You are on page 1of 51

Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021

Instrumentation Diagram) _ Yulan Ibnu


Mulkam, ST

P&ID Reviews
using
Hazops Method
Process Engineering Summer School
July 31st, 2021
TTK Goes to Campus

Presented by
Yulan Ibnu Mulkam, ST
HAZOP Facilitator for Refinery Units

• RU II Dumai • RU IV Cilacap
• RU II Sei Pakning • RU V Balikpapan
• RU III Plaju • RU VI Balongan
Process Safety Consultant in various Industries:
Upstream Offshore & Onshore Facilities
Oil Refinery Unit
Gas Processing Plant
Bio-Refinery Plant
Petrochemical Plant
Power Plant

P&ID Review using HAZOPS Method 1


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Process Safety Review


Methods

Qualitative Methods Safety Reviews

Checklists
Preliminary Hazard Analysis (PHA)
What-If Reviews
Hazard and Operability Reviews (HAZOP)
Bow-Tie Analysis (BTA)
Fishbone

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 2


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Quantitative Methods Safety Reviews

Event Trees
Fault Trees
Failure Modes and Effects Analysis
Layers of Protective Analysis (LOPA;
semiqualitative)
Safety Integrity Level (SIL) Analysis

Source : Safety and Security Review for the Process Industries, 4th Edition.

Hazard and Operability


Reviews
(HAZOP)

P&ID Review using HAZOPS Method 3


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Origins Of Qualitative Safety Reviews


HAZOP reviews originally began in the chemical industry in the United
Kingdom during the 1960s.
Imperial Chemical Industries Ltd. (ICI) developed a standardized method of
analyzing processing hazards based on basic operation conditions and then
changed individual parameters one at a time to see the subsequent
consequences.
This evolved into a standard practice within their company and soon found its
way into the general chemical industry (although it was not universally or
consistently applied).

Source : Safety and Security Review for the Process Industries, 4th Edition.

Limitations and Disadvantages

It needs a moderate level of skill to implement.


It may be slower to implement than other
methods.

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 4


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Advantages

It uses a systematic and logical approach.


It can analyze a combination of failures.
It provides an insight into operability features.

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP
TEAM

P&ID Review using HAZOPS Method 5


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Minimum Team Members


Team Leader
Scribe
Project Manager (Project, Process, or Facility
Engineer)
Operations or Manufacturing Representative
Loss Prevention/Safety Representative
Security Officer (for SVA)

Source : Safety and Security Review for the Process Industries, 4th Edition.

Supplemental Members
PSM Coordinator
Maintenance Representative
HSE (Health, Safety, and Environmental) Representative
Process, Chemical, Manufacturing, Facility, or Construction Engineers
Drilling or Production Engineers
Project Designers/Engineers (Electrical, Instrumentation, Piping, etc.)
Operation Technicians or Supervisors
Specialized Consultants
Equipment Fabricators or Vendors

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 6


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Leadership Influences

Look at things from the other person’s perspective.


Offer genuine appreciation and praise.
Harness the power of enthusiasm.
Respect the dignity of others.
Don’t be overly critical.
Give people a good reputation to live up to.
Keep a sense of fun and balance.

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP
REFERENCE DATA

P&ID Review using HAZOPS Method 7


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Reference Data


Piping and Instrumentation Drawings (P&IDs) that are “as-built” verified for the existing
processing facilities.
Plot plan or equipment and main piping layout and pertinent elevation drawings,
including surface drainage arrangements.
Cause and effects charts (SAFE charts) with schedule of alarm and trip settings
P&IDs for vendor packages
System design philosophy and process description
Fire and explosion protection system drawings or arrangements (fire and gas
detection/alarm, protection passive and active)
Chemical and physical properties of commodities involved, especially hazardous
materials (crude oil Gas Oil Ratio (GOR), Material Safety Data Sheets (MSDS),
Permissible Exposure Limits (PELs), etc.)

