The transportation and shipping of 73 wind turbines The transport of 788 over-dimensional loads
ex China to Australia The strict adherence to Quality, Health, Safety and
The full ocean charter of 9 vessel carrying 210,000 Environment throughout the project
freight tons of project cargoes
The Interface management at load and discharge
ports including jobsite
GULLEN RANGE WIND FARM | PROJECT LOGISTICS
1 Project Manager
1 Project Lead Coordinator
1 Project Supervisor at Port of discharge, load in & out
1 Project Supervisor on site the wind farm site
1 Project Interface Manager China & Australia
Transport Engineering Services 1 Project Administration & Finance
GULLEN RANGE WIND FARM | PROJECT LOGISTICS
deugro Australia’s project team, together with deugro In addition we utilized CAR’s (Corrective Action
China pre-inspected all the cargo prior to each voyage. Reports) to raise any issues related to the cargo, cargo
handling or other project related issues. The CAR’s
Cargo condition and integrity was checked including assist both deugro and our clients to review and
adherence to Australia’s strict quarantine regulations improve processes in the logistics chain during the
prior to loading to minimize the risk of potential execution phase.
quarantine holds which would impact on the
construction schedule.
Onshore Services Australia Besides managing around 788 over dimensional loads
with blades of 50m in length, deugro also coordinated
Quite often the onshore logistics component of a
the unloading of the trucks at the Goulbourn windfarm
project, from receiving the cargo under the vessels
site in New South Wales.
hook up to final delivery to jobsite, can be complex and
challenging with additional pressure placed on the
construction schedule by issues such as travel curfews,
escorts and permit requirements.
Commitment to QHSES