Professional Documents
Culture Documents
commissioning a
new machine for reliability
centered lubrication
FOr rOughLy $500 in hArDwAre eXPenSeS, ALOng with the COSt OF COnSuM-
Key cOncePTs AbLeS, a machine may be fitted for better performance and reduced long-
term cost of care. The actual hardware cost is irrelevant when one considers
• A machine criticality and financial the amount of production that a given machine is responsible for during its
analysis can determine if the normal lifecycle. The decision should proceed on either discretionary capital
machine justifies targeted upgrades or the existing maintenance expense budget. Resistance to do so is not an
for improved productivity. economic decision. It may be an academic decision, but, if so, this can be
remedied with simple explanation of the consequences of moisture, air and
• The actual hardware cost is irrel- particulate in the oil.
evant when considering the amount Commissioning a new production machine is never an easy task. Even
under the best of circumstances, there are a multitude of timing and priority
of production value a machine is
decisions to be made and managed. Between the design engineers, the project
responsible for during its normal management firm, the machine assembly contractor and the purchasing de-
lifecycle. partment, there are more than enough errors, revisions and obstacles to test
one’s patience—the hectic pace only escalates the challenges.
• A rule-of-thumb target for flow rate If the upgrades aren’t part of the original purchase specification, the next
is the volume needed to circulate the best opportunity to make these simple changes will be just before the ma-
sump contents two times per hour chine is commissioned. Regardless of the timing, these changes are needed to
for non-hydraulic systems and four improve management of the machine’s lubrication-related reliability require-
times per hour for hydraulic systems. ments. Once production begins to ramp up, the likelihood of taking machines
down purposefully for these upgrades is low. In addition, simple adjust-
ments will enable the condition-monitoring group to see machine condition
Trivia alert: There are 62,000 miles of blood vessels in the human body—laid end to end they would circle the earth 2.5 times. 25
Net Cost per year $ 3,237.27
Average Cost per Event $ 12.03 Figure 4. Breather-filler ports and a typical r
New Machinery Plant Operations Maintenance Actions once the machine is in op-
Original Machining Debris Washdown Actiions New Oil Drum eration. Quality parts and
Assembly Debris Process Contaminants Oil Handling Containers systems suppliers will have
Run‐off Fluids Atmospheric Debris Oil Top‐Up Activities
2nd Tier Parts OEM Wear Debris Parts Replacement flushing systems equipped
with substantial filtration
capacity used to wash as-
Figure 2 | Sources of common sump contaminants.
Figure 3. Reasonable roll-off cleanliness standards.
sembly debris out of the
components and parts as
Equipment Type ISO Cleanliness Target one of the final steps prior
Element Bearings 16/14/12
Heavy Duty Gear Drives 17/15/12
to shipment of the complet-
Diesel Engines 18/16/14 ed system. It is common for
Journal Bearings 17/15/13 these parts cleaning systems
Hydroastatic Transmissions 16/14/12 to have particle counting Figure 4 | Breather-filler ports
Screw Compressors 18/16/14
capacity that report an ISO and a typical replacement filter-
Hydraulic Component Types ISO Cleanliness Target filler.
Vane Pumps (≤ 3500 PSI: ≥ 2000 PSI) 17/16/13 code through the washing
Axial Piston Pumps (≤ 3500 PSI: ≥ 2000 PSI) 17/16/13 process until the parts are fi-
Radial Piston Pumps (≤ 3500 PSI: ≥ 2000 PSI) 16/14/12 nally clean. Figure 3 offers some suggested cleanliness speci-
Servo‐Control Circuits 14/12/10
fications for a variety of
common components.
Proportional Control Circuits 15/14/12
upgrade the vent-fill port.
One of the lowest cost and high-
est benefit upgrades is accomplished by trading out the stan-
Figure 4.
Figure 3 Breather-filler
| Reasonable roll-off cleanliness
ports and standards. filter-filler.
a typical replacement
dard vent-fill port with a filter-filler port. Most OEM breath-
er-filler ports are little more than a coarse sieve of steel mesh
quartile represents machines that can arguably be run to fail- or steel wool packed into a locking cap, which is intended
ure and warrant little added attention. These might become to keep very large (visible) particulate out of the machine
candidates for sealed-for-life lubrication. as it cycles through hydraulic function or cycles thermally.