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP Reference Data


ERPs indicating responsibilities and duties of management (if available, the
local fire station pre-incident plan should also be provided)
Operating procedures (including startup/shutdown and emergency) and
maintenance schedules
Process Flow Diagrams (PFDs) and material and energy balances
Electrical hazardous area diagrams
Full description and system design calculations of ESD isolation and depressing
(blowdown) capabilities including headers, vents, and flares
Design duties and basis of calculation of all relief valves, rupture disks, etc.
Corrosion monitoring and prevention systems

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 8


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Reference Data


Engineering design data sheets for all plant items including vendor items
Data sheets for instruments and control valves
Piping and material specifications (if not indicated elsewhere)
Flare, vent, and drainage header diagrams
Electrical single-line diagrams
Instrumentation philosophy (local/remote control, hardwired/data highway,
failure mode(s), analog/digital, emergency alarms, DCS display alarm
histories, etc.)
Drawings showing interfaces to existing systems

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP Reference Data


Special studies or calculations (vapor dispersions, blast over pressure, etc.)
Environmental ambient data (expected temperatures, weather, seismic, etc.)
Utilities specifications and reliability (power, water, sewer, etc.)
Design codes and standards employed (API, NFPA, ANSI, ASME, IEC, ISA, NACE,
etc.)
Manning levels, distribution of personnel, levels of supervision, and
evacuation routes or plans
Job Safety Analysis (JSA) for critical tasks
Ergonomic or human factors features (color coding, accessibility, practical
use, languages and instructions, etc.)

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 9


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP
PROCEDURE

HAZOP Study Procedure


Definitions
Initiate the study
Define Scope and objectives
Define roles and responsibilities
Preparation
Plan the study
Collect data and documentation
Establish guide words and deviation

Source : BS EN 61882:2016 Hazard and Operability Studies (HAZOP studies) – Application Guide

P&ID Review using HAZOPS Method 10


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Study Procedure


Examination
Structure the examination
Perform the examination
Documentation and Follow Up
Establish method of recording
Output the study
Record the information
Sign off the documentation
Follow up and responsibilities

Source : BS EN 61882:2016 Hazard and Operability Studies (HAZOP studies) – Application Guide

HAZOP
WORKSHEET

P&ID Review using HAZOPS Method 11


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Worksheet
Guideword (GW): Simple word or phrase used to generate deviations by
application on a system or process activities (e.g., pressure, level, and temp)
Deviation: A departure from the design and operating intention (e.g., high,
low, more, and less)
Causes: Reasons that deviations occur (failures, wrong operation, etc.)
Consequences: The effects of a deviation resulting from various causes (fire,
explosion, process upset, etc.)
Safeguards: Measures taken to prevent or mitigate the risk of accidents
(operator surveillance, instrumentation, ESD, blowdown, etc.)
Severity: The magnitude of physical or intangible loss consequences
(qualitative measure of consequences compared to industry experience)

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP Worksheet
Likelihood: A measure of the expected frequency of an event’s occurrence
(qualitative measure of probability based on historical data or theoretical
estimate)
Ranking: The qualitative estimation of risk from severity and likelihood levels
in order to provide a prioritizing of risk based on its magnitude (refer to
corporate risk matrix for ranking based on severity and likelihood levels)
Recommendations: Activities identified that may reduce a risk through the
lowering of a probability or consequence level (suggested safety improvement
to a process to reduce risk level)
Comments: Technical notes of the facility, system, or process under study
(supplemental information about the issue being discussed)

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 12


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP
REVIEW

HAZOP Review Step

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 13


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Review Step

Define the assumptions about the facility to be accepted


during the review process.
Define the boundaries and operational mode(s) of the
facility under review.
Select and confirm the scope of a node.
Explain the general design intentions and operating
conditions of the node.
Specify the node’s process parameters.

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP Review Step


Select a process parameter (flow, pressure, etc.) and
specify the design intention relating to this parameter.
Apply a deviation (more, less, etc.) to the parameter and
develop a meaningful scenario (causes/hazards) from the
intention.
Identify all scenarios (causes/hazards) of the deviation
from the intention.
Identify all major consequences associated with each
cause without regard to safeguards.
Specify predominate safeguards against each
consequence.
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 14


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Review Step


Determine the probability and severity of each consequence
Make recommendations to mitigate the consequences if the severity or
probability is unacceptable, according to the company’s risk acceptance
levels.
Reiterate above steps for other guidewords.
Reiterate above steps for other process parameters.
Reiterate above steps for all other nodes in review.
The review team should rank all produced recommendations in priority of
assigned risk for schedule of implementation. Ranking of recommendations
assists senior management in allocating resources.
Prepare summary and listing of recommendations in order of priority
(ranking).

