Case Study

Liwa Plastics Industries Complex Project


Case Study:
Liwa Plastics Industries
Complex Project
The Liwa Plastics Industries Complex (LPIC) Project is a major capital investment project
in Oman. The total investment value exceeds USD 6 billion, with financing provided
by multiple international Export Credit Agencies (ECAs) from Europe and Asia. Owned
by ORPIC (Oman Refineries & Petrochemical Company LLC), it shall increase Oman’s
production of petrochemicals and increase fuel production, generating 450 direct jobs
and over 1,200 indirect jobs in Oman to have a positive effect on the Omani economy.

A demethanizer column,
with a lengh of 59.55 m, for
the steam cracker unit

EPC1 Package – Steam Cracker Unit

Volume 42 Breakbulk Max. Heavy Lift 21,000+ Truck 580+ Heavy Zero LTIs and
850,000 FRT and Heavy Lift 1,230 MT, length Movements Transportation Exemplary
in total Vessel Charters up to 115 m to project sites Loads QHSES
into Port of Sohar, to project sites Performance
Oman

2 of 6 | www.deugro.com
EPC3 Package – NGL Extraction Plant

Volume 14 Breakbulk Max. Heavy Lift 70+ Heavy Zero LTIs and
170,000 FRT and Heavy Lift 535 MT, length Transportation Exemplary
in total Vessel Charters up to 53 m Loads QHSES
into Sohar and to project sites Performance
Duqm ports,
Oman

Road transportation
of a massive 535 MT
demethanizer unit

deugro was awarded two of the planning, engineering and design


main logistics packages: LPIC EPC1 of the project logistics solution
Package (steam cracker unit and to the operational delivery of the
utilities) and LPIC EPC3 Package project cargo.
(natural gas liquids extraction
plant). The two contract awards to deugro
complimented and supported
Both projects combined represent involvement of the wider deugro
over 1 million freight tons of group companies, such as dteq
equipment to be shipped by Transport Engineering Solutions
deugro from multiple global (dteq), providing tailor-made
origins into Sohar, Oman. This engineering solutions throughout
was an unprecedented volume of all project phases, and dship
equipment to be imported into Carriers, providing cost-effective
Oman. tramp services for heavy lift and
project cargo to support deugro
deugro’s involvement from the within this project scope. With
very early stages of the project this specialized set-up, we offered
was pivotal to the successful value-added services in varying
awards and allowed for a seamless aspects of the project.
transition—from conception,

3 of 6 | www.deugro.com
» A movement like this takes
months of planning and
engagement with all parties. «
Richard Juergens, Project Manager Oman

which ensured professional and


efficient execution.

The project had a truly global


supply chain for the provision of
technology and equipment from
over 30 countries. This meant that
deugro was able to leverage its
global offices network to provide
logistics support in collecting origin
cargo from equipment vendors
across the globe.

deugro also provided clients


with dedicated teams of in-house
logistics specialists based in the
client’s offices to work directly with
The demethanizer unit the key project stakeholders on
traveling a distance of approx. end-to-end logistics solutions.
600 km across the country

Location dynamic and pre-emptive manner Working and investing in


ensured that freight movements, Oman
The project was split over multiple visibility and operational assurance
locations within Oman. The EPC1 was always achieved. deugro invested locally within
package was destined for the job Oman, opening two new offices in
site in the proximity of Sohar, just the country, along with training and
7 kilometers from the port. The Many project teams and upskilling the local project logistics
laydown facility was just stakeholders teams, delivering the project with a
14 kilometers away. With the EPC3 high level of Omani in-country value
package, inland distances and the The LPIC Project was delivered (ICV).
associated transport challenges through two international deugro
were much greater. The site Control Tower teams managing the This investment developed the
location was some 450 kilometers offshore scope from Rotterdam and levels of in-country technical and
from the Port of Sohar and Seoul. These Control Tower teams logistical knowledge and regulatory
600 kilometers from the Port of were built up exclusively for this experience, which provided a stable
Duqm – both of which were utilized unique project execution. Onshore foundation for the operational
for inbound cargo discharge. in Oman, deugro’s Sohar office delivery of the onshore scope of
managed the receipt, clearance work for this project. deugro in
deugro operations and and delivery of all equipment and Oman benefited from the ability
management teams were materials. This use of experienced to develop the local team not only
positioned strategically dependent project logistics experts, local in terms of staff numbers but
on project demands and freight Omani colleagues and senior also competence, training and
thru-flow. The ability for the deugro engagement provided an empowerment.
deugro team to work in an intuitive, unrivaled mix of competencies

4 of 6 | www.deugro.com
Scope of work and project
execution

The challenging scope of work


included transporting over 1 million
freight tons of general cargo and
heavy lift project equipment from
vendors’ worldwide facilities, and
delivering it safely to the job sites
in Oman. This end-to-end logistics Top: Storage bullets weighing up
solution was delivered through to 1,230 MT Bottom: Cold boxes
a carefully developed logistics being loaded out in the USA
plan, involving over 150 deugro
people managing all aspects of the Liwa Plastics Industries Complex exemption processes. By providing
logistics supply chain. Project. All heavy cargo at the HS Code consultancy services and
Sohar Port was supervised by establishing the initial exemption
Congestion at the Port of Sohar deugro personnel, and we ensured list, reporting on all cargo
presented a major risk. The high that our contractors complied with movements into Oman was in line
volumes of both container and transport design and strict HSE with Omani customs requirements.
heavy lift cargo required careful requirements at all times. This process included direct
scheduling and management support to both EPCs and the
of port facilities and resources. To successfully accomplish project owner in successfully
Regular project planning and road transportation, deugro, in applying for and processing all duty
forecasting meetings were held cooperation with dteq, carried out refunds owed to the project.
to identify logistics bottlenecks at multiple infrastructure studies and
the ports and provide contingency consulted with the Department
solutions to ensure delays of Transport, the Royal Omani
and congestion were kept to a Police and various construction
minimum. contractors.

Throughout the whole execution, deugro was intrinsically involved


our teams remained focused on with the EPC clients and the
maintaining a highly safe, secure project owner in providing critical
and healthy environment for our support in the application and
staff and all parties involved in the management of the project duty

5 of 6 | www.deugro.com
Innovation and unique challenging heavy lift operation.
techniques This same principal was leveraged
in numerous other circumstances
Throughout the delivery of the and proved to be highly successful
project, deugro collaborated with throughout the project. It enabled
the clients in identifying innovative us to gain support from our client,
cost saving initiatives and changing empowering deugro logistics
procurement terms in their global specialists to complete more
sourcing. One example was the logistics and, in turn, provide
unbundling of three 330-metric- significant savings.
tonne time-critical boiler modules.
deugro worked together with the Watch the film of the EPC3
client to safely provide precarriage, Package transportation: deugro
loading and lashing on board the group – Orpic Liwa Plastics
vessel in Italy. This reduced costs Industries Complex EPC-3
by 60 percent and improved permit
times, while increasing control
and assurance for this technically

» We offered cost-saving initiatives while increasing


operational and schedule assurance for various
critical shipments. «

Boiler package with a height


of 17.4 m on stools

6 of 6 | www.deugro.com