMSCFD Secondary Hub/Land based Storage
Land Based Regas 12 Location Smelter MPP
14
Iso Tank Regas System 7 Location Kebutuhan Gas Smelter 100 MMSCFD Land based Regas Terminal Small Vessel Route
14
Kementerian ESDM Republik Indonesia LNG Iso tank Regas System Isotank Barge Route
CLUSTER IV (NATUNA)
Primary Hub
Pontianak
Commercial Ports
Commercial Shipping Route
Pioneer Shipping Route
*) Transportation Ministerial Regulation No. 29 / 2014 about Maritime Environment Pollution Prevention 16
**) m/m: microgram/mililiter 1616
Kementerian ESDM Republik Indonesia
GAS INFRASTRUCTURE ROADMAP 2016 – 2030 *)
Period I Period II Period III
No. URAIAN
Existing 2016 2017 2018 2019 2020 2021 – 2025 2026 – 2030
Open Access 3,665 6,153 6,153 6,215 6,776 7,390 9,604 12,580
Upstream Dedicated 4,110 4,123 4,123 4,123 4,123 4,123 4,123 4,123
1 Pipeline [KM]
Downstream Dedicated 4,213.54 9,177 9,211 9,431 11,546 11,546 13,480 13,584
Own Use 46 66 66 66 66 66 66 66
Large Plant 2 4 5 5 5 5 6 6
2 Liquefaction [UNIT]
Mini Plant 0 3 5 7 7 9 10 12
Regasification FSRU 2 2 5 9 10 11 11 12
3
[UNIT] Land based 1 17 24 46 62 64 66 68
CNG Application Inland 14 68 72 72 106 108 108 161
4
[UNIT] Marine 2 4 6 9 12 15 20 30
GAS FUELING CNG 84 136 163 189 210 289 800 1,300
5 STATIONS
LNG 0 0 0 0 2 4 7 12
[UNITS]
LGV 27 27 77 80 100 120 200 400
Distribution Network Area
6 0 8 12 16 20 25 75 150
[AREA]
7 City Gas 924 1.308 1.5
197K 326K 608K 3 million 5 million
[CONNECTION] million million million
*) cumulative total
17
17
Kementerian ESDM Republik Indonesia
Closing Remarks
• Supply & demand gap for natural gas will start in 2019 in which
Indonesia will start importing gas.
• Until 2025, there will be surplus & deficit of LNG Cargo. This calls for a
strategy to manage supply and demand of LNG.
• The gas infrastructure roadmap until 2030 needs US$ 48.2 billion of
investment.
• Virtual pipeline will supply gas using shipping routes in 4 clusters, in
which key components for successful virtual pipeline implementation:
State Owned Enterprise, PLN, experienced companies, & local content.
19
19
Kementerian ESDM Republik Indonesia