Source : Safety and Security Review for the Process Industries, 4th Edition.

HAZOP
GUIDEWORDS

P&ID Review using HAZOPS Method 15


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP Parameter

Source : HAZOP Guide to Best Practice, 3rd Edition, IChemE.

Basic Guide Words and Their Generic


Meanings

Source : BS EN 61882:2016 Hazard and Operability Studies (HAZOP studies) – Application Guide

P&ID Review using HAZOPS Method 16


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Guide Words Relating To Clock Time And


Order Or Sequence

Source : BS EN 61882:2016 Hazard and Operability Studies (HAZOP studies) – Application Guide

HAZOP Deviation Matrix

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 17


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

HAZOP
POSSIBLE CAUSES

Parameter, Deviation, and Possible


Causes

Flow
High
Increased pumping capacity
Increased suction pressure
Reduced delivery head
Greater fluid density
Exchanger tube leaks

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 18


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Flow
High
Restriction orifice plates not installed
Cross-connection of systems
Control faults
Control valve trim changed
Running multiple pumps

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Flow
Less
Restriction
Wrong routing
Filter blockage
Defective pump(s)
Fouling of vessel(s), valves, orifice plates

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 19


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Flow
Less
Density or viscosity changes
Cavitation
Drain leaking
Valve not fully open

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Flow
None
Wrong routing
Blockage
Incorrect slip plate
One-way (check) valve in backward
Pipe or vessel rupture

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 20


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Flow
None
Large leak
Equipment failure
Isolation in error
Incorrect pressure differential
Gas locking

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Flow
Reverse
Defective one-way (check) valve
Siphon effect
Incorrect pressure differential
Two-way flow
Emergency venting
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 21


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Flow
Reverse
Incorrect operation
In-line spare equipment
Pump failure
Pump reversed
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Level
High
Outlet isolated or blocked
Inflow greater than outflow control failure
Faulty level measurement
Gravity liquid balancing
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 22


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Level
High
Flooding
Pressure surges
Corrosion
Sludge
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Level
Low
Inlet flow stops
Leak
Outflow greater than inflow
Control failure
Faulty level measurement
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 23


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Level
Low
Draining of vessel
Flooding
Pressure surges
Corrosion
Sludge

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
High
Surge problems
Connection to high pressure
Gas (surge) breakthrough
Inadequate volume of vents
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 24


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
High
Incorrect vent set pressure for vents
Relief valves isolated
Thermal overpressure
Positive displacement pumps
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
High
Failed open PCV
Boiling
Freezing
Chemical breakdown
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 25


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
High
Scaling
Foaming
Condensation
Sedimentation
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
High
Gas release
Priming
Exploding
Imploding
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 26


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
High
External fire
Weather conditions
Hammer
Changes in viscosity/density
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
Low
Generation of vacuum conditions
Condensation
Gas dissolving in liquid
Restricted pump/compressor line
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 27


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
Low
Undetected leakage
Vessel drainage
Blockage of blanket gas regulating valve
Boiling
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
Low
Cavitation
Freezing
Chemical breakdown
Flashing
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 28


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
Low
Sedimentation
Scaling
Foaming

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
Low
Gas release
Priming
Exploding
Imploding
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 29


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
Low
Fire conditions
Weather conditions
Changes in viscosity/density

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Pressure
Low
Cavitation
Freezing
Chemical breakdown
Flashing
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 30


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Pressure
Low
Sedimentation
Scaling
Foaming

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Temperature
High
Ambient conditions
Fouled or failed exchanger tubes
Fire situation
Cooling water failure
Defective control valve
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 31


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Temperature
High
Heater control failure
Internal fires
Reaction control failures
Heating medium leak into process
Faulty instrumentation and control

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Temperature
Low
Ambient conditions
Reducing pressure
Fouled or failed exchanger tubes

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 32


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Temperature
Low
Loss of heating
Depressurization of liquefied gas—Joule
Thompson effect
Faulty instrumentation and control

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Part of
Concentration Wrong
Leaking isolation valves
Leaking exchanger tubes
Phase change
Incorrect feedstock specification
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 33


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Part of
Concentration Wrong
Process control upset
Reaction byproducts
Ingress of water, steam, fuel, lubricants,
corrosion products from high pressure system
Gas entrainment

