Professional Documents
Culture Documents
ELECTRICAL SAFETY
TOP PRIORITY AREA
No warning
Probability for fatality high
Minimum 15 persons die out of electric
shock every day
35% of the fires are due to electricity
ELECTRICAL HAZARD
CONSEQUENCES
Electric Shock
Electrical Burns
Electrical Fire & Explosion
ELECTRICAL SHOCK
VOLTAGE
CURRENT
RESISTANCE
VOLTAGE
Low voltage (Up to 250 V)
Medium Voltage (Up to 650 V)
High Voltage(Up to 33 KV)
Extra High Voltage(Above 33 KV)
ELECTRIC CURRENT
Magnitude
Duration
Type
Frequency
ELECTRICAL RESISTANCE
Opposition offered to the flow of current
Metals
Wood
Rubber
Oil
HUMAN BODY RESISTANCE
Emergency Plan
Emergency Equipment
First Aid Treatment
Fire Fighting Systems
INDIAN ELECTRICITY RULES
11 Chapters
Preliminary (Definitions)
Inspectors (Qualifications& Powers)
Licence (Application,Approval)
General Safety Requirements
General conditions (Supply & use of energy)
LV & MV Systems
HV & EHV Systems
O/H lines, U/G cables, Generating Stations
Electric Tractions
Additional Precautions (Mines, Oil fields)
Miscellaneous (Penalties& Procedures)
RULE 3
Manager to authorize competent persons
Rule 3(6)
Registered factory with more than 250KW
connected load to authorize persons to ensure the
compliance of safety provisions of IE Rules
Rule 3(7)
To appoint safety Officer by supplier
Rule 29
Construction, installation,
protection ,operation and maintenance of
supply lines and apparatus to ensure the
safety of human, animals and property
Rule 30
The supplier to ensure the safety of his lines
and apparatus at consumers premises
Rule 31
Supplier to provide cut out at consumers premises.
Rule 32
Earthed neutral to be identified
Not to provide cut out in neutral
Rule 33
Supplier to provide earthed terminal at consumers
premises
In HV and EHV the consumer should also provide
earthed terminal
Rule 34
Owner to ensure that the bare conductors are
inaccessible
Switches to be readily accessible for disconnection
Rule 35
In MV,HV and EHV Systems Danger notices in
three languages (Every generator, motor,
transformer, support structures of HV and EHV
systems)
Rule 36
Before handling lines and apparatus proper
isolation and earthling to be ensured by the
authorized person
All PPE to be provided and used
All tools to be inspected periodically
Rule 37
For traveling cranes suitable switches to cut off all
voltages in single operation
Rails to be electrically continuous and earthed
Rule 38
Cables of portable electrical equipment to be
heavily insulated and protected from mechanical
injury
Rule 40
Street boxes to be protected from water/gas
ingress
Rule 41
Identification of different circuits, voltage
levels, double feeding
Rule 43
First aid boxes
Fire extinguishers
Gas Masks
Artificial respirators
Rule 44
Instructions for restoration of persons suffering
from electric shock (Training, competence)
Rule 44A
Intimation of accidents within 24 Hrs. and report
within 48 Hrs.
Rule 45
Addition, Alteration ,Repair only by a licensed
contractor under the direct supervision of a
supervisor holding a competency certificate
Rule 46
Installation to be inspected and tested once
in 5 years by the inspector
Rule 47
The supplier to test the installation of the
consumer before the commencement of the
supply /before the recommencement after
the break of 6 months
Rule 47A
Generating plant of capacity 10KW and
above, equipment should not be
commissioned without the written approval
of the inspector.
Rule 48
Precaution against leakage before connection
Insulation resistance of 1MEGA OHM between
the live conductor and earth (1Minute)(LV/MV
equipments)(500VDC)
Insulation resistance of 5MEGA OHM between
the live conductor and earth (1Minute)(HV
equipments)(2.5KV DC)