Professional Documents
Culture Documents
1
CONTENTS
1. Definitions
2. PV design
3. Solar resource
4. PV installation
5. PV design with PVsyst software
6. Other options
7. Practical example
CENTRO NACIONAL DE ENERGÍAS RENOVABLES
NATIONAL RENEWABLE ENERGY CENTER
1. DEFINITIONS
NORMATIVA Y CERTIFICACIÓN FV
3
1. DEFINITIONS
PV modules
PV cell: Device that converts sunlight into direct current (DC).
PV modules: Association of PV cells connected.
Peak power: Power of the PV module in STC.
STC (Standard tests conditions):
Solar irradiance: 1000 W/m2
Spectral distribution: AM 1,5G
Cell temperature: 25ºC
1. DEFINITIONS
Installation
PV installation: Power system designed to supply usable solar power by means of photovoltaics.
It consists of an arrangement of several components, including solar modules to absorb and
convert sunlight into electricity, sometimes a solar inverter to change the electrical current from
DC to AC, as well as mounting, cabling, and other electrical accessories to set up a working
system.
PV generator: PV modules association to generate electric power.
PV string: PV modules connected in series.
PV inverter: Electronic device to convert DC voltage and current into AC voltage and current.
Electrical boxes: Boxes where electrical connections and protections devices are placed.
Nominal power of the PV installation: Sum of the nominal power of PV inverters.
Peak power of the PV installation: Sum of the peak power of PV modules.
Performance Ratio (PR): The Performance Ratio of the system is defined as the ratio between
the energy fed into the grid by the PV system and the energy generated by the same system
working in STC and without losses. The PR represents the deviation of the system from ideal
conditions.
1. DEFINITIONS
PV string 1
PV string 2
CENTRO NACIONAL DE ENERGÍAS RENOVABLES
NATIONAL RENEWABLE ENERGY CENTER
2. PV DESIGN
NORMATIVA Y CERTIFICACIÓN FV
7
2. PV DESIGN
In order to build a PV plant, from a technical point of view, following steps are needed:
Solar resource estimation.
Typical meteorological year (TMY) obtained from databases, meteorological stations, etc.
Location study: Horizon line, near shadows, terrain (for soiling), etc.
PV plant design.
PVsyst is a commercial software able to do this task.
Other PV simulation software: PV sol, Solarius PV, BlueSol Design 4, Plantpredict, etc.
Energy production estimation.
PV project writing.
PV plant execution.
CENTRO NACIONAL DE ENERGÍAS RENOVABLES
NATIONAL RENEWABLE ENERGY CENTER
3. SOLAR RESOURCE
NORMATIVA Y CERTIFICACIÓN FV
9
3. SOLAR RESOURCE
The solar radiation on the earth’s surface is determined by two different factors: astronomical and
climatic factors:
Astronomical factors. Are dependent on the relative position of sun and earth and the
geographic coordinates of the site considered: latitude and longitude. They determine the
radiation path through the atmosphere and the incident angle of sun’s beams. The position of
sun regarding a determined point on the earths surface can be characterized by two angles:
Suns Height (α). Is the angle between the horizontal and the line to the sun.
Azimuth (γ). Is the angular displacement from South of the projection of beam radiation
on the horizontal plane (for Northern hemisphere).
3. SOLAR RESOURCE
Climatic factors. Not all the maximum radiation expected for each sun’s height and location will
always be visible from Earth’s surface. Clouds, the amount of water steam, ozone, aerosols and
other components suspended in the atmosphere might attenuate the solar radiation because of
the absorption, reflexion and scattering of this radiation.
Global Radiation (G) is defined as the total amount of sun radiation on a point in earth’s surface.
Global Radiation is composed by:
Beam (direct) radiation (B). Is the solar radiation received from the sun without having been
scattered by the atmosphere.
Diffuse Radiation (D). Is the solar radiation received from the sun after being scattered by the
atmosphere.
Reflected Radiation (R). Is a proportion of the radiation incident on the ground and reflected
from it. Depends strongly on the ground type.
3. SOLAR RESOURCE
Conclusions:
The solar resource evaluation is based on the historical data and depends on the atmospheric
and climatic conditions of the site location.
Solar irradiation and ambient temperature are the main parameters that have influence in a direct
way on the photovoltaic electric production, however aspects related to wind or precipitations are
also important.
The meteorological data could be obtained from databases with historical data files (at least 10
years) enough to define a Typical Meteorological Year (TMY) for the site.
3. SOLAR RESOURCE
Source: Vaisala
3. SOLAR RESOURCE
Source: Solargis
3. SOLAR RESOURCE
Source: Solar-Med-Atlas
CENTRO NACIONAL DE ENERGÍAS RENOVABLES
NATIONAL RENEWABLE ENERGY CENTER
4. PV INSTALLATION
NORMATIVA Y CERTIFICACIÓN FV
17
4. PV INSTALLATION
Mohammed bin Rashid Al Maktoum Solar Park - Phase II, 260MW, CdTe, DEWA-Dubai built by TSK
4. PV INSTALLATION
Roof PV systems
4. PV INSTALLATION
32
5. PV DESIGN WITH PVSYST SOFTWARE
PVsyst is a simulation software package for the study, sizing and data analysis of complete PV
systems.
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Project
Variants
5. PV DESIGN WITH PVSYST SOFTWARE
5. PV DESIGN WITH PVSYST SOFTWARE
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
Solar Synthetic
Monthly
Location hourly data
Resource values
generation
Preliminary First
results simulation
Design
Re-design Optimization
iteration
6. OTHER OPTIONS
NORMATIVA Y CERTIFICACIÓN FV
105
6. OTHER OPTIONS
7. PRACTICAL EXAMPLE
NORMATIVA Y CERTIFICACIÓN FV
118
THANK YOU
FOR YOUR
ATTENTION
119
www.cener.com