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
As Well as
Contaminants
Leaking exchanger tubes
Leaking isolation valves
Incorrect operation of system
Interconnected systems
Wrong additives
Ingress of air: shutdown and start-up conditions

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 34


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
As Well as
Contaminants
Elevation changes, fluid velocities
Ingress of water, steam, fuel, lubricants, corrosion
Products from high-pressure system
Gas entrainment
Feed stream impurities (mercury, H2S, CO2, etc.)
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Other Than
Wrong Material
Incorrect or off specification feedstock
Incorrect operation
Wrong material delivered

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 35


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Viscosity
More
Incorrect material or composition
Incorrect temperature
High solids concentration
Settling of slurries

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Viscosity
Less
Incorrect material or composition
Incorrect temperature
Solvent flushing

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 36


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Relief System
Relief philosophy (process/fire)
Type of relief device and reliability
Relief valve discharge location

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Relief System
Pollution implications
Two-phase flow
Low capacity (inlet and outlet)

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 37


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Corrosion / Erosion
Cathodic protection arrangements (internal and
external)
Coating applications
Corrosion monitoring methods and frequencies
Materials specification
Zinc embrittlement
Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Corrosion / Erosion
Stress corrosion cracking
Fluid velocities
Sour service (H2S, mercury, etc.)
Riser splash zone

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 38


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Service Failures
Instrument air
Steam
Nitrogen
Cooling water

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Service Failures
Hydraulic power
Electric power
Water supply
Telecommunications

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 39


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Service Failures
PLCs/computers/DCS
HVAC
Fire protection (detection and suppression)

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Abnormal Operation
Purging
Flushing
Start-up
Normal shutdown

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 40


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Abnormal Operation
Emergency shutdown
Emergency operations
Inspection of operating machines
Guarding of machinery

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Maintenance / Procedures
Isolation philosophy
Drainage
Purging
Cleaning

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 41


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Maintenance / Procedures
Drying
Access
Rescue plan
Training

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Maintenance / Procedures
Pressure testing
Work permit system
Condition monitoring
Lift and manual handling

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 42


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Static
Flame arrestors
Hot work
Hot surfaces
Auto-ignition or pyrophoric materials

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Spare Equipment
Installed/not installed
Availability of spares
Modified specifications
Storage of spares
Catalog of spares
Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 43


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes
Sampling / Procedures
Sampling procedure
Time for analysis results
Calibration of automatic samplers
Reliability/accuracy of representative
sample
Diagnosis of results

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Time
Too long
Too short
Wrong time

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 44


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Action
Overkill
Underestimated
None
Reverse

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Action
Incomplete
Knock-on
Wrong action

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 45


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Information
Confusing
Inadequate
Missing
Misinterpreted

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Information
Partial
Stress
Wrong information

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 46


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Sequence
Operation too early
Operation too late
Operation left out
Operation performed backward

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Sequence
Operation not completed
Supplemental action taken
Wrong action in operation

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 47


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Safety Systems
Fire and gas detection and alarms
Emergency shutdown (ESD) arrangements
Emergency response/pre-incident plans
Firefighting response

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes

Safety Systems
Emergency training
Threshold limit values (TLVs) of process
materials and method of detection
First aid/medical resources
Vapor and effluent disposal

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 48


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Safety Systems
Testing of safety equipment
Compliance with local and national
regulations
Quantitative risk assessments

Source : Safety and Security Review for the Process Industries, 4th Edition.

Parameter, Deviation, and Possible


Causes
Global
Layout and arrangement
Public encroachment toward facility
Weather (temperature, humidity, flooding, winds,
sandstorm, blizzards, etc.)
Geological or seismic
Human factors (labeling, identification, access,
instructions, training, qualifications, etc.)

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Review using HAZOPS Method 49


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Parameter, Deviation, and Possible


Causes

Global
Fire and explosion
Adjacent facility exposures
Incorrect rail car operations or
precautions
Cyberattacks on operating systems

Source : Safety and Security Review for the Process Industries, 4th Edition.

P&ID Reviews
using
Hazops Method
Examples

P&ID Review using HAZOPS Method 50


Topic-6 _ Tata Letak Pabrik & P&ID (Piping and July 31st, 2021
Instrumentation Diagram) _ Yulan Ibnu
Mulkam, ST

Thank You
Process Engineering Summer School
July 31st, 2021
TTK Goes to Campus

P&ID Review using HAZOPS Method 51

You might also like