If one wished to further refine the decision process, a These fixtures provide no help from a contamination-control
thorough Failure Modes and Effects Analysis (FMEA) for the perspective.
top and second quartile machines could be used to narrowly Several companies provide filter-filler upgrades designed
determine which machines would receive which upgrades. to fit the same six-hole mounting pattern used for the breath-
The central reason to upgrade a brand new machine is er-filler default option. It is typically a simple unscrew-and-
to address the underlying causes of failure that are present replace option. Some filter-filler options include a fluid
within the production environment. Some causes can be quick-connection fitting where top-up fluid is added to the
avoided, and others have to be mitigated. system. This option should include a drop-tube to bring top-
The most prevalent and problematic contributors to fail- up oil to the tank below the normal tank level. This is pro-
ure are the microscopic atmospheric (dust) particles and vided to avoid air churning from oil dropping from the top of
moisture present in the air surrounding the machine and the the tank. Figure 4 provides an example of the breather-filler
production process the machine supports. standard option and Figure 5 provides a look at a typical
Figure 5. Filter-filler adapter options and cross-section diagram. (Courtesy of JLM
filter-filler alternative.
Systems)
sumP cOnTamInaTIOn
Prevention of sump contamination is generally less
costly than removal. Contaminants enter machine
sumps in a variety of ways. Figure 2 offers an abbre-
viated list of possible causes or entry points.
establish vendor roll-off cleanliness specifications.
Roll-off cleanliness specifications for machine and
component suppliers is a strong addition to the bid
specification. A roll-off specification is a limit value
stating how much contaminant may be left in the
machine after manufacturing. This is typically pro-
vided in the form of an ISO cleanliness code that the
supplier must achieve on the flushing fluid used to
wash out the machines and/or components prior to
shipping.
The cleanliness target should reflect the cleanli- Figure 56. |Lip
Figure Filter-filler adapter
seal function at options interface.diagram. (Courtesy
and cross-section
the shaft-sump
ness level expected of the maintenance department of JLM Systems)
Figure 6 | Lip seal function at the shaft-sump interface.
CHEMICAL COMPANY
67$<,1*32:(5
7DPLQFR¶V6\QHUJH[DQG6\QHUJH[7
DQLPHDGGLWLYHVVLJQL¿FDQWO\ERRVWSHUIRUPDQFH
ZKLOHH[WHQGLQJWKHOLIHRI\RXUPHWDOZRUNLQJÀXLGV
:KHQ\RXIRUPXODWHZLWKWKH6\QHUJH[SURGXFWUDQJHRI
DPLQHDGGLWLYHVWKH\ZLOOEHWKHUHIRUWKHOLIHRIWKHÀXLG
6RPHDPLQHVIDOORXWRIHPXOVLRQVLQKDUGZDWHU6RPHDPLQHVZLOOOHDYH\RXU
V\VWHPWKURXJKYRODWLOL]DWLRQ6\QHUJH[DPLQHVZRQ¶W0267DGGLWLYHV
QHJDWLYHO\LPSDFWS+VWDELOLW\6\QHUJH[DQG6\QHUJH[7RIIHU
H[FHOOHQWFRQVLVWHQF\IRUWKHOLIHRI\RXUPHWDOZRUNLQJÀXLG
.H\EHQH¿WVRI6\QHUJH[SURGXFWV
&RPSOHWHO\ZDWHUVROXDEOH
2XWVWDQGLQJFRUURVLRQLQKLELWLRQSURSHUWLHV
/RZRGRUORZYRODWLOLW\DQGKLJKÀDVKSRLQW
([FHOOHQW+(6SUR¿OHV
(QKDQFHGHPXOVLRQVWDELOLW\
2XWVWDQGLQJFRXSOLQJDJHQW V\QHUJH[DPLQHFRP
28 Did you know? Almost a third of all STLE members hold one of the society’s
machine function. This film is dependent on the lubricant’s dimension of greatest concern. For instance, servo-control
viscosity at operating temperature. Once the separating film valves are most sensitive to particles in the 3-4 micron
is established, the machine should operate, assuming other range. Focusing on 12 micron-size particles will assure a
design parameters are correct, without incident through the large population of the particles prone to cause the most
warranty period. concern will remain in the system. Regardless of the system
Machine builders will defer to the details provided in the designer’s sentiments, a system with servo-valves will not
bid specification for the provision of lifecycle-enhancing lu- produce the inherent valve reliability with 12 micron tar-
brication condition control features such as intercoolers and get elements (Bx= 200) that a 3 micron element (Bx= 200)
heaters, high-efficiency/high-surface area filters and hous- would provide. As the system pressure increases, the degree
ings, diffusers and baffles in the sumps, etc. If those features of influence also increases.
are not present in the bid specification, it is nearly certain
that the machine will arrive with the minimum set of fea-
tures needed to function through the warranty period.
High surface area/high beta-ratio filtering systems (ele- Machine managers tend to underestimate
ments and housings) are considered to be high-value sys-
tems and incur a higher cost across the entire market. Unless
the amount of time that a machine will
the OEM can see the path to gain extra market value from in- require support for reliability centered
stalling higher quality options, it is unlikely they would pro-
vide them as part of the original build. If the bid specification
lubrication practices each year.
is silent (about element size and quality), it is also likely that
the system will only meet minimum system requirements.
For the sake of machine-reliability protection, a filter system Accordingly, the scheme for element selection should
upgrade is in order. focus on the component sensitivity threshold of the most
Reflecting on the ISO cleanliness targets noted earlier, sensitive item in the circuit (3 micron or lower) for any el-
the machine’s reliability target should be identified and ement used to perform the bulk of solid-particle removal.
communicated to the facility element suppliers. Quality That would also be the case for breather elements (used to
suppliers will be able to provide specific input on the num- replace the breather-filler ports). The return line element
ber of elements, optimum placement of elements and the should remain porous to allow ready flow for high viscosity
respective beta value of each element needed to achieve the requirements.
reliability target.
High pressure, hydraulic systems for low viscosity hy- summaRy
draulic fluids are frequently equipped with seemingly As stated at the beginning of this article, for roughly $500
tight element specifications (B12 =100-200; B10 = 75-200) in hardware and the cost of consumables, a machine can be
for pressure lines and porous specifications (B20 = 75-200) fitted for a lifetime of better care access. When one consid-
for return lines. Porous limits reflect the practical difficul- ers the amount of production that a given machine is re-
ty of returning cold-oil under gravity to the tank, so that sponsible for, the dollar value is irrelevant, and this decision
isn’t necessarily a weakness. However, unless side-stream should proceed on variable capital or with expense money.
(kidney-loop) elements also are in use, the heavy work of Resistance to do so is not an economic decision. It may be
particle removal is conducted by exceptionally high cost, an academic decision, but, if so, this can be remedied with
low dirt-holding capacity pressure line elements. The par- simple explanation of the consequences of moisture, air and
ticle capture effectiveness of the pressure-line filter element particulate in the oil.
is also influenced by line surges that occur normally with Collaboration may be warranted for the work culture,
system operation. Pressure-line elements represent a rela- and, if so, that will take time. Beyond this, the only reason
tively high cost, mildly effective but necessary filtering op- that management should not wish to pursue something that
tion, and should not be used to fulfill the majority of fluid is fractions of a penny per year of expected production value
cleansing. is that the reliability community didn’t get the attention of
Side-stream elements should provide the dominant role the key manager for long enough period of time to make the
for sump particle removal and may also be equipped for case for improvement. We just didn’t make the case!
moisture removal. These should be constructed for relatively
low flows and low pressures. A rule-of-thumb flow rate for
side-stream filtration is two times sump capacity for circula- Mike Johnson, CLS, CMRP, MLT II, MLA III,
tion systems and four times capacity for hydraulic systems is the principal consultant for Advanced
up to about 200 gallon capacities. Machine Reliability Resources, in
The target particle size should be defined by the com- Franklin, Tenn. You can reach him at
ponent with the greatest sensitivity and reflect the particle mike.johnson@precisionlubrication